This document is a bid form for the Ohio Department of Transportation (ODOT) Contract 147-25, specifically for Traffic Sign and Support Installation and Removal services. The contract is a multiple award contract with Lake Erie Construction listed as a vendor, allowing multiple vendors to submit pricing for various sign installation and removal services across different categories and completion speeds (standard and rush).
The contract covers 15 distinct service groups ranging from furnishing and installing ground mounted supports (including U-channel, pipe, structural beam, and wood supports) to erecting signs on various support types, removing and disposing of signs and supports, and providing maintenance of traffic services. Pricing is itemized for each specific service, with standard and rush completion rates. For example, furnishing and installing a ground mounted No. 3 Post U-channel support ranges from $12.50 to $14.00 depending on completion speed. The contract includes comprehensive pricing for sign installation, removal, attachment, and traffic management, with mobilization included and limited to up to ten sites per district per purchase order. Prices are effective for the entire contract duration and follow ODOT Construction and Material Specifications.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ODOT_147-25__Traffic_Sign_and_Support_Installation_Removal_AFFIRMATION.pdf | ||
| Signature__38_.pdf | ||
| 147-25spec.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Standard Wage Pricing
147-25 SIGN INSTALLATION, SIGN REMOVAL
| Vendor Name | Lake Erie Construction | ||||
| This is a multiple award contract. Vendors may submit pricing for any of the items and locations below. Bidders should submit descriptive literature in accordance with Section 7 of the Specifications and Requirements for items bid. All pricing submitted shall be effective for the entire duration of the contract. | |||||
| Group 1 - Furnish and Install Ground Mounted Post | |||||
| Items 1-4 & 1-5: Furnish and install ground mounted yielding square post support in anchor base foundation in accordance with Item 630 of the ODOT Construction and Material Specifications and Standard Construction Drawings TC-41.20, TC-42.10 and TC-42.20. Unit bid price includes furnishing and installation of anchor base. | |||||
| Item | |||||
| Number | Item | Unit of Measure | Completion | Unit Bid Price | |
| 1-1 | Furnish and Install Ground Mounted Support, No. 3 Post, U-channel | Foot | Standard | $12.50 | |
| Rush | $14.00 | ||||
| 1-2 | Furnish and Install Ground Mounted Support, No. 4 Post, Piggyback U-channel | Foot | Standard | $14.50 | |
| Rush | $16.00 | ||||
| 1-3 | Furnish and Install Ground Mounted Support, No. 6 Post, Piggyback U-channel | Foot | Standard | $16.00 | |
| Rush | $17.50 | ||||
| 1-4 | Furnish and Install Ground Mounted Support, No. 3 Post, Square | Foot | Standard | $16.00 | |
| Rush | $17.50 | ||||
| 1-5 | Furnish and Install Ground Mounted Support, No. 4 Post, Square | Foot | Standard | $18.00 | |
| Rush | $19.50 |
| Group 2 - Furnish and Install Ground Mounted Pipe Support | |||||
| Group 2 Items: Furnish and install ground mounted pipe support in concrete foundation in accordance with Item 630 of the ODOT Construction and Material Specifications, Standard Construction Drawings TC-42.10 and TC-42.20, and Plan Insert Sheet 204115. Furnish and install slip base connection when specified on the purchase order. | |||||
| Item | |||||
| Number | Item | Unit of Measure | Completion | Unit Bid Price | |
| 2-1 | Furnish and Install Ground Mounted Pipe Support Foundation | Each | Standard | $900.00 | |
| Rush | $920.00 | ||||
| 2-2 | Furnish and Install Ground Mounted Support, Pipe | Foot | Standard | $58.00 | |
| Rush | $60.00 | ||||
| 2-3 | Furnish and Install Triangular Slip Base Connection | Each | Standard | $360.00 | |
| Rush | $380.00 |
| Group 3 - Furnish and Install Ground Mounted Structural Beam Support | |||||
| Group 3 Items: Furnish and install ground mounted structural beam support in concrete foundation in accordance with Item 630 of the ODOT Construction and Material Specifications and Standard Construction Drawings TC-41.10, TC-42.10 and TC-42.20. Furnish and install slip base connection when specified on the purchase order. | |||||
| Item | |||||
| Number | Item | Unit of Measure | Completion | Unit Bid Price | |
| 3-1 | Furnish and Install Ground Mounted Structural Beam Support Foundation, S4x7.7 | Each | Standard | $845.00 | |
| Rush | $875.00 | ||||
| 3-2 | Furnish and Install Ground Mounted Structural Beam Support, S4x7.7 | Foot | Standard | $39.00 | |
| Rush | $42.00 | ||||
| 3-3 | Furnish and Install Breakaway Structural Beam Connection, S4x7.7 | Each | Standard | $310.00 | |
| Rush | $325.00 | ||||
| 3-4 | Furnish and Install Ground Mounted Structural Beam Support Foundation, W6x9 | Each | Standard | $900.00 | |
| Rush | $925.00 | ||||
| 3-5 | Furnish and Install Ground Mounted Structural Beam Support, W6x9 | Foot | Standard | $41.00 | |
| Rush | $44.00 | ||||
| 3-6 | Furnish and Install Breakaway Structural Beam Connection, W6x9 | Each | Standard | $325.00 | |
| Rush | $345.00 | ||||
| 3-7 | Furnish and Install Ground Mounted Structural Beam Support Foundation, W10x12 | Each | Standard | $975.00 | |
| Rush | $1,010.00 | ||||
| 3-8 | Furnish and Install Ground Mounted Structural Beam Support, W10x12 | Foot | Standard | $45.00 | |
| Rush | $48.00 | ||||
| 3-9 | Furnish and Install Breakaway Structural Beam Connection, W10x12 | Each | Standard | $465.00 | |
| Rush | $485.00 | ||||
| 3-10 | Furnish and Install Ground Mounted Structural Beam Support Foundation, W8x18 | Each | Standard | $1,010.00 | |
| Rush | $1,050.00 | ||||
| 3-11 | Furnish and Install Ground Mounted Structural Beam Support, W8x18 | Foot | Standard | $55.00 | |
| Rush | $59.00 | ||||
| 3-12 | Furnish and Install Breakaway Structural Beam Connection, W8x18 | Each | Standard | $560.00 | |
| Rush | $585.00 | ||||
| 3-13 | Furnish and Install Ground Mounted Structural Beam Support Foundation, W10x22 | Each | Standard | $1,050.00 | |
| Rush | $1,080.00 | ||||
| 3-14 | Furnish and Install Ground Mounted Structural Beam Support, W10x22 | Foot | Standard | $63.00 | |
| Rush | $67.00 | ||||
| 3-15 | Furnish and Install Breakaway Structural Beam Connection, W10x22 | Each | Standard | $950.00 | |
| Rush | $975.00 | ||||
| 3-16 | Furnish and Install Ground Mounted Structural Beam Support Foundation, W12x30 | Each | Standard | $1,180.00 | |
| Rush | $1,240.00 | ||||
| 3-17 | Furnish and Install Ground Mounted Structural Beam Support, W12x30 | Foot | Standard | $75.00 | |
| Rush | $79.00 | ||||
| 3-18 | Furnish and Install Breakaway Structural Beam Connection, W12x30 | Each | Standard | $800.00 | |
| Rush | $825.00 |
| Group 4 - Furnish and Install Ground Mounted Solid Wood Support | |||||
| Group 4 Items: Furnish and install ground mounted solid wood support in accordance with Item 630 of the ODOT Construction and Material Specifications and Traffic Engineering Manual Section 221-5 and Figure 298-26. | |||||
| Item | |||||
| Number | Item | Unit of Measure | Completion | Unit Bid Price | |
| 4-1 | Furnish and Install Ground Mounted Support, Solid Wood 4x4 (nominal) | Foot | Standard | $27.00 | |
| Rush | $29.00 | ||||
| 4-2 | Furnish and Install Ground Mounted Support, Solid Wood 4x6 (nominal) | Foot | Standard | $29.00 | |
| Rush | $31.00 | ||||
| 4-3 | Furnish and Install Ground Mounted Support, Solid Wood 6x6 (nominal) | Foot | Standard | $30.00 | |
| Rush | $34.00 | ||||
| 4-4 | Furnish and Install Ground Mounted Support, Solid Wood 6x8 (nominal) | Foot | Standard | $35.00 | |
| Rush | $38.00 |
| Group 5 - Erect ODOT-furnished sign or sign assembly on Ground Mounted Support | |||||
| Group 5 Items: Erect ODOT-furnished flat sheet or extrusheet sign or plaque on ground mounted post, pipe or structural beam support in accordance with Item 630 of the ODOT Construction and Material Specifications, Standard Construction Drawings TC-41.20, TC-51.11 and TC-51.12, and Plan Insert Sheet 204115. Unit bid price includes picking up the sign or plaque at the ODOT District Office or other location within the District as specified on the purchase order, and transporting to the work site. | |||||
| Item | |||||
| Number | Item | Unit of Measure | Completion | Unit Bid Price | |
| 5-1 | Sign Erected, Flat Sheet, on Ground Mounted Support (standard) | Square | |||
| Foot | Standard | $6.50 | |||
| Rush | $7.00 | ||||
| 5-2 | Sign Erected, Extrusheet, on Ground Mounted Support | Square | |||
| Foot | Standard | $9.00 | |||
| Rush | $10.00 |
| Group 6 - Erect ODOT-furnished sign or sign assembly on Overhead Support | |||||
| Group 6 Items: Erect ODOT-furnished flat sheet or extrusheet sign or plaque on rigid or span wire overhead support in accordance with Item 630 of the ODOT Construction and Material Specifications and Standard Construction Drawings TC-17.11, TC-51.11 and TC-51.12. Unit bid price includes picking up the sign or plaque at the ODOT District Office or other location within the District as specified on the purchase order, and transporting to the work site. | |||||
| Item | |||||
| Number | Item | Unit of Measure | Completion | Unit Bid Price | |
| 6-1 | Sign Erected, Flat Sheet, on Overhead Span Wire Support | Square | |||
| Foot | Standard | $6.50 | |||
| Rush | $7.00 | ||||
| 6-2 | Sign Erected, Flat Sheet, on Rigid Overhead Support | Square | |||
| Foot | Standard | $7.00 | |||
| Rush | $8.00 | ||||
| 6-3 | Sign Erected, Extrusheet, on Rigid Overhead Support | Square | |||
| Foot | Standard | $9.00 | |||
| Rush | $10.00 |
| Group 7 - Erect ODOT-furnished sign assembly on breakaway support | |||||
| Group 7 Item: Furnish and install breakaway support and foundation in accordance with Item 630 of the ODOT Construction and Material Specifications and Standard Construction Drawings HL-10.13, HL-20.11, and TC-87.10. | |||||
| Item | |||||
| Number | Item | Unit of Measure | Completion | Unit Bid Price | |
| 7-1 | Sign Assembly Erected, RRFB, on Breakaway Support | Foot | Standard | $7,500.00 | |
| Rush | $8,750.00 | ||||
| 7-2 | Sign Assembly Erected, School Flasher, on Breakaway Support | Foot | Standard | ||
| Rush | |||||
| 7-3 | Sign Assembly Erected, LED enhanced solar powered sign assembly, on Breakaway Support | Foot | Standard | ||
| Rush | |||||
| 7-4 | Sign Assembly Erected, Solar Powered LED Beacon Sign assembly, on Breakaway Support | Foot | Standard | ||
| Rush | |||||
| 7-5 | Sign Assembly Erected, Speed Feedback Sign assembly, on Breakaway Support | Foot | Standard | ||
| Rush | |||||
| 7-6 | Sign Assembly Erected,Solar Powered Sequential Flashing Chevron Sign assembly, on Breakaway Support | Foot | Standard | $7,500.00 | |
| Rush | $8,750.00 | ||||
| 7-7 | Sign Assembly Erected, Hard-Wired Sequential Flashing Chevron Sign assembly, on Breakaway Support | Foot | Standard | ||
| Rush |
| Group 8 - Furnish and Install Sign Attachment Assembly | |||||
| Group 8 Item: Furnish and install sign attachment assembly in accordance with Item 630 of the ODOT Construction and Material Specifications and Standard Construction Drawing TC-22.20. | |||||
| Item | |||||
| Number | Item | Unit of Measure | Completion | Unit Bid Price | |
| 8-1 | Furnish and Install Sign Attachment Assembly | Each | Standard | $570.00 | |
| Rush | $595.00 |
| Group 9 - Remove and Dispose Flat Sheet or Extrusheet Sign | |||||
| Group 9 Items: Removal and disposal of ground mounted and overhead mounted signs are in accordance with Item 630 of the ODOT Construction and Material Specifications. | |||||
| Item | |||||
| Number | Item | Unit of Measure | Completion | Unit Bid Price | |
| 9-1 | Remove and Dispose Sign, Flat Sheet, On Ground Mounted Support | Each | Standard | $20.00 | |
| Rush | $25.00 | ||||
| 9-2 | Remove and Dispose Sign, Extrusheet, On Ground Mounted Support | Each | Standard | 150 | |
| Rush | 175 | ||||
| 9-3 | Remove and Dispose Sign, Extrusheet, On Overhead Support | Each | Standard | 225 | |
| Rush | 250 |
| Group 10 - Remove and Dispose Ground Mounted Post | |||||
| Group 10 Items: Removal and disposal of ground mounted sign support posts are in accordance with Item 630 of the ODOT Construction and Material Specifications. | |||||
| Item | |||||
| Number | Item | Unit of Measure | Completion | Unit Bid Price | |
| 10-1 | Remove and Dispose of Ground Mounted Support, No. 3 Post, U-channel or Square | Each | Standard | $20.00 | |
| Rush | $25.00 | ||||
| 10-2 | Remove and Dispose of Ground Mounted Support, No. 4 Post, Piggyback U-channel or Square | Each | Standard | $20.00 | |
| Rush | $25.00 | ||||
| 10-3 | Remove and Dispose of Ground Mounted Support, No. 6 Post, Piggyback U-channel or Square | Each | Standard | $25.00 | |
| Rush | $30.00 | ||||
| 10-4 | Remove and Dispose of Ground Mounted Support, No. 6 Post, Piggyback U-channel or Square | Each | Standard | $25.00 | |
| Rush | $30.00 |
| Group 11 - Remove and Dispose Ground Mounted Pipe Support | |||||
| Group 11 Items: Removal and disposal of ground mounted pipe supports are in accordance with Item 630 of the ODOT Construction and Material Specifications. | |||||
| Item | |||||
| Number | Item | Unit of Measure | Completion | Unit Bid Price | |
| 11-1 | Remove and Dispose Ground Mounted Pipe Support Foundation | Each | Standard | $195.00 | |
| Rush | $220.00 | ||||
| 11-2 | Remove and Dispose Ground Mounted Support, Pipe | Each | Standard | $45.00 | |
| Rush | $50.00 | ||||
| 11-3 | Remove and Dispose Triangular Slip Base Connection | Each | Standard | $40.00 | |
| Rush | $45.00 |
| Group 12 - Remove and Dispose Ground Mounted Structural Beam Support | |||||
| Group 12 Items: Removal and disposal of ground mounted structural beam supports are in accordance with Item 630 of the ODOT Construction and Material Specifications. | |||||
| Item | |||||
| Number | Item | Unit of Measure | Completion | Unit Bid Price | |
| 12-1 | Remove and Dispose Ground Mounted Structural Beam Support, Connection, and Foundation, S4x7.7 | Each | Standard | $180.00 | |
| Rush | $195.00 | ||||
| 12-2 | Remove and Dispose Ground Mounted Structural Beam Support, Connection, and Foundation, W6x9 | Each | Standard | $200.00 | |
| Rush | $215.00 | ||||
| 12-3 | Remove and Dispose Ground Mounted Structural Beam Support, Connection, and Foundation, W10x12 | Each | Standard | $215.00 | |
| Rush | $225.00 | ||||
| 12-4 | Remove and Dispose Ground Mounted Structural Beam Support, Connection, and Foundation, W8x18 | Each | Standard | $225.00 | |
| Rush | $240.00 | ||||
| 12-5 | Remove and Dispose Ground Mounted Structural Beam Support, Connection, and Foundation, W10x22 | Each | Standard | $230.00 | |
| Rush | $245.00 | ||||
| 12-6 | Remove and Dispose Ground Mounted Structural Beam Support, Connection, and Foundation, W12x30 | Each | Standard | $245.00 | |
| Rush | $260.00 |
| Group 13 - Remove and Dispose Ground Mounted Solid Wood Support | |||||
| Group 13 Items: Removal and disposal of solid wood supports are in accordance with Item 630 of the ODOT Construction and Material Specifications. | |||||
| Item | |||||
| Number | Item | Unit of Measure | Completion | Unit Bid Price | |
| 13-1 | Remove and Dispose Ground Mounted Support, Solid Wood 4x4 (nominal) | Each | Standard | $35.00 | |
| Rush | $40.00 | ||||
| 13-2 | Remove and Dispose Ground Mounted Support, Solid Wood 4x6 (nominal) | Each | Standard | $40.00 | |
| Rush | $45.00 | ||||
| 13-3 | Remove and Dispose Ground Mounted Support, Solid Wood 6x6 (nominal) | Each | Standard | $45.00 | |
| Rush | $50.00 | ||||
| 13-4 | Remove and Dispose Ground Mounted Support, Solid Wood 6x8 (nominal) | Each | Standard | $55.00 | |
| Rush | $60.00 |
| Group 14 - Maintenance of Traffic and Mobilization | |||||
| Group 14 Items: Maintain traffic in accordance with Item 614 of the ODOT Construction and Material Specifications, the Maintenance of Traffic Standard Drawings, the 2012 Ohio Manual of Uniform Traffic Control Devices, and the District Permitted Lane Closure schedule. Payment will be for each set-up required to complete the work. | |||||
| Item | |||||
| Number | Item | Unit of Measure | Completion | Unit Bid Price | |
| 14-1 | Maintenance of Traffic, One Lane Closure on a Two Lane Highway | Each | Standard | $1,200.00 | |
| Rush | $1,450.00 | ||||
| 14-2 | Maintenance of Traffic, One Lane Closure on a Four Lane Undivided Highway | Each | Standard | $1,350.00 | |
| Rush | $1,850.00 | ||||
| 14-3 | Maintenance of Traffic, One Lane Closure on a Four Lane or Greater Divided Highway | Each | Standard | $1,350.00 | |
| Rush | $1,850.00 | ||||
| 14-4 | Maintenance of Traffic, Shoulder Closure on Any Highway | Each | Standard | $975.00 | |
| Rush | $1,325.00 | ||||
| 14-5 | Maintenance of Traffic, Two Lane Closure on a Four Lane or Greater Divided Highway | Each | Standard | $1,550.00 | |
| Rush | $2,050.00 | ||||
| 14-6 | Law Enforcement Officer | Hour | Standard | $70.00 | |
| Rush | $80.00 | ||||
| 14-7 | Portable Changeable Message Sign (PCMS) | Each | Standard | $1,650.00 | |
| Rush | $2,150.00 |
| Group 15 - Mobilization | |||||
| Group 15 Items: Mobilization will be included in each purchase order. Each mobilization includes up to a maximum of ten sites per District per purchase order. | |||||
| Item | |||||
| Number | Item | Unit of Measure | Completion | Unit Bid Price | |
| 15-1 | Mobilization | Each | Standard | $1,100.00 | |
| Rush | $1,450.00 |
File details come from the government source that posted it. Updated .