FMD_PreBID_Bullets.pdf
PDF 15 KB Posted
- Attached to
- CADES COVE SEWAGE LAGOON SITE UPGRADES
- Solicitation number
- P16PS02576
About this file
Site Visit Bullets
View the file
Other files
| File | Type | Posted |
|---|---|---|
| P16PS02576-Highlighted.pdf | ||
| Sol_P16PS02576_Amd_000001.pdf | ||
| 01100_Summary_of_Work_-_Lagoon_Repairs.docx | DOCX document | |
| CCLagoon_LOCATIONS.pdf | ||
| Specs_Lagoon_site_upgrades_7-28-2016.pdf | ||
| Clauses_-_UCF.docx | DOCX document | |
| Lagoon_Structure_-_Elect_details.pdf | ||
| Sol_P16PS02576.pdf | ||
| DB_WD_TN160078.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Great Smoky Mountains National Park Facility Management Division
National Park Service U.S. Department of the Interior
Pre-Solicitation Meeting – Cades Cove Lagoon
1. Introductions / Roles and Responsibilities
2. Contracting Officer’s overview
3. GRSM Special Issues
a. Safety – wildlife, worksite, visitor, motorist
b. Communications – cell phones have limited coverage in the park
c. Environmental Topics– it’s a park, respect it as such
Prevention of exotic weeds; clean equipment before bringing it into Park Cultural Resources – It is a historic district – archaeologist will be onsite during work.
Natural Resources - Wildlife (bear management issues)) Erosion control, Mulch, use of straw bales/straw mulch is not permitted for use in the park Food storage (lunch) – pack it in, pack it out, secure all food in a cab of a vehicle or equipment; do not store coolers in the beds of trucks, do not discard food waste in construction dumpsters. Remove food waste, wraps daily from the construction site
Construction debris shall be removed from the park Spill Kits and pollution prevention
d. Law Enforcement – Expectations are contractor complies with all motor vehicle regulations and laws. Trucks to enter through closest entrance. No special provisions because your working for the Park.
e. Firearms – No carrying firearms while working
f. Inclement Weather Access – Access will not be permitted until snow removal NPS snow removal operations are complete unless otherwise stated
g. Progress meetings identify a reoccurring day that works for all parties and time (determine meeting frequency, weekly or bi-weekly). – Only required if project falls behind
Additional Comments at Site Visit
- On Electrical pricing, contractor to use an RV pedestal with loop feed lugs, breaker and at least on 20 Amp receptacle.
File details come from the government source that posted it. Updated .