Test all the Main Engine Automationand Control System operations for the Port and Stbd Main Engines.
Solicitation number
N32205-20-Q-2162
Issued by

View the file

Other files

File Type Posted
KANAWHA SOW-T-AO196_L-3_Groom_DTD12-5-19.docx DOCX document
CSS KANAWA PATUXENT COMBO 20Q2162.docx DOCX document
PXT-KAN L3 SSJ CCOMBO-redacted.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USNS PATUXENT

T-AO 201

MACHINERY, PROPULSION

4 JAN 2020

ITEM NO. 200 MSC/ADC/BJD

ME CONTROL CONSOLE INSPECTION & TESTING

1.0 ABSTRACT

1.1 Provide the services of an L3 Henschel Field Service Engineer to test all the Main Engine Automation and Control System operations for the Port and Stbd Main Engines, support Annual Inspection of Main Engine Shutdowns for ABS and make adjustments to control parameters for optimal engine performance and power distribution.

1.2 Perform software update

2.0 REFERENCES/ENCLOSURES:

2.1 REFERENCES

2.1.1 Engine Room Centralized Control System TM No. 0965-LP-110-9010_0_0 (On Board Vessel)

2.1.2 550WI027 TAO ABS Automated Test Procedure

2.1.3 Excel format Test Procedure

2.1.4 ADDA Box Manual

2.2 ENCLOSURES: None

3.0 ITEM LOCATION/DESCRIPTION

3.1 Control Console System

3.1.1 Propulsion Control and Monitoring Console (ERC)

3.1.2 Ship Control Console (SCC)

3.1.3 Main Engine Local Control Console

3.1.4 Main Engine Pneumatic Control Panels

3.1.5 Remote Sensors throughout the ship

3.1.6 Remote Terminal Units (RTUs) 1-14 throughout the ship

3.1.7 Local Control Panels and pushbuttons throughout the ship

3.1.8 Tank Level Indicator System (TLI) Engine Room

3.1.9 Steering Gear alarms

3.1.10 EDG Alarms

3.2 Contractor Furnished Material: None

4.0 GOVERNMENT FURNISHED EQUIPMENT/MATERIAL/SERVICES: None

5.0 NOTES:

5.1 Period of Performance: MTA Availability Period of performance 8/25/20 - 9/12/20, followed by 2 day sea Trial

5.1.1 Service Representative for Inspection, Adjustment and testing

5.1.1.1 (21 Man Days total) 25 August 2020 - 14 September 2020; One (1) service representative

5.1.1.2 (4 Man Days) 30 August 2020 – 2 September 2020; Software Engineer

5.2 Location: TBD (contractor to estimate using Charleston, SC.

5.3 Service Engineer will be required to attend twenty four (24) hour overnight sea trial with the vessel

6.0 NOT USED

7.0 STATEMENT OF WORK REQUIRED

7.1 Provide the services of a L-3 field service technical representative to perform troubleshoot, repair, adjust and test the Propulsion Control and Monitoring Systems throughout the ship.

7.1.1 Verify/calibrate Temperature sensing thermocouple and RTD circuits throughout the main engine and auxiliary systems.

7.1.2 Accomplish the procedures for references 2.1.2, 2.1.3 and 2.1.4.

7.1.3 Verify/calibrate main engine and turbocharger rpm indicators and propulsion shaft rpm indicators

7.1.4 Test and demonstate all propulsion, ship’s service diesel generator, and emergency diesel generator safety shutdowns in the presence of the ABS surveyor.

7.1.5 Demonstrate all safety interlocks: main engine start A type and B type, main engine clutch interlocks A type and B type, Shaft brake, PTO Mode 2 and Mode 3

7.1.6 Demonstrate main engine slowdown controls with overrides.

7.1.7 Demonstate auto de-clutch and shaft brake on reduction gear lube oil head tank low-low level.

7.1.8 Demonstrate all vital pumps standby auto start.

7.1.9 Verify/calibrate p/s main engine fuel rack fuel rack position indicators and set main engine cam switches to appropriate fuel rack setpoint.

7.1.10 Verify/calibrate p/s propeller pitch indicators.

7.1.11 Verify/test communication between computers and RTUs.

7.1.12 Demonstrate bilge level alarms in the engine room, pump room and motor rooms

7.1.13 Demonstrate emergency diesel and steering gear control and alarms.

7.1.14 Make adjustment/repairs to address the following issues;

7.1.14.1 In mode 1 and mode 2, observed Port main engine rpm indication reads lower than STBD when throttles are matched. Shaft speed and pitch are also varied between Port and STBD. Port shaft rpm reads lower and pitch read higher than STBD. This was observed at local control and in ERC. T/S why Port reads lower.

7.1.14.2 At 50% throttle both ME's fluctuate between above and below 300 rpms. Causing Alpha interlock to activate/deactivate continuously, which opens and closes exhuast gas bypass valves. Manual adjustment to RPM trim necessary to keep engine speed above 300rpm to prevent Aplha interlock from activating. Preventing excess wear on ships equipment.

7.1.14.3 Console point ID No.900 ships speed reads inaccurately. Currently shows 37knts astern while answering a bell of 70% both Main Engines.

7.1.14.4 Indication panel is reading 0 psi when clutched in at 140psi.

7.1.14.5 Alarm page indicates Port & Stbd ME injector cooling water expansion tank level High & Low. System has been previously removed per an approved T-Alt.

7.1.14.6 Port & Stbd HP and TQ monitor is reading inaccurately, calibration required per the tech manual.

7.1.14.7 At 20% throttle engine rpm reads 311 with rpm trim pot at 12 o'clock

7.1.14.8 At 17% throttle engine rpm reads 301 and no response with rpm trim pot. "A' interlock activates

7.1.14.9 L-3 CFR#1 06-27-19; The ME Lube Oil Temperature Hi alarm will only work if the main engine is running. This inhibit is not needed and should be removed on both main engines. ID Parameter 111 and 211. L-3 sofware engineer shall rectify software and remove this inhibit.

7.1.14.10 L-3 CFR#1 06-27-19; the Shaft Thrust Bearing ID parameter 330 and 430 alarm window is not active when the thrust bearing circuits are put into an alarm using the RTD or temperature switch contact for these points. All other functions of the thrust bearing / slowdown circuits work correctly. L-3 software engineer to rectify linking the alarm windows for ID330 and ID430 to the lamp driver circuit responsible for engizing these alarm windows.

7.1.15 L-3 field service technical representative shall attend Dock Trials with COLT Pielstick Rep to demonstrate Load Balance to satisfaction of Chief Engineer.

7.1.16 L-3 software engineer shall update software to most current version and make corrections as necessary to ensure console is operating correctly and as designed.

7.1.17 L-3 field service technical representative shall attend two day Sea Trial.

7.1.18 Provide final report of repairs accomplished for groom and completed Test Procedure (Ref 2.1.2)

8.0 GENERAL REQUIREMENTS : None additional