Sol_P15PS00694_Amd_000005.pdf
PDF 91 KB Posted
- Attached to
- Devil's Postpile Impacted Soil Remediation Federal contract opportunity
- Solicitation number
- P15PS00694
About this file
P15PS00694
View the file
Other files for this federal contract opportunity
Show all 22
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
P15PS00694
x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT
THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
PPG
San Francisco CA 94123 Building 201, Fort Mason
DOI, NPS, PWR - GOGA MABO
PPG
San Francisco CA 94123 Building 201, Fort Mason
NPS, PWR - GOGA MABO
12060406/25/2015000005
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
05/08/2015
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Suggested COR: SMITCHE2
The purpose of this amendment is to incorporate a revised statement of work and contract price schedule, respond to questions from potential offerors, incorporate information from pre-proposal meeting/site visit, incorporate a clause into Section H regarding options, incorporate provisions to Section M regarding options, and extend the due date for receipt of offers.
The date and time set for receipt of offers is extended to July 7, 2015 at 1300 PDT(1:00 pm
PDT).
Official Government responses to questions received from offerors are below and are
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Dane Johnson
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
NSN 7540-01-152-8070
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 3
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
P15PS00694/000005
incorporated into the solicitation and any resultant contract. ANY FUTURE QUESTIONS
RECEIVED MAY OR MAY NOT BE ANSWERED AT THE
DESCRETION OF THE GOVERNMENT.
A revised statement of work and contract price schedule, both dated June 24, 2015, are attached and incorporated into the solicitation and any resultant contract.
The minutes and sign in sheet from the pre-proposal meeting/site visit are attached and incorporated into the solicitation and any resultant contract.
The following clause is incorporated into Section
H of the solicitation: SPECIAL CLAUSE 1: OPTION
FOR ADDITIONAL SERVICES SEPARATELY PRICED LINE
ITEMS - The Government may require the delivery of the numbered line items identified in the
Schedule as option items at the price stated in the Schedule. The Contracting Officer may unilaterally exercise the option by written notice to the Contractor within 180 days after contract award. Performance of added line item tasks shall be at the price negotiated in the contract Schedule. (End of clause)
The following provisions are incorporated into
Section M of the solicitation: PROVISIONS
SPECIAL PROVISION 1: EVALUATION OF OPTIONS
EXERCISED AT TIME OF CONTRACT AWARD - Except when it is determined not to be in the Government¿s best interests, the Government will evaluate the total price for the basic requirement together with any option(s) exercised at the time of award. (End of provision) SPECIAL PROVISION 2:
EVALUATION OF OPTIONS - Except when it is determined not to be in the Government¿s best interests, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s). (End of provision)
Q1 - Are there any weight or size restrictions for vehicles on the roads leading to the remediation site?
A1 - Yes, see SOW paragraph 3.7.
Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
3 3
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
P15PS00694/000005
Q2 - Are there any erosion controls required post-construction after the grading is complete but prior to the revegetation that is to be performed by the NPS?
A2 - Yes, see SOW paragraph 3.15.1.