This document contains a past performance evaluation questionnaire and a solicitation for a telepathology system. The Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 16 is seeking quotes for a telepathology system by August 28, 2020. The incumbent contractor must provide contract details and the evaluator rates the contractor's past performance on factors such as responding to questions, fulfilling requirements, scheduling, staffing, communication, billing and more. The evaluator also provides an overall rating of the contractor's ability and notes strengths, weaknesses, and other issues.

View the file

Other files

File Type Posted
36C25620Q1000 0001_1.docx DOCX document
Solicitation 36C25620Q1000.pdf PDF
36C25620Q1000_1.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT

Department of Memorandum Veterans Affairs

Date: 07/31/2020

To: Prospective Evaluators

From: Lakeisha White, Contracting Officer

Subject: Solicitation 36C25620Q1000 Telepathology System

1. The VISN 16 is conducting a proposal evaluation for subject solicitation. Under the solicitation, the VA will perform a Source Selection evaluation in accordance with Part 15.101-1, Tradeoff Process of the Federal Acquisition Regulation.

2. The individual completing this questionnaire shall be the Owner, Owner’s Representative or User of the project/space and must be knowledgeable of the contractor’s day-to-day operations and overall contractor’s performance.

3. Complete the questionnaire by indicating your rating and providing comments wherever applicable.

Handwritten responses are acceptable, however, if handwritten, responses must be legible. For any rating of L or N, it is requested that you provide an explanation and attach it to your response. This can be a copy of a discrepancy report or other documentation and the contractor’s corrective measures. The narratives need not be lengthy but should be detailed and descriptive. Space for narrative comments is included on the last page of the survey. If more space is needed, use the back of the survey or attach additional pages. As this questionnaire relates to an ongoing solicitation for the services identified it is requested that all information provided within the questionnaire be safeguarded against unauthorized disclosure. Once complete, please sign the document in the space provided.

4. Your time and effort in providing this vital information is greatly appreciated and is critical to our evaluation. Government contracts may be awarded after review of your questionnaire.

Please allow sufficient time to complete this questionnaire and return the completed package as soon as possible but no later than 8/21/2020. You may e-mail to lakeisha.white@va.gov.

5. If you have any questions, please contact Lakeisha White, Contracting Officer at lakeisha.white@va.gov. Thank you for your cooperation and quick response to this request.

//signed// Lakeisha White Contracting Officer

1 Attachment:

Past Performance Questionnaire

PAST PERFORMANCE QUESTIONNAIRE

CONTRACT IDENTIFICATION

The Contractor Must Fill Out This Section (Customer must complete concur or does not concur)

Part 1:

a. Contractor:

b. Contract number:

c. Contract type:

e. Was this a competitive contract? Yes ___________ No ________

f. Period of performance:

g. Initial contract price: $____________________________

h. Current/final contract price: $____________________________

i. Crew Size:

j. List all types of equipment used for service provided:

k. Description of service provided: (Please include any unusual requirements.)

The Customer Must Fill Out Remaining Sections

Customer concurs / does not concur with contractors statements above.

Part II

CUSTOMER OR AGENCY IDENTIFICATION

a. Customer or agency name:

b. Customer or agency description (if applicable):

c. Geographic description of services under this contract, i.e., local, nationwide, worldwide, other commands:

EVALUATOR IDENTIFICATION

a. Evaluator’s name:

b. Evaluator’s title:

c. Evaluator’s phone/fax number:

d. Number of year’s evaluator worked with Contractor:

EVALUATION

Please indicate your level of confidence based on your past experience with the contractor that they can satisfactorily perform the following elements by circling the appropriate letter using the scale provided. This scale is defined as follows:

Performance Confidence Assessment

High Confidence (H) Based on the offeror’s performance record, essentially no doubt exists that the offeror will successfully perform the required effort.

Significant Confidence (S) Based on the offeror’s performance record, little doubt exists that the offeror will successfully perform the required effort.

Confidence (C) Based on the offeror’s performance record, some doubt exists that the offeror will successfully perform the required effort

Unknown Confidence (U) No performance record is identifiable

“IAW FAR 15.305(a)(2)(iii) & (iv)

Little Confidence (L) Based on the offeror’s performance record, substantial doubt exists that the offeror will successfully perform the required effort. changes to the offeror’s existing process may be necessary in order to achieve contract requirements.

No Confidence (N) Based on the offeror’s performance record, extreme doubt exists that the offeror will successfully perform the required effort.

PERFORMANCE

P1. :Contractor’s ability to respond to Questions in a timely manner H S C U L N

P2. Contractor’s ability to fulfill contract requirements so there are no unexpected maintenance activity or latent defects H S C U L N

P3. Contractor’s ability to complete contract requirements H S C U L N

P4. Contractor’s ability to provide adequate Staffing levels for the project size and Complexity H S C U L N

P5. Contractor’s ability to communicate schedule and problem issues adequately and consistently H S C U L N

P6. Contractor’s ability for problem solving H S C U L N

P7. Contractor’s timeliness and accuracy of Billing. H S C U L N

Provide any explanation you may feel is required to clarify any of the above responses. Provide additional sheets as required:

QUALITY

Q1. Contractor’s ability to provide an effective quality control program to ensure contract compliance. H S C U L N

Q2. Contractor ability to identify and correct weaknesses in management relative to contractor, personnel (quantity and/or quality), planning/scheduling, and quality of service H S C U L N

Q3. Contractor’s ability to correct discrepancies in contract performance. H S C U L N

SCHEDULE

S1. Contractor’s ability to resolve contract problems Timely and effectively without extensive customer guidance H S C U L N

S2. Contractor’s ability to successfully respond to emergency and/or surge situations without extensive customer guidance to include Special Event/Visit H S C U L N

Weather Delays H S C U L N Gov Caused Delays H S C U L N

MANAGEMENT

M1. Contractor’s ability to provide experienced/qualified management personnel to meet contract requirements. H S C U L N

M2. Contractor’s ability to resolve customer complaints timely. H S C U L N

Part IV Government contracts only: Has/was this contract partially or completely terminated for default or convenience or are there any pending terminations?

Yes ____ Default ____ Convenience _____ Pending Terminations ____ NO ____ If yes, explain (e.g., inability to meet price, performance, or delivery schedules, etc.)

Narrative Summary

a. What were the contractor’s greatest strengths in the performance of the contract?

b. What were the contractor’s greatest weaknesses in the performance of the contract?

c. Were there any environmental compliance difficulties experienced during performance of this contract?

d. Would you have any reservations about soliciting this contractor in the future or having them perform one of your critical and demanding projects?

e. Are there any other issues not covered you feel important to note about performance of this contractor?

Part V Considering all the information provided above, please rate your overall opinion on the contractor’s ability to accomplish requirement.

(High Confidence) (Significant Confidence) (Confidence) (Unknown Confidence) (Low Confidence) (No Confidence)

Evaluator’s Signature Date

Thank you for your prompt response and assistance!

Lakeisha White Contracting Officer Lakeisha.white@va.gov

File details come from the government source that posted it. Updated .