Question 1:
Does the government require the 2 sharepoint FTE to work onsite or is remote work allowed? (submitted 2/2/17) Government answer (2/2/17):
The two contractor FTE the Government estimates will be necessary to do the work are anticipated to have to do the work onsite. Some offsite work may be considered depending on the circumstances.
Question 2:
Is security clearance required to be considered for this contract? (submitted 2/2/17) Government answer (2/2/17):
No, but it would be considered by OPIC as a highly favorable capability since it would allow contractor personnel to be onboarded much more quickly.
Question 3:
When do you expect the work to ideally start? (submitted 2/2/17) Government answer (2/2/17):
No later than 1 March 2017, preferably sooner.