This document outlines road maintenance requirements for a stewardship contract to be awarded by the Department of Agriculture Forest Service Rocky Mountain Region. The contractor will be responsible for pre-haul, during haul, and post-haul maintenance of approximately 19 miles of roads, including slide and slump repair, ditch cleaning, surface blading, drainage structure maintenance, and roadway vegetation maintenance. The contract also requires felling of timber on 331 acres and removal of sawtimber and non-sawtimber. The estimated period of performance is from July 16, 2020 to August 30, 2024. A pre-solicitation meeting will be held on October 9, 2019 and questions must be directed in writing to the contacts provided.

DRAFT - Appendix C

View the file

Other files for this federal contract opportunity

Other files attached to Pearl Cache Stewardship, newest first.
File Type Posted
Pre-Sol_Sign-In___Pearl_Cache.pdf PDF
DRAFT_-_Map___Pearl_Cache.pdf PDF
DRAFT_-_Appendix_B___Pearl_Cache.pdf PDF
DRAFT_-_Solicitation___Pearl_Cache.pdf PDF
DRAFT_-_Appendix_A___Pearl_Cache.pdf PDF
Pre-Sol___Pearl_Cache.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DRAFT Pearl Cache Stewardship Appendix C

APPENDIX C - ROAD MAINTENANCE REQUIREMENTS

Contractor shall maintain roads in accordance with the following Contract Road Maintenance Requirements Summary:

Contractor will be responsible for doing all pre, during and post haul road maintenance.

Termini Applicable Pre-Haul Road Maintenace Specifications

Road From To Miles T-

T-801 T-

T-

T-

T-

NFSR 169 Junction w/

LCR 86

Junction w/

NFSR 175

3.6 C C C C C

NFSR 173 Junction w/

LCR 86

Junction w/temp rd. into

20A

3.6 C C C C C

NFSR 175 Junction w/

NFSR 169

Termination Pt.

in unit 6B

0.8 C C C C C

NFSR 300 Junction w/

LCR 86

Termination Pt.

@ intersection w/ Killpecker

Trail

6.4 C C C C C

NFSR 300.A Junction w/

NFSR 300

Termination Pt.

at northern boundary of Unit 25A

0.2 C C C C C

NFSR 333 Junction w/

NFSR 300

Termination Pt.

at temp. rd. for unit 23

0.2 C C C C C

NFSR

175.1A

Junction w/

NFSR 175

Termination Pt.

in unit 6A

0.2 C C C C C

*NFSR 169 Junction w/NFSR 175

Junction w/

LCR 80C

11.7 C C C C C

*If Contractor elects to haul this direction, maintenance requirements apply to the section of road that hauling occurs on. Line Items 006 and 007 lump sum payment applies

Termini Applicable During Haul Road Maintenace Specifications

Road From To Miles T-

T-801 T-

T-

T-

Junction w/

NFSR 175

3.6 C C C C C

NFSR 173 Junction w/

LCR 86

Junction w/temp rd. into

20A

3.6 C C C C C

NFSR 175 Junction w/

NFSR 169

Termination Pt.

in unit 6B

0.8 C C C C C

NFSR 300 Junction w/

LCR 86

Termination Pt.

@ intersection w/ Killpecker

Trail

6.4 C C C C C

NFSR 300.A Junction w/

NFSR 300

Termination Pt.

at northern boundary of Unit 25A

0.2 C C C C C

NFSR 333 Junction w/

NFSR 300

Termination Pt.

at temp. rd. for unit 23

0.2 C C C C C

NFSR

175.1A

Junction w/

NFSR 175

Termination Pt.

in unit 6A

0.2 C C C C C

*NFSR 169 Junction w/

NFSR 175

Junction w/

LCR 80C

11.7 C C C C C

*If Contractor elects to haul this direction, maintenance requirements apply to the section of road that hauling occurs on. Line Items 006 and 007 lump sum payment applies

Termini Applicable Post Haul Road Maintenace Specifications

Road From To Mile s

T-

*T-

T-

T-

T-

Junction w/

NFSR 175

3.6 C C C C C

NFSR 173 Junction w/

LCR 86

Junction w/temp rd. into

20A

3.6 C C C C C

NFSR 175 Junction w/

NFSR 169

Termination Pt.

in unit 6B

0.8 C C C C C

NFSR 300 Junction w/

LCR 86

Termination Pt.

@ intersection w/ Killpecker

Trail

6.4 C C C C C

NFSR 300.A Junction w/

NFSR 300

Termination Pt.

at northern boundary of Unit 25A

0.2 C C C C C

NFSR 333 Junction w/

NFSR 300

Termination Pt.

at temp. rd. for unit 23

0.2 C C C C C

NFSR

175.1A

Junction w/

NFSR 175

Termination Pt.

in unit 6A

0.2 C C C C C

*NFSR 169 Junction w/

NFSR 175

Junction w/

LCR 80C

11.7 C C C C C

*If Contractor elects to haul this direction, maintenance requirements apply to the section of road that hauling occurs on. Line Items 006 and 007 lump sum payment applies

NFSR = National Forest System Road, LCR = Larimer County Road

*The maximum volume of Contractor responsibility for Slide and Slump repair is 10 cubic yards

ROAD MAINTENANCE T-SPECIFICATIONS FOR STEWARDSHIP CONTRACTS

No. Specification Title T-800 Definitions T-801 Slide and Slump Repair T-802 Ditch Cleaning T-803 Surfacing Blading T-805 Drainage Structures T-807 Roadway Vegetation

SPECIFICATION T-800 DEFINITIONS

Wherever the following terms or pronouns are used in Specifications T-801 through T-807, the intent and meaning shall be interpreted as follows:

800-1.1 - Agreement. Maintenance projects require a mutually acceptable method to resolve the problems which arise when incompatible situations arise between drawings and specifications and actual conditions on the ground to allow orderly and satisfactory progress of the maintenance.

These specifications have been developed in anticipation of those problem areas and have provided that such changes will be by Agreement.

It is intended that drawings and specifications will govern unless "on-the-ground" conditions warrant otherwise, when specifications call for "Agreement", "agreed", or "approval" such Agreement or approval shall be promptly confirmed in writing.

800-1.2 - Annual Road Maintenance Plan. A plan prepared by various users of one or several roads.

The plan is an Agreement on maintenance responsibilities to be performed for the coming year.

800-1.3 - Base Course. Material used to reinforce Subgrade or, as shown on drawings, placed on Subgrade to distribute wheel loads.

800-1.4 - Berm. Curb or dike constructed to prevent Roadway runoff water from discharging onto embankment slope.

800-1.5 - Borrow. Select Material taken from designated borrow sites.

800-1.6 - Crown, Inslope, and Outslope. The cross slope of the Traveled Way to aid in drainage and traffic maneuverability.

800-1.7 - Culverts. A conduit or passageway under a road, trail, or other obstruction. A culvert differs from a bridge in that it is usually entirely below the elevation of the Traveled Way.

800-1.8 - Drainage Dip. A dip in the Traveled Way which intercepts surface runoff and diverts the water off the Traveled Way. A Drainage Dip does not block the movement of traffic.

800-1.9 - Drainage Structures. Manufactured structures which control the runoff of water from the Roadway including Inslope, overside drains, aprons, flumes, downdrains, downpipes, culverts and the like.

800-1.10 - Dust Abatement Plan. A table which lists the road, dust palliative, application rates, and estimated number of subsequent applications.

800-1.11 - Lead-off Ditches. A ditch used to transmit water from a Drainage Structure or Drainage Dip outlet to the natural drainage area.

800-1.12 - Material. Any substances specified for use in the performance of the work.

800-1.13 – Pre haul Maintenance. Road maintenance work which must be accomplished to maintain the roads to a satisfactory condition commensurate with the Contractor's use, provided Contractor's Operations do not damage improvements under FAR 52.236-9 or National Forest resources and hauling can be done safely. This work will be shown in the Annual Road Maintenance Plan as provided in 800- 1.2.

800-1.14 - Roadbed. The portion of a road between the intersection of Subgrade and sideslopes, excluding that portion of the ditch below Subgrade.

800-1.15 - Road Maintenance Plan. A table which shows applicable road maintenance specifications to be performed by Contractor on specific roads.

800-1.16 - Roadside. A general term denoting the area adjoining the outer edge of the Roadway.

800-1.17 - Roadway. The portion of a road within the limits of excavation and embankment.

800-1.18 - Shoulder. That portion of Roadway contiguous with Traveled Way for accommodation of stopped vehicles, for emergency use, and lateral support of base and Surface Course, if any.

800-1.19 - Slide. A concentrated deposit of Materials from above or on back slope extending onto the Traveled Way or Shoulders, whether caused by mass land movements or accumulated raveling.

800-1.20 - Slough. Material eroded from the backslope which partially or completely blocks the ditch, but does not encroach on the Traveled Way so as to block passage of traffic.

800-1.21 - Slump. A localized portion of the Roadbed which has slipped or otherwise become lower than that of the adjacent Roadbed and constitutes a hazard to traffic.

800-1.22 - Special Project Specifications. Specifications which detail conditions and requirements peculiar to the individual project.

800-1.23 - Subgrade. Top surface of Roadbed upon which Base Course or Surface Course is constructed. For roads without Base Course or Surface Course, that portion of Roadbed prepared as the finished wearing surface.

800-1.24 - Surface Course. The Material placed on Base Course or Subgrade primarily to resist abrasion and the effects of climate. Surface Course may be referred to as surfacing.

800-1.25 - Surface Treatment Plan. A table which lists the roads and surface treatments to be applied.

800-1.26 - Traveled Way. That portion of Roadway, excluding Shoulders, used for the movement of vehicles.

800-1.27 - Turnouts. That portion of the Traveled Way constructed as additional width on single lane roads to allow for safe passing of vehicles.

800-1.28 - Water Source. A place designated on the Road Maintenance Map for acquiring water for road maintenance purposes.

800-1.29 - Waterbar. A dip in the Roadbed which intercepts surface runoff and diverts the water off the Roadway. A waterbar is not designed to be traversable by logging trucks.

SPECIFICATION T-801 SLIDE AND SLUMP REPAIR

DESCRIPTION

1.1 Slide removal is the removal from Roadway and disposal of any Material, such as soil, rock, and vegetation that cannot be routinely handled by a motor grader during Ditch Cleaning, T-802, and Surface Blading, T-803 Operations.

Slump repair is the filling of depressions or washouts in Roadway which cannot be routinely filled by a motor grader during Surface Blading, T-803 Operations.

Slide removal and Slump repair includes excavation, loading, hauling, placing, and compacting of waste or replacement Material and the development of disposal or borrow areas.

REQUIREMENTS

3.1 Slide Material, including soil, rock and vegetative matter which encroaches into the Roadway, shall be removed. The slope which generated the Slide Material shall be reshaped during the removal of the Slide Material with the excavation and loading equipment. Slide Material deposited on the fillslope and below the Traveled Way will not be removed unless needed for slope stability or to protect adjacent resources.

Surface and Base Courses shall not be excavated during Slide removal operations.

Slide Material which cannot be used for other beneficial purposes shall be disposed of at sites designated by the Forest Service. Material placed in disposal sites will not require compaction unless shown on Road Maintenance Plan. Side casting may be approved by the Forest Service. Side casting into streams, lakes or water courses will not be permitted.

3.2 When filling Slumps or washouts, Material shall be moved from agreed locations or borrow sites, placed in layers, and compacted by operating the hauling and spreading equipment uniformly over the full width of each layer.

Existing aggregate surfacing shall be salvaged when practical and re-laid after depressions have been filled.

Damaged aggregate base, aggregate surfacing, and bituminous pavement shall be repaired under Specification T-804 Surfacing Repair.

The repaired areas of the Slump shall conform to the cross-section which existed prior to the Slump and shall blend with the adjacent undisturbed Traveled Way.

3.3 The maximum volume of Contractor responsibility for Slide and Slump repair is 10 Cubic yards per 100 foot station. Greater volumes of Slide and Slump repair are Forest Service responsibility.

SPECIFICATION T-802 DITCH CLEANING

DESCRIPTION

1.1 Ditch cleaning is removing and disposing of all Slough Material and other debris from Roadway ditches, including outlet and lead-off ditches, to provide a free-draining waterway.

REQUIREMENTS

3.1 Ditch cleaning shall be repeated during the year as often as necessary to facilitate proper drainage.

3.2 All Slough Material or other debris which might obstruct water flow in the Roadway ditch shall be removed. Material removed from the ditch, if suitable, may be blended into existing native road surface or Shoulder or placed in designated Berms in conjunction with Surface Blading T-803 operations.

Material removed from ditches that is not by Agreement blended into existing roads or placed in Berms shall be loaded and hauled to the disposal site designated by the Forest Service.

3.3 Roadway backslope or Berm shall not be undercut.

SPECIFICATION T-803 SURFACE BLADING

DESCRIPTION

1.1 Surface blading is keeping a native or aggregate Roadbed in a condition to facilitate traffic and provide proper drainage. It includes maintaining the Crown, Inslope or Outslope of the Traveled Way, Turnouts, and Shoulder; repairing Berms; blending approach road intersections; and cleaning bridge decks, Drainage Dips, and Lead-off Ditches.

REQUIREMENTS

3.1 Surface blading shall be performed before, during, and after Contractor's use as often as necessary to facilitate traffic and proper drainage.

3.2 The surface blading shall preserve the existing cross-section. Surface irregularities shall be eliminated and the surface left in a free-draining state and to a smoothness needed to facilitate traffic.

Surface Material which has been displaced to the Shoulders or Turnouts shall be returned to the Traveled Way. The blading operation shall be conducted to prevent the loss of surface Material and to provide for a thorough mixing of the Material being worked.

3.3 Water, taken from Water Sources designated on Contract Area Map, shall be applied during blading if sufficient moisture is not present to cut, mix, or compact the surface Material.

3.4 On native surfaced roads, Material generated from backslope sloughing, and ditch cleaning may be blended with the surface Material being worked. On aggregate surfaced roads this Material shall not be blended with Surface or Base Course Material unless agreed otherwise.

3.5 Roadway backslopes or Berms shall not be undercut, nor shall new Berms be established unless agreed otherwise.

Berms shall be repaired by placing Material, as needed to restore the Berm, to reasonably blend with existing line, grade, and cross-section.

3.6 Drainage Dips and Lead-off Ditches shall be cleaned and maintained to reasonably blend with existing line, grade, and cross-section.

3.7 Intersecting roads shall be bladed for a distance of 50 feet to assure proper blending of the two riding surfaces.

3.8 Rocks or other Material remaining on the Traveled Way after the final pass that are larger than 4 inches in diameter or are larger than the maximum size of imported surfacing shall be removed from the Traveled Way. Unless otherwise designated by the Forest Service, the oversized Material shall be disposed of by sidecasting. Sidecasting into streams, lakes, or water courses will not be permitted.

3.9 Material resulting from work under this specification shall not remain on or in structures, such as Culverts, overside drains, cattleguards, ditches, Drainage Dips, and the like.

3.10 Material resulting from work under this specification, plus any other accumulated debris, shall be removed from bridge decks and the deck drains opened. This includes existing debris under pre haul maintenance.

SPECIFICATION T-805 DRAINAGE STRUCTURES

DESCRIPTION

1.1 This work consists of maintaining Drainage Structures and related items such as conveyor belt water deflectors, inlet and outlet channels, existing riprap, trash racks, and drop inlets.

MATERIALS

2.1 All Materials used in the maintenance of Drainage Structures shall conform by type and specification to the Material in the structure being maintained.

REQUIREMENTS

3.1 Drainage Structures and related items shall be cleared of all foreign Material which has been deposited above the bottom of the structure and all vegetative growth which interferes with the flow pattern. Material removed that cannot be incorporated into maintenance work shall be hauled to a disposal site designated by the Forest Service.

3.2 If outlet or inlet riprap was installed by Contractor as a construction item or existed prior to Contractor’s haul, it shall be maintained in good condition including the replacement of riprap if necessary to previous line, grade and cross-section.

3.3 Perform maintenance to insure the proper functioning of the head walls, aprons, inlet assemblies, overside drains, riprap, trash racks, and other facilities related to the Drainage Structure.

SPECIFICATION T-807 ROADWAY VEGETATION

DESCRIPTION

1.1 This work consists of cutting vegetative matter including brush and trees from within the Roadway limits.

REQUIREMENTS

3.1 Vegetative matter with the Roadway which impedes vehicular travel or interferes with road maintenance operations, such as surface blading and ditch and culvert cleaning shall be removed. Downed timber meeting utilization standards shall be cut in appropriate lengths and decked along the Roadside in locations where the Traveled Way or sight distances will not be impaired.

3.2 Vegetative matter removed from the Roadway shall be treated by the specified method and as required by the task order.