FA8903-23-D-XXXX/FA8903-23-F-XXXX
Attachment 1
28 March 2023
STATEMENT OF WORK
FOR
CERCLA REMEDIAL INVESTIGATION AND RESPONSE ACTIONS
AT
THE FORMER MCCLELLAN AFB, CALIFORNIA
PROJECT(S): PRJY20237242
CONTRACT: FA8903-23-D-XXXX
TO: FA8903-23-F-XXXX
28 MARCH 2023
DRAFT
FA8903-XX-D-XXXX/FA8903-XX-F-XXX
28 March 2023
CONTRACT SECTION C -- STATEMENT OF WORK
CERCLA Remedial Investigation and Response Actions at
The Former McClellan AFB
PART A – INTRODUCTION
This statement of work (SOW) defines requirements for A-E services in support of the Air Force
Civil Engineer’s environmental program area. Place of performance shall be at the Former
McClellan AFB located in Sacramento, California.
McClellan AFB was placed on the Nation Priorities List (NPL) on July 22, 1987. In 1989, the
Air Force, United State Environmental Protection Agency (USEPA) Region 9, and the California
Department of Health Services (CDHS) signed an Interagency Agreement (IAG) for the cleanup.
The IAG was executed in 1990. CDHS was later reorganized, and Department of Toxic
Substances Control (DTSC) assumed CDHS’s responsibilities under the Interagency Agreement.
In addition to DTSC, the State of California is represented by the Central Valley Regional Water
Quality Control Board (RWQCB) for issues affecting the state’s waters. Under the Installation
Restoration Program (IRP), the investigation and remediation of contamination at the installation has been conducted in accordance with the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA).
The Final Perfluorinated Compound Preliminary Assessment (PA), former McClellan Air Force
Base California dated 2016 identified 52 potential aqueous film forming foam (AFFF) release areas. Fifteen areas were categorized as no further action. The 37 remaining AFFF areas were determined to have potential or confirm AFFF releases requiring further investigation. A Site
Investigation (SI) was completed in 2020. The SI identified perfluorooctane sulfonate (PFOS) and perfluorooctanoic acid (PFOA) exceeding the 2016 USEPA lifetime health advisory (HA) within 9 groundwater monitoring wells. Analytical results also indicated that seven soil samples had concentrations of PFOS exceeding the USAF-calculated screening level.
The goals of this task order (TO) are to accomplish a CERCLA Remedial Investigation (RI) and
Response Actions that characterizes environmental conditions, defines the nature and extent of per- and polyfluoroalkyl substances (PFAS) contaminants, assesses risk to human health and the environment, identifies preliminary remedial alternatives, and identifies and implements response actions (i.e., removal or interim remedial actions). The contractor is to produce all necessary documents to meet the goals of the task order. As the technical expert in emerging contaminants including knowledge of PFAS, the intent is that new or changing analytical methodologies, regulatory or DoD guidance and requirements, toxicity criteria and ecological benchmarks, and technologies to assess and remediate PFAS will be utilized throughout the TO.
In carrying out each work assignment issued in this TO, the Contractor shall furnish the personnel, services, equipment, materials, facilities, and other requirements necessary for, and incidental to, the performance of work set forth herein. The contractor will collaborate with the environmental project team consisting of Air Force representatives, federal and state regulators, and other applicable stakeholders.
As a highly technical A-E firm, individuals performing technical services are credentialed
28 March 2023 members of architectural, planning, science, and engineering professions such as toxicologist, ecologist, hydrologist, geologist, chemist, architects, landscape architects, environmental engineers and scientists, planners, cost estimators, Computer Assisted Design and Drafting technicians, publication writers/editors, technical writers, graphic artists, and Geographic
Information System (GIS) analysts. These individuals are expected to possess and maintain the knowledge and experience to accomplish the specified tasks.
Generally, a credentialed professional (a) is licensed (e.g., registered professional engineer) to practice in the state where a facility is located and (b) commands the necessary expertise, in terms of knowledge and experience, to undertake the specified task. An environmental professional’s specific expertise may be evinced through certifications such as Diplomate
Environmental Engineer, Certified Hazardous Materials Manager, Qualified Environmental
Professional, Certified Industrial Hygienist, and American Institute of Certified Planners.
1.0 GENERAL SCOPE.
The contractor shall provide A-E Services for the Air Force Civil Engineer Center (AFCEC) environmental projects and are expected to complete activities such as:
• Developing and updating of plans documenting the methods and procedures that will be used to conduct the remedial investigation including defining the nature and extent of
PFAS contamination
• Collecting and analyzing geologic, geophysical, hydrogeological, ecological, chemical, physical and hydrologic data
• Collecting and analyzing environmental samples such as groundwater, soil, surface water, sediment, tissue, and drinking water
• Managing and disposing of investigation derived waste and other waste generated during the execution of the activities
• Refining the Conceptual Site Model using validated environmental data to identify migration and sample pathways by which populations may be exposed to contaminants
• Performing a source strength assessment of PFAS impacted vadose zone sources
• Conducting a CERCLA Baseline Risk Assessment to evaluate the risk to human health and the environment
• Conducting removal actions to respond to imminent threats to human health and the environment such as hot-spot soil removals, providing alternate water including bottled water and treatment systems
• Evaluating preliminary remedial alternative options to support RI scoping and response actions
• Designing and implementing interim remedial actions to manage/prevent migration of known contamination or stabilize the site
• Preparing CERCLA documents such as remedial investigation, time critical removal actions, non-time critical removal actions (Engineering Evaluation/Cost Analysis
[EE/CA], Action Memorandum, and Workplan), and other decision documents such as an Explanation of Significant Differences, interim proposed plans and interim Record of
Decision
• Supporting meetings such as public, stakeholder, and regulatory interface
28 March 2023
• Updating the CERCLA administrative record and information repository with applicable work products and reports
• Preparing and presenting expert testimony
1.1 Architectural-Engineering Services.
1.1.1 Title I Services.
Provide services related to specific construction projects and consisting of conducting field surveys and investigations to obtain design data and preparing contract plans, specifications, cost estimates, and estimated construction periods of performance. Perform Title I services including all aspects of design of environmental remediation systems such as preparation and/or review of contract plans, specifications, scheduling, cost estimates, preparation of operating and design manuals. Title I efforts also encompass those efforts required to support and develop design work, including planning and programming, program management, project scoping, studies, investigations, evaluations, consultations, conceptual design, value engineering, and operation, monitoring, topographic survey services, optimization of environmental treatment or control systems, and infrastructure systems.
1.1.2 Title II Services. Not Applicable to this TO.
1.1.3 Other A-E Services.
Provide a full range of environmental services in support of the work specified in this TO as necessary for the implementation of environmental restoration projects. These efforts include planning, project management, scoping, research, data gathering, permit preparation, sampling and analysis, investigations, evaluations, removal actions, and monitoring. Additional tasks include sampling drinking water, performing removal actions such as hot-spot removals, providing emergency bottled water, and installing and maintaining treatment systems.
1.2 Program Requirements for A-E Services. Not Applicable to the TO.
1.2.1 Environmental.
Provide environmental services to meet the goals, as specified in this TO.
1.2.1.1 Environmental Restoration.
The goals of this TO are to accomplish environmental restoration activities such as remedial investigation and response actions that characterize environmental conditions, define the nature and extent of PFAS contaminants, assess risk to human health and the environment, identify feasible remedial alternatives, design interim remedial actions, and identify and implement removal actions to protect drinking water or non-drinking water. All project activities shall assess the use of Green and Sustainable Remediation practices to the fullest extent without reduction in human health and environmental protection. Response actions may be required to reduce or limit an imminent threat to human health or the environment, manage/prevent
28 March 2023 migration of known contamination, or stabilize the site.
1.2.1.2 Conservation, and Environmental Planning and Programming. Not Applicable to the TO.
1.2.1.3 Environmental Quality. Not Applicable to this TO.
1.2.2 Other Areas of Essential Support. Not Applicable to this TO.
PART B – ADMINISTRATIVE AND MANAGERIAL REQUIREMENTS
The Contractor shall provide management, planning, performance measurement and cost status reporting pertinent to the performance of the requirements identified in this TO.
2.0 APPLICABLE DOCUMENTS.
The Contractor shall comply with all applicable (1) federal, state, and local environmental statutes, instructions, manuals, handbooks, regulations, guidance, policy letters, and rules
(including all changes and amendments), and (2) Presidential Executive Orders in effect on the date of issuance of this TO, including Unified Facilities Criteria (UFC) and Unified Facilities
Guide Specifications (UFGS). In addition, the Contractor shall refer to the Air Force Civil
Engineer Center (AFCEC) Technical Services Quality Assurance Program, Guidance for
Contract Deliverables (GCD), current version, unless otherwise specified. This GCD is a reference document to be used in the generation of contract deliverables. For reference, below are project-specific documents pertaining to this TO (current version or most recent publication):
• Final Basewide Perfluorinated Compounds (PFCs) Perliminary Assessment (PA), Former
McClellan Air force Base (AFB), DSR #2290-5, August 2016, AR# 538223
• Final Perfluorinated Compounds (PFCs), Site Investigation (SI) for Aqueous Film forming Foam (AFFF) Areas at former McClellan AFB, DSR #2296-5, December 2020, AR #604980
• United States Environmental Protection Agency (USEPA Draft Method 1633, August
• United States Environmental Protection Agency (USEPA), Human Health Toxicity
Values for Perfluorobutane Sulfonic (PFBS) Acid (CASRN 375-73-5) and Related
Compound Potassium Perfluorobutane Sulfonate (CASRN 29420-49-3), EPA/600/R-
20/345F, April 2021
• Code of Federal Regulations, Title 40 - Protection of Environment, Part 300—National
Oil and Hazardous Substances Pollution Contingency Plan
• DoD Manual, 4715.20. Defense Environmental Restoration Program Management, 9
March 2012 (Incorporating Change 1, August 31 2018)
• Department of Defense Instruction (DoDI) Number 4715.18, Emerging Chemicals of
Concern, 4 September 2019
• DoDI 4715.15 Environmental Quality Systems, Publication April 17, 2017 Change 3, July 8, 2019
28 March 2023
• DoDI 4715.07 Defense Environmental Restoration Program May 21, 2013 Incorporating
Change 2, August 31, 2018
• Department of the Air Force Instruction (DAFI) 32-7020, The Environmental Restoration
Program, 12 March 2020
• Department of the Air Force Guidance Memorandum to Department of the Air Force
Instruction 32-7020, Environmental Restoration Program, DAFI32-7020_AFGM2020-
01, 15 December 2020
• Air Force Manual 32-1067, Water and Fuel Systems, 4 Aug 2020
• Department of Defense (DoD) Department of Energy (DoE) Consolidated Quality
Systems Manual (QSM) for Environmental Laboratories, Version 5.4, 2021
• DoD General Validations Guidelines, Nov 2019
• DoD Data Validation Guidelines Modules 1 thru 4
• Derivation of PFAS Ecological Screening Values, Argonne National Laboratory, PFAS
Ecological Screening Values, Sep 2021
• Assistant Secretary of Defense for Sustainment, Investigating Per- and Polyfluoroalkyl
Substances within the Department of Defense Cleanup Program, Sep 2021
• Assistant Secretary of Defense for Sustainment, Update for Establishing a Consistent
Methodology for the Analysis of Per- and Polyfluoroalkyl Substances in Media Other than Drinking Water, Dec 2021
• Environmental Data Quality Workgroup (EDQW) EPA SW-846 Method 8327 Statement on DENIX https://www.denix.osd.mil/edqw/home/
• DoD Information for EPA Method 533, https://denix.osd.mil/edqw/documents/documents/epa-method-533/
• DoD Guidance for PFAS Analysis in Biota, https://denix.osd.mil/edqw/documents/documents/pfas-biota/
• Air Force, Memorandum: SAF/IE Policy on Perfluorinated Compounds (PFCs) of
Concern, 11 August 2016
• EPA Fact Sheet - PFOA & PFOS Drinking Water Health Advisories, May 2016, EPA
800-F-16-003
• Guidance for Conducting Remedial Investigations and Feasibility Studies Under
CERCLA, EPA/540/G-89/004, October 1988
• Drinking Water Health Advisory for Perfluorooctane Sulfonate (PFOS), EPA, EPA822-
R-16-004, May 2016
• Drinking Water Health Advisory for Perfluorooctanoic Acid (PFOA), EPA, EPA822-R-
16-005, May 2016
• Regional Screening Levels, USEPA https://www.epa.gov/risk/regional-screening-levels-rsls Semiannual Revisions
• EPA, Integrated Risk Information System (IRIS), https://www.epa.gov/iris
• EPA, Provisional Peer-Reviewed Toxicity Values (PPRTVs), https://www.epa.gov/pprtv
• Memorandum regarding Interim Recommendations to Address Groundwater
Contaminated with Perfluorooctanoic Acid and Perfluorooctanesulfonate, U.S. EPA
Office of Land and Emergency Management, Directive No. 9283.1-47 (USEPA, Dec
2019)
• Risk Assessment Guidance for Superfund - Parts A, B, D, E, and F (USEPA, December
1989, December 1991a, December 2001, July 2004, and January 2009, respectively).
DRAFT
https://www.denix.osd.mil/edqw/home/ https://denix.osd.mil/edqw/documents/documents/epa-method-533/ https://denix.osd.mil/edqw/documents/documents/pfas-biota/ https://www.epa.gov/risk/regional-screening-levels-rsls https://www.epa.gov/risk/regional-screening-levels-rsls https://www.epa.gov/iris https://www.epa.gov/pprtv
28 March 2023 https://www.epa.gov/risk/risk-assessment-guidance-superfund-rags-part
• Role of the Baseline Risk Assessment in Superfund Remedy Selection Decisions
(USEPA, April 9 1991)
• Guidance for Data Usability in Risk Assessment (Parts A and B) (USEPA, December
1991b 11 and May 1992a)
• Guidelines for Exposure Assessment (USEPA, May 1992b)
• Guidelines for Human Exposure Assessment, EPA/100/B-19/001, October 2019
• Land Use in the CERCLA Remedy Selection Process (USEPA, May 1995)
• EPA Risk Characterization Program (USEPA, March 1995)
• Supplemental Guidance for Developing Soil Screening Levels for Superfund Sites
(USEPA, 16 December 2002a)
• Calculating Upper Confidence Limits for Exposure Point Concentrations at Hazardous
Waste Sites (USEPA, December 2002b)
• Human Health Toxicity Values in Superfund Risk Assessments, Office of Solid Waste and Emergency Response (OSWER) Directive 9285.7-53 (USEPA, December 2003).
• Guidelines for Carcinogen Risk Assessment (USEPA, March 2005a)
• Supplemental Guidance for Assessing Susceptibility from Early-Life Exposure to
Carcinogens (USEPA, March 2005b)
• Exposure Factors Handbook: 2011 Edition (USEPA, September 2011)
• Human Health Evaluation Manual, Supplemental Guidance: Update of Standard Default
Exposure Factors (USEPA, February 2014)
• Determining Groundwater Exposure Point Concentrations, OSWER Directive 9283.1-42, (USEPA, February 2014)
• ProUCL Version 5.1 Technical Guide Statistical Software for Environmental
Applications for Data Sets with and without Nondetect Observations (USEPA, October
2015)
• Ecological Risk Assessment Guidance for Superfund: Process for Designing and
Conducting Ecological Risk Assessments, Interim Final (EPA, 1997b)
• Guidelines for Ecological Risk Assessment (EPA, 1998b)
• EPA EcoUpdate Series (EPA, 1991-2008, http://www.epa.gov/oswer/riskassessment/ecoup)
• ASTM E1689-95 Standard Guide for Developing Conceptual Site Models for
Contaminated Sites, 1 January 2014
• Superfund Removal Guidance for Preparing Action Memorandum, (EPA September
2009)
• Guide to Preparing Superfund Proposed Plans, Records of Decision, and Other Remedy
Selection Decision Documents, EPA 540-R-98-031 (USEPA Jul 1999)
• The Role of Screening-Level Risk Assessments and Refining Contaminants of Concern in Baseline Ecological Risk Assessments (EPA, June 2001)
• Supplemental Guidance to ERAGS: Region 4, Ecological Risk Assessment (EPA, March
2018)
• Superfund Accelerated Cleanup Models (EPA, April 1992) https://www.epa.gov/risk/risk-assessment-guidance-superfund-rags-part http://www.epa.gov/oswer/riskassessment/ecoup
28 March 2023
The Contractor shall be responsible for identifying and complying with all applicable requirements as they pertain to the project requirements for this TO.
3.0 TASK ORDER MANAGEMENT, PLANNING, AND REPORTING SERVICES.
The Contractor shall plan project activities, including the development, implementation, and maintenance of project schedules, events, status of resources, report(s) on the activities, and progress toward accomplishing project objectives. The Contractor shall document for government review and approval the results of the project efforts for this TO.
3.1 Project Web Site.
Establish a project web site, in collaboration with the Air Force technical team, with real-time worldwide access available to government personnel and other project stakeholders approved by
AFCEC. The website will consist of items such as a deliverable tracker, project data/deliverables, a task order specific Request for Information (RFI) tracker, a photo log, project schedule, meeting minutes, issues/risk identification and resolution, and project status for
TO. Information Assurance (IA) requirements for DoD information systems and/or data storage must meet the Technical security requirements of the DoD/AF environment and is the responsibility of the service provider to meet the mandates defined in Department of Defense
Instructions (DoDI) 8510.01 dated 28 Nov 07. Responsibility for procedural and administrative security is shared between the service provider and the supported entity contracting for the service and must meet the Defense Information System Agency (DISA) Best Security
Practices. (Contract Data Requirements List [CDRL] A001A)
3.2 Work Breakdown Structure Requirements.
Prepare and submit for government approval a Work Breakdown Structure (WBS). The WBS shall be used to report the cost and schedule status for this project. All tasks required under this
TO shall be included in the WBS. (CDRL B001)
3.3 Schedule and Planning Requirements.
Develop, submit, and maintain schedules for tracking work progress, as specified in this TO.
3.3.1 Project Planning Chart. Not Applicable to this TO.
3.3.2 Integrated Master Schedule.
Prepare and submit an Integrated Master Schedule (IMS) for approval. The IMS shall detail the project schedule and status through the use of Gantt charts and Critical Path Method (CPM) analyses. Schedule activities shall be reported by the approved WBS. The Contractor shall prepare the IMS in accordance with the IMS Instructions. (CDRL B003)
3.4 Cost and Status Reporting.
Prepare and submit progress reports, as specified in this TO.
28 March 2023
3.4.1 Contractor’s Progress, Status, and Management Report.
Prepare and submit a monthly Contractor Progress, Status, and Management Report (CPSMR).
The CPSMR shall be used to review and evaluate the overall progress of the project, along with any existing or potential problem areas. The CPSMR shall include a summary of the events that occurred during the reporting period, discussion of performance, identification of problems, proposed solutions, corrective actions taken, and outstanding issues. (CDRL B004)
3.4.2 Performance and Cost Report. Not Applicable to this TO.
3.4.3 Funds and Man-Hours Expenditure Report.
Implement and maintain a cost accounting system and prepare a Funds and Man-Hours
Expenditure Report (FMER) to correlate the status of expensed funds and man-hours against the progress of the work completed and the negotiated budget. The FMER and associated graphics shall detail the current project status and identify funds and man-hours required to complete the assigned tasks. (CDRL C002)
3.5 Photo Documentation.
Include digital photo documentation as part of deliverables, specified in this TO, where appropriate. The Contractor shall include photo documentation of site(s) and building(s) under investigation, field activities, and sample locations. All photography shall be coordinated/approved by the AF or appropriate property owners. (CDRL B005)
3.6 Task Order Scoping.
Perform TO scoping and plan development services (see RI scoping section 9.4.2). Specifically, the goals are to complete surveys to enable preliminary scoping of project issues and to develop and/or confirm Data Quality Objectives (DQOs). Visit the assigned site(s) and make all preliminary studies of the site/facility locations and accessibility such as identification and condition of existing wells; number of wells requiring redevelopment; number of project locations; number and type of personnel required; number and type of site(s) and supporting data desired; special or modified project capabilities, issues, and procedures required; equipment required; and type of procedures to ensure that the project activities comply with applicable requirements. (CDRLs A002)
3.7 Environmental Resources Program Information Management System (ERPIMS)
Data Management.
Comply with the Environmental Resources Program Information Management System
(ERPIMS) data deliverable requirements for all field-derived data/information supported by
ERPIMS data structure including, but not limited to, sampling data, relevant QA/QC data, lithology, groundwater, monitoring well location, well installation, well maintenance, and/or abandonment information. After receipt of the contract, the Contractor shall submit an ERPIMS
Data Submission Schedule (CDRL B006A) within 30 days of award to establish the projected
28 March 2023 framework for ERPIMS data submissions. The Contractor shall record and enter field and laboratory data and submit this data as specified in the latest ERPIMS Data Loading Handbook
(DLH) using the latest version of the ERPIMS software utility (ERPTools). ERPIMS data submissions (CDRL B006B) are required within 90 days of sample collection unless a written waiver or extension is obtained from the CO in coordination with the AFCEC. The AFCEC website offers the latest DLH, ERPTools client software, ERPIMS policy, ERPIMS Help Desk contact info, data submission requirements, ERPTools training schedules, and more. Data submissions shall be error-free, pass all validation checks and fully comply with the ERPIMS
DLH. The Contractor shall ensure that any required corrections are accomplished within both this contract POP and before funding expiration. The preferred procedure is for laboratories to use ERPTools to input/submit chemistry data for initial validation, import, and submission by the
Prime Contractor. ERPTools training is available to prime and laboratory contractors.
3.8 Meeting and Conference Services.
Provide support for meetings and conference services, as specified in this TO.
3.8.1 Meeting/Teleconference Support.
Attend and/or support meetings and teleconferences as required by the Contracting Officer’s
Representative (COR) with the customer and/or government representative(s). The purpose of the meetings is to facilitate and discuss activities such as contract discussions, progress reviews, project scoping, planning, remedial investigation (RI) scoping and activities, risk assessment activities, removal actions, design reviews, planning/programming charrette activities, project definition charrette activities, design charrette activities, construction reviews, project status, and the general exchange of information concerning current and future activities. It is anticipated for bidding purposes that meeting participation and facilitation will include:
• 1 onsite technical meetings per year
• 1 teleconference per week
• 2 Program Management Reviews in San Antonio per year
Prepare and submit for approval presentation materials, agendas, and minutes for all meetings, at the request of the COR. (CDRLs B007, B008, and B009)
3.8.2 Public Meetings and Hearings.
Present technical information and provide logistical support (e.g., facilities, audiovisual, handouts, report(s), recordings, verbatim transcripts, translations, slides, synopsis) for events and/or meetings such as Restoration Advisory Board (RAB) meetings or other meetings in support of status reviews, RI scoping, the government’s position, or a decision documents.
Ensure that all required parties are included in public meeting, to include a court reporter, if needed.
It is anticipated for bidding purposes that public meeting participation and coordination will include:
28 March 2023
• 2 onsite meetings
• 2 presentations
Prepare and submit for approval presentation materials, agendas, and minutes for all public meetings and hearings, at the request of the COR. (CDRLs B007, B008, B009)
3.8.3 Conference and Event Support. Not Applicable to this TO.
3.9 Regulatory/Professional Interface.
Assist with oral/written interaction with interested parties related to the project. Forums may include administrative proceedings, judicial proceedings, regulatory and professional formal and informal meetings such as RI scoping, BRAC Cleanup Team, etc. Prepare products such as presentation materials, agendas, minutes, publications, news releases, public notices, and the maintenance of mailing list(s).
It is anticipated for bidding purposes that meeting participation and facilitation will include:
• 2 onsite regulatory meetings per year
• 6 teleconferences per year
Assist in project technical review, analysis, and discussions to integrate comments from regulators, other stakeholders, and interested parties on programs and related data and studies.
Develop options for responses and prepare report(s) to communicate government priorities to regulatory agencies and other interested parties.
Assist with the review and interpretation of new statutory and regulatory requirements and make recommendations for planning and integration as it applies to the assigned project and this TO.
(CDRLs A001B, B007, B008, B009)
3.10 Notification Requirements.
Notify the Contracting Officer (CO) and COR of critical issues that may affect the contract performance and/or human health and the environment. The types of issues that require notification include, but are not limited to, health risks, spills, unexpected utility crossings, unusual weather conditions, unacceptable materials, changes in critical personnel, and
Unexploded Ordnance (UXO). As an example, if unanticipated UXO was discovered during field activities, the Contractor would be required to immediately stop work, report the discovery to the COR, and implement the appropriate safety precautions. Commencement of field activities could not continue until clearance was received from the CO. On critical issues, oral notification should be made immediately, followed by written notification within three calendar days. (CDRL A003)
3.11 Work Site Coordination.
Coordinate work site activities to ensure the protection of human health and the environment; the prevention of damage to property, utilities, materials, supplies, and equipment; and the avoidance of work interruptions.
28 March 2023
Conduct work in compliance with the DoD environmental policy and guidance. The Contractor must comply with Occupational Safety and Health Administration (OSHA) safety and health regulations and local safety office requirements. The Contractor is required to provide the CO and COR copies of any OSHA report(s) submitted during the duration of this TO. (CDRL
A004)
3.12 Spatial Data (Map) Requirements.
All products associated with this contract that provide a map representation of the location of installation features (historical, existing, or planned) including installation maps, site plans, area development plans, walls-out as-built depictions, or other related overhead (plan) views of an installation (partial or entire) must adhere to the following requirements. (NOTE: This requirement does not currently involve walls-in facility floor plans or interior renderings.)
All maps and associated data must comply with the latest version of Spatial Data Standards for
Facilities, Infrastructure, and Environment (SDSFIE) available from the SDSFIE web site. The
SDSFIE web site address will be provided under separate cover at the task order level. These data will be organized using the current version of the standard approved by the Headquarters
Air Force Geo Integration Office (HAF GIO) as the functional lead for installation mapping and visualization. The SDSFIE will determine file and feature class identification and definition, attribution and valid domain values. When any geospatial information collected as a result of the contract includes information identified in the Common Installation Picture (CIP) or recognized
Mission Data Set (MDS) the Contractor will deliver data consistent with the established requirements for the data and will ensure functionality with the receiving system. Information must be collected at no less than 1:1200 scale for base cantonment areas and 1:4800 scale for larger undeveloped base areas. Spatial data will meet or exceed National Map Accuracy
Standards at those scales. Metadata will be provided and will use Federal Geographic Data
Committee (FGDC) Content Standards for Digital Geospatial Metadata (CSDGM) for organization.
Geospatial data must be delivered in a geo-referenced GIS (Geographic Information System) format (feature-based file structures with one-to-one cardinality between spatial records and attribute records) which would include Environmental Systems Research Institute’s (ESRI) shapefile and geodatabase formats. All attribute data as specifically outlined in the task order contract must be included either in the GIS data file or as a separate table with a SDSFIE key variable that may be used to relationally join the separate table with the GIS data file. All geospatial data must be delivered in the North American Datum 1983 (NAD83) projection, State
Plane Coordinate System, using feet or metric coordinate units. Further guidance on mapping units, coordinate systems and projections is available from the Installation GIO.
Mapping- or Survey-Grade Global Positioning Systems (GPS) or comparable traditional survey methods will be used to collect geospatial data. The use of mapping- or survey-grade GPS will depend on the precision requirements of the product data. These requirements will be specified later in this SOW for all contract activities where geospatial data are involved. In the case of contracts involving utility construction, location and attribute data will be obtained at the time of
28 March 2023 excavation. Further information about precision requirements should be obtained from the installation GIO.
Source data and product data remain the property of the US Government. The Contractor may be required to explain and demonstrate the company's process for protecting all geospatial data, including but not limited to geometry, attributes, metadata, topologies, and relational database schemas and operations used in association with this SOW. The Contractor may be required to sign a non-disclosure agreement attesting to the same before source data are released. Further information about security and nondisclosure requirements should be obtained from the installation GIO. Some installation map data, source and/or product, may be considered by the government to be “sensitive, but unclassified.” The intent of this clause is to prevent intentional or unintentional dissemination of “sensitive, but unclassified” information to include unauthorized access to the source and product data by any entity wishing to do harm to the
USAF or United States Government while the data resides on the contractor's computer network.
The contractor is not authorized to release this information to any third party without the explicit consent of the Headquarters Air Force Office of the Civil Engineer (AF/A7C) or its involved installation. All source information must be returned to the government POC or destroyed upon completion of this project. (CDRL A005)
4.0 TASK ORDER PROJECT PLAN DEVELOPMENT SERVICES.
Project and/or site-specific planning documents and development requirements are required under this TO. Plans must comply with the specifications, procedures, and methodologies (such as approved Federal Facilities Agreements [FFAs]) in the site/project specific plan(s). Project plans may include any of the following as appropriate to this TO. The COR shall approve (in writing) any proposed modification to, or deviation from, any activity described in these documents, following approval by the CO.
4.1 Quality Program Plan (QPP).
4.1.1 General.
The goal of the QPP is to develop project specific DQOs in consensus with the restoration project team to ensure data of adequate quality are collected to support project decisions.
Prepare and update the QPP according to the Uniform Federal Policy (UFP) Quality Assurance
Project Plan (QAPP) using Optimized UFP-QAPP Worksheets (United States Environmental
Protection Agency [EPA], March 2012) and EPA Guidance on Systematic Planning Using the
Data Quality Objectives Process, February 2006.
QPP includes the Work Plan (WP), Field Sampling Plan (FSP), Sampling and Analysis Plan
(SAP), and the Health and Safety Plan (HSP) (as required by 29 Code of Federal Regulations
(CFR) 1910.120. Maintaining and updating the QPP is required to ensure data quality and usability throughout the TO.
The current version of the UFP-QAPP Worksheets, QSM and General Data Validation
Guidelines can be found at the following website: https://www.denix.osd.mil/edqw/home/ .
https://www.denix.osd.mil/edqw/home/
28 March 2023
4.1.2 Work Plans (WPs).
Prepare WPs in UFP QAPP format to meet DQOs to accomplish the TO goals and to comply with DoD, USAF, USEPA, state, and local regulations. (CDRLs A007)
4.1.3 Health and Safety Plan (HSP).
Prepare an HSP to comply with Air Force, OSHA, USEPA, state, host nation, and local health and safety regulations utilizing existing documentation to the extent practical to comply with Air
Force, OSHA, USEPA, state, and local health and safety regulations regarding the proposed work effort. The Contractor shall use USEPA guidelines for designating the appropriate levels of protection needed at the study sites as applicable. The Contractor shall maintain written certification that the approved HSP has been reviewed with all personnel that work at the project site prior to their mobilization. (CDRL A008)
4.1.4 Sampling and Analysis Plan (SAP).
Prepare SAPs covering all applicable methods and activities employed as part of the well installation, sampling, quality control/quality assurance (QA/QC), analytical data requirements such as data validation and data usability, and other activities required such as sampling of groundwater, sediment, soil, soil pore water, surface water, drinking water, and tissue. Research and use existing documentation to the extent practical. The SAP includes the FSP. Prepare project/site specific addenda to capture additional activities during the TO. (CDRL A009)
4.1.5 Construction Quality Plan (CQP). Not Applicable to this TO.
4.2 Design Work Plan. Not Applicable to this TO.
5.0 MANAGEMENT OF CHEMISTRY SERVICES.
The goal of chemistry services management is to ensure the quality of all required chemistry services performed and that all chemistry-related tasks are conducted in accordance with the
DoD practices such as method-specific requirements, DoD Quality Systems Manual, data validation requirements, and QPP.
Identify a Project Chemist as one of the key personnel in the project QPP. The Project Chemist will act as a POC on all chemistry related issues and shall be responsible for ensuring that all
DoD practices and the DQOs are met and corrected where necessary.
5.1 Quality Assurance.
Adhere to project specific DQOs to ensure data of adequate quality are obtained such that decisions are made with technically defensible data of known and documented quality. The
Contractor shall ensure that analytical laboratories maintain accreditation under the DoD
Environmental Laboratory Accreditation Program (ELAP) to DoD Quality Systems Manual for
Environmental Laboratories (QSM) accreditation ), version 5.1 or newer, and meets all state and
28 March 2023 federal requirements, for the project matrices and methods throughout the contract and achieve target analyte levels to meet data quality objectives such as detections limits, limit of detections
(LODs), and limits of quantitation. DQOs shall be developed in consensus with the restoration project team and in accordance with USEPA QA/G4, Guidance for the Data Quality Objective
Process (most recent version), DoD/Air Force policy and guidance, and documented in the project QPP. Incorporate QA/QC requirements identified by the current version of the
Department of Defense (DoD) Quality Systems Manual, DoD general and method-specific validation guidelines, and DoD guidance in the QPP. PFAS analysis for all matrices (i.e., groundwater, surface water, soil, and sediment) shall be performed by a DoD ELAP accredited laboratory using a liquid chromatography tandem mass spectrometry (LC/MS/MS) method that is on the laboratory’s DoD ELAP scope of accreditation and is compliant with the requirements in the DoD QSM (version 5.3 or most current) for Environmental Laboratories, Table B-15.
The Contractor shall ensure that project decisions will be supported by data usability determinations aided by the results of data validation. The Contractor shall be responsible for assessing the environmental data’s quality by performing data validation against criteria established within the analytical method, the DoD QSM, the DoD General Data Validation
Guidelines, and the UFP QAPP. It is anticipated that data validation is performed by a party independent of the laboratory. The website address is https://www.denix.osd.mil/edqw/home/.
Conduct all laboratory services in accordance with the approved project QPP. Samples shall not be submitted for analysis until the QPP is approved by AFCEC. It is expected that the QPP include requirements for analytical reporting, data validation and procedures, and data usability assessments including:
• Performance of Stage 4 validation on 10 percent of each sample delivery group (SDG), and Stage 2B validation on 90 percent of each SDG
• Performance of Stage 4 validation on 100 percent of any drinking water data (includes groundwater from private and public wells)
Any validation that reveals significant deviations from project requirements will require a higher stage of validation to uncover the source.
Meet target analytical control limits for all media in accordance with DoD QSM. It is expected that quality control samples will be collected at a rate of 10% for sample replicates and at a rate of 20% for matrix spikes. Ensure that laboratory QA/QC adjusts to developing DoD, Air Force, or regulatory requirements or standards.
As part of the QPP, prohibit products containing PFAS such as Teflon, Tyvek suits, and Decon
90 to avoid cross contamination issues during the sampling and analysis.
Ensure that all requirements specified in the project QPP are met. If not met, the Contractor may be required to re-accomplish sampling and analysis at the Contractor’s expense.
5.2 Laboratory Selection.
Select a laboratory accredited under the DoD Environmental Laboratories Accreditation Program https://www.denix.osd.mil/edqw/home/
28 March 2023
(ELAP) for the most current version of the QSM and maintains the current QSM accreditation for all methods and matrices specified in the QPP throughout the period of performance. Select a laboratory with analytical capabilities sufficient for the methods specified in the QPP and adequate throughput capacity to handle the project’s analytical workload during all field activities. The accreditation shall include required state laboratory accreditation where appropriate.
New or improved PFAS analytical methods are likely to come into existence in the near future.
Prior to use for PFAS analysis, the laboratory must be DoD ELAP accredited, have the method and reported analytes on the laboratory’s DoD ELAP scope of accreditation, and be in compliance with the version of the DoD QSM to which the laboratory is accredited.
If necessary, the Contractor may establish an onsite laboratory at the project site. On-site test laboratories shall be accredited under DoD ELAP, including accreditation for the project media and methods, and must meet all state and federal requirements, including state certifications where appropriate.
5.3 Analytical Data Management.
Ensure that all hard copy and electronic data deliverables supplied by the laboratory are complete and adequate to support the quality and usability of the data. Submit raw data packages to
AFCEC. Data packages shall meet DoD, Air Force, and federal and state standards. Include all validation and information required to recreate the analysis, such as correspondence with the laboratory regarding Quality Assurance and Quality Control (QA/QC) measurements, deviations, exceedances and documentation of corrective actions. The Contractor shall meet ERPIMS data deliverable requirements (see Section 3.7). Hard copy reports must be Level IV reports with
QA/QC results, chromatographs, and manual integrations completed during analysis. (CDRL
A012)
PART C – PLANNING SERVICES
The Contractor shall provide A-E services in support of installation planning and programming activities. Planning activities may include those activities necessary to assess and manage environmental implications and conditions of installation activities as well as planning associated with managing the installation and its associated infrastructure.
6.0 ENVIRONMENTAL PLANNING AND PROGRAMMING
The Contractor shall develop, update, integrate, publish and present environmental planning and programming services, as specified in this TO.
6.1 Professional Planning and Programming. Not Applicable to this TO.
6.2 Environmental Baseline Surveys (EBSs). Not Applicable to this TO.
6.3 Environmental Impact Analysis Process (EIAP). Not Applicable to this TO.
6.4 Air Traffic and Airspace Analysis. Not Applicable to this TO.
6.5 Airfield and Airspace Obstruction Analysis. Not Applicable to this TO.
28 March 2023
6.6 Natural and Cultural Resources. Not Applicable to this TO.
6.6.1 Cultural Resources. Not Applicable to this TO.
6.6.2 Natural Resources. Not Applicable to this TO.
6.6.3 Integrated Natural Resource Management Plan (INRMP). Not Applicable to the
TO.
6.7 Noise Management. Not Applicable to this TO.
6.8 Permits and Site Access Agreements.
At the direction of the government, support the identification and procurement of access agreements and or rights of entry necessary to implement this project. Support the identification and procurement of permits, utility clearances, etc. to implement this project. It is expected that this effort will include activities such as:
• Maintaining all needed permissions and clearance to areas such as remedial investigation areas, as these areas may be on active airfield, other secured areas, private well locations, or private property. For private property the Contractor activities shall be at the direction of the government. Prior to work being performed on private property, the government will obtain permissions for site access; in some instances, this could take up to eight weeks or more.
• Determining and obtaining all required site-specific training needed to access and work on sites
• Coordinating and scheduling work and area access with the BRAC Environmental
Coordinator (BEC) or his local representative and with the current property owners
• Preparing Federal Aviation Administration (FAA) obstruction clearance permits for work within the active airfield
• Supporting coordination with authorities for access at cultural and natural resource areas
• Providing metes and bounds survey(s) as required to establish easements on the property utilizing a registered land surveyor (CDRLs A001C)
6.9 Project Environmental and Land Use Plans. Not Applicable to this TO.
6.10 Asset Management Planning. Not Applicable to this TO.
PART D – ENVIRONMENTAL SERVICES
Title I and Other Environmental A-E Services are anticipated for environmental projects, including those related to environmental restoration as identified in this SOW. For environmental services, all on-site workers (contractor and subcontractor) performing hazardous operations, including working with hazardous materials, must have completed the OSHA
1910.120 Hazardous Waste Operations and Emergency Response (HAZWOPER) training and/or other applicable training as appropriate to project location (Continental United States), plus annual refresher courses. The Contractor shall maintain documentation supporting training records and have the site-specific HSP on site, available for workers and/or regulatory review.
28 March 2023
7.0 TITLE I SERVICES FOR ENVIRONMENTAL PROJECTS. Identified at a later date, if applicable
7.1 Design Overview.
The objective of the design project is to complete the design of a practical, implementable, and effective system to meet project remedial action objectives and cleanup goals. The government shall provide pertinent and available background information concerning the project.
Designs specified in this contract are to be identified at a later date. This could include activities such as interim remedial actions, removal actions, new construction, upgrades, maintenance, or repair to reduce an imminent threat to human health or the environment, manage migration, and stabilize the site. Designs shall comply with the DoD policy, federal, state and local requirements. The design projects could include interim remedial actions such as the upgrade and/or expansion of existing remedial systems and/or new remedial systems.
• Design elements to be identified at a later date.
7.1.1 Cost Estimates.
As part of any design identified at a later date, develop a detailed cost estimate for construction and implementation of the project with detailed labor, material, subcontractor, and other costs using an accepted industry standard format (we recommend the current constructions standards institute [CSI] format).
Develop life cycle cost estimates for planning and budgeting. These cost estimates shall detail, by fiscal year, the various development, construction, O&M, and LTM costs.
7.1.2 Design Plans and Specifications.
Develop clear and comprehensive design plan(s) and specifications with a supporting Design
Analysis or Basis of Design Report as identified at a later date if required. Include critical information like the design basis, discussion of technical factors, design assumptions, detailed engineering drawings, equipment tables, material tables, permits required, submittal register(s), appendices with data and calculations, and any applicable LEED™ documentation.
7.1.3 Operations and Maintenance Plan.
As part of any design effort identified at a later date, develop an Operations and Maintenance
(O&M) Plan to cover both implementation and long-term maintenance. The plan shall include documentation for the comprehensive system, not simply for each component. Include information such as the start-up procedures and sampling requirements, specifications, description of normal O&M, potential problems, contingencies, description of equipment, routine testing requirements, replacement parts and sources, and other industry standard requirements.
28 March 2023
7.1.4 Project Schedule.
As part of any design effort identified at a later date, develop a project schedule for construction and implementation.
7.2 Environmental Design Reviews.
The design and design criteria shall be submitted for review to support any activities included at a later date. Disposition of the comments shall be determined at the respective review meeting and the results shall be incorporated into the next required design phase submittal. The specific requirements for each design phase will be identified at a later date.
8.0 TITLE II SERVICES FOR ENVIRONMENTAL PROJECTS. Not Applicable to this
TO.
8.1 Construction Submittal Review. Not Applicable to this TO.
8.2 Design Update. Not Applicable to this TO.
8.3 Evaluation of Ongoing Actions. Not Applicable to this TO.
8.4 Field Oversight. Not Applicable to this TO.
8.5 Inspections. Not Applicable to this TO.
8.6 Submittal Register Review. Not Applicable to this TO.
8.7 Treatment, Storage, and Disposal Facility Audits. Not applicable to this TO.
9.0 OTHER ENVIRONMENTAL A-E SERVICES.
Provide a full range of environmental services in support of the work specified as necessary for the implementation of environmental restoration projects. The intent is that contractor maintains the latest scientific knowledge of per- and polyfluoroalkyl substances (PFAS) such as source attribution; PFAS fingerprinting; new or changing analytical methodologies; DoD, Air Force and regulatory policy, guidance and requirements; toxicity criteria and ecological benchmarks; and…