This document is a quote/proposal letter from York Electric, Inc., a Dayton, Ohio-based electrical contractor, dated November 07, 2025, addressed to Richard Clark at DRC (reference number SRC0000034314 – 714 – APA Lebanon Electrical). The company, which has been in business since 1946 and is a member of the National Electrical Contractors Association (NECA), is providing an electrical work proposal for a specific project.

The proposal covers electrical work for 8 work station cubicles at a total cost of $19,880.00. The scope of work includes providing conduit, fittings, supports, hangers, penetrations, circuit breakers, wiring, and wiring connections to power poles installed by a cubicle installer. The electrical work will route conduit and wiring from power poles through the drop ceiling to an electrical breaker panel in the utility room, with provisions for additional 20 Amp circuit breakers. The work is to be performed during regular work hours (7:30am to 4:30pm, Monday through Friday) and will adhere to local and national electrical code requirements.

View the file

Other files

File Type Posted
DOC112125-11212025122613.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

York Electric, Inc.

530 East Second Street PO Box 3138 Dayton, Ohio 45401

(937) 223-2580 (937) 223-5714 yorkelectric@ameritech.net

November 07, 2025

To Richard Clark - DRC, Ref: SRC0000034314 – 714 – APA Lebanon Electrical

Richard, Our quote for the electrical work for subject solicitation consists of the following scope of work for the amount of 19,880.00.

We include conduit , fittings, supports, hangers, penetrations, circuit breakers, wiring, and wiring connections to 8 work station cubicles. This work includes wiring connections into 8 power poles which are installed by the cubicle installer .

The power poles extend from connections to the cubicles to the drop ceiling from which the conduit and wiring are routed to the electrical breaker panel located in utility room . This circuit breaker panel will provide spacing for additional 20 Amp circuit breakers for the cubicles. The electrical work would be best performed during cubicle installation in order to ensure appropriate assembly sequence All work to be performed during regular Monday through Friday work days during regular work hours 7:30am to 4:30pm . All work is to be performed in accordance with local and national electrical code requirements .

Please let us know if there’s any other questions .