Perfomance Work Statement_Repair Fire Department Heat Pump.pdf
PDF 528 KB Posted
- Attached to
- 157 ARW Heat Pump Repair
- Solicitation number
- W50S8A22Q0030
View the file
Other files
| File | Type | Posted |
|---|---|---|
| W50S8A22Q0030_Responses 18 July 22.pdf | ||
| W50S9A22Q0030_Question Responses 23 June 22.pdf | ||
| Provisions and Clauses FINAL.pdf | ||
| WD 2015-4013.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Ver. January 2021
PERFORMANCE WORK STATEMENT (PWS)
FOR
Repair Bldg 243 HVAC, Geothermal Heat Pumps
1.0 General:
1.1 Scope: The contractor shall provide all personnel, equipment, tools, materials, supervision, and quality control necessary, except as specified in Paragraph 3.0 as Government Furnished, to perform services necessary to remove and replace the existing, end-of-life geothermal ground source heat pumps within Bldg. 243 at Pease Air National Guard Base (ANGB), NH as identified by this PWS.
1.1.1 Objectives: Remove and dispose the four (4) existing, end-of-life 130 MBH water-to-water heat pumps, 200 gallon storage tank, and associated pumps and Variable Frequency Drive (VFD), and other associated appurtenances and replace with two (2) new 250 MBH water-to-water heat pumps, new storage tank, and in-line pumps with integral VFD. Contractor will provide operational, safe, complete and usable systems in line with industry standards and within the intent of this project. Perform ancillary tasks necessary to support the work, such as scheduling, work oversight, customer support, cleaning project site daily and coordination with the Base Civil Engineer.
1.2 Background: The 157th Civil Engineer Squadron is in need of HVAC Services. The Fire Department at Pease ANGB has an existing geothermal heat pump system which circulates hot or cold water through an in-floor radiant loop for heating and air handlers for cooling of the main building and vehicle bay. The system is currently comprised of four (4) heat pumps installed in parallel to the loop. All heat pumps in the system are degraded or have failed, and are beyond repair. A natural gas fired boiler has previously been installed, in the place of the fifth, failed heat pump, to supplement the degraded capacity of the heat pumps in the winter, and will remain integrated into the new system permanently. The ground source well water is very corrosive, and the source water coil must be a copper nickel coil to withstand these conditions.
1.3 Period of Performance (PoP): The Period of Performance shall begin once the contract is in effect and completed work is to be accomplished by October 30th, 2022.
1.4 General Information:
1.4.1 Place and Performance of Services: The contractor shall provide services between the hours of 0730-1630 on Monday through Friday, except on recognized US holidays or when the Government facility/installation is closed due to local or national emergencies, administrative closings, or similar Government-directed facility/installation closings. Performance shall be at Pease ANGB, NH, Bldg 243. The contractor shall at all times maintain an adequate work force for the uninterrupted performance of all tasks defined within this PWS when the Government facility/installation is not closed for the above reasons. When hiring personnel, the contractor shall keep in mind that the stability and continuity of the work force are essential.
1.4.1.1 Telework: Teleworking is/is not authorized.
1.4.1.2 Unscheduled gate closures by the Security Police may occur at any time causing all personnel entering or exiting a closed installation to experience a delay. This cannot be predicted or prevented. Contractors are not compensated for unexpected closures or delays. Vehicles operated by contractor personnel are subject to search pursuant to applicable regulations. Any moving violation of any applicable motor vehicle regulation may result in the termination of the contractor employee’s installation driving privileges.
1.4.1.3 The contractor’s employees shall become familiar with and obey the regulations of the installation; including fire, traffic, safety and security regulations while on the installation. Contractor employees should only enter restricted areas when required to do so and only upon prior approval. All contractor employees shall carry proper identification with them at all times, and shall be subject to such checks as may be deemed necessary. The contractor shall ensure compliance with all regulations and orders of the installation, which may affect performance. The Government reserves the right to direct the removal of an employee from Government property or revoke access to Government systems for misconduct, security reasons, or any overt evidence of communicable disease. Removal of contractor employees for reasons stated above does not relieve the Contractor from responsibility for total performance of this contract.
1.4.2 Recognized Holidays: The following are recognized United States (US) holidays.
The contractor shall not perform services on these days:
1.4.3.1 New Year’s Day: January 1st
1.4.3.2 Martin Luther King, Jr.’s Birthday
1.4.3.3 President’s Day
1.4.3.4 Memorial Day
1.4.3.5 Juneteenth Day: June 19th
1.4.3.6 Independence Day: July 4th
1.4.3.7 Labor Day
1.4.3.8 Columbus Day
1.4.3.9 Veteran’s Day: November 11th
1.4.3.10 Thanksgiving Day
1.4.3.11 Christmas Day: December 25th
1.4.3 Quality Control (QC): The contractor shall develop and maintain an effective QC Plan (QCP) to ensure services are performed in accordance with this PWS. The contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. The contractor’s QCP is the means by which it assures itself that its work complies with the requirements of the contract. As a minimum, the contractor shall develop QC procedures that address the areas identified in Technical
Exhibit 1, Performance Requirements Summary (PRS). A final QCP shall be submitted to the Contracting Officer (KO) NLT 10 days after contract award. After acceptance of the QCP, the contractor shall obtain the Contracting Officer’s (KO’s) acceptance in writing of any proposed changes to its QCP.
1.4.5 Access and General Protection/Security Policy and Procedures. The contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the Contracting Officer’s (KO). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the local installation’s Security Forces, Director of Emergency Services or local Security Office. The contractor shall ensure compliance with all personal identity verification requirements as directed by DoD, Headquarters Air Force (HAF) and/or local policy. Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.
1. The contractor shall obtain base identification and vehicle passes, if required, for all contractor personnel who make frequent visits to or perform work on the Air Force installation(s) cited in the contract. Contractor personnel are required to wear or prominently display installation identification badges or contractor-furnished, contractor identification badges while visiting or performing work on the installation.
2. The contractor shall submit a written request on company letterhead to the contracting officer listing the following: contract number, location of work site, start and stop dates, and names of employees and subcontractor employees needing access to the base. The letter will also specify the individual(s) authorized to sign for a request for base identification credentials or vehicle passes. The contracting officer will endorse the request and forward it to the issuing base pass and registration office or Security Forces for processing. When reporting to the registration office, the authorized contractor individual(s) should provide a valid driver s license, current vehicle registration, valid vehicle insurance certificate, and [insert any additional requirements to comply with local security procedures] to obtain a vehicle pass.
3. During performance of the contract, the contractor shall be responsible for obtaining required identification for newly assigned personnel and for prompt return of credentials and vehicle passes for any employee who no longer requires access to the work site.
4. When work under this contract requires unescorted entry to controlled or restricted areas, the contractor shall comply with AFI 31-101, Integrated Defense, and DODMAN5200.02_AFMAN 16-1405, Air Force Personnel Security Program
5. Upon completion or termination of the contract or expiration of the identification passes, the prime contractor shall ensure that all base identification passes issued to employees and subcontractor employees are returned to the issuing office.
6. Failure to comply with these requirements may result in withholding of final payment.
1.4.5.1. Reserved
1.4.5.2 Reserved
1.4.5.3 Antiterrorism Awareness Level I Training (AT Level I). All contractor employees, to include subcontractor employees, requiring access to US Government installations, facilities and controlled access areas shall complete AT Level I training within 15 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. AT Level I may be accomplished by a Level I qualified instructor; completing the Force Protection computer-based training (CBT) course on the Advanced Distributed Learning System (ADLS) or Joint Knowledge Online at http://jko.jten.mil. Tracking for each contractor or subcontractor employee is the responsibility of the KO or unit AT Representative. The contractor shall submit certificates of completion for each affected contractor and subcontractor employee to the KO within 15 calendar days after completion of training by each employee or subcontractor personnel.
1.4.5.4 Reserved.
1.4.5.5 Communications Security/Information Technology (COMSEC/IT) Security. All communications with DoD organizations are subject to COMSEC review. All telephone communications networks are continually subject to intercept by unfriendly intelligence organizations. DoD has authorized the military departments to conduct COMSEC monitoring and recording of telephone calls originating from, or terminating at, DoD organizations. Therefore, the contractor is advised that any time contractor personnel place or receive a call they are subject to COMSEC procedures. The contractor shall ensure wide and frequent dissemination of the above information to all employees dealing with DoD information. The contractor shall abide by all Government regulations concerning the authorized use of the Government's computer network, including the restriction against using the network to recruit Government personnel or advertise job openings.
1.4.5.6 Reserved
1.4.5.6.1 Reserved
1.4.5.6.2 Reserved
1.4.5.6.3 Mark and safeguard files, output products, and storage media per classification level and disseminate them only to individuals authorized to receive them with a valid need to know.
1.4.5.6.4 Reserved
1.4.5.6.5 Reserved
1.4.5.7 Reserved
1.4.5.8 Reserved
1.4.5.9 Reserved
1.4.5.10 Reserved
1.4.5.11 Reserved
1.4.5.12 Reserved
1.4.5.13 Reserved
1.4.5.14 Reserved
1.4.6 Physical Security. The contractor shall safeguard all Government property provided for contractor use. At the close of each work period, Government facilities, equipment and materials shall be secured.
1.4.6.1 Reserved
1.4.7 Special Qualifications: Contractors must ensure that any personnel performing under a contract are fully trained, licensed, certified, and otherwise qualified to provide the desired services.
1.4.8 Post Award Conference/Periodic Progress Meetings: The contractor agrees to attend any post award conference convened by the KO in accordance with FAR 42.5.
The KO and other Government personnel, as appropriate, may meet periodically with the contractor to review the contactor’s performance. At these meetings, the KO will apprise the contractor of how the Government views the contractor’s performance and the contractor shall apprise the Government of problems, if any, being experienced. The contractor shall resolve outstanding issues raised by the Government. Contractor attendance at these meetings shall be at no additional cost to the Government.
1.4.9 Contract Manager (CM): The contactor shall designate a CM who shall ensure performance under this contract. The name of this person, and an alternate who shall act for the contractor when the CM is absent, shall be designated in writing to the KO.
The CM or alternate shall have full authority to act for the contractor on all contract matters relating to daily operation of this contract. The CM shall work through the KO to resolve issues, receive technical instructions, and ensure adequate performance of services. The CM shall ensure that contractor employees do not perform any services outside the scope of the contract without an official modification issued by the KO. The CM shall ensure contractor employees understand that services performed outside the scope of the contract are performed wholly at the expense of the contractor.
1.4.10 Identification of Contractor Employees: All contractor personnel attending meetings, answering Government telephones and working in other situations where their contractor status is not obvious to third parties are required to identify themselves as such to avoid creating an impression that they are Government employees. The contractor shall ensure that all documents or reports produced by contractor personnel are suitably marked as contractor products or that contractor participation is appropriately disclosed. The contractor’s status as a “contractor” shall be predominantly displayed in all correspondence types (to include signature blocks on e-mail) and dealings with Government or non-Government entities. Contractor personnel shall wear identification badges distinguishing themselves as such. The badges shall have the company name, employee name and the word “contractor” displayed.
1.4.10.1 The contractor shall retrieve all identification media (including vehicle passes) from its employees who depart employment for any reason. The contractor shall return all identification media (i.e., badges and vehicles passes) to the KO within 14 days of an employee’s departure.
1.4.11. Combating Trafficking in Persons: The United States Government has adopted a zero tolerance policy regarding trafficking in persons. Contractors and contractor employees shall not engage in severe forms of trafficking in persons during the period of performance of the contract; procure commercial sex acts during the period of performance of the contract; or use forced labor in the performance of the contract. The Contractor shall notify its employees of the United States Government’s zero tolerance policy, the actions that will be taken against employees for violations of this policy. The contractor shall take appropriate action, up to and including termination, against employees or subcontractors that violate the US Government policy as described at
FAR 22.17.
1.4.12 Reserved
1.4.13 Reserved
1.4.14 Organizational Conflicts of Interest (OCI): The contractor and subcontractor personnel performing services under this contract may receive, have access to or participate in the development of proprietary or source selection information (e.g., cost or pricing information, budget information or analyses, specifications or work statements, etc.) or perform evaluation services which may create a current or subsequent OCIs, as defined in FAR Subpart 9.5. The contractor shall notify the KO immediately whenever it becomes aware that such access or participation may result in any actual or potential OCI and shall promptly submit a plan to the KO to avoid or mitigate any such OCI. The contractor’s mitigation plan will be determined to be acceptable solely at the discretion of the KO. In the event the KO unilaterally determines that any such OCI cannot be satisfactorily avoided or mitigated, the KO may impose other remedies as he or she deems necessary, including prohibiting the contractor from participation in subsequent contracted requirements which may be affected by the OCI.
1.4.15 Reserved
2.0 Definitions and Acronyms:
2.1 Definitions:
2.1.1 Contractor: A supplier or vendor awarded a contract to provide specific supplies or service to the Government. The term used in this contract refers to the prime.
2.1.2 Defective Service: A service output that does not meet the standard of performance associated with the PWS.
2.1.3 Deliverable: Anything that can be physically delivered and includes non-manufactured things such as meeting minutes or reports.
2.1.4 Key Personnel: Contractor personnel that are evaluated in a source selection process and that may be required to be used in the performance of a contract by the PWS. When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the persons that are listed in the proposal.
2.1.5 Physical Security: Actions that prevent the loss or damage of Government property.
2.1.6 Quality Assurance: The Government procedures to verify that services being performed by the Contractor are performed according to acceptable standards.
2.1.7 Quality Assurance Surveillance Plan (QASP): An organized written document specifying the surveillance methodology to be used for surveillance of contractor performance.
2.1.8 Quality Control: All necessary measures taken by the Contractor to ensure that the quality of an end product or service shall meet contract requirements.
2.1.9 Subcontractor: One that enters into a contract with a prime contractor. The Government does not have privity of contract with the subcontractor.
2.2 Acronyms:
AEI Army Enterprise Infostructure AR Army Regulation AT/OPSEC Antiterrorism/Operational Security BI Background Investigation CM Contract Manager COR Contracting Officer Representative DA Department of the Army
DD254 Department of Defense Contract Security Classification Specification DFARS Defense Federal Acquisition Regulation Supplement DoD Department of Defense FAR Federal Acquisition Regulation GFP/M/E/S Government Furnished Property/Material/Equipment/Services HQDA Headquarters, Department of the Army HSPD Homeland Security Presidential Directive IA Information Assurance IS Information System(s) KO Contracting Officer NGB National Guard Bureau OCI Organizational Conflict of Interest PII Personally Identifiable Information PIPO Phase In/Phase Out POC Point of Contact PRS Performance Requirements Summary PWS Performance Work Statement QA Quality Assurance QASP Quality Assurance Surveillance Plan QC Quality Control QCP Quality Control Program SCR Service Contract Reporting SSN Social Security Number TE Technical Exhibit USD(I) Under Secretary of Defense for Intelligence
3.0 Government Furnished Property, Material, Equipment and Services (GFP/M/E/S):
The Government will provide the property, material, equipment, and/or services listed below solely for the purpose of performance under this contract:
3.1 Property: The Government will furnish the necessary workspace for the contractor to perform services outlined in this PWS to include a clear workspace surrounding
3.2 Utilities: All utilities in the facility will be available for the contactor’s use in the performance of this contract. The contractor shall instruct employees in utilities conservation practices. The contractor shall operate under conditions that preclude the waste of utilities, which include turning off the water faucets or valves after using the required amount.
4.0 Contractor Furnished Property, Materials, and Equipment (CFP/M/E):
4.1 General: Except for those items specifically stated to be Government-Furnished in Paragraph 3.0, the contractor shall furnish everything required to perform these services as indicated in Paragraph 1.1.
4.2 Reserved
5.0 Requirements:
5.1 The contractor shall:
5.1.1 Accomplish the assigned work by employing and utilizing qualified personnel with appropriate combinations of education, training, and experience. The contractor shall match personnel skills to the work or task with a minimum of under/over employment of resources.
5.1.2 Reserved
5.1.3 Provide all personnel labor, materials, equipment, expertise, and permitting necessary to provide demolition of the existing equipment and installation and commissioning of the new equipment resulting in a fully functional final product in line with the intent of this contract.
5.1.4 Perform ancillary tasks necessary to support the work, such as scheduling, work oversight, customer support, cleaning project site daily and coordination with the Base Civil Engineer.
5.1.5 Provide a work plan to be approved by the Base Civil Engineer prior to performing any work. The work plan will include at a minimum, a work schedule, a list of all major components by make and model, and a written description with drawings of how the new equipment will be integrated into the existing mechanical room space as well as the overall building heating system, specifically detailing connections and modifications to controls enabling the new equipment to function as intended, in concert with the existing system. Any other equipment or mechanical system within the mechanical room that must be altered, removed and reinstalled, or relocated to accommodate the Contractor’s work plan must be reinstalled properly, fully functional and operating as designed, and in compliance with all applicable building codes and industry standards and is within the scope of this project. The work plan should be submitted for acceptance by the Base Civil Engineer prior to any material being purchased.
5.1.6 Commission and operate/monitor the system under load for a 24 hour period.
5.1.7 Provide new as-built drawings depicting all modifications to the mechanical room and specifically to the HVAC system, in PDF and AutoCAD format on a DVD, to supplement the original as-built drawings. Provide an updated version to the written description of the control sequence.
5.1.8 Provide an orientation of operations and maintenance of the new equipment to the Base Civil Engineer maintenance staff as part of the project closeout.
5.1.9 Provide a warrantee of all work for 1 year, in addition to any manufacturer warrantees. Provide all equipment factory warrantee information.
5.2 Product specifications:
5.2.1 Install two (2) new Water-to-Water heat pumps that provide 250 MBH of heating and 260 MBH of cooling at 50°F. The new associated circulators shall deliver 35 GPM to the building loop. New units will connect to the supply and return lines in the same manner/flow direction as the heat pump system which was removed. All new system components shall be fully compatible and integrated to the existing Invensys Controls LonWorks controls systems and shall have full capability to be converted to BACnet controls in the future. New heat pumps should be a Climate Master TMW340BFS20N0C or equivalent (28 Ton, 460v/60/3, R410A, DXM board w/MPC, Ultra quiet cabinet, Copper Nickel source water coil, Copper load coil).
5.2.2 Install new inline pumps with integral VFD replacing original P-1 and P-2. Each new pump shall deliver 93 GPM at 30’ of head and be 480v/3 phase.
5.2.3 Provide a new insulated 200 gallon buffer tank. Tank shall have same connections as the existing tank similar to a low loss header.
5.2.3 Provide expansion tank, makeup water, automatic air vent and all other associated hydronic specialties required for a fully functional heating system.
5.3 Project Specifications:
5.3.1 Site Preparation: Develop and present to the Base Civil Engineer a detailed work plan describing how the four (4) existing heat pumps, 200 gallon storage tank, existing P-1 & P-2 pumps, external P-1 & P-2 VFDs, and associates appurtenances will be isolated from the system and safely removed, and the new equipment will be installed, wired, and controlled.
5.3.2 Scheduling Work: Work should be scheduled to create minimal downtime in the facility heating system, and to occur when the outside temperatures will not fall below freezing. The Fire Department is a 24-hour, emergency response work center, and must remain operational.
5.3.3 Dismantling: Isolate, demolish and remove the four (4) existing heat pumps, 200 gallon storage tank, existing pumps P-1 & P-2, P-1 & P-2 external VFDs, and associates appurtenances. Demolition must be completed in such a way as to not damage or impact the function of the remaining heat pump system components.
System will be installed in a manner that does not impede the functionality or ability to perform maintenance on this or any other mechanical systems in the mechanical room.
5.3.4 Installation: Install two (2) new Water-to-Water heat pumps, associated pumps, buffer tank, and all associated appurtenances. Provide all supports, piping, and insulation. New units will connect to the supply and return lines in the same manner/flow direction as the heat pump system which was removed. Existing wall mounted boiler, associated appurtenances, control panels, and other existing equipment within the mechanical room may need to be relocated/reconfigured inside the mechanical room to install the new heat pumps. Provide expansion tank, makeup water, automatic air vent and all other associated hydronic specialties required for a fully functional heating system. Provide shutoff valves on return and supply piping per 2015 International Mechanical Code Section 1005 page 86. System will be installed in a manner that does not impede the functionality or ability to perform maintenance on this or any other mechanical systems in the mechanical room.
5.4 Project Closeout and Deliverables: The contractor will provide a warranty of all work performed under this contract for 365 days from the date of final acceptance of the project. Any defect of equipment, material, design or workmanship, and further damages caused by these defects, which occur prior to this date, will be the responsibility of the contractor to correct. Contractor will also provide all equipment manuals & specifications, manufacturer warranty information, and up to 8 hours of orientation and training on the new equipment’s operation and maintenance, to Pease ANGB maintenance personnel.
6.0 Applicable Publications: Publications applicable to this PWS are listed below:
Publication (Chapter/Page)
Date of Publication
Mandatory or Advisory
Website
Federal Acquisition Regulation https://www.acquisition.gov/?q=browsefar Defense Federal Acquisition
Regulation Supplement http://www.acq.osd.mil/dpap/dars/dfarspgi/current/in dex.html or https://www.acquisition.gov/dfars Joint Travel Regulation (JTR) https://www.defensetravel.dod.mil/site/travelreg.cfm
DoDM 1000.13-M-V1 DoD Identification (ID) Cards (Enclosure 2, paragraph 3.b)
01/23/2014 (Change 1:
07/28/2020) http://www.esd.whs.mil/Directives/issuances/dodm
Federal Information Processing Standards (FIPS) Publication 201-2 Personal Identity Verification (PIV) of Federal Employees and Contractors
(paragraph 9)
August 2013 http://nvlpubs.nist.gov/nistpubs/FIPS/NIST.FIPS.201 -2.pdf
DoDM 5200.2 Procedures for the DoD Personnel Security Program
(PSP)
04/03/2017 https://www.esd.whs.mil/Directives/issuances/dodm/
DoDI 5200.46 DoD Investigative and Adjudicative Guidance for Issuing the Common
Access Card (CAC)
09/09/14 (Change 1:
05/04/2018) https://www.esd.whs.mil/Directives/issuances/dodi/
Homeland Security Presidential Directive (HSPD)-12
Policy for a Common Identification Standard for Federal Employees and
Contractors
08/27/2004 https://www.dhs.gov/homeland-security-presidential-directive-12
DoDI 5400.11 Department of Defense Privacy and
Civil Liberties Programs
01/29/2019 https://www.esd.whs.mil/Directives/issuances/dodi/
DoD 5400.11-R Department of Defense Privacy
Program
05/14/2007 https://www.esd.whs.mil/Directives/issuances/dodm/
DoDD 8140.01 Cyberspace Workforce Management
10/05/2020 https://www.esd.whs.mil/Directives/issuances/dodd/
DoD 8570.01-M Information Assurance Workforce
Improvement Program
12/19/2005 (Change 4:
11/10/2015) https://www.esd.whs.mil/Directives/issuances/dodm/
DoD 5220.22-M National Industrial Security Program
Operating Manual (NISPOM)
02/28/2006 (Change 2:
05/18/2016) https://www.esd.whs.mil/Directives/issuances/dodm/
AFI 10-245
Antiterrorism
03/28/2013 (Certified current
03/30/2017) https://www.e-publishing.af.mil/Product- Index/#/?view=pubs&orgID=10141&catID=1&series
=-1&modID=449&tabID=131
AFI 31-101
Security Forces Standards and
Procedures
08/18/2020 https://www.e-publishing.af.mil/Product- Index/#/?view=pubs&orgID=10141&catID=1&series
=-1&modID=449&tabID=131
AFMAN 31-113
Security Forces Standards and Procedures
03/05/2013 Change 1:
12/02/2015 https://www.e-publishing.af.mil/Product- Index/#/?view=pubs&orgID=10141&catID=1&series
=-1&modID=449&tabID=131
AFPD 17-1
Information Dominance Governance and Management
04/12/2016 https://www.e-publishing.af.mil/Product- Index/#/?view=pubs&orgID=10141&catID=1&series
=-1&modID=449&tabID=131
AFMAN 17-1301
Computer Security (COMPUSEC) 02/12/2020 https://www.e-publishing.af.mil/Product-
Index/#/?view=pubs&orgID=10141&catID=1&series =-1&modID=449&tabID=131
AFI 10-701
Operations Security
7/24/2019 (Change 1:
06/09/2020) https://www.e-publishing.af.mil/Product- Index/#/?view=pubs&orgID=10141&catID=1&series
=-1&modID=449&tabID=131
TECHNICAL EXHIBIT 1
Deliverables Schedule
(Deliverables must be identified in the PWS and then summarized here. See examples below)
PWS Reference / Deliverable Title
Frequency Number of Copies
Medium/Format Submit To
1.4.5.3 AT Level 1
Awareness Training
Certificates
Provide within 15 calendar days after employee completes training.
1 Electronic Submission
KO
1.4.10 Identification
Media
Return within 14 days of employee’s departure from contract performance.
Original(s) Hard Copy KO
5.1.5 Work Plan to be submitted
NLT 15 days prior to the start of performance
1 Hard Copy/Electronic
Submission
KO
5.1.7 As-built drawings submitted
NLT 15 days prior ot he start of performance
1 Hard Copy/Electronic
Submission
KO
5.4 All equipment
manuals & specifications, manufacturer warranty information
Upon completion of installation
1 Hard copy KO
5.4 Maximum 2
hours of orientation and training on the new equipment operation and maintenance to Pease ANGB personnel.
Upon completion of Installtion
1 In person meeting
KO