P09 Final SOW Upgrade_Lenel System 08-03-2020.pdf

PDF 183 KB Posted

Attached to
N063--RO355 Upgrade Lenel Physical Security System Federal contract opportunity
Solicitation number
36C10E20Q0249
Issued by
Department of Veterans Affairs Veteran Benefits Administration Headquarters

View the file

Other files for this federal contract opportunity

Other files attached to N063--RO355 Upgrade Lenel Physical Security System, newest first.
File Type Posted
36C10E20Q0249 0002_1.docx DOCX document
S02 Rules of Behavior.pdf PDF
36C10E20Q0249.docx DOCX document
2015-5717 REV12.pdf PDF
36C10E20Q0249 Instructions to Offerors 08-03-2020.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK FOR TO UPGRADE LENEL SECURITY SYSTEM AT SAN

JUAN REGIONAL OFFICE (355).

1. General Information:

1.1. Title of Project: Procurement to Upgrade Lenel Physical Security System.

1.2. Scope of Work- Background: The San Juan Regional Office needs to upgrade the Lenel

Security System and its components Dongle Id: 49124, PELCO SYSTEM 9760 and DELL PRECISION R5400 to include, something equal or compatible with NVR 16 Channel 24TB, cameras PELCO. Also, to include six (6) additional Duress Buttons model: Honeywell or equal, replacing twenty-two (22) cameras and adding ten (10) cameras. Contractor shall provide one (1) Physical Access Control System (PACS) model: HID MultiClass or equal at the Private Security Officers Control Room in the basement.

The main Physical Security System with rack and DVR is located in the Security Guard Control Room and remote system in Room Office 232 (PIV Room). Replace the Lenel Precision Towers for the Control Room in the basement model: Dell Precision T3500 and Room Office 232, model: Dell OPTILEX 780 or equal or equal with 22” monitors Hewlett Packard or equal. Monitors must be TAA compliant.

1.3. Performance Period: The Contractor shall coordinate delivery schedule with station point of contact.

2. Scope of Work: Contractor shall provide all labor, supervision, materials, parts and equipment, tools and transportation to install and upgrade the Lenel Security System. Convert from analog to High Definition.

2.1. Tasks: The Contractor shall perform the following tasks:

2.1.1. The Contractor shall provide all necessary racks system, two (2) mid-towers, one located in the basement model: Dell Precision T3500 or equal and one at the PIV Room Office 232 model: Dell OPTILEX 780 or equal.

2.1.2. As the current set-up, all cameras must be able to be monitored from the Basement and

2nd Floor, PIV Room, Office 232.

2.1.3. Room Office 232 - shall have a tower Dell OPTILEX 780 or equal, with 22” monitor Hewlett Packard, keyboard and mouse. Also, shall have a Camera: Model 24Z704 USB-SYS- L or equal, and printer Model Fargo Direct to Card 550 (DTC 550 Card) or equal.

2.1.4. Cameras: All new cameras shall have color sensor imaging systems.

2.1.5. A total of thirty-two (32) cameras will be part of this procurement, twenty-two (22) will be replaced and ten (10) will be added to the system. An IP keypad joystick TVK800-Truvision or equal.

2.1.6. A total of sixteen (16) cameras shall be wall mounted and two (2) will be installed in light poles. All wall mounted cameras shall be installed at a height that cannot be easily tampered with and shall use same location as currently installed. Out of sixteen (16) cameras, four (4) are new cameras, wall mounted.

2.1.7. A total of fourteen (14) cameras will be installed in ceiling, which four (4) are new.

2.1.8. Contractor shall replace the following twenty-two (22) cameras: Exterior Near Basement Entrance, Exterior located facing Honeywell, Exterior loading dock, Exterior Visitor’s walk-way, Exterior Main Entrance, Checkpoint, Public Contact waiting area, Public Contact Hallway, 2nd Floor Entrance, Director’s waiting area, Mezzanine Exterior, Stairwell West, Stairwell East, Freight Elevator waiting area, 3rd Floor Freight Elevator, 3rd Floor Passenger Elevator, 3rd Floor Stairwell West, 3rd Floor Stairwell East, two (2) Exterior Cameras freight elevator entrance, Two (2) Exterior Cameras Passenger elevator.

2.1.9. Contractor shall install ten (10) additional cameras: Exterior Visitor Parking, Checkpoint, Near

Vending Machine toward checkpoint, Public Contact waiting area, 1st Floor Freight Elevator, 3rd Floor exterior passenger elevator toward multilevel parking, Stairwell Multi-level parking near Building, Stairwell Multi-level parking last floor, two (2) cameras on light pole. Cameras model: PELCO or equal and Dongle ID: 49124.

2.1.10. Cameras shall be no less than sixteen (16) megapixels and shall have high definition (HD) day/night capability. These cameras shall have self-learning video analytics with Power over Ethernet, 24 VAC or 12 VDC power input.

2.1.11. Eighteen (18) cameras, model PELCO (PTZ) or equal, for exterior cameras shall be dome type and a minimum resolution of five (5) megapixels.

2.1.12. The recording devices dongle: 49124 shall provide sufficient memory to allow for the recording for sixty (60) days minimum.

2.1.13. After completion of the installation, the Contractor shall coordinate with point of contact and

ITOPS testing the integration and installation of the products to ensure the system is working and properly configured.

2.1.14. Door with new PACS is working properly.

2.1.15. The Contractor shall provide system training. On-site training provided shall meet the minimum requirements as suggested by the software manufacturer and for RO System Administrators. The anticipated number of RO personnel to train are three (3). Two (2) administrators and one (1) user and security guards.

2.1.16. Clean-Up: The contractor shall remove any trash generated during upgrade of the security system the installation from the facility.

2.2. INSTALLLATION OF NEW PAC SYSTEM IN BASEMENT:

2.3. PAC System: A new proximity card reader HID Multiclass or equals to be installed at the Security Guard Control Room located in the Basement. The newly installed reader shall be connected to the newly upgraded Lenel System and have full connection to the current PAC System. Contractor shall provide all connectors, wiring or any other necessary components detrimental to the operation of the reader. This PACS shall be able to read Oberthur PIV cards and ensure proper installation on the PIV client stations.

2.4. Duress Buttons:

2.4.1. The Contractor shall install seven (7) duress button model Honeywell intrusions or equal and all necessary cables and equipment at the following locations: five (5) the National Call Center Supervisors, one (1) IPC Coach cubicle and one (1) Education Office 231.

2.4.2. The main server to connect the duress buttons is located at the Security Control

Room in the Basement.

2.4.3. The additional duress buttons shall be equal and compatible to those currently installed at the RO.

3. WARRANTY:

3.1 Equipment: The contractor warranty shall include all necessary recommended manufacturer’s instructions and accepted industry standards on all equipment identified in the Equipment Maintenance Plan. All maintenance, services, repairs, patches, upgrades will be conducted onsite and cannot be able to be performed remotely. This is a stand-alone system and will not have internet connectivity.

3.2 Personnel: The Contractor is responsible to supervise their own employees while on the facilities. Contractor’s personnel shall follow rules and regulations according to VA Regional Office, Federal Protective Service and ISSO Rules of Behaviors. Government shall neither supervise contractor employees nor control the method by which the contractor performs the required tasks. Under no circumstances shall the Government assign tasks to, or prepare work schedules for, individual contractor employees.

3.3. Contractor shall provide mfg., warranty expiration date upon date of final acceptance.

4. Place of Performance: (Set-up, Delivery and Installation costs shall be included in your price.). The building has a loading dock available.

Department of Veterans Affairs 50 Carr. 165 Guaynabo PR 00968

5. Hours of Operation: The contractor is responsible for conducting business, between the hours of 7:00am -6:00pm Monday thru Friday and Saturdays from 6:00am thru 3:30pm, except Federal holidays or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings. When necessary, to avoid interruptions and operations of VA Staff, and with prior coordination, the contractor will have to work after duty hours. At all time, the Contractor must maintain an adequate workforce for the uninterrupted performance of all tasks defined within this Statement of Work when the Government facility is not closed for the above reasons.

Federal Holidays:

New Year's Day Martin Luther King's Birthday President's Day Memorial Day Independence Day Labor Day Columbus Day Veteran's Day Thanksgiving Day Christmas Day

6. GENERAL REQUIREMENTS

6. 1. The Contractor shall complete all work within thirty (30) calendar days of contract award.

6.2. The Contractor shall provide all manuals, documentation for the installed products including a diagram of the network connection, location of equipment installed, cabling, duress buttons, PAC system. This diagram will be use as reference for future repair, maintenance or system upgrade.

6.3. The Contractor will verify if the dial-up line can be used only for outbound purpose. If it does, as recommended by ISSO and ITOP, will be used as outbound ONLY.

6.4. The Contractor shall provide all necessary hardware and software.

6.5. Staging and Storage: Contractor shall not deliver any equipment or material to the facility.

VA Regional Office does not have the capability to store any equipment.

6.6. This contract shall not require access to a VA system or VA sensitive information (e.g., system administrator privileged access to a VA system, or contractor systems or processes that utilize VA sensitive information). This Physical Security System will not access, interfere, exchange, store, communicate or transmit any information regarding VA data. This system is a stand-alone and will not have internet capability, therefore cannot and will not be able to access remotely. VA sensitive data or information is protected and will not be affected by the upgrade of the security system.

6.7. When project is completed, the Contractor will provide a certification indicating that installation DOES NOT and WIL NOT interfere, access, communicate under any circumstances with VA data.

Also, will certify that equipment does not have internet connection and CANNOT be accessed remotely.

7. SAFETY AND HEALTH

7.1. All work shall comply with the applicable requirements of 29 CFR 1910/1926 and 40 CFR 761.

All work shall comply with applicable state and municipal safety and health requirements.

Where there is a conflict between applicable regulations, the most stringent will apply.

7.2. The Contractor shall assume full responsibility and liability for compliance with all applicable regulations pertaining to the health and safety of personnel during the execution of work. The Contractor shall hold the Government harmless for any action on its part or that of its employees or subcontractors, which results in illness or death.

7.3. The Contractor shall provide all necessary safety equipment and ensure that such equipment and all relevant safety procedures are adequate for the job being performed and are utilized properly.

7.4. Wherever practical, the work area shall be barricaded or otherwise blocked off from the public or occupants to prevent unauthorized entry into the work area.

8. SECURITY REQUIREMENTS

8.1. Picture ID will be required for all persons entering the building. Contractor(s) and/or sub-contracted personnel must sign the VA Privacy and Information Security Awareness and Rules of Behavior (ROB) prior to begin this project.

8.2. The Contractor shall provide all supervision, transportation, labor, material, and professional services to install the access control solution, as described in this Statement of Work. Contractors are used, the Project Manager (PM) that is representing the contractor shall provide the names of personnel and companies that those personnel work for, to the POC listed on this SOW at least 72 hours in advance of the arrival of any personnel utilized by the awarded contractor.

8.3. All material, tools, and equipment will be subject to search and/or scanning upon entry to building.

9. Rules of Behaviors: See attachment to this Statement of Work.

9.1.

Rules of Behavior for FY 20.pdf

STATEMENT OF WORK FOR TO UPGRADE LENEL SECURITY SYSTEM AT SAN JUAN REGIONAL OFFICE (355).

File details come from the government source that posted it. Updated .