Sol_P17PS01509.pdf

PDF 336 KB Posted

Attached to
Asphalt Overlay in White River and Ohanapecosh Cam Federal contract opportunity
Solicitation number
P17PS01509
Issued by
Department of the Interior National Park Service

About this file

P17PS01509

View the file

Other files for this federal contract opportunity

Other files attached to Asphalt Overlay in White River and Ohanapecosh Cam, newest first.
File Type Posted
Sol_P17PS01509_Amd_000001.pdf PDF
Map_2-Ohanapecosh.pdf PDF
Map_1_White_River.pdf PDF
P17PS01509_Read_Me_First.pdf PDF
Attachment_2_-_Past_Performance_Questionaire.docx DOCX document
Attachment_1_Wage_Determination.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION, OFFER,

AND AWARD

2. TYPE OF SOLICITATION

6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.

PAGE OF PAGES

7. ISSUED BY CODE 8. ADDRESS OFFER TO

SOLICITATION

(Construction, Alteration, or Repair)

1. SOLICITATION NO. 3. DATE ISSUED

IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.

9.

INFORMATION

a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."

CALL:

FOR

SEALED BID (IFB)

NEGOTIATED (RFP)

NPS, PWR - OLYM MABO

Mount Rainier National Park

55210 238th Ave E Ashford WA 98304-9751

PPY

Submit Electronically -pam_griffin@nps.gov

Pamela Griffin 360 569 6541

1x 06/16/2017

P17PS01509

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)

Request for Proposals #P17PS01509 is for Hot Asphalt Mix (HMA) commercial asphalt paving in the White River and Ohanapecosh Campgrounds within Mount Rainier National

Park. The Contractor shall provide all supervision, project management, labor, equipment, supplies, materials, bonds, insurance, etc. to complete the project and perform all work in accordance with the Statement of Work, wage determination, and other attachments to this solicitation. The period of performance will be between

September 5, 2017 and October 12, 2017.

PROJECT LOCATION: The White River Campground is located on the eastern side of

Mount Rainier NP, approximately 44 miles south of Enumclaw, WA. All campground loop roads, entrance road and parking area are to be paved (approximately 1200 tons). Ohanapecosh Campground is also located on the eastern side of Mount Rainier

National Park, approximately 11 miles north of Packwood, WA. Campground Loops A and

C are to be paved (approximately 1200 tons). Maps and information are available at www.nps.gov/MORA.

SITE VISIT: A group site visit will be held June 27, 2017 at 10am. - details with exact location can be found in Section L of the clauses.

Continued ...

11. The Contractor shall begin performance

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and is not required.is, b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

d. Offers providing less than

12b. CALENDAR DAYSYES NO

(If "YES", indicate within how many calendar days after award in Item 12b.)

10 40 calendar days and complete it within ________________ ________________ calendar days after receiving

Section F

07/14/2017

NSN 7540-01-155-3212

x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________

STANDARD FORM 1442 (Rev. 4-85)

Prescribed by GSA

FAR(48 CFR) 53.236-1(d)

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than item 14.)

CODE FACILITY CODE

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGEMENT OF AMENDMENTS

OFFER (Must be fully completed by offeror)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this document and return (Contractor is not required to sign this document.)

Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.

No further contractual document is necessary.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE

BY

2PAGE OF

DOI, NPS, PWR - OLYM MABO - MORA

55210 238th. Ave. E.

Ashford WA 98304-9751

PY2

Pamela Griffin

28. NEGOTIATED AGREEMENT 29. AWARD

Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, copies to issuing office.)

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

STANDARD FORM 1442 (REV. 4-85) BACK

Continued...

ITEM NO.

(A)

SUPPLIES/SERVICES

(B)

QUANTITY

(C)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

NAME OF OFFEROR OR CONTRACTOR

3 29

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

P17PS01509

DETAILS: This is a best value negotiated procurement set-aside for small business concerns in accordance with FAR Part 19.5. The NAICS code for this project is 237310, Highway, Street and

Bridge Construction and the small business size standard is $36.5 million, average annual gross receipts for the past three years. All work will be performed under a single firm-fixed-price construction contract subject to the Wage Rate

Requirements (Construction), formerly known as the Davis-Bacon Act. The contractor will have 40 days to complete the project after the Notice to

Proceed is issued. The estimated magnitude of this construction project is between $250,000 and

$500,000.

All eligible responsible sources may submit a proposal which shall be considered by the

National Park Service, however offerors who have not established and/or maintained an active registration at www.SAM.gov prior to the offer due date and time will be considered either ineligible or non-responsive and will not be considered for award.

Legacy Doc #: NPS

Period of Performance: 09/05/2017 to 10/12/2017

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

RFP #P17PS01509, White River & Ohana CG Paving Mount Rainier National Park

SECTION B: Contract Price Schedule

INSTRUCTIONS

On lump-sum-priced line items, provide the total price only. If no specific line item exists for a portion of the work, include the costs in a related item. In case of errors in summations, the total of the corrected amounts govern. Round totals and extended prices to whole dollars.

Line Item Number Description Estimated

Quantity Price per Ton

In Place Extended

Total

001 White River Campground Paving (Project #216921 1200 tons $__________ $___________

002 Ohanapecosh Campground Paving (Project #216623) 1200 tons $__________ $____________

TOTAL PRICE: $_______________

Business name: _____________________________________ Phone number: ____________________

DUNS number: _____________________________________ CAGE code: _____________________

Point of contact name: ________________________________ E-mail: __________________________

My business’ registration is active in SAM __yes __no;

The online representations and certifications apply to this offer (see 52.204-8(b)(2)): __yes __no;

Our VETS reporting is current __yes __no.

Proposal instructions: Complete this page and return with other documents described in Section L.

SECTION C: Description/Specifications

PROJECT LOCATION AND SCOPE

White River Campground: The asphalt work to be completed in this proposal is located at White River Campground and parking area. The White River Campground is located approximately 44 miles south of Enumclaw, WA and approximately 6 miles west of the intersection of SR 410 and Sunrise Park Road.

The White River Campground is a popular, busy campground during peak summer months with as many as 400 campers in residence. The paving locations are all of the campground loops within the campground plus the entrance road and the parking area (approximately 1200 tons). The scope of work is to grind abutments to existing asphalt pavement, overlay existing asphalt with 2.5” thick Hot Mix Asphalt (HMA) class ½” commercial asphalt. Tamp and seal all edges/joints with AR4000. Apply tack coat to existing surface prior to asphalt overlay.

Ohanapecosh Campground: The asphalt work to be completed in this proposal is located on the A and C Loops of the Ohanapecosh Campground. The Ohanapecosh Campground is located approximately 11 miles north of Packwood, WA and approximately 4 miles north of the intersection of US 12 and SR 123.

The Ohanapecosh Campground is a popular, busy campground during peak summer months with as many as 800 campers in residence. The paving locations are campground road Loop A & C (approximately 1200 tons). The scope of work is to grind abutments to existing asphalt pavement, overlay existing asphalt with 2.5” thick Hot Mix Asphalt (HMA) class ½” commercial asphalt. Tamp and seal all edges/joints with AR4000. Apply tack coat to existing surface prior to asphalt overlay.

SPECIFICATIONS

All work shall be in accordance with Washington State Department of Transportation Standard Specifications for Road, Bridge and Municipal Construction, Amended April 4, 2016 for HMA and as amended in this specification.

No work shall take place on holidays or weekends without prior approval of the Contracting Officer.

Period of Performance is anticipated to be Sept 5 through Oct 12, 2017, Monday through Thursday, 6 am to 5:00 pm

Maintaining Traffic: Traffic control will be provided by NPS employees during the placement of the asphalt. The campground loop roads will be closed to traffic during overlay operations. NPS is to provide appropriate barricades and signage. Roads shall be open to the public when work is not taking place.

Surface Preparation: Cleaning the existing surface of all loose material, dirt, or other deleterious substances by approved methods will be accomplished by contractor. Prior to application of asphalt, no dry aggregate or other loose material shall be permitted on the surface.

For located repair sites: dig out to 2” depth below existing asphalt (where required by COR); apply asphalt to bring surface to a level grade before applying the 2.5” inch asphalt overlay. Field verify with Contracting Officer’s Representative at repair site. Note: Most repairs are utility trenches that have not been paved or roots heaving the existing pavement.

Crack sealing of all butt joints is required to prevent water and debris entry in the joints. Grind all butt joints where new asphalt meets existing pavement. Grinds shall be a minimum of 2” depth. All joints shall have an elevation difference at joints less than 0.25 inches.

Apply a uniform coat of asphalt (tack coat) to all surfaces on which HMA is to be placed or abutted.

Apply tack coat to cover the cleaned existing pavement with a thin film of residual asphalt free of streaks and bare spots. Apply a heavy application of tack coat to all joints. See WSDOT standard specifications for allowable tack coat materials.

For HMA, place at temperatures between two hundred fifteen (215) and three hundred twenty-five (325) degrees F with a self-propelled laydown machine. Pre-level all potholes and other depressions with HMA and compact. Final surface applications shall be rolled with a roller sufficient to achieve compaction results in compliance with WSDOT standard specifications.

PRE-BID SITE VISIT

A Pre-Bid site visit to all paving locations is scheduled for Tuesday, June 27, 2017 at 10 am. Meet at the White River Campground parking area. After the White River Campground site walk-through, attendees will travel to the Ohanapecosh Campground for site specific questions and clarifications. Attendance is highly recommended as it will be up to the vendor to verify all estimated quantities, including repair work and grind areas.

SPECIAL PRECAUTIONS

Contractor shall be responsible for containment and/or cleanup of any spilled materials. In particular, Contractor shall remove any excess asphalt not compacted into the finished road surface along the edges of the project. Even small amounts of excess asphalt are not acceptable.

ACCIDENT PREVENTION PROGRAM

Before on-site work begins, submit for approval an accident prevention program. The Contracting Officer will review the proposed program for compliance with OSHA and project requirements. If the program requires any revisions or corrections, the Contractor shall resubmit the program within 5 days. No payments will be made until the program is approved. The program shall include:

• Name of responsible supervisor to carry out the program.

• First aid procedures.

• Training, both initial and continuing.

Planning for possible emergency situations, to include motor vehicle accidents, personal injuries, hazardous material spills, taking into consideration type of construction, site conditions, and degree of exposure of persons and property.

ACCIDENT REPORTING

Reportable Accidents: A reportable accident is defined as death, occupational disease, traumatic injury to employees or the public, property damage by accident in excess of $100, and fires. Notify Contracting Officer immediately in the event of a reportable accident. Within 7 days of a reportable accident, fill out and forward to the Contracting Officer a DI-134 form, which may be obtained from Contracting Officer.

All Other Accidents: The Contractor shall report all other accidents to the Contracting Officer as soon as possible and assist the Contracting Officer and other officials as required in the investigation of the accident.

QUALIFICATIONS OF EMPLOYEES

Ensure that employees are physically qualified to perform their assigned duties in a safe manner. Do not allow employees to work whose ability or alertness is impaired because of drugs, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury.

Operators of vehicles, mobile equipment, hoisting equipment, and hazardous plant equipment shall be able to understand signs, signals, and operating instructions, and be capable of operating such equipment.

Provide operating instructions for all equipment. Newly hired operators shall be individually tested by an experienced operator or supervisor to determine if they are capable of safely operating equipment.

Contractor shall at all times conduct their operations to ensure the least inconvenience to the public and park staff.

HOUSEKEEPING

Keep project site neat, orderly and in a safe condition at all times. Store and use equipment, tools, and materials in a manner that does not present a hazard.

HAULING RESTRICTIONS

Comply with all legal load restrictions in the hauling of materials. Load restrictions on park roads are identical to the state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.

AIR AND WATER POLLUTION CONTROL

Take all necessary reasonable measures to reduce air and water pollution by any material or equipment used during construction. Wet down dry materials and rubbish to prevent blowing dust.

Do not dispose of volatile wastes or oils in storm or sanitary drains.

Do not allow waste materials to be washed into streams or bodies of water.

SANITARY FACILITIES

Toilet facilities are located at White River Entrance Station and Campground, Ohanapecosh Visitor Center and Campground.

Smoking: Smoking within buildings or temporary storage sheds is prohibited.

MEASUREMENT AND PAYMENT

Measurement will be by certified load ticket net weight. Payment will be lump sum based on per ton of asphalt in place. No payment will be made for unused asphalt delivered to the site and not placed.

SECTION D: Packaging and Marking (not used)

SECTION E: Inspection and Acceptance

52.246-12 Inspection of Construction. (AUG 1996)

52.252-2 Clauses Incorporated By Reference (Feb 1998) This RFP and resulting contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at these addresses: https://www.acquisition.gov/?q=browsefar and http://www.ecfr.gov/cgi-bin/text-idx?SID=e3fdab2f32e71039c0f3823dcff65823&tpl=/ecfrbrowse/Title48/48chapter14.tpl https://www.acquisition.gov/?q=browsefar

SECTION F: Deliveries or Performance

52.211-18 Variation in Estimated Quantity. (APR 1984)

52.242-14 Suspension of Work. (APR 1984)

52.211-10 Commencement, Prosecution, and Completion of Work. (APR 1984) The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than40 calendar days after receiving the notice to proceed. The time stated for completion shall include final cleanup of the premises.

SECTION G: Contract Administration Data

1452.201-70 Authorities and Delegations (SEPT 2011)

(a) The Contracting Officer is the only individual authorized to enter into or terminate this contract, modify any term or condition of this contract, waive any requirement of this contract, or accept nonconforming work.

(b) The Contracting Officer will designate a Contracting Officer's Representative (COR) at time of award. The COR will be responsible for technical monitoring of the contractor's performance and deliveries. The COR will be appointed in writing, and a copy of the appointment will be furnished to the Contractor. Changes to this delegation will be made by written changes to the existing appointment or by issuance of a new appointment.

(c) The COR is not authorized to perform, formally or informally, any of the following actions:

(1) Promise, award, agree to award, or execute any contract, contract modification, or notice of intent that changes or may change this contract;

(2) Waive or agree to modification of the delivery schedule;

(3) Make any final decision on any contract matter subject to the Disputes Clause;

(4) Terminate, for any reason, the Contractor's right to proceed;

(5) Obligate in any way, the payment of money by the Government.

(d) The Contractor shall comply with the written or oral direction of the Contracting Officer or authorized representative(s) acting within the scope and authority of the appointment memorandum.

The Contractor need not proceed with direction that it considers to have been issued without proper authority. The Contractor shall notify the Contracting Officer in writing, with as much detail as possible, when the COR has taken an action or has issued direction (written or oral) that the Contractor considers to exceed the COR's appointment, within 3 days of the occurrence. Unless otherwise provided in this contract, the Contractor assumes all costs, risks, liabilities, and consequences of performing any work it is directed to perform that falls within any of the categories defined in paragraph (c) prior to receipt of the Contracting Officer's response issued under paragraph (e) of this clause.

(e) The Contracting Officer shall respond in writing within 30 days to any notice made under paragraph (d) of this clause. A failure of the parties to agree upon the nature of a direction, or upon the contract action to be taken with respect thereto, shall be subject to the provisions of the Disputes clause of this contract.

(f) The Contractor shall provide copies of all correspondence to the Contracting Officer and the COR.

(g) Any action(s) taken by the Contractor, in response to any direction given by any person acting on behalf of the Government or any Government official other than the Contracting Officer or the COR acting within his or her appointment, shall be at the Contractor's risk.

1452.204-70 Release of Claims—Department of the Interior (JUL 1996) After completion of work and prior to final payment, the Contractor shall furnish the Contracting Officer with a release of claims against the United States relating to this contract. The Release of Claims form (DI-137) shall be used for this purpose. The form provides for exception of specified claims from operation of the release.

G.1 Appointment of Contractor Representative / Superintendent Prior to commencement of work on this contract, the contractor shall provide to the Contracting Officer and COR the name and telephone number of at least one responsible individual who will serve to respond to operational problems and/or emergencies on a daily basis. The contractor agrees that notice to the designated representative shall constitute notice to the contractor and agrees to be bound by any commitments or representations made by the representative.

G.2 Electronic Invoicing and Payment Requirements - Internet Payment Platform (IPP) (April 2013) Payment requests must be submitted electronically through the U.S. Department of the Treasury's Internet Payment Platform System (IPP; https://www.ipp.gov).

"Payment request" means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions- Commercial Items included in commercial item contracts. The IPP website address is: https://www.ipp.gov.

Under this contract, the following documents are required to be submitted as an attachment to the IPP invoice (upload your business invoice as an attachment to the IPP invoice before you click “submit” in IPP):

1. Contractor’s standard business invoice,

2. Signed certification required by FAR clause 52.232-5,

3. Schedule of values for work being invoiced, and

4. If submitting a final invoice, also attach a signed copy of the Release of Claims form.

Contractor’s failure to attach the required documentation as specified above will result in the IPP invoice being rejected, and cause a delay in payment.

The Contractor must use the IPP website to register access and use IPP for submitting requests for payment. The Contractor Government Business Point of Contact (as listed in www.SAM.gov record) will receive enrollment instructions via email from the Federal Reserve Bank of Boston (FRBB) prior to contract award or within 3 - 5 business days after the contract award date. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email ippgroup@bos.frb.org or phone (866) 973-3131.

If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation.

G.3 NOTICE TO CONTRACTORS - CONTRACTOR PERFORMANCE ASSESSMENT REPORTING

SYSTEM (Dec 2015)

1. FAR 42.1502 directs all Federal agencies to collect past performance information on contracts. The

Department of the Interior (DOI) has implemented the Contractor Performance Assessment Reporting System (CPARS) to comply with this regulation. One or more past performance evaluations will be conducted in order to record your contract performance as required by FAR 42.15.

2. The past performance evaluation process is a totally paperless process using CPARS. CPARS is a web-based system that allows for electronic processing of the performance evaluation report. Once the report is processed, it is available in the Past Performance Information Retrieval System (PPIRS) for Government use in evaluating past performance as part of a source selection action.

3. We request that you furnish the Contracting Officer (CO) with the name, position title, phone number, and email address for each person designated to have access to your firm's past performance evaluation(s) for the contract no later than 30 days after award. Each person granted access will have the ability to provide comments in the Contractor portion of the report and state whether or not the Contractor agrees with the evaluation, before returning the report to the Assessing Official (AO). Information in the report must be protected as source selection sensitive information not releasable to the public.

4. When your Contractor Representative(s) are registered in CPARS, they will receive an automatically generated email with detailed login instructions. Further details, systems requirements, and training information for CPARS is available at https://www.cpars.gov/.

5. Within 60 days after the end of a performance period, the AO will complete an interim or final past performance evaluation, and the report will be accessible at https://www.cpars.gov/.

a. Contractor Representatives may then provide comments in response to the evaluation, or return the evaluation without comment.

b. Your comments should focus on objective facts in the AO's narrative and should provide your views on the causes and ramifications of the assessed performance.

c. All information provided should be reviewed for accuracy prior to submission.

d. If you elect not to provide comments, please acknowledge receipt of the evaluation by indicating https://www.acquisition.gov/sites/default/files/current/far/html/Subpart%2042_15.html https://www.acquisition.gov/sites/default/files/current/far/html/Subpart%2042_15.html https://www.cpars.gov/ https://www.cpars.csd.disa.mil/ https://www.cpars.csd.disa.mil/

"No comment" in the space provided, and then selecting “Accept the Ratings and Close the Evaluation”.

e. Your response is due within 60 calendar days after receipt of the CPAR. On day 15, the evaluation will become available in PPIRS-RC marked as “Pending” with or without comments and whether or not it has been closed.

f. If you do not sign and submit the CPAR within 60 days, it will automatically be returned to the Government and will be annotated: "The report was delivered/received by the contractor on (date). The contractor neither signed nor offered comment in response to this assessment."

6. The following guidelines apply concerning your use of the past performance evaluation:

a. Protect the evaluation as source selection information. After review, transmit the evaluation by completing and submitting the form through CPARS. If for some reason you are unable to view and/or submit the form through CPARS, contact the CO for instructions.

b. Strictly control access to the evaluation within your organization. Ensure the evaluation is never released to persons or entities outside of your control.

c. Prohibit the use of or reference to evaluation data for advertising, promotional material, pre-award surveys, responsibility determinations, production readiness reviews, or other similar purposes.

7. If you wish to discuss a past performance evaluation, you should request a meeting in writing to the CO no later than seven days following your receipt of the evaluation. The meeting will be held in person or via telephone or other means during your 60-day review period.

8. A copy of the completed past performance evaluation will be available in CPARS for your viewing and for Government use supporting source selection actions after it has been finalized.

SECTION H: SPECIAL CONTRACT REQUIREMENTS

H.1 Wage Determination U.S. Department of Labor General Wage Decision #WA17001(Pierce Co, WA), is incorporated into this solicitation/contract, as shown in Section J.

H.2 Site-Specific Accident Prevention Plan A site-specific Accident Prevention Plan (APP) covering on-site work to be performed by the contractor and all subcontractors is required. The prime contractor shall be responsible for development, implementation, and oversight of the plan. The plan shall address site-specific safety and health requirements and procedures based upon specific anticipated conditions, and address anticipated tasks, their related hazards, and anticipated control measures. In addition, work performed under this contract shall comply with applicable federal, state, and local safety and occupational health laws and regulations. This includes, but is not limited to, Occupational Safety and Health Administration (OSHA) standards, 29 CFR, and FAR clause 52.236-13, Alt 1.

Should any unforeseen hazards become evident during the performance of work, the contractor shall bring such hazard to the attention of the COR, both verbally and in writing for resolution as soon as possible. In the interim necessary action shall be taken to re-establish and maintain safe working conditions in order to safeguard on-site personnel, visitors, the public, and the environment.

H.3 Preconstruction Conference The Contracting Officer may conduct a preconstruction conference; the successful offeror will be notified and will be required to attend in person or by phone. The Contracting Officer’s notification will include specific details regarding the date, time, and location of the conference, any need for attendance by subcontractors, and information regarding the items to be discussed.

H.4 Notice of Required Bonds A bid bond for no less than 20% of the offered price is required with the offer. The awardee (successful offeror) shall furnish performance and payment bonds, using Standard Forms 25 and 25A, within 10 days after contract award. The penal sum of the bonds shall equal 100% of the contract price.

H.5 Interpretations of Contract: Notice of Ambiguities

(a) This written contract and any and all identified writings or documents incorporated by reference herein or physically attached hereto constitute the parties' complete agreement and no other prior or contemporaneous agreements either written or oral shall be considered to change, modify, or contradict it. Any ambiguity in the contract will not be strictly construed against the drafter of the contract language but shall be resolved by applying the most reasonable interpretation under the circumstances, giving full consideration to the intentions of the parties at the time of contracting.

(b) It shall be the obligation of the Contractor to exercise due diligence to discover and to bring to the attention of the Contracting Officer at the earliest possible time any ambiguities, discrepancies, inconsistencies, or conflicts in or between the specifications and the applicable drawings or other documents incorporated. Failure to comply with such obligation shall be deemed a waiver and release of any and all claims for extra costs or delay arising out of such ambiguities, discrepancies, inconsistencies, and conflicts.

H.6 1452.228-70 Liability Insurance—Department of the Interior (JUL 1996)

(a) The Contractor shall procure and maintain during the term of this contract and any extension thereof liability insurance in form satisfactory to the Contracting Officer by an insurance company which is acceptable to the Contracting Officer. The named insured parties under the policy shall be the Contractor and the United States of America. The amounts of the insurance shall be not less than as follows:

$1,000,000 each person $1,000,000 each occurrence $2,000,000 property damage

(b) Each policy shall have a certificate evidencing the insurance coverage. The insurance company shall provide an endorsement to notify the Contracting Officer 30 days prior to the effective date of cancellation or termination of the policy or certificate; or modification of the policy or certificate which may adversely affect the interest of the Government in such insurance. The certificate shall identify the contract number, the name and address of the Contracting Officer, as well as the insured, the policy number and a brief description of contract services to be performed. The contractor shall furnish the Contracting Officer with a copy of an acceptable insurance certificate prior to beginning the work.

(c) The Contractor shall also maintain compensation insurance for employees engaged in the work, complying with the worker's compensation laws of the State in which the work is to be performed, and furnish evidence of such coverage to the Contracting Officer at the same time as the liability insurance certificate.

H.7 Subcontracting Requirements In accordance with FAR clause 52.219-14, Limitations on Subcontracting, the small business prime contractor is required to perform a minimum percentage of the cost of contract performance incurred for personnel/labor. A worksheet is provided for the contractor to document their and their subcontractors' labor costs. This worksheet must be completed and provided with the proposal showing anticipated figures, and resubmitted with actual figures as part of contract close-out.

H.8 Substitutions of Key Personnel and Key Subcontractors In connection with this contract, key personnel and key subcontractors will be limited to individuals and firms that were specifically identified in the Contractor's accepted proposal. The Contractor shall obtain the Contracting Officer's written consent before making any substitution for these designated in-house key personnel or key subcontractors. If the Contractor proposes a substitution, it shall submit the same type of information that was submitted in the accepted proposal to the Contracting Officer for evaluation and approval. The level of qualifications and experience submitted in the accepted proposal or that required by the solicitation, whichever is greater, is the minimum standard for any substitution.

Key personnel are those performing the usual functions of project manager and on-site project superintendent.

Key subcontractors are those who will perform buried reinforced potable water concrete tank construction, including associated deep excavation and shoring.

SECTION I: Contract Clauses

52.202-1 Definitions. (NOV 2013)

52.203-3 Gratuities. (APR 1984)

52.203-5 Covenant Against Contingent Fees. (MAY 2014)

52.203-6 Restrictions on Subcontractor Sales to the Government. (SEP 2006)

52.203-7 Anti-Kickback Procedures. (MAY 2014)

52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity. (MAY 2014)

52.203-10 Price or Fee Adjustment for Illegal or Improper Activity. (MAY 2014)

52.203-12 Limitation on Payments to Influence Certain Federal Transactions. (OCT 2010)

52.203-17 Contractor Employee Whistleblower Rights and Requirement to Inform Employees of Whistleblower Rights (APR 2014)

52.203-19 Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements (JAN 2017)

52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper. (MAY 2011)

52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards. (OCT 2016)

52.204-13 System for Award Management Maintenance. (OCT 2016)

52.204-14 Service Contract Reporting Requirements (JAN 2014)

52.209-6 Protecting the Government's Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment. (OCT 2015)

52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters (JUL 2013)

52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (NOV 2015)

52.215-2 Audit and Records—Negotiation (OCT 2010)

52.215-8 Order of Precedence - Uniform Contract Format. (OCT 1997)

52.219-6 Notice of Total Small Business Set-Aside (Nov 2011)

52.219-8 Utilization of Small Business Concerns. (OCT 2014)

52.219-14 Limitations on Subcontracting (JAN 2017)

52.219-28 Post-Award Small Business Program Rerepresentation. (JUL 2013)

52.222-3 Convict Labor. (JUN 2003)

52.222-4 Contract Work Hours and Safety Standards Act - Overtime Compensation. (MAY 2014)

52.222-6 Construction Wage Rate Requirements (MAY 2014)

52.222-7 Withholding of Funds. (MAY 2014)

52.222-8 Payrolls and Basic Records. (MAY 2014)

52.222-9 Apprentices and Trainees. (JUL 2005)

52.222-10 Compliance with Copeland Act Requirements. (FEB 1988)

52.222-11 Subcontracts (Labor Standards). (MAY 2014)

52.222-12 Contract Termination - Debarment. (MAY 2014)

52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations. (MAY 2014)

52.222-14 Disputes Concerning Labor Standards. (FEB 1988)

52.222-15 Certification of Eligibility. (MAY 2014)

52.222-21 Prohibition of Segregated Facilities. (APR 2015)

52.222-26 Equal Opportunity. (SEP 2016)

52.222-27 Affirmative Action Compliance Requirements for Construction. (APR 2015)

52.222-37 Employment Reports on Veterans. (FEB 2016)

52.222-40 Notification of Employee Rights Under the National Labor Relations Act. (DEC 2010)

52.222-50 Combating Trafficking in Persons. (MAR 2015)

52.222-54 Employment Eligibility Verification. (OCT 2015)

52.222-55 Minimum Wages Under Executive Order 13658 (DEC 2015)

52.222-60 Paycheck Transparency (Executive Order 13673) (Oct 2016)

52.222-62 Paid Sick Leave Under Executive Order 13706 (JAN 2017)

52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction Contracts (SEP 2013)

52.223-5 Pollution Prevention and Right-to-Know Information. (MAY 2011)

52.223-6 Drug-Free Workplace. (MAY 2001)

52.223-15 Energy Efficiency in Energy-Consuming Products (Dec 2007)

52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving. (AUG 2011)

52.225-13 Restrictions on Certain Foreign Purchases. (JUN 2008)

52.227-1 Authorization and Consent (DEC 2007)

52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (DEC 2007)

52.227-4 Patent Indemnity--Construction Contracts. (DEC 2007)

52.228-2 Additional Bond Security. (OCT 1997)

52.228-5 Insurance - Work on a Government Installation. (JAN 1997)

52.228-11 Pledges of Assets. (JAN 2012)

52.228-12 Prospective Subcontractor Requests for Bonds. (MAY 2014)

52.228-14 Irrevocable Letter of Credit (NOV 2014)

52.228-15 Performance and Payment Bonds - Construction. (OCT 2010)

52.229-3 Federal, State, and Local Taxes. (FEB 2013)

52.232-5 Payments under Fixed-Price Construction Contracts. (MAY 2014)

52.232-17 Interest (MAY 2014)

52.232-23 Assignment of Claims. (MAY 2014)

52.232-27 Prompt Payment for Construction Contracts. (JAN 2017)

52.232-33 Payment by Electronic Funds Transfer-System for Award Management (JUL 2013)

52.232-39 Unenforceability of Unauthorized Obligations (JUN 2013)

52.232-40 Providing Accelerated Payments to Small Business Subcontractors (DEC 2013)

52.233-1 Disputes, Alt. 1. (MAY 2014, DEC 1991)

52.233-3 Protest after Award. (AUG 1996)

52.233-4 Applicable Law for Breach of Contract Claim. (OCT 2004)

52.236-2 Differing Site Conditions. (APR 1984)

52.236-3 Site Investigation and Conditions Affecting the Work. (APR 1984)

52.236-4 Physical Data (APR 1984)

52.236-5 Material and Workmanship. (APR 1984)

52.236-6 Superintendence by the Contractor. (APR 1984)

52.236-7 Permits and Responsibilities. (NOV 1991)

52.236-8 Other Contracts. (APR 1984)

52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements. (APR 1984)

52.236-10 Operations and Storage Areas. (APR 1984)

52.236-11 Use and Possession Prior to Completion. (APR 1984)

52.236-12 Cleaning Up. (APR 1984)

52.236-14 Availability and Use of Utility Services. (APR 1984)

52.236-15 Schedules for Construction Contracts (APR 1984)

52.236-17 Layout of Work. (APR 1984)

52.236-21 Specifications and Drawings for Construction. (FEB 1997)

52.242-13 Bankruptcy. (JUL 1995)

52.242-14 Suspension of Work. (APR 1984)

52.243-4 Changes. (JUN 2007)

52.244-6 Subcontracts for Commercial Items. (JAN 2017)

52.246-21 Warranty of Construction. (MAR 1994) - Alternate I (APR 1984)

52.248-3 Value Engineering - Construction. (OCT 2015)

52.249-2 Termination for Convenience of the Government (Fixed-Price). (APR 2012) - Alternate I (SEP 1996)

52.249-10 Default (Fixed-Price Construction). (APR 1984)

52.253-1 Computer Generated Forms. (JAN 1991)

1452.215-70 Examination of Records by the Department of the Interior (APR 1984)

52.222-35 Equal Opportunity for Veterans. (OCT 2015)

(a) Definitions. As used in this clause— “Active duty wartime or campaign badge veteran,” “Armed Forces service medal veteran,” “disabled veteran,”

“protected veteran,” “qualified disabled veteran,” and “recently separated veteran” have the meanings given at

FAR 22.1301.

(b) Equal opportunity clause. The Contractor shall abide by the requirements of the equal opportunity clause at 41 CFR 60-300.5(a), as of March 24, 2014. This clause prohibits discrimination against qualified protected veterans, and requires affirmative action by the Contractor to employ and advance in employment qualified protected veterans.

(c) Subcontracts. The Contractor shall insert the terms of this clause in subcontracts of $150,000 or more unless exempted by rules, regulations, or orders of the Secretary of Labor. The Contractor shall act as specified by the Director, Office of Federal Contract Compliance Programs, to enforce the terms, including action for noncompliance. Such necessary changes in language may be made as shall be appropriate to identify properly the parties and their undertakings.

52.222-36 Affirmative Action for Workers With Disabilities. (JUL 2014)

(a) Equal opportunity clause. The Contractor shall abide by the requirements of the equal opportunity clause at 41

CFR 60-741.5(a), as of March 24, 2014. This clause prohibits discrimination against qualified individuals on the basis of disability, and requires affirmative action by the Contractor to employ and advance in employment qualified individuals with disabilities.

(b) Subcontracts. The Contractor shall include the terms of this clause in every subcontract or purchase order in excess of $15,000 unless exempted by rules, regulations, or orders of the Secretary, so that such provisions will be binding upon each subcontractor or vendor. The Contractor shall act as specified by the Director, Office of Federal Contract Compliance Programs of the U.S. Department of Labor, to enforce the terms, including action for noncompliance. Such necessary changes in language may be made as shall be appropriate to identify properly the parties and their undertakings.

52.223-9 Estimate of Percentage of Recovered Material Content for EPA-Designated Items. (MAY 2008) https://www.acquisition.gov/sites/default/files/current/far/html/Subpart%2022_13.html#wp1085590

(a) Definitions. As used in this clause - "Postconsumer material" means a material or finished product that has served its intended use and has been discarded for disposal or recovery, having completed its life as a consumer item. Postconsumer material is a part of the broader category of "recovered material."

"Recovered material" means waste materials and by-products recovered or diverted from solid waste, but the term does not include those materials and by-products generated from, and commonly reused within, an original manufacturing process.

(b) The Contractor, on completion of this contract, shall -

(1) Estimate the percentage of the total recovered material content for EPA-designated item(s) delivered and/or used in contract performance, including, if applicable, the percentage of post-consumer material content; and

(2) Submit this estimate to Contracting Officer.

52.223-17 Affirmative Procurement of EPA-designated Items in Service and Construction Contracts. (MAY 2008)

(a) In the performance of this contract, the Contractor shall make maximum use of products containing recovered materials that are EPA-designated items unless the product cannot be acquired—

(1) Competitively within a timeframe providing for compliance with the contract performance schedule;

(2) Meeting contract performance requirements; or

(3) At a reasonable price.

(b) Information about this requirement is available at EPA’s Comprehensive Procurement Guidelines web site, www.epa.gov/cpg/. The list of EPA-designated items is available at www.epa.gov/cpg/products.htm.

52.225-9 Buy American - Construction Materials. (MAY 2014)

(a) Definitions. As used in this clause— “Commercially available off-the-shelf (COTS) item”—

(1) Means any item of supply (including construction material) that is—

(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and

(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.

“Component” means an article, material, or supply incorporated directly into a construction material.

“Construction material” means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site.

Materials purchased directly by the Government are supplies, not construction material.

“Cost of components” means—

(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or

(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.

“Domestic construction material” means—

(1) An unmanufactured construction material mined or produced in the United States;

(2) A construction material manufactured in the United States, if—

(i) The cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic; or

(ii) The construction material is a COTS item.

“Foreign construction material” means a construction material other than a domestic construction material.

“United States” means the 50 States, the District of Columbia, and outlying areas.

(b) Domestic preference.

(1) This clause implements 41 U.S.C. chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the component test of the Buy American statute is waived for construction material that is a COTS item. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.

(2) This requirement does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows: [Contracting Officer to list applicable excepted materials or indicate “none”] None; however all COTS items are considered domestic regardless of their place of manufacture (see definition above).

(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that—

(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;

(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or

(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.

(c) Request for determination of inapplicability of the Buy American statute.

(1)(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including—

(A) A description of the foreign and domestic construction materials;

(B) Unit of measure;

(C) Quantity;

(D) Price;

(E) Time of delivery or availability;

(F) Location of the construction project;

(G) Name and address of the proposed supplier; and

(H) A detailed justification of the reason for use of foreign construction materials cited in…

This is the start of the file's text. The full file is on GovTribe.