SPECIFICATIONS
FOR
LAPWAI CREEK BRIDGE PROJECT
NEZ PERCE NATIONAL HISTORICAL PARK
SPALDING, IDAHO
TABLE OF CONTENTS
DIVISION 1
Section 0100 Summary of Work
Section 0200 List of Services
Section 0300 Definition of Line Items
Section 0400 Submittals
Section 0500 Accident Prevention
Section 0600 Contractor’s Quality Control
Section 0700 Closeout
DIVISION 2
Section 0800 Contamination
SECTION 0100
SUMMARY OF WORK
PART 1 GENERAL
1.1 WORK COVERED BY CONTRACT DOCUMENTS
1.1.1 Project Description
Lapwai Creek Bridge is located 11 miles east of Lewiston, Idaho at the Spalding headquarters of
Nez Perce National Historical Park. This 64-foot-long steel and timber expansion bridge serves vehicle and pedestrian traffic. It has a 10-ton load capacity, accommodates one vehicle lane, and is the only access over Lapwai Creek to the park’s Spalding picnic ground and a Nez Perce tribal cemetery.
This project will repair timber deck boards and curbing, which must be routinely replaced because chemically-treated lumber is not permitted over Lapwai Creek, a critical habitat for salmon. Metal bridge supports and components also require scraping and sanding, followed by a minimum of one coat of paint, to sustain bridge integrity and structural soundness. The project duration is one week.
The contractor will establish measures to prevent contaminating Lapwai Creek and the creek bed.
A containment tarp or similar suspension device customarily used to capture work debris is preferred. The contractor is responsible to properly dispose waste materials and debris at an approved waste facility.
The contractor will not use equipment in the watered streambed of Lapwai Creek. All repairs requiring equipment will be conducted from the creek banks, bridge, or road surface. The contractor will repair, replant, and reseed all vegetation including maintained lawns damaged during the course of the project.
1.1. 2 Location
The work is located at Nez Perce National Historical Park Headquarters Complex, in Spalding, Idaho.
1.2 WORK SCHEDULING
Work will be conducted Monday through Friday from 7:00 a.m. to 4:30 p.m., with provision for daytime extension as park and contractor determine. Weekend work may be conducted as mutually agreed, particularly as expedites restoring park operations and public bridge access.
Temporary closure will be permitted, particularly during deck plank replacement. In order to minimize disruption of park operations, the contractor will submit a detailed work plan 30 days prior to start. The plan will describe work activities and anticipated bridge closure. If for some reason bridge closure must be extended, the contractor shall so inform the park to enable public notice.
1.3 OCCUPANCY OF PREMISES
The buildings are in normal occupied mode during performance of work under this Contract.
Before work is started, the Contractor shall arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment.
1.4 EXISTING WORK
In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer.
1.5 TEMPORARY SERVICES
A. Telephone: There are no public pay telephones available at the work site.
B. Water: Contractor shall provide cool, potable water for construction personnel in locations convenient to work stations. Potable water is available on site.
C. Sanitary facilities: Contractor shall provide and maintain within the construction area minimum field-type sanitary facilities approved by the Contracting Officer. Maintain these conveniences at all times without nuisance. Include provisions for pest control and elimination of odors. Government toilet facilities will not be available to Contractor's personnel.
1.6 STORAGE
An onsite fenced staging area is available within ½ mile for contractor equipment and material, and unsecured staging is available at a designated location at the worksite. The park accepts no liability or responsibility for contractor materials and equipment stored or otherwise kept on its premises.
1.7 EMPLOYEE PARKING
Contractor employees will park privately owned vehicles in an area designated by the
Contracting Officer. This area will be within reasonable walking distance of the construction site. Contractor employee parking must not interfere with existing and established parking requirements of the government installation.
--End of Section--
SECTION 02
LIST OF SERVICES
PART 1 GENERAL
1.1 DESCRIPTION
The intent of this section is to explain in detail the work to be performed under this contract.
All items listed in this section must be completed to satisfy the contract and fall under one of the two bid items.
1.2 REDECKING BRIDGE
A. Replace approximately 1400 square feet of 2”x 12” (actual) timber decking planks fastened with equivalent sized nails to the existing ones. The timbers will be replaced with number 2 or better grade red fir. Deck boards will be installed with a gap of 1/8” to
1/4” of an inch between boards to allow for expansion of boards. B. Remove vegetation and debris from decking joints.
C. Replace the three rows of 6”x 8” (actual) curbing timbers in their entirety fastened with hardware of identical size and location spanning the 64’ of bridge. Curbing timbers will be replaced with fir timbers of equal or better grade.
1.3 REPAINTING AND FINISHING OF METAL COMPONENTS
A. Scrape, clean, and paint all steel components with two coats with a metal preservative type paint that matches existing color.
B. Install/fabricate steel coping at the 8 ends of glulam floor beams to help preserve and prevent the beams from further separation and deterioration. Coping will extend from the bridge edge to the end of the beam. Coping will encapsulate enough of the beam to prevent further separation. Coping will be painted with two coats of paint that matches the existing color of the bridge.
SECTION 0300
DEFINITION OF LINE ITEMS
PART 1 GENERAL
1.1 DESCRIPTION
A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends and another begins.
B. If no contract line item exists for a portion of the work, include the costs in a related item
1.2 CONTRACT LINE ITEM NO. 1 – REDECKING BRIDGE
A. This item includes the demolition and removal of existing bridge deck and installation of new bridge decking.
B. Measurement will be by Lump sum.
C. Payment will be made at the contract Lump sum price.
1.3 CONTRACT LINE ITEM NO. 2 –REPAINTING AND FINISHING OF METAL
COMPONENTS
A. Scrape, clean, and paint all steel components with two coats with a metal preservative type paint that matches existing color.
B. Measurement will be by Lump sum.
C. Payment will be made at the contract Lump sum price.
Section 0400
SECTION 0500
ACCIDENT PREVENTION
PART 1 GENERAL
1.1 DESCRIPTION
A. The work of this section consists of establishing an effective accident prevention program and providing a safe environment for all personnel and visitors. The
Contractor is responsible to conduct his work safely and protect the health and safety of his employees, subcontractors and visitors to the job site.
1.2 SUBMITTALS
A. Accident Prevention Program: Before on-site work begins, submit for approval an accident prevention program that complies with OSHA and project requirements. The
Contracting Officer will review the proposed program. If the program requires any revisions or corrections, the Contractor shall resubmit the program within 10 days. No progress payments will be made until the program is approved. The program shall include:
1. Name of responsible supervisor to carry out the program.
2. Weekly safety meetings.
3. First aid procedures.
4. Outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to ensure property protection and safety of the public, National
Park Service personnel, and Contractor's employees.
5. Training, both initial and continuing.
6. Planning for possible emergency situations, such as floods, fires, cave-ins, slides, explosions, power outages, and wind storms. Such planning shall take into consideration the nature of construction, site conditions, and degree of exposure of persons and property.
7. Housekeeping as it relates to safety
8. Fire Protection
9. Fall Protection
10. Hazardous Materials and Hazardous Waste Management
B. Submit a copy of test reports, as required by OSHA, for personnel working with hazardous materials.
C. Submit a report of safety meetings and of inspections.
D. Upon request, submit proof of employees' qualifications to perform assigned duties in a safe manner.
1.3 QUALITY ASSURANCE
A. Clauses entitled "Accident Prevention" and "Permits and Responsibilities" of the contract.
In case of conflicts between Federal, state, and local safety and health requirements, the most stringent shall apply. Equipment or tools not meeting OSHA requirements will not be allowed on the project sites. Failure to comply with the requirements of this section and related sections may result in suspension of work.
B. Qualifications of Employees:
i. Ensure that employees are physically qualified to perform their assigned duties in a safe manner.
ii. Do not allow employees to work whose ability or alertness is impaired because of drugs, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury.
iii. Operators of vehicles, mobile equipment, hoisting equipment, and hazardous plant equipment shall be able to understand signs, signals, and operating instructions, and be capable of operating such equipment. Provide operating instructions for all equipment. Newly hired operators shall be individually tested by an experienced operator or supervisor to determine if they are capable of safely operating equipment.
1.4 ACCIDENT REPORTING
A. Reportable Accidents: A reportable accident is defined as death, occupational disease, traumatic injury to employees or the public, property damage by accident in excess of
$100, and fires. Notify Contracting Officer immediately in the event of a reportable accident. Within 7 days of a reportable accident, fill out and forward to Contracting
Officer an Accident/Property Damage Report (Form CM-22). Form may be obtained from the Contracting Officer.
B. All Other Accidents: The Contractor shall report all other accidents to the Contracting
Officer as soon as possible and assist the Contracting Officer and other officials as required in the investigation of the accident.
PART 2 PRODUCTS
2.1 FIRST AID FACILITIES
A. Provide adequate facilities for the number of employees and the type of construction at the site.
2.2 PERSONNEL PROTECTIVE EQUIPMENT
A. Meet requirements of NIOSH and MSHA.
B. EMERGENCY INSTRUCTIONS
A. Provide workers with instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at the work site.
PART 3 EXECUTION
3.1 EGRESS
A. Provide and maintain adequate egress at all times in accordance with the Life Safety Code
(NFPA 101). No corridor, aisle, stairway, door, or exit shall be obstructed or used in a manner that interferes with egress.
3.2 PROTECTIVE EQUIPMENT
A. Inspect personal protective equipment, such as fall protection, daily and maintain in a serviceable condition. Clean, sanitize, and repair, as appropriate, personal items before issuing them to another individual.
B. Inspect and maintain other protective equipment and devices before use and on a periodic Basis to ensure safe operation.
C.
3.3 SAFETY MEETINGS
A. As a minimum, conduct weekly safety meetings for all levels of employees and document. Notify the Contracting Officer of meeting dates and times. These meetings shall be used to review the effectiveness of the Contractor's safety effort, to resolve current health and safety problems, to provide a forum for planning safe construction activities, and for updating the accident prevention program. The
Contracting Officer or COR may attend the meeting and enter the results of the meetings into the daily log.
3.4 HARD HATS AND PROTECTIVE EQUIPMENT AREAS
A. A hard hat area will be designated by the Contracting Officer. The hard hat area shall be posted by the Contractor in a manner satisfactory to the
Contracting Officer.
B. It is the Contractor's responsibility to require all those working on or visiting the site to wear hard hats and other necessary protective equipment at all times. As a minimum, provide three hard hats for use by visitors.
3.5 TRAINING
A. First Aid: Provide adequate training to ensure prompt and efficient first aid.
B. Hazardous Material: Train and instruct each employee exposed to hazardous material in safe and approved methods of handling and storage. Hazardous materials are defined as explosive, flammable, poisonous, corrosive, oxidizing, irritating, or otherwise harmful substances that could cause death or injury.
Comply with Section 09 90 80 “Lead Based Paint Treatment and Painting”.
3.6 SAFETY COMPLIANCE
A. The Contractor must comply with all OSHA federal regulations (29 CFR 1910) and Washington state regulations governing the safety of workers performing the type of work described in this contract. At or before the pre-construction conference, the Contractor must submit for approval of the Contracting Officer a written safety plan demonstrating compliance with all applicable federal and state safety regulations.
3.7 FIRE PREVENTION AND PROTECTION:
A. The Contractor must provide all equipment and procedures necessary for fire protection on site.
B. Hazard Control: The contractor must take all necessary precautions to prevent fire during construction. The Contractor must not store flammable or combustible liquids in non-approved containers and provide adequate ventilation during use of volatile or noxious substances.
C. Spark Arresters: Equip all gasoline or diesel powered equipment with spark arresters approved by the U. S. Forest Service. Locate internal combustion equipment so that exhausts discharge well away from combustible materials.
D. Smoking within buildings or temporary storage sheds is prohibited. The Contractor must collect all cigarette butts and dispose of them off site.
3.8 BARRIERS
A. Contractor must fence, barricade, or otherwise block off the immediate work area to prevent unauthorized entry to the work area and to ensure the safety of pedestrians and vehicles. Barrier material may be new or used, but must be suitable for intended purpose. Contractor must post the construction site with caution signs to alert occupants and visitors of safety hazards.
SECTION 0600
CONTRACTOR QUALITY CONTROL
PART 1 GENERAL
1.1 DESCRIPTION
A. The work of this section consists of preparing and executing a Quality Control Program.
1.2 RELATED REQUIREMENTS
A. "Inspection of Construction" clause of the contract.
1.3 SUBMITTALS
A. Quality Control Plan:
1. After contract award and before the Pre-Construction conference, submit for approval a written Contractor Quality Control (CQC) plan.
2. If the plan requires any revisions or corrections, the Contractor shall resubmit the plan within 10 days.
3. The Government reserves the right to require changes in the plan during the contract period as necessary to obtain the quality specified.
4. No change in the approved plan may be made without written concurrence by the
Contracting Officer.
5. The plan shall include:
a. A list of personnel responsible for quality control and assigned duties. Include each person's qualifications.
b. A copy of a letter of direction to the Contractor's Quality Control Supervisor outlining assigned duties.
c. Names, qualifications, and descriptions of laboratories to perform sampling and testing, and samples of proposed report forms.
d. Methods of performing, documenting, and enforcing quality control of all work.
e. Methods of monitoring and controlling environmental pollution and contamination as required by regulations and laws.
B. Contractor's Quality Control Daily Reports: Submit showing all inspections and tests on the first workday following the date covered by the report. Utilize the forms attached at the end of this section.
C. If the CQC plan and Quality Control Daily Reports are not submitted as specified, the Contracting Officer may retain all payments until such time a plan is accepted and implemented, or may retain payments for work completed on days there are no Quality Control daily reports.
1.4 QUALITY ASSURANCE
A. General:
1. The quality of all work shall be the responsibility of the Contractor. Testing shall be the responsibility of an independent testing laboratory.
2. Inspect and test all work as needed to ensure that the quality of materials, workmanship, construction, finish, and functional performance is in compliance with applicable specifications and drawings.
3. Quality Control Daily Reports shall be completed by the Quality Control
Supervisor.
B. Quality Control Staff:
1. The Contractor's Quality Control Supervisor may also perform the duties of
Project Superintendent.
2. The Contractor's designated Quality Control Supervisor shall be on the project site whenever contract work is in progress.
3. The Contractor's job supervisory staff may be used to assist the Quality
Control Supervisor supplemented, as necessary, by additional certified testing technicians.
PART 2 EXECUTION
2.1 OFF-SITE CONTROL
A. Items that are fabricated or assembled off-site shall be inspected for quality control at the place of fabrication.
2.2 ON-SITE CONTROL
A. Notification:
1. Notify the Contracting Officer at least 48 hours in advance of the preparatory phase meeting.
2. Notify the Contracting Officer at least 24 hours in advance of the initial and follow-up phases.
B. Inspect and test as work progresses to ensure compliance with contract requirements until completion of work.
C. Additional Inspection may be required on the same feature of work for the following reasons:
1. Quality of on-going work is unacceptable.
2. Changes occur in the applicable quality control staff, on-site production supervision, or work crew.
3. Work on a particular feature of work is resumed after a substantial period of inactivity.
2.3 DOCUMENTATION
A. Maintain Quality Control Daily Reports, Daily Test Report Information Sheets, and of quality control activities and tests.
B. Quality Control Daily Reports may not be substituted for other written reports required under clauses of the contract, such as Disputes, Differing Site
Conditions, or Changes.
2.4 ENFORCEMENT
A. The Contractor shall stop work on any item or feature pending satisfactory correction of any deficiency noted by the quality control staff or the Contracting
Officer.
CONTRACTOR'S QUALITY CONTROL DAILY REPORT
REPORT NO. SHEET 1 OF
6. REMARKS:
PROJECT CONTRACT NO. DATE
PARK TIVE ON THE CONTRACTOR'S REPRESENTA
JOB
WEATHER (Rain, Snow, Cloudy, Windy, etc.)
RAINFAL
L Inches
TEMPERATU
RE
GROUND CONDITIONS (Dry, D amp, Wet, Frozen, etc.)
MAX. MIN.
PRIME CONTRACTOR 1.
NO. EMPLOYEES BY JOB
CATEGORIES
Hours Y EQUIPMENT HEAV
B ON JO
NO.
UNITS
. WORKING HRS
YE
S
N O
Comments
ACTOR: WORK PERFORMED BY PRIME CONTR
MATERIALS DELIVERED SITE OFFICIAL VIS ITORS TO
2 A. SUBCONTRACTOR, re tha If mo ( n one :
subcontractor use copies of following page.)
NO. EMPLOYEES BY JOB
CATEGORIES
Hours HEAVY EQUIPMENT
ON JOB
NO.
UNITS
HRS . WO RKING
YE
S
N O
Comments
WORK PERFORMED BY SUBCONTRACTOR:
) Inspections performed, results, and corrective actions ( SPECIFIC INSPECTIONS: 3.
Complete and attach Test Report Information ( Check if any testing was performed today. 1 TESTING: 4.
Sheets.)
Type and Location of Testing:
VERBAL INSTRUCTION RECEIVED FROM GOVERNMENT ON CONSTRUCTION DEFICIENCIES OR 5.
RE-TESTING REQUIRED:
7. CERTIFICATION:
I certify that the above report is complete and correct and that I, or my authorized representative, have inspected all work performed this day by the prime contractor and each subcontractor and determined that all materials, equipment, and workmanship are in strict compliance with the plans and specifications except as may be noted above.
Contractor's Quality Control Representative
SUBCONTRACTOR WORK CONTINUED: CONTRACT NO. REPORT NO.
SHEET OF
SUBCONTRACTOR, 2
NO. EMPLOYEES BY JOB
CATEGORIES
Hours HEAVY EQUIPMENT
ON JOB
NO.
UNITS
HRS. WORKING
NO Comments YES
WORK PERFORMED BY SUBCONTRACTOR:
SUBCONTRACTOR, 2
NO. EMPLOYEES BY JOB
CATEGORIES
Hours HEAVY EQUIPMENT
ON JOB
NO.
UNITS
HRS. WORKING
Comments NO YES
WORK PERFORMED BY SUBCONTRACTOR:
2 SUBCONTRACTOR,
NO. EMPLOYEES BY JOB
CATEGORIES
Hours HEAVY EQUIPMENT
ON JOB
NO.
UNITS
HRS. WORKING
YES Comments NO
WORK PERFORMED BY SUBCONTRACTOR:
SUBCONTRACTOR, 2
NO. EMPLOYEES BY JOB
CATEGORIES
Hours HEAVY EQUIPMENT
ON JOB
NO.
UNITS
HRS. WORKING
YES NO COMMEN
TS
WORK PERFORMED BY SUBCONTRACTOR:
DAILY TEST REPORT INFORMATION SHEET
CERTIFICATION:
CONTRACT NO. REPORT NO. SHEET OF
1. Individual Making Inspection or Test:
2. Testing Laboratory; Name: Phone #:
Address:
3. Description of Work and Test Method:
Location of Samples and Tests or Inspections: 4.
Specification Section: 5.
6. Inspection or Test Data:
Test Results and Interpretations of Test Results: 7.
8. Comments or Professional Opinion About Compliance of Inspected Work or Tested Work with contract Document Requirements:
9. Recommendations:
10. Corrective Actions Taken:
I certify that the above testing report is complete and correct and that all testing performed this day for this contract is in strict compliance with the plans and specifications except as noted above.
SECTION 0700
PROJECT CLOSEOUT
PART 1 GENERAL
1.1 DESCRIPTION
A. The work of this section consists of final cleanup, closeout submittals, and final inspection procedures.
PART 2 PRODUCTS
2.1 CLEANING MATERIALS
A. As recommended by the manufacturer of surface to cleaned.
3.1 CLEANING
A. Before scheduling the final inspection, remove all tools, equipment, surplus materials, and rubbish. Restore or refinish surfaces that are damaged due to work of this contract to original condition. Remove grease, dirt, stains, foreign materials, and labels from finished surfaces. Thoroughly clean building interiors. Pick up all construction debris from the site. At time of final inspection, project shall be thoroughly clean and ready for use.
3.2 CLOSEOUT SUBMITTALS
A. Submit before final inspection request.
1. Waste Management Worksheets.
3.3 SUBSTANTIAL COMPLETION AND FINAL INSPECTION
A. When project, or designated portion of project, is substantially complete, request in writing a final inspection. Upon receipt of written request that project is substantially complete, the Contracting Officer will proceed with inspection within 10 days of receipt of request or will advise the Contractor of items that prevent the project from being designated as substantially complete.
B. If, following final inspection, the work is determined to be substantially complete, Contracting Officer will prepare a list of deficiencies to be corrected before final acceptance and issue a Letter of Substantial Completion. Contractor shall complete the work described on the list of deficiencies within 21 calendar days, as weather permits. If the Contractor fails to complete the work within this time frame, the Contracting Officer may either replace or correct the work with an appropriate reduction in the contract price or charge for re-inspection costs in accordance with the Inspection of Construction clause of the contract.
C. If, following final inspection, the work is not determined to be substantially complete;
Contracting Officer will notify Contractor in writing. After completing work, Contractor shall request a new final inspection. All re-inspection costs may be charged against the Contractor in accordance with the Inspection of Construction clause of the contract.
3.4 FINAL ACCEPTANCE OF THE WORK
A. After all deficiencies have been corrected, a Letter of Final Acceptance will be issued.
Project Waste Management Plan Worksheet
A B C D E F G H I J
Material
Quantity
Recycled
(in tons)
Quantity
Salvaged or
Reused
(in tons)
A + B =
Total
Quantity
Diverted from
Landfill
Quantity
To Landfill
(in tons)
C + D =
Total
Quantity
Generate d
(in tons) Tip
Fee/Ton at
Landfill
C x F =
Tip Fee
Savings resulting from Landfill
Diversion
Cost of
Recycling
(R), Salvage (S), or
Reuse (Re)
(Specify R, S, or Re)
Revenue from Recycling, Salvage, or Reuse
G - H + I
Total
Cost
(-) or
Savings
(+) from
Diversion
Asphalt/Concrete
Brick/Masonry/Tile
Building Materials
(doors, windows, fixtures, shingles, lumber, insulation, sheet goods, etc.)
Carpet
Carpet Padding, Foam Only
Cardboard
Ceiling Tile
Drywall
Glass
Scrap Metal
Aluminum
Copper
Steel
Unpainted Wood &
Pallets
Yard Trimmings, Brush, Trees, Stumps, etc.
Garbage/Trash
Other
Column Totals
Total
Quantity
Recycled
Total
Quantity
Reused or
Salvaged
Total
Quantity
Diverted from
Landfill
Total
Quantity
To
Landfill
Total
Quantity
Generated
Tip Fee
Savings from
Diversion
Total Cost of
Recycling, Salvage, or
Reuse
Revenue from Recycling, Salvage, or Reuse
Total
Cost
(-) or
Savings
(+) from
Diversion
Percentage Diverted = ______________ (C divided by E from Column Totals) Should meet 60% diversion goal
*See Appendix B for Standard Solid Waste Volume to Weight Conversions
Appendix B
STANDARD SOLID WASTE CONVERSIONS
The following sections provide conversions for solid waste and recyclable materials. Section 1 provides formulas to convert solid waste volume (cubic yards) into tons. Section 2 includes conversion factors to estimate the volume and weight of a number of solid waste and recyclable materials.
1. To convert cubic yards to tons:
A: For un-compacted trash, to convert the units of cubic yards into tons, using the standard density of trash value of 250 pounds per cubic yard:
Using “X” cubic yards, multiply by 250 pounds per cubic yard, divide by 2000 pounds per ton, to obtain value in tons.
“X” cubic yards x 250 pounds ÷ 1 ton = ______ tons cubic yard 2000 pounds This equals:
“X” cubic yards x 0.125 tons = _______ tons cubic yard
In this case, 8 cubic yards = one ton.
B: To determine your own density value for un-compacted trash (instead of using the standard value of 250 pounds per cubic yard), using a 32 gallon trash can:
(1) Weigh the trash can both filled and empty (use a full 32 gallon trash can filled with trash roughly level to the top);
(2) Subtract the empty weight from the filled weight to get the weight of trash ( filled weight – empty weight = weight of trash);
(3) Use the formula, using “Y” your weight of trash (pounds), divided by 0.15 cubic yards per 32 gallon trash can, to obtain your value in pounds per cubic yard; which equals:
“Y” pounds / 0.15 cubic yards = ________ pounds
32 gallon can 32 gallon can cubic yard
(4) Substitute this value for the 250 pounds per cubic yard value in Method A above.
This would be the more accurate measure of your park’s specific waste.
C: For compacted trash, to convert cubic yards into tons:
To use a compaction ratio, multiply the appropriate ratio times the un-compacted trash weight in Formula
A to obtain the compacted trash weight.
“X” cubic yards x 3 (compaction ratio) x 250 pounds x 1 ton = ______ tons
1 cubic yard 2000 pounds
Typical compaction ratios for trash: 3:1 (typical)
4:1 (higher-compaction vehicles)
If you or your hauler don’t know the compacting ratio, the typical values for compacted trash are 500 to 1000 lbs./cubic yard, average 700 lbs./cubic yard. Use 700 lbs. per cubic yard if you don’t have more accurate re
For compacted trash, 0.4 is used instead of 0.125 in Formula A:
“X” cubic yards x 0.4 tons = _______ tons cubic yard
D: To convert container size to cubic yards for un-compacted waste:
If you don't have size and weight information on your specific containers, then these typical values can be used:
1 cubic yard = 202 gallons
32 gallon can = 0.15 cubic yards
60 gallon tote = 0.30 cubic yards
90 gallon tote = 0.45 cubic yards
2. EPA’s Standard Volume-to-Weight Conversion Factors
Category
Recyclable Materials
(u/c = uncompacted/ compacted & baled) Volume
Estimated Waste
( in pounds )
FOOD SCRAPSA Food scraps, solid and liquid fats 55-gal drum 412
GLASS BottlesB
Whole Bottles
Semicrushed Crushed (mechanically)
Uncrushed to manually broken
Refillable Whole BottlesC
Refillable beer bottles
Refillable soft drink bottles
8 oz glass container
1 yd3
1 yd3
1 yd3
55-gal drum
1 case = 24 bottles
1 case = 24 bottles
1 case = 24 bottles
500-700
1,000-1,800
1,800-2,700
10-14
12-22
LEAD-ACID
BATTERIES
CarD
TruckE
MotorcycleE
1 battery
1 battery
1 battery
39.4 lb
53.3 lb lead and plastic
9.5 lb lead and plastic
METALS Aluminum CansF
Whole Compacted (manually) Uncompacted
Ferrous (tin coated steel cans) G
Whole
Flattened
Whole
Major AppliancesE
Air conditioners (room)
Dishwashers
Dryers (clothes)
Freezers
Microwave ovens
Refrigerators
Ranges Washers (clothes)
Water heaters
1 yd3
1 yd3
1 full grocery bag
1 case = 24 cans
1 yd3
1 yd3
1 case = 6 cans
1 unit
1 unit
1 unit
1 unit
1 unit
1 unit
1 unit
1 unit
1 unit
50-75
250-430
1.5
0.9
64.2
181.1
SECTION
02410033
PAPER NewspaperF
Uncompacted
Compacted/baled
12 in. stack Old Corrugated ContainersF
Uncompacted
Compacted
Baled
Computer PaperF
Uncompacted
Compacted/baled
1 case
White LedgerF
Stacked (u/c)
Crumpled (u/c)
Ream of 20# bond; 8.5”x11”
Ream of 20# bond; 8.5”x14”
White ledger pads
Tab CardsF
Uncompacted
Compacted/baled
Miscellaneous Paper
Yellow legal padsF
Colored message padsF
Telephone directoriesH
Mixed Ledger/Office PaperF
Flat (u/c)
Crumpled (u/c)
1 yd3
1 yd3
1 yd3
1 yd3
1 yd3
1 yd3
1 yd3
2,800 sheets
1 yd3 1 yd3 ream
= 500 sheets 1 ream = 500 sheets
1 case = 72 pads
1 yd3
1 yd3
1 case = 72 pads
1 carton = 144 pads
1 yd3
1 yd3
1 yd3
360-505
720-1,000
50-150 (300)
300-500
700-1,100
1,310
375-465/755-925
110-205/325
6.4
1,215-1,350
380/755
110-205/610
PLASTICJ PET (Soda Bottles)
Whole bottles (uncompacted)
Whole bottles (compacted)
Whole bottles (uncompacted)
Baled
Granulated
Granulated
8 bottles (2 L size)
HDPE (Dairy)
Whole (uncompacted)
Whole (compacted)
Baled
HDPE (Mixed)
Baled
Granulated
Granulated
Other Plastic
Uncompacted
Compacted/baled
Mixed PET and HDPE (Dairy)
Whole
Film
1 yd3 1 yd3 gaylord
30” x
62” semiload gaylord
16 L
1 yd3
1 yd3
32” x 60”
32” x 60” gaylord semiload
1 yd3
30-40
40-53
500-550
30,000
700-750
400-500
800-1,000
42,000
400-700
Baled
Baled
1 yd3 1 yd3 semiload 30” x 42” x 48”
400-700
TEXTILESH Mixed Textiles 1 yd3
TIRES Car Tires
Whole tireE
Crumb rubberK
Truck Tires
Whole tireE
Crumb rubberK
1 tire
1 tire
1 tire
1 tire
WOOD Wood chipsL
PalletsF
1 yd3
30-100 (40 avg )
YARD
TRIMMINGSF
Grass Clippings
Uncompacted
Compacted
Leaves
Uncompacted
Compacted
Vacuumed
1 yd3
1 yd3
1 yd3
1 yd3
1 yd3
350-450
550-1,500
200-250
300-450
FURNISHINGSE Foam rubber mattress 1 mattress 55
MUNICIPAL
SOLID WASTEM
Residential waste
(uncompacted at curb)
Commercial-industrial waste
(uncompacted)
MSW (compacted in truck)
MSW (landfill density)
1 yd3
1 yd3
1 yd3
1 yd3
150-300
300-600
500-1,000
750-1,250
A. Information obtained from Washington State.
B. Draft National Recycling Coalition Measurement Standards and Reporting Guidelines presented to NRC membership.
October 31, 1989.
C. Personal communication with a representative from Allwaste. November 6, 1995.
D. Battery Council International. 1995. 1994 National Recycling Rate Study.
E. U.S. EPA. 1995. Methodology for Characterization of Municipal Solid Waste in the United States: 1994
Update. EPA530-R-96-001. Washington, DC.
F. U.S. EPA. 1993. Business Guide for Reducing Solid Waste. EPA530-K-92-004. Washington, DC.
G. Personal communication with a representative from the Steel Recycling Institute. November 1, 1995.
H. Information obtained from Massachusetts State.
I. Information obtained from New Jersey and New York States.
J. Personal communication with a representative from the American Plastics Council. November 2, 1995.
K. Personal communication with a representative from the Scrap Tire Management Council. November 6, 1995.
L. Information obtained from Northeast Forest Products, Martin Mulch Company, and the Solid Waste
Association of North America.
M. Solid Waste Association of North America, Manger of Landfill Operations Training and Certification Course.
January 1989.
N. Information obtained from New Jersey and New York States.
SECTION 0800
CONTAMINATION
PREVENTION
PART 1 GENERAL
1.1 PROJECT DESCRIPTION
1.1.1 General Requirements
Do not begin demolition until authorization is received from the Contracting Officer. The work includes demolition and removal of resulting rubbish and debris. Remove rubbish and debris from Government property daily, unless otherwise directed. Store materials that cannot be removed daily in areas specified by the Contracting Officer.
The contractor will establish measures to prevent contaminating Lapwai Creek and the creek bed. A containment tarp or similar suspension device customarily used to capture work debris is preferred. The contractor is responsible to properly dispose waste materials and debris at an approved waste facility.
1.2 ITEMS TO REMAIN IN PLACE
Take necessary precautions to avoid damage to existing items to remain in place, to be reused, or to remain the property of the Government. Repair or replace damaged items as approved by the Contracting Officer. Coordinate the work of this section with all other work indicated. Construct and maintain shoring, bracing, and supports as required. Ensure that structural elements are not overloaded. Increase structural supports or add new supports as may be required as a result of any cutting, removal, deconstruction, or demolition work performed under this contract. Provide new supports and reinforcement for existing construction weakened by demolition or removal work. Repairs, reinforcement, or structural replacement require approval by the Contracting Officer prior to performing such work.
1.2.1 Existing Construction Limits and Protection
The contractor will establish measures to prevent contaminating Lapwai Creek and the creek bed. A containment tarp or similar suspension device customarily used to capture work
1.2.2 Weather Protection
Protect building interior and materials and equipment from the weather at all times. Have materials and workmen ready to provide adequate and temporary covering of exposed areas.
1.3 QUALITY ASSURANCE
1.3.1 Dust and Debris Control
The contractor will establish measures to prevent contaminating Lapwai Creek and the creek bed. A containment tarp or similar suspension device customarily used to capture work
1.4 Submittal
Complete and submit Waste Management Worksheet, see Section 01 77 00 Project CloseOut.
PART 2 PRODUCTS -Not used.
3.1 EXISTING FACILITIES TO BE REMOVED
3.1.1 BRIDGE DECKING
Remove existing bridge decking and associated components in their entirety down to sub deck.
Notify the COR of rot and water-damaged sub deck.
3.2 CLEANUP
Remove and transport the debris in a manner that prevents spillage on streets or adjacent areas. Apply local regulations regarding hauling and disposal.
3.3 DISPOSAL OF REMOVED MATERIALS
3.3.1 Regulation of Removed Materials
Dispose of debris, rubbish, scrap, and other non-salvageable materials resulting from removal operations with all applicable federal, state and local regulations.
3.3.2 Burning on Government Property
Burning of materials removed from demolished and deconstructed structures will not be permitted on Government property.
3.3.3 Removal from Government Property
Transport waste materials removed from Government property for legal disposal.
-- End of Section --