DRFP_HITSS_III_-_Attachment_I_-_Incentive_Fee_Plan.pdf

PDF 1000 KB Posted

Attached to
Headquarters Information Technology Support Services (HITSS III) Federal contract opportunity
Solicitation number
NNH17579608R
Issued by
National Aeronautics and Space Administration Headquarters

About this file

DRFP HITSS III - Attachment I Incentive Fee Plan

View the file

Other files for this federal contract opportunity

Other files attached to Headquarters Information Technology Support Services (HITSS III), newest first.
File Type Posted
HITSS_III_RFP,_Amendment_9.pdf PDF
HITSS_III_RFP_Attach_A_-PWS_Rev_7,_Amend_9.pdf PDF
HITSS_III_RFP_-_QA_206-212.pdf PDF
HITSS_RFP_SF_30_Amend_8.pdf PDF
HITSS_III_RFP_Attach_A_-PWS,_Rev_6.pdf PDF
HITSS_III_RFP,__Attach_I,_IFP,_Rev1,_Amed_7.pdf PDF
HITSS_III_RFP_-_QA_156-184.pdf PDF
HITSS_III_RFP_-_QA_135-155.pdf PDF
HITSS_III_RFP_-_Enclosure_3-_IWA,_Rev_1.pdf PDF
HITSS_III_RFP_Attach._A_-PWS,_Rev_5,_Amend_5.pdf PDF
HITSS_III_RFP_-_QA_85-134.pdf PDF
HITSS_III_RFP_Attach._A_-PWS_Rev_4_Amend_4.pdf PDF
HITSS_III_RFP_-_Encl._1_RTO_REV1_Amend_4.pdf PDF
RFP_Attachment_A_-PWS,_Rev3.pdf PDF
RFP_-_Attach._C_IDIQ_Matrix_-_Rev_1,_Amend_3.pdf PDF
SF_30_HITSS_RFP_amend_2.pdf PDF
HITSS_III_RFP_-_QA_1-4.pdf PDF
HITSS_III_RFP_-_Attachment_A__PWS_7-18-17.pdf PDF
RFP_-_Exhibit_15-_PastPerfQuest.pdf PDF
SF30,_Amendment_1.pdf PDF
HITSS_III_RFP_-_Attach._B_-_PIV.pdf PDF
HITSS_III_RFP_-_Exhibits_1-14B.pdf PDF
HITSS_III_RFP_-_Attach._G_ITSA.pdf PDF
HITSS_III_RFP_-_Attach._I_-_IFP.pdf PDF
HITSS_III_RFP_-_Attach._D_GFP.pdf PDF
HITSS_III_RFP_Attach._A_-PWS.pdf PDF
HITSS_III_RFP_Cover_Letter.pdf PDF
HITSS_III_RFP-_Attach._F_FM.pdf PDF
HITSS_III_RFP_-_Attach._O_-_IAGP.pdf PDF
HITSS_III_RFP_-_Enclosure_2-_QASP.pdf PDF
HITSS_III_RFP_-_Attach._E_DD_254.pdf PDF
HITSS_III_RFP_-_Exhibit_15-_PPQ.pdf PDF
HITSS_III_RFP_-Attach._M_-_CPE.pdf PDF
HITSS_III_RFP_Clauses.pdf PDF
HITSS_III_RFP_-_Attach._H_-CHD.pdf PDF
DRFP_HITSS_III_Q&A_19.pdf PDF
DRFP_HITSS_III_Q&A_1-18.pdf PDF
DRFP_HITSS_III_-_Revised_Cover_Letter.pdf PDF
DRFP_HITSS_III_-_Exhibit_15-_PastPerfQuest.pdf PDF
DRFP_HITSS_III_-_Attachment_B_-_PIV.pdf PDF
DRFP_HITSS_III_-_Enclosure_3-_Incumbent_Weighted_Average.pdf PDF
DRFP_HITSS_III_-_Attachment_H_-Contract_Historical_Data.pdf PDF
DRFP_HITSS_III_-_Enclosure_1_-_RTO.pdf PDF
DRFP_HITSS_III_-_Attachment_C_IDIQ_Direct_Labor_Rates_Matrices.pdf PDF
DRFP_HITSS_III_-_Attachment_E_DD_254.pdf PDF
DRFP_HITSS_III_-_Attachment_O_IAGP.pdf PDF
DRFP_HITSS_III_-Attachment_M_-_Contractor_Proposed_Enhancements.pdf PDF
DRFP_HITSS_III_-_SF_33.pdf PDF
DRFP_HITSS_III_-_Enclosure_2-_QASP_.pdf PDF
DRFP_HITSS_III_-_Attachment_F_Financial_Management_Reporting.pdf PDF
Show all 50

Headquarters Information Technology Support Services (HITSS III) has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NNH17579608R

Attachment I

ATTACHMENT I

INCENTIVE FEE PLAN AND INCENTIVE FEE

FOR

HEADQUARTERS INFORMATION TECHNOLOGY

SUPPORT SERVICES (HITSS) III

FEBRUARY 2017

I. INTRODUCTION

This Incentive Fee Plan reflects the agreement between the Government and the

Contractor regarding incentive fees available under the contract. It explains the applicability and operation of incentive fee clauses contained elsewhere in the contract.

This plan addresses only the negotiated incentive fees. It does not apply to tasks ordered under the contract on a cost-plus-fixed-fee basis (CPFF) under the Indefinite Delivery

Indefinite Quantity (IDIQ) provisions.

II. BACKGROUND

This contract includes a cost-plus-incentive-fee (CPIF) core requirement for information technology support services for the Information Technology and Communications

Division. In addition, some IDIQ tasks may be ordered on a CPIF basis. Under the core requirement and CPIF task orders, there are incentive fees for technical performance and cost. The operation of these incentives is detailed in this plan.

III. INCENTIVE FEES

Contract Clause B.2, Estimated Cost and Incentive Fee (Core), provides the estimated cost and incentive fee applicable to the core requirement of this contract as follows:

Target Cost, Target Fee, Total Target Cost and Fee, Minimum Fee and Maximum Fee.

Contract Clause B.2, Estimated Cost and Incentive Fee (IDIQ), provides the estimated cost and incentive fee applicable to any tasks awarded as CPIF tasks under this contract as follows: Target Cost, Target Fee, Total Target Cost and Fee, Minimum Fee and

Maximum Fee.

In accordance with Clauses B.8, Incentive Fee Pools (Core), the incentive fees negotiated under the contract are divided between the technical and cost incentive fee pools as follows: technical performance 60% and cost performance 40%. The amount of the incentive fee the Contractor earns depends on performance in each of the incentive fee areas being measured. Technical performance incentive fee is earned based solely on technical performance. Cost performance incentive fee is earned based on cost performance.

The two incentive fee pools are separate and distinct, and the fee earned from each is determined separately based on different performance parameters. The two incentive fee pools are discussed individually in the following sections.

A. Technical Performance Incentive Fee

The Government and the Contractor agree that:

1. During each evaluation period, the Contractor may earn technical performance incentive fee for the core requirement based on the performance level achieved for each performance requirement identified in the tables in Section III.A.4.

2. During each evaluation period, the Contractor may earn technical performance incentive fee for CPIF tasks awarded under the IDIQ provisions of the contract, based on the performance levels established in the task order. Each CPIF task order will have its own set of performance standards and weightings, including method of calculation of the incentive fees.

3. The evaluation periods for which technical incentive fee is available is in accordance with the chart below for the entire period of performance, which includes a 1-year base and four 1-year options.

AVAILABLE TECHNICAL INCENTIVE FEE

FOR EACH PERIOD

Contract

Period

Incentive

Fee

Period

Start Date - End Date

Technical

Incentive

Fee

Fee Min Target Max

Base

Contract Start Date plus 6 months $TBD*

TBP** TBP TBP

Base 2 6-month period thereafter $TBD TBP TBP TBP

Option 1 3 6-month period thereafter $TBD TBP TBP TBP

Option 1 4 6-month period thereafter $TBD TBP TBP TBP

Option 2 5 6-month period thereafter $TBD TBP TBP TBP

Option 2 6 6-month period thereafter $TBD TBP TBP TBP

Option 3 7 6-month period thereafter $TBD TBP TBP TBP

Option 3 8 6-month period thereafter $TBD TBP TBP TBP

Option 4 9 6-month period thereafter $TBD TBP TBP TBP

Option 4 10 6-month period thereafter $TBD TBP TBP TBP

Total $TBD TBP TBP TBP

*TBD: To Be Determined, based on the negotiated fees and phasing.

**TBP: To Be Proposed.

4. Each required service (and associated performance requirement) shall be evaluated by the Government using the Incentive Fee Quality Assurance Plan

Appendix 1, which provides details as to how samples are selected and evaluated. Each required service is weighted so that 100% of the evaluation for technical performance (and resulting technical performance incentive fee) will be derived from the performance requirements in this document.

a. For Incentive Period 1, the technical performance incentives will be based on selected metrics from Technical Preparedness, Service

Operational Readiness, Program and Project Management Readiness, Risk Management, Integration Readiness, and Transition Readiness.

b. For Incentive Periods 2 through 10, the technical performance incentive fee pool shall be apportioned (weighted) between the technical performance categories as listed below.

Performance Category Number of

Performance Requirements

Incentive Fee (IF)

Program Management and Project Management

3 15%

Customer Relationship Management 1 15%

Configuration Management 1 4%

Applications Development and Information Management

3 11%

Emerging Technology 1 5%

NASA Headquarters Data Center and Cloud Services

15%

Systems Engineering and Integration 1 5%

IT Security 3 25%

COMSEC 1 5%

Total 100%

Specific details concerning each performance requirement are contained in Section

III.A.4.

5. The technical performance requirements for the core requirement are identified in the following tables.

Incentive Period 1: Transition and Stabilization

IF

Metric

PWS Section Required Service Performance Requirement

Fee Amount

Performance Level Incentive Fee (IF)

T&S-1 3.0

Completion of Actions from

Transition Readiness Review

(TRR)

Outstanding actions from the TRR shall be completed within the required time period.

Maximum Fee

96% - 100% of the actions are completed by the due date.

15% Target

Fee 90% - 95% of the actions are completed by the due date.

Minimum Fee

Less than 90% of the actions are completed by the due date.

T&S-2 3.0

Completion of Actions from Integration

Readiness Review

(IRR)

Outstanding actions from IRR shall be completed within the required time period

Maximum Fee

96% - 100% of the actions are completed by the due date.

5% Target

Fee 90% - 95% of the actions are completed by the due date

Minimum Fee

86% - 89% of the actions are completed by the due date.

T&S-3 3.0

Content of Plans, Reports, and Deliverables for Technical Preparedness

Technical preparedness plans, reports, and deliverables will be evaluated based on requirements in the PWS.

Maximum Fee

93%-100% of the required elements in each plan/report/deliverable are completed and approved.

10% Target

Fee

86%-92% of the required elements in each plan/report/deliverable are completed and approved.

Minimum Fee

Less than 86% of the required elements in each plan/report/deliverable are completed and approved.

T&S-4 3.0

Content of Plans, Reports, and Deliverables for Service Operational Readiness

Service Operational Readiness plans, reports, and deliverables will be evaluated based on requirements in the PWS.

Maximum Fee

93%-100% of the required elements in each plan/report/deliverable are completed and approved.

10% Target

Fee

86%-92% of the required elements in each plan/report/deliverable are completed and approved.

Minimum Fee

Less than 86% of the required elements in each plan/report/deliverable are completed and approved.

T&S-5 3.0

Content of Plans, Reports, and Deliverables for Program and Project Management Readiness

(PPMR)

Program and Project Management Readiness plans, reports, and deliverables will be evaluated based on requirements in the PWS.

Maximum

93%-100% of the required elements in each plan/report/deliverable are completed and approved.

10% Target

Fee

86%-92% of the required elements in each plan/report/deliverable are completed and approved.

Minimum Fee

Less than 86% of the required elements in each plan/report/deliverable are completed and approved.

T&S-6 3.0

Completion of Actions for Program Management Readiness Review and Project Management Readiness Review

Outstanding actions from Program Management Readiness Review and Project Management Readiness Review shall be completed within the required time period.

Maximum Fee

96% - 100% of the actions are completed by the due date.

10%

Target Fee

86%-92% of the actions are completed by the due date.

Minimum Fee

Less than 86% of the actions are completed by the due date.

T&S-7 3.0

Content of Plans, Reports, and Deliverables for Risk Management

Risk Management plans, reports, and deliverables will be evaluated based on

93%-100% of the required elements in each plan/report/deliverable are completed and approved.

10% Target

Fee

82%-92% of the required elements in each plan/report/deliverable are completed and approved.

Minimum Fee

Less than 82% of the required elements in each plan/report/deliverable are completed and approved.

T&S-8 3.0

Completion of Actions for Risk Management Review

Outstanding actions from Risk Management Review

Maximum Fee

96% - 100% of the actions are completed by the due date.

10% Target

Fee 86%-92% of the actions are completed by the due date.

Minimum Fee

Less than 86% of the actions are completed by the due date.

T&S-9 3.0

Content of Plans, Reports, and

Deliverables for Integration

Readiness Review

Integration Readiness Review plans, reports, and deliverables will be evaluated based on

93%-100% of the required elements in each plan/report/deliverable are completed and approved.

10% Target

Fee

82%-92% of the required elements in each plan/report/deliverable are completed and approved.

Minimum Fee

Less than 82% of the required elements in each plan/report/deliverable are completed and approved.

T&S-10 3.0

Stakeholder Satisfaction with Transition and Stabilization

Ratings from transition stakeholders shall be no less than a "4" on a scale of 1-5, with "5" being the highest.

Maximum Fee

91% - 100% meet the criteria.

10% Target

Fee 85% - 90% meet the criteria.

Minimum Fee

Less than 85% meet the criteria.

100%

Incentive Periods 2 - 10: Contract Operations

Program Management

Metric

PWS Section

Required Service

Performance Requirement Fee

Amount Performance Level

Incentive Fee (IF)

1 2.2.2.2 Financial and

Resource Reporting

All objectives and requirements for financial reporting are met. Financial and resource data is captured at the levels required. The following levels will be evaluated for incentive fee:

•Contract Level Report •Program Level Report •Project Level Report

Maximum Fee

98%-100% of financial data is accurate at the level of reporting required.

10%

Target Fee

95%-97% of financial data is accurate at the level of reporting required.

Minimum Fee

Less than 95% of financial data is accurate at the level of reporting required.

2 2.3.2, 2.3.3

Adherence to Service

Request and Project

Schedules

For all Work Requests/Service Requests and Projects completed during the evaluation period, all end dates shall be met in accordance with the baseline schedule completion date.

Maximum Fee

99% - 100% meet the criteria.

5%

Target Fee 96% - 98% meet the criteria.

Minimum Fee

Less than 96% meet the criteria.

Program-Wide Services

Metric

PWS Section Required Service Performance Requirement

Fee Amount

Performance Level Incentive Fee (IF)

22 (and subsections) Configuration Management

Management of Configuration Items and

Configuration Management Data

Maximum Fee

Audits of configuration items, configuration management data, and compliance with CM standards and governance have

0 corrective actions for the contractor to mitigate/correct.

5% Target

Fee

Audits of configuration items, configuration management data, and compliance with CM standards and governance have

1 corrective action for the contractor to mitigate/correct.

Minimum Fee

Audits of configuration items, configuration management data, and compliance with CM standards and governance have more than 1 corrective actions for the contractor to mitigate/correct.

4 26

Application & Website

Development Services and Web

Services

Functional Quality (SLA 26- 0-2), process quality (SLA

26-0-3), and technical quality (SLA 26-0-4) of Application & Website

Development Services and Web Services

Maximum Fee

Meet SLAs more than 99% of the time.

10% Target

Fee Meet SLAs 98% - 99% of the time.

Minimum Fee

Meet SLAs less than 98% of the time.

5 26 Post Release

Defects

All application version releases shall be error free and not require post-release bug fixes.

Maximum Fee

More than 98% are error free

10% Target

Fee 98 % are error free

Minimum Fee

Less than 98% are error free

6 26

Application, Website, Web Service, and IT

System Inventory

Maintenance of the application, website, web service, and IT system inventory in accordance to PWS requirements, SLAs, and metrics.

Maximum Fee

Meets SLAs, metrics, and requirements more than 98% of the time

7% Target

Fee Meets SLAs, metrics, and requirements 98% of the time

Minimum Fee

Meets SLAs, metrics, and requirements less than 98% of the time

Program-Wide Services

IF

Metric

PWS Section Required Service Performance Requirement

Fee Amount

Performance Level Incentive Fee (IF)

7 28 Emerging

Technology

Emerging Technology Research and Trending in accordance to PWS requirements, deliverables, and governance

Maximum Fee

More than 10 new technologies, innovations, and/or techniques are identified, evaluated/tested, piloted and/or implemented each month.

5%

Target Fee

10 new technologies, innovations, and/or techniques are identified, evaluated/tested, piloted and/or implemented each month.

Minimum Fee

Less than 10 new technologies, innovations, and/or techniques are identified, evaluated/tested, piloted and/or implemented each month.

8 11 Customer

Satisfaction Surveys

Customer surveys shall include an Overall Rating of no less than a "4" on a scale of 1-5, with "5" being the highest rating.

Maximum Fee

98%-100% meet the criteria.

10% Target

Fee 95%-97% meet the criteria.

Minimum Fee

Less than 95% meet the criteria.

9 39.2 Compliance with

Patch Management Plan

Compliance with Patch Management Plan. Data center servers shall be patched in accordance with the approved patch management plan and schedule. (Metric 39-2-1 in

PWS)

Maximum Fee

99% - 100% meet the criteria.

8%

Target Fee

95% - 98% meet the criteria.

Minimum

Less than 95% meet the criteria.

Program-Wide Services

Metric

PWS Section Required Service Performance Requirement

Fee Amount

Performance Level Incentive Fee (IF)

10 36 Systems and Applications Availability

Systems and Applications Availability

Maximum Fee

More than 99.95% availability

10% Target Fee 98% -99.95% availability

Minimum Fee

Less than 98% availability

11 44.1 Vulnerability

Mitigation

All system vulnerabilities shall be mitigated within the specified times, based on the assessed severity.

Maximum Fee

98% - 100% meet the criteria.

10% Target Fee 95% - 97% meet the criteria.

Minimum Fee

92% - 94% meet the criteria.

12 44.4 Incident

Management

All IMS tickets assigned to the organization shall be acknowledged and work begun within the required time.

Maximum Fee

98% - 100% meet the criteria.

5% Target Fee 95% - 97% meet the criteria.

Minimum Fee

92% - 94% meet the criteria

13 47 COMSEC Inventory

All COMSEC equipment, material, and transaction records shall be accurate and no COMSEC violations within the control and responsibility of the contractor shall occur.

Maximum Fee

100% meet the criteria.

5% Target Fee 99% meet the criteria

Minimum Fee

98% meet the criteria.

100%

6. For each performance requirement, a comparison of the performance level achieved and the performance level associated with each fee amount

(maximum fee, target fee, or minimum fee) will be made to determine the appropriate fee amount. Additionally, the performance level achieved will be rounded down, if required, when making the comparison. For example, a performance level achieved of 98.7% would be rounded down to 98% and not rounded up to 99%. The only exception is for Metric #12, Systems and

Applications Availability. For that metric, the calculation will be performed to two decimal places and the metric will be determined according to the performance levels listed.

7. The required services, performance requirements, performance levels and incentive fee weights may be adjusted by mutual agreement between the

Government and the Contractor. Any adjustments shall be made by a modification to the contract prior to the start of an incentive period.

8. The Contracting Officer’s decision as to the amount of technical performance incentive fee earned each evaluation period is a unilateral determination based on the established performance requirements and the performance levels achieved, and may be subject to the Disputes clause. All technical performance incentive fee payments for each evaluation period shall be final.

B. Cost Performance Incentive Fee

The Government and the Contractor agree that:

1. Cost performance incentive fee payable shall be determined based on the final total allowable cost at the completion of the contract compared against the target cost in accordance with the share ratios and procedures specified in

Clauses B.2 and B.3.

2. Target cost and target fee:

a. The target cost and target fee specified in this Schedule are subject to adjustment if the contract is modified in accordance with paragraph (d) of

Clause B.5 or as specified in each individual task order.

b. “Target cost,” as used in this contract means the estimated cost of this contract as initially negotiated, adjusted in accordance with paragraph (d) of Clause B.5.

3. The Contractor may bill for provisional payment of cost performance incentive fees in accordance with Clause G.12.

APPENDIX 1:

INCENTIVE FEE QUALITY ASSURANCE PLAN

HEADQUARTERS IT SUPPORT SERVICES (HITSS) CONTRACT

INCENTIVE FEE QUALITY ASSURANCE PLAN

This Incentive Fee Quality Assurance Plan (QAP) is developed to provide a disciplined process for evaluating the contractor’s performance in order to determine conformity with the performance requirements of the Performance Work Statement. It is designed to aid the performance monitors in providing effective and systematic surveillance of contractor performance, and to provide the contractor with specific details of how the performance requirements will be evaluated. This plan consists of a sampling guide for each performance requirement identifying how and when surveillance will be performed.

The following sections of the sampling guide are explained:

Method of Surveillance – Identifies the method to be used for selecting samples (100%

Inspection or Random Sample).

When a random sample will be selected, the following general process will be used to choose the samples:

1. The number of transactions (or tickets or other workload indicator) occurring during the time period will be determined and the transactions will be sorted by the initiation date (or other appropriate criteria).

2. The samples will be selected in a manner that ensures they are spread across the entire time period that is sampled (e.g., every fifth ticket will be a part of the sample). The spread between each transaction sampled will vary depending upon the sample size and actual number of transactions occurring during the evaluation period.

Lot Size – The estimated workload during a 6-month evaluation period.

Sample Size – The number or percentage of items from the lot that will be sampled.

Performance Requirement – Identifies the performance standard associated with a work requirement.

Sampling Procedure – Describes the procedure to be used in selecting the samples to be inspected, how often samples will be taken, and the relative weight of the samples.

Inspection Procedure – Describes what will be inspected and how, and how the metric will be calculated.

METRIC #T&S-1

Completion of Actions from Transition Readiness Review (TRR)

1. Method of Surveillance: 100% Inspection.

2. Lot Size: Approximately 50 open actions from the TRR that will be due for completion during the first six months of the contract. The actions will be documented in a Transition Plan. The associated deliverable with this metric is a plan that states all actions and states status of each action with cross reference to the

Integrated Schedule for contract transition.

Transition Requirement

Area

Transition Activity Transition Product

Transition Readiness

TR Requirement 1 Transition Readiness

Review (TRR)

Transition Plan and

Integrated Schedule

3. Sample Size: 100% of lot.

4. Performance Requirement: Open actions identified during the TRR shall be completed within the required due date.

5. Sampling Procedure: All TRR actions assigned to the contractor that have required completion dates during the first six months of the contract will be included in the sample. All actions will be of equal weight.

6. Inspection Procedure: The Government will review a report of closed TRR actions assigned to the contractor on a monthly basis. The actual completion date of all actions completed during the month will be examined to determine if they met the required due date. At the end of the 6-month period, the total number of actions completed by the required due date will be divided by the total number of actions due, then multiplied by 100 to determine the percentage completion.

METRIC #T&S-2

Completion of Actions from Operational Readiness Review (IRR)

7. Method of Surveillance: 100% Inspection.

8. Lot Size: Approximately 30 open actions from the IRR that will be due for completion during the first six months of the contract.

9. Sample Size: 100% of lot.

10. Performance Requirement: Open actions identified during the IRR shall be

11. Sampling Procedure: All IRR actions assigned to the contractor that have required completion dates during the first six months of the contract will be included in the sample. All actions will be of equal weight.

12. Inspection Procedure: The Government will review a report of closed IRR actions assigned to the contractor on a monthly basis. The actual completion date of all actions completed during the month will be examined to determine if they met the required due date. At the end of the 6-month period, the total number of actions

METRIC #T&S-3

Content of Plans, Reports, and Deliverables for Technical Preparedness

2. Lot Size: 9 deliverables across the 5 Technical Preparedness requirements. (All deliverables are of equal weight). The required deliverables are:

Transition

Requirement Area

Transition Activity Transition Product

Technical Preparedness (TP)

TP Requirement 1 Technical Readiness

Assessment

Technical Readiness Report, Part

1 - Assessment Findings and

Mitigation Plan

Technical Readiness Report, Part

2 – Technology Inventory

(includes all CI/assets)

TP Requirement 2 Resource Plan and Staffing

Activity

Resource Management Plan and

Staff Plan (includes all resumes)

Staff plan (includes all resumes)

Organizational CONOPS

Interviews of key and critical personnel/roles

TP Requirement 3 Technical Governance

Activity

Technical Governance

Stabilization Plan

TP Requirement 4 Technical Roadmap

Development

Technical Roadmap (Contract

Year 1)

TP Requirement 5 Technical Portfolio

Assessment

Technical Readiness Report, Part

3 – Technical Portfolio

Assessment, Maintenance Plan, and Recommended Improvements

4. Performance Requirement: Content specific to the 9 deliverables listed above will address the requirements as outlined in the PWS.

5. Sampling Procedure: The 9 deliverables will be uploaded to the Contract

Management portal or applicable document repository for review by ITCD.

6. Inspection Procedure: The Government will review each of the 9 deliverables submitted during the six month period to determine if the following elements have been addressed:

Identifies the goal or goals that are addressed in the deliverable

Identifies the required skills needed

States assessment findings and analysis results

States recommendations for each of the Technical Preparedness Requirement areas.

States risks, gaps, deficiencies, and recommended and/or proposed mitigations

States that overall implementation can be accomplished within the estimated cost of the contract; or includes an estimated cost and basis of estimate (must provide estimated cost and basis of estimate to successfully meet this element)

Discusses points of integration across services, processes, services providers, contracts, etc.

Discusses technical preparedness of the contractor required for transition and stabilization of services, technical capabilities, and operations

Is delivered and available by the due date

Each deliverable counts towards successfully meeting the metric. The total number of deliverables meeting success criteria and acceptance for completion by the government will be divided by 9, then multiplied by 100, to determine if the overall metric has been met.

METRIC #T&S-4

Content of Plans, Reports, and Deliverables for Service Operational Readiness

2. Lot Size: 9 deliverables across the 5 Service Operational Readiness requirements.

(All deliverables are of equal weight). The required deliverables are:

Transition

Requirement Area

Transition Activity Transition Product

Service Operational Readiness (SOR)

SOR Requirement 1 Assessment of Service

Operations (each service)

Service Operations Assessment

Report

SOR Requirement 2 SLA, OLA, and Performance

Review, Findings

Determination, and

Recommendation (each service)

SLA, OLA, and Performance

Measures Inventory (for each service)

Findings Report (for each service)

Recommendation and Proposed

Schedule for Implementing

Recommendations (for each service)

SOR Requirement 3 ITIL Framework Review and

Continuous Service

Improvement Recommendation

ITIL Framework Findings Report

Continuous Service

Improvement Recommendation and Plan

SOR Requirement 4 Operational Readiness Planning and Management

Operational Readiness Plan

Operational Readiness Report

SOR Requirement 5 MoA Review and Assessment MoA Review Report and

Recommendation

4. Performance Requirement: Content specific to the 9 deliverables listed above will

5. Sampling Procedure: The 9 deliverables will be uploaded to the Contract

6. Inspection Procedure: The Government will review each of the 9 deliverables

States assessment findings and analysis results

States recommendations for each of the Service Operational Readiness

Requirement areas.

States risks, gaps, deficiencies, and recommended and/or proposed mitigations

States that overall implementation can be accomplished within the estimated cost of the contract; or includes an estimated cost and basis of estimate (must provide estimated cost and basis of estimate to successfully meet this element)

Discusses points of integration across services, processes, services providers, contracts, etc.

Discusses technical, risk, operational, and programmatic preparedness of the contractor required for transition and stabilization of services, technical capabilities, and operations government will be divided by 9, then multiplied by 100, to determine if the overall

METRIC #T&S-5

Content of Plans, Reports, and Deliverables for Program and Project Management

Readiness

2. Lot Size: 11 deliverables across the 5 Program and Project Management Readiness requirements. (All deliverables are of equal weight). The required deliverables are:

Transition Requirement

Area

Transition Activity Transition Product

Program and Project Management Readiness (PPMR)

PPMR Requirement 1 Project Management

Readiness Review

Project Management

Readiness Report

PPMR Requirement 2 Program Management

Readiness Review

Program Management

Readiness Report

PPMR Requirement 3 Project Management Tool

Inventory and CONOPS

Planning

Project Management Tool

Inventory

Project Management

CONOPS

PPMR Requirement 4 Program Management Tool

Inventory and CONOPS

Planning

Program Management Tool

Inventory

Program Management

CONOPS

PPMR Requirement 5 Task Order Management and Customer Relationship

Management

Task Order Management

SOP(s)

Customer Relationship

Management SOP

Contract Level

Communications Plan

Transition Communications

Plan

Customer Satisfaction

Survey and Report

4. Performance Requirement: Content specific to the 11 deliverables listed above will address the requirements as outlined in the PWS.

5. Sampling Procedure: The 11 deliverables will be uploaded to the Contract

6. Inspection Procedure: The Government will review each of the 11 deliverables

States assessment findings and analysis results

States recommendations for each of the Program and Project Management

Readiness Requirement areas.

States risks, gaps, deficiencies, and recommended and/or proposed mitigations

States that overall implementation can be accomplished within the estimated cost of the contract; or includes an estimated cost and basis of estimate (must provide estimated cost and basis of estimate to successfully meet this element)

Discusses points of integration across services, processes, services providers, contracts, etc.

Discusses program and project management preparedness of the contractor required for transition and stabilization of services, technical capabilities, and operations government will be divided by 11, then multiplied by 100, to determine if the overall

METRIC #T&S-6

Completion of Actions from Program and Project Readiness Review (PPMRR)

2. Lot Size: Approximately 30 open actions from the PPMRR that will be due for

4. Performance Requirement: Open actions identified during the PPMRR shall be

5. Sampling Procedure: All PPMRR actions assigned to the contractor that have required completion dates during the first six months of the contract will be included in the sample. All actions will be of equal weight.

6. Inspection Procedure: The Government will review a report of closed PPMRR actions assigned to the contractor on a monthly basis. The actual completion date of all actions completed during the month will be examined to determine if they met the required due date. At the end of the 6-month period, the total number of actions

METRIC #T&S-7

Content of Plans, Reports, and Deliverables for Risk Management Readiness

2. Lot Size: 6 deliverables across the 5 Risk Management Readiness requirements. (All

Transition Activity Transition Product

Risk Management (RM)

RM Requirement 1 Risk Management Planning Risk Management Plan

RM Requirement 2 Risk Management Tool

Inventory

Risk Management Tool

Inventory

RM Requirement 3 Risk Management

Framework

Risk Management

Framework

RM Requirement 4 Risk Management

Readiness Review

Risk Management

Readiness Report

(transition readiness)

RM Requirement 5 Risk Management

Reporting

Risk Management Report

(contract level)

Risk Management Report and Mitigation Plan (for each service)

4. Performance Requirement: Content specific to the 6 deliverables listed above will

5. Sampling Procedure: The 6 deliverables will be uploaded to the Contract

6. Inspection Procedure: The Government will review each of the 6 deliverables

States assessment findings and analysis results

States recommendations for each of the Risk Management Readiness

Requirement areas.

States risks, gaps, deficiencies, and recommended and/or proposed mitigations

States that overall implementation can be accomplished within the estimated cost of the contract; or includes an estimated cost and basis of estimate (must provide estimated cost and basis of estimate to successfully meet this element)

Discusses points of integration across services, processes, services providers, contracts, etc.

Discusses risk management preparedness of the contractor required for transition and stabilization of services, technical capabilities, and operations government will be divided by 6, then multiplied by 100, to determine if the overall

METRIC #T&S-8

Completion of Actions from Risk Management Readiness Review (RMRR)

2. Lot Size: Approximately 30 open actions from the RMRR that will be due for

4. Performance Requirement: Open actions identified during the RMRR shall be

5. Sampling Procedure: All RMRR actions assigned to the contractor that have required completion dates during the first six months of the contract will be included in the sample. All actions will be of equal weight.

6. Inspection Procedure: The Government will review a report of closed RMRR actions assigned to the contractor on a monthly basis. The actual completion date of all actions completed during the month will be examined to determine if they met the required due date. At the end of the 6-month period, the total number of actions

METRIC #T&S-9

Content of Plans, Reports, and Deliverables for Integration Readiness

8. Lot Size: 6 deliverables across the 5 Integration Readiness requirements. (All

Transition Activity Transition Product

Integration Readiness (IR)

IR Requirement 1 OCA and OCI Preparation OCI

OCA

IR Requirement 2 Service and Program

Integration Assessment and

Planning

Service Integration

Assessment and Plan

Program Integration

Assessment and Plan

IR Requirement 3 Technology Integration

Assessment

Technology Integration

Assessment Report (what technology and tools should be integrated for service operations and reporting)

IR Requirement 4 Data Model and Data

Architecture Assessment and Improvement Plan

Data Model and Data

Architecture Review and

Findings Report

Data Model and Data

Architecture Improvement

Plan

IR Requirement 5 Integration Readiness

Review

Integration Readiness

Report

9. Sample Size: 100% of lot.

10. Performance Requirement: Content specific to the 8 deliverables listed above will

11. Sampling Procedure: The 8 deliverables will be uploaded to the Contract

12. Inspection Procedure: The Government will review each of the 8 deliverables

States assessment findings and analysis results

States recommendations for each of the Integration Readiness Requirement areas.

States risks, gaps, deficiencies, and recommended and/or proposed mitigations

States that overall implementation can be accomplished within the estimated cost of the contract; or includes an estimated cost and basis of estimate (must provide estimated cost and basis of estimate to successfully meet this element)

Discusses points of integration across services, processes, services providers, contracts, etc.

Discusses integration requirements and preparedness of the contractor required for transition and stabilization of services, technical capabilities, and operations government will be divided by 6, then multiplied by 100, to determine if the overall

METRIC #T&S-10

Stakeholder Satisfaction with Transition and Stabilization

2. Lot Size: Approximately 50 customer surveys.

4. Performance Requirement: Surveys submitted by transition stakeholders shall include an Overall Rating of no less than a "4" on a scale of 1-5, with "5" being the highest rating.

5. Sampling Procedure: Surveys will be sent to all transition stakeholders, which include task monitors on the core requirement and task owners of all tasks issued during the first six months of the contract. Surveys will also be sent to all managers in the IT and Communications Division. All surveys returned from transition stakeholders will be included in the sample. All surveys will be of equal weight.

6. Inspection Procedure: The Government will review the survey responses and will count the number of surveys that include an Overall Rating of at least “4”. (Although surveys may consist of ratings for more than one element of performance, the only rating that will be used to determine this metric is the “Overall Rating”.) Surveys meeting the metric will be divided by the total number of surveys received, then multiplied by 100, to determine if the metric was met.

PROGRAM MANAGEMENT (PWS SECTION 2.0)

METRIC #1

Financial and Resource Reporting

2. Lot Size: 4 reports containing specific elements (1 report (contract level report) containing 2 elements across all task orders, 2 reports (program, and service level reports) containing 12 required elements; 1 report (project level report) containing10 elements). Each report will be of equal weight (1/3 of metric) for incentive fee evaluation. The required reports included in this metric are listed below. The following levels will be evaluated for incentive fee:

a. Contract Level Report (All task orders)

1. CORE Invoice

2. CORE 533 Report

3. IDIQ Invoices

4. IDIQ 533 reports

b. Program Level Report (Totals for each major PWS section)

1. Planned costs

2. actual costs

3. planned labor categories

4. actual labor categories

5. actual hours

6. planned hours

7. cost variance

8. hour variances

9. labor category variance

10. cost forecast

11. hours forecast

12. labor category forecast

c. Service Level Report (Totals of each element listed below by each service supported on the contract)

1. Planned costs

2. actual costs

3. planned labor categories

4. actual labor categories

5. actual hours

6. planned hours

7. cost variance

8. hour variances

9. labor category variance

10. cost forecast

11. hours forecast

12. labor category forecast

d. Project Level Report (for each project in the reporting period)

1. Planned costs

2. actual costs

3. actual hours

4. planned hours

5. planned schedule

6. actual schedule

7. cost variance

8. hour variances

9. schedule variance

10. earned value

4. Performance Requirement: All reports containing the required reporting elements are accurate and meet the requirements as described in the PWS.

5. Sampling Procedure: The reports will be uploaded to the Contract Management portal (or applicable document repository) and related data will be stored in a NASA financial reporting system for review by ITCD.

6. Inspection Procedure: The Government will review each of the four reports been addressed with accuracy:

For the Contract Level Report, the Government will review each of the invoices and 533 reports each month for accuracy.

For the Program Level Report, the Government will review each of the 12 report elements for consistency with PWS requirements as well as accuracy against labor categories, costs, and hours proposed (for each major PWS section) by the contractor during the contractor’s proposal and final numbers at contract award

OR based on adjusted baseline per approved revisions to staffing/labor categories, hours, and costs due to changes in PWS section requirements.

For the Service Level Report, the Government will review each of the 12 report elements for consistency with PWS requirements as well as accuracy against labor categories, costs, and hours proposed by the contractor during contractor’s proposal and final numbers at contract award OR based on adjusted baseline per approved revisions to staffing/labor categories, hours, and costs due to changes in service requirements.

For the Project Level Report, the Government will review each of the 10 report elements for consistency with PWS requirements as well as project management plans, estimates, and schedules.

Each report counts (1/3) as successfully meeting the metric. The metric will be calculated as follows:

For Contract level reporting, each of the 4 elements will count equally. 1 point will be given to each element for which PWS requirements are met and for which there is accuracy in the data.

Contract Level Report % = [(total number of elements meeting PWS requirements and accuracy) /4] * 1/4

For Program level reporting, each of the12 elements will count equally. 1 point will be given to each element for which PWS requirements are met and for which there is accuracy in the data.

Program Level Report % = [(total number of elements meeting PWS requirements and accuracy) /12] * 1/4

For Service level reporting, each of the12 elements will count equally. 1 point will be given to each element for which PWS requirements are met and for which there is accuracy in the data.

Service Level Report % = [(total number of elements meeting PWS requirements and accuracy) /12] * 1/4

For Project level reporting, each of the 10 elements will count equally. 1 point will be given to each element for which PWS requirements are met and for which there is accuracy in the data based on project management plans, estimates, and schedules.

Project Level Report % = [(total number of elements meeting PWS requirements and accuracy based on project management plans, estimates, and schedules) /10] * 1/4

To determine if the metric is met:

Total metric % = Contract Level Report % + Program Level Report % +

Service Level Report % + Project Level Report %

PROGRAM MANAGEMENT (PWS SECTION 2.0)

METRIC #2

Adherence to Service/Work Request Schedules

2. Lot Size: Approximately 125 Service/Work Requests per month or approximately

750 Service Requests per 6-month period.

3. Sample Size: 100% of all Service/Work Requests with scheduled completion dates within the 6 month period of performance.

4. Performance Requirement: All Service/Work Requests with completion dates that fall within the 6 month review period shall be completed by the scheduled completion date.

5. Sampling Procedure: The HQ ITCD Service/Work Request Intake management system shall be used to identify the service/work requests with scheduled completion dates that fall within the period. All service/work requests will be of equal weight.

6. Inspection Procedure:

a. At the end of the 6-month period, the Government will access the service/work request intake management system.

b. The Government will compare the service/work request scheduled completion dates with actual completion dates. If there are interim completion dates or milestones associated with a service/work request, only the final date will be used to determine if the metric was met.

c. The total number of service/work request with actual completion dates by the scheduled dates shall be divided by the total number with scheduled completion dates within the 6 month period.

d. Service/work requests that received Government approval to extend the scheduled completion date beyond that period shall not be included in this calculation.

PROGRAM-WIDE SERVICES (PWS SECTION 22.0)

METRIC #3

Configuration Management

Management of Configuration Items and Configuration Management Data

2. Lot Size: Approximately 100 configuration items. The following types of configuration items will be reviewed:

25 - SOPs and Process Documents

25 – Applications (Inventory Attribute Data (in the HQ ITCD application portfolio/application inventory repository for each application)

25 – Applications (Information STRAW, APAT, or other agency repository for each application)

5 – VM specifications

25 – Service Level Configuration Items

3. Sample Size: 100%.

4. Performance Requirement: For each type of configuration item, Metric 22-1-1 and

SLA 22-1-1 will be met.

5. Sampling Procedure: The Government will randomly select 25 SOPs and process documents, inventory attribute data for 25 applications in the HQ ITCD application portfolio/inventory, attribute data for 25 applications in the agency repository of applications for 25 applications, 5 VM specifications, and 25 configuration items

(across 5 service areas). The Government will review the configuration items for accuracy of information and attribute data.

For SOPs and Process Documents:

The accuracy of SOPs and Process documents will be assessed by the Government.

Accuracy of information, configuration item state, and configuration item status will be reviewed by the Government to determine if metric 22-1-1 and SLA 22-1-1 are met.

Each SOP and process document will have equal weight. The percentage of SOPs and processes meeting the metric and SLA is calculated as follows:

SOP and Process Accuracy % = [(total number of SOPs and processes meeting PWS requirements and accuracy) /25] * 1/5

For Application Inventory Attribute Data in the HQ ITCD application portfolio/application inventory repository, the accuracy of attribute data will be assessed by the Government. Examples of attribute data reviewed by the Government are:

application acronym, application owner, application owner organization, authentication method, hosting facility/location, programming language(s), version of programming languages, etc.

HQ ITCD Application Inventory Accuracy % = [(total number of applications with complete and accurate records) /25] * 1/5

For Application Inventory Attribute Data in the agency application portfolio/application inventory repository (STRAW, APAT, or other approved repository), the accuracy of attribute data will be assessed by the Government. Examples of attribute data reviewed by the Government are: application acronym, application owner, application owner organization, authentication method, hosting facility/location, programming language(s), version of programming languages, etc.

Agency HQ Application Inventory Accuracy % = [(total number of applications with complete and accurate records) /25] * 1/5

For VM Specifications, the Government will review specifications under configuration management that are in approved and deployed status. The specifications will be reviewed against VM configurations in the HQ ITCD data center and cloud environment.

Specification documents with approved and deployed status much reflect configurations deployed in the data center and cloud environment.

VM Specifications Accuracy % = [(total number of specifications with completely accurate information)/5]*1/5

For Service Level Configuration Items:

The accuracy of 5 configuration items will be assessed for 5 service areas by the

Government. Accuracy of information, configuration item state, and configuration item status will be reviewed by the Government to determine if metric 22-1-1 and SLA 22-1-1 are met. Each configuration item will have equal weight. The percentage of configuration items meeting the metric and SLA is calculated as follows:

Service Level Configuration Item Accuracy % = [(total number of service level configuration item meeting metric, SLA, PWS requirements and accuracy) /25] *

1/5

To determine the total percentage of incentive fee metric accomplished, Total metric % = SOP and Process Accuracy % + HQ ITCD Application Inventory

Accuracy % + Agency HQ Application Inventory Accuracy % + VM Specifications

Accuracy % + Service Level Configuration Item Accuracy %

PROGRAM-WIDE SERVICES (PWS SECTION 26.0)

METRIC #4

Application & Website Development Services and Web Services

Functional Quality (SLA 26-0-2), Process Quality (SLA 26-0-3), and

Technical Quality (SLA 26-0-4)

8. Lot Size: Approximately 10 application, website, and/or web service releases monthly or approximately 60 application, website, and/or web service releases per 6-month period.

9. Sample Size: 100% of all completed and/or implemented application, website, and/or web service releases within the 6 month period of performance.

10. Performance Requirement: All application, website, and/or web services approved for deployment and/or deployed within the six months will meet requirements and

SLAs as follows:

Service Level

Agreement

Description SLA

SLA 26-0-2 Functional Quality – Do applications meet functional requirements?

Response times by transaction

Number of defects by severity level

All response time requirements are met 99.95% of the time.

For enhancements, 0% increase in defects

Code delivered with 0 severity level 1 defects

SLA 26-0-3 Technical Quality and standard adherence – Does the delivered application meet all required specifications?

Cyclomatic complexity

(CC)

Dead code

Unstructured code

Compliance with Coding

Standards

CC < 10 per module

0% dead code

<5% unstructured code

100% compliance, ensured through inspections

SLA 26-0-4 Process Quality – How well do development processes perform?

Defect removal rates of > 95%

Service Level

Agreement

Description SLA

Defect removal rate

Defect density

Defect densities of < 3 per module

11. Sampling Procedure: The HQ ITCD code repository, HQ ITCD test management and test result system, and code reviews will be used to identify the application, website, and/or web service releases meeting SLAs 26-0-2, 26-0-3, and 26-0-4. All applications, websites, and/or web services will be of equal weight.

12. Inspection Procedure:

a. Throughout the 6-month period, the Government will access the code repository and the test management/test result system to review code for applications, websites, and/or web services.

b. The Government will review code in the code repository to determine if

SLA 26-0-3 is met.

c. The Government will review test results in the test management/test results system to determine if SLA 26-0-4 is met.

d. The Government will review functional and operational requirements as well performance test results and post deployment defects to determine if

SLA 26-0-2 is met.

e. The total number of applications, websites, and/or web services meeting

SLAs will be divided by the total number of applications, websites, and/or web services reviewed within the 6 month period.

PROGRAM-WIDE SERVICES (PWS SECTION 26.0)

METRIC #5

Post Release Defects

2. Lot Size: Approximately 180 releases per 6-month period.

4. Performance Requirement: All application version releases shall be error free and not require post-release bug fixes.

5. Sampling Procedure: Each deployment will be monitored for defects that require bug fixes. All deployments will be of equal weight.

6. Inspection Procedure: The Government will review all releases for defects.

Releases with no defects will count as a successful releases and will meet the metric.

The percentage for the metric shall be calculated as the number of successful releases divided by the total number of releases multiplied by 100.

The percentage for the metric shall then be compared to metric 26-0-1 to determine the level (maximum, target, minimum) of incentive fee awarded.

PROGRAM-WIDE SERVICES (PWS SECTION 26.0)

METRIC #6

Application, Website, Web Service, and IT System Inventory

1. Method of Surveillance: 100% inspection.

2. Lot Size: Complete inventory of applications, websites, web services, and IT systems.

4. Performance Requirement: Maintenance of the application, website, web service, and IT system inventory shall be maintained in accordance to PWS requirements, metrics, and SLAs.

5. Sampling Procedure: A quarterly audit will be performed on the application, website, web service, and IT system inventory to assess the accuracy of data against requirements, CM standards/requirements, SLAs, and metrics.

a. Each application record, website record, web service, and IT system record will be reviewed for accurate information and for compliance with metrics, SLAs, requirements, and CM standards/requirements.

b. The results of the audit will be tallied to show the total percentage of all applications, websites, web services, and IT system data for which there is accurate data and for which requirements, CM standards/requirements, SLAs, and metrics are met.