NOAA Standard Specification 533-1A Potable-Water-Tank-System-Disinfection.pdf

PDF 111 KB Posted

Attached to
Reference Documents for DORFP 1305M224R0042 – NOAA Ship Thomas Jefferson FY25 Repairs Services
Solicitation number
1305M224R0042
Issued by

About this file

This document is a standard specification from the National Oceanic and Atmospheric Administration (NOAA) for disinfecting potable water tanks and systems on NOAA ships. The specification includes requirements for isolating and rinsing the tanks, adding a chlorine solution to achieve a minimum free available chlorine (FAC) content of 100 parts per million, monitoring the FAC levels, and draining and refilling the tanks. It also requires disinfection of the entire potable water system, including monitoring FAC levels throughout the distribution system and validating that levels are below 1.0 ppm after disinfection. The contractor must submit a condition report to the Contracting Officer's Representative within 24 hours of completing the disinfection process.

The related federal contract opportunity is a Delivery Order Competition for an existing multiple award IDIQ contract for NOAA dockside support services for the NOAA Ship Thomas Jefferson. This is a special notice providing reference documents for the solicitation, which has the number 1305M224R0042. Only contractors already awarded a Region II IDIQ contract will be considered for this award.

View the file

Other files

File Type Posted
625-6634893J_Doors Hatches Windows and Airports.pdf PDF
Refrigeration Valves and Parts.pdf PDF
561-6634811 Steering System Hydraulic Sys.pdf PDF
TJ_85_TJ-085-002_RevJ_BOOKLET OF GENERAL PLANS.pdf PDF
TJ-432-003_Rev -0_Dial Telephone System LAN System Modifications.pdf PDF
Hose McCann 2213-100-451_PA_GA Layout.pdf PDF
521-6634792E Fire Main Sys Arr Dets.pdf PDF
TJ-583-023B Davit Hydraulic Modifications_103556824.pdf PDF
521-6634791D Fire Main System Dia.pdf PDF
refer system drawing with cond.pdf PDF
Liferaft Certificates.pdf PDF
Compressor_Start_Up_Report.pdf PDF
TJ-985-6634639O Fire Control Plan_130928347.pdf PDF
Amdt_0001-TJ-985-6634639O Fire Control Plan_130928347.pdf PDF
Amdt_0001-Liferaft Certificates.pdf PDF
Amdt_0001-TJ-583-023B Davit Hydraulic Modifications_103556824.pdf PDF
Amdt_0001-561-6634811 Steering System Hydraulic Sys.pdf PDF
Comdial Wiring Panels_J-boxes.pdf PDF
243-6634745A Shaft Brake Arrngmnt.pdf PDF
320-6634679_Cableway Arrangement and Details.pdf PDF
163-6634821_Seachest Details.pdf PDF
501-6634837B Reach Rod ARR_Details.pdf PDF
512-6634841_ HVAC Diagram.pdf PDF
TJ-551-004 Whistle Comp Air System Arrangement_Details.pdf PDF
TJ FY25 Fire Sys Inventory_Portable Fire Extinguishers.pdf PDF
NOAA Standard Specification AMC-635-2 Thermal Insulation for Compartments.pdf PDF
NOAA Thomas Jefferson Ships Registry TTS.pdf PDF
Fire and Detection Alarm System_As Built_12122023.pdf PDF
TJ-170-6634883-F.pdf PDF
101-6634865 Structural Module 6.pdf PDF
TJ-180-001_Generic winch foundation.pdf PDF
TJ-635-6634624_Insulation Layout and Details.pdf PDF
151-6634890 Bulwark and Misc Details.pdf PDF
TJ-233-03 EMD Engine_Maintenance Instruction_1722 Rev I.pdf PDF
TJ-514-003_-_Refrigerant System and Condensate Piping Modifications.pdf PDF
TJ-583-03A Davit_Hydrographic Survey Launch (HSL).pdf PDF
501-6634831_Piping Module No 3.pdf PDF
Zenitel Bill of Materials_Item 3.11.pdf PDF
NOAA Thomas Jeffersonr2_XLS_Zenitel.xls XLS spreadsheet
426-6634694 Gyro Compass Sys.pdf PDF
633-67635_Installation Drawing ICCP Equipment.pdf PDF
514-3275003-6 REV A AC PIPING INSTL 2ND DK_BLW.pdf PDF
801-6634641_Table of Offsets.pdf PDF
512-6634850F HVAC ARRNGMNT ENGRM_124644191.pdf PDF
Electro-Motive MI 1722_Maintenance Instruction.pdf PDF
Hose McCann 6080-PNL-437-DS_R0_Panel Wiring.pdf PDF
801-6634640_Hull Lines.pdf PDF
NOAA Standard Specification 997-1B Drydocking-Routine_Drydock-Work.pdf PDF
TJ-331-002 LIGHTING MODS INCID TO SEWAGE TANK AERATION SYSTEM_124586215.pdf PDF
EMI 17300_Feedeback Linkage Diagram.pdf PDF
Show 40 more

Latest 50 of 188 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

533-1A August 2018

Superseding

MOC-533-1

AUGUST 1991

STANDARD SPECIFICATION

POTABLE WATER TANK and SYSTEM DISINFECTION

1. SCOPE

1.1 This specification contains the general requirements for disinfecting the potable water tanks and system on NOAA ships.

2. REFERENCES

2.1 “Vessel Sanitation Program, 2011 Construction Guidelines, U.S. Department of Health and Human Services, section 22.10, Disinfection of the Potable Water System”.

3. DEFINITIONS

3.1 Free Available Chlorine (FAC) - Concentration of residual chlorine in water present as dissolved gas (Cl2), hypochlorous acid (HClO), and/or hypochorite ion (CIO-). A test kit which measures free chlorine will indicate the combined concentrations of HCLO, ClO-, and Cl2.

4. REQUIREMENTS

4.1 Potable Water Tank Disinfection

4.1.1 General Requirements

a. Isolate the potable water tanks to be disinfected from the rest of the potable water service system. Thoroughly rinse and drain each tank’s interior.

b. The chlorine solution used to disinfect the tank must be diluted and added through a sounding tube or threaded connection. Immediately after adding the chlorine solution, rinse the sounding tube or threaded connection with at least five gallons of potable water.

4.1.2 Disinfection Procedure

a. Fill the tank with potable water until it starts to overflow, then stop. Exercise care not to pressurize the tank. As the tank fills, add chlorine solution to achieve at least 100 parts per million (ppm) Free Available Chlorine (FAC) content in the completely filled tank.

b. Monitor the FAC content hourly for at least four hours. If the FAC content drops below 50 ppm at any time, add additional chlorine solution to raise the FAC content back to 100 ppm and restart the four hour monitoring period. Continue monitoring and raising the FAC content until the FAC content remains at or above 50 ppm for a four hour period.

c. If disinfecting more than one tank, repeat the above procedure for each tank. At the contractor’s discretion, the same water may be used to disinfect each consecutive tank, as long as the initial FAC content is increased to 100 ppm at the start of the four-hour monitoring period.

d. Drain each tank and refill with potable water. Repeat the above disinfection procedure, except start with an initial FAC content of at 1.0 ppm or greater and monitor the FAC content for 30 minutes. Continue monitoring and raising the FAC content until the FAC content remains at or above

0.2 ppm for a 30 minute period.

e. Drain each tank and refill with potable water until the total FAC content falls below 1.0 ppm.

4.2 Potable Water System Disinfection

4.2.1 Disinfect the entire Potable Water System, including the potable water tanks, in accordance with reference 2.1 and the potable water tank disinfection requirements in 4.1 above.

4.2.2 Monitor the FAC at various plumbing fixtures on each deck throughout the vessel (forward, aft, port, and starboard) to ensure that the 50 ppm free residual chlorine has circulated throughout the distribution system to include the distant sampling points.

4.2.3 After completion of the disinfection process, take additional samples at the same distant plumbing fixtures to validate that the FAC levels at these points are below 1.0 ppm.

4.2.4 Within 24 hours, submit a written Condition Report to the Contracting Officer’s Representative (COR) with the sample locations and FAC readings.

APPENDIX A

The following checklists are for guidance only. The Contractor is required to meet all requirements in the specification, whether or not they are captured accurately or fully in the checklists.

Potable Water Tank Disinfection Checklist

Check Delivery Period Action Service 1 Prior Tank Disinfection Perform Isolate the Potable Water Tank (s) from the rest of the system.

2 Prior Tank Disinfection Perform Rinse and drain the Potable Water Tank(s) interiors.

3 Tank Disinfection Perform Fill tank with potable water until it starts to overflow.

Do not pressurize tank.

4 Tank Disinfection Perform Add diluted chlorine solution to tank through a sounding tube or threaded connection until FAC is above 100 ppm.

5 Tank Disinfection Perform Rinse sounding tube or threaded connection with at least 5 gallons of fresh potable water.

6 Tank Disinfection Monitor Each hour, measure the FAC. If the FAC drops below 50 ppm, add additional chlorine solution until it is above 100ppm, and rinse the sounding tube or threaded connection. Continue this process until the FAC stays above 50 ppm for four consecutive hours.

7 Tank Disinfection, if more than one tank

Perform Repeat steps 3 – 6 for each tank.

8 Tank Disinfection Perform Drain each tank and fill with potable water until the FAC falls below 1.0 ppm.

Potable Water System Disinfection Checklist 1 System Disinfection Perform Clean, Disinfect, and Flush potable water tanks and potable water system using potable water with 50 ppm FAC for a minimum of 4 hours.

2 System Disinfection Monitor Monitor various plumbing fixtures on each deck throughout the vessel (forward, aft, port, and starboard) to ensure that the 50 ppm FAC has circulated throughout the distribution system to include distant sampling points.

3 System Disinfection Perform Flush the tanks and system with potable water until the FAC drops below 1.0 ppm.

4 System Disinfection Monitor Monitor various plumbing fixtures on each deck throughout the vessel (forward, aft, port, and starboard) to ensure that the FAC is below 1.0 ppm throughout the distribution system to include distant sampling points.

5 System Disinfection Submit Submit to the COR a Condition Report that includes the sampling locations and FAC measurements taken in steps 2 and 4.

1. SCOPE
1.1 This specification contains the general requirements for disinfecting the potable water tanks and system on NOAA ships.
2. REFERENCES
2.1 “Vessel Sanitation Program, 2011 Construction Guidelines, U.S. Department of Health and Human Services, section 22.10, Disinfection of the Potable Water System”.
3. DEFINITIONS
3.1 Free Available Chlorine (FAC) - Concentration of residual chlorine in water present as dissolved gas (Cl2), hypochlorous acid (HClO), and/or hypochorite ion (CIO-). A test kit which measures free chlorine will indicate the combined concentration...
4. REQUIREMENTS
4.1 Potable Water Tank Disinfection
4.1.1 General Requirements
a. Isolate the potable water tanks to be disinfected from the rest of the potable water service system. Thoroughly rinse and drain each tank’s interior.
b. The chlorine solution used to disinfect the tank must be diluted and added through a sounding tube or threaded connection. Immediately after adding the chlorine solution, rinse the sounding tube or threaded connection with at least five gallons of...
4.1.2 Disinfection Procedure
a. Fill the tank with potable water until it starts to overflow, then stop. Exercise care not to pressurize the tank. As the tank fills, add chlorine solution to achieve at least 100 parts per million (ppm) Free Available Chlorine (FAC) content in th...
b. Monitor the FAC content hourly for at least four hours. If the FAC content drops below 50 ppm at any time, add additional chlorine solution to raise the FAC content back to 100 ppm and restart the four hour monitoring period. Continue monitoring an...
c. If disinfecting more than one tank, repeat the above procedure for each tank. At the contractor’s discretion, the same water may be used to disinfect each consecutive tank, as long as the initial FAC content is increased to 100 ppm at the start of ...
d. Drain each tank and refill with potable water. Repeat the above disinfection procedure, except start with an initial FAC content of at 1.0 ppm or greater and monitor the FAC content for 30 minutes. Continue monitoring and raising the FAC content u...
e. Drain each tank and refill with potable water until the total FAC content falls below 1.0 ppm.
4.2 Potable Water System Disinfection
4.2.1 Disinfect the entire Potable Water System, including the potable water tanks, in accordance with reference 2.1 and the potable water tank disinfection requirements in 4.1 above.
4.2.2 Monitor the FAC at various plumbing fixtures on each deck throughout the vessel (forward, aft, port, and starboard) to ensure that the 50 ppm free residual chlorine has circulated throughout the distribution system to include the distant samplin...
4.2.3 After completion of the disinfection process, take additional samples at the same distant plumbing fixtures to validate that the FAC levels at these points are below 1.0 ppm.
4.2.4 Within 24 hours, submit a written Condition Report to the Contracting Officer’s Representative (COR) with the sample locations and FAC readings.
4.3
APPENDIX A
The following checklists are for guidance only. The Contractor is required to meet all requirements in the specification, whether or not they are captured accurately or fully in the checklists.