Summary
This is a Request for Proposals issued by the Dalton Public Schools Board of Education for the construction of a new field house at Hammond Creek Middle School located at 330 Pleasant Grove Drive, Dalton, Georgia 30720. The project encompasses construction of a new middle school athletic field facility including bleachers, field lighting, concessions, utilities, concrete, restrooms, press box, fencing, paving, and related improvements. A mandatory Pre-Proposal Meeting will be held on January 6, 2022, at 10:00 a.m. at the project site, with contractors arriving more than five minutes late prohibited from attendance. Proposals must be submitted in three tabbed notebooks to the Dalton Public Schools Maintenance and Operations Department at 412 South Hamilton Street, Dalton, Georgia 30720, no later than 2:00 p.m. local time on January 21, 2022. The Board reserves the right to reject any or all proposals and to conduct subsequent discussions and negotiations with interested contractors. Proposals will remain open for acceptance for sixty days from the submission deadline.
Contract Documents are available from the Project Architect, KRH Architects, for a non-refundable deposit of $25.00 per set. Proposals must include a completed Proposal Form with the contractor's lump sum contract price, a Bid Bond equal to five percent of the proposed price, and a completed Contractor's Qualification Statement. The Board will award the contract to the responsible and responsive contractor whose proposal is most advantageous, based on the following weighted evaluation criteria: prior experience and references with comparable projects (40 points), proposed lump sum contract price (40 points), history of project completion without disputes or litigation (10 points), and completeness and accuracy of the proposal (10 points). Contractors must demonstrate minimum Worker's Compensation and General Liability Insurance, possess all necessary federal, state, and local licenses and permits, comply with Georgia work authorization requirements per O.C.G.A. 13-10-91, and submit a current Business License or Occupational Tax Certificate from their state of residence.
Text of this file
REQUEST FOR PROPOSALS
A New Field House for Hammond Creek Middle School
THE DALTON PUBLIC SCHOOLS, BOARD OF EDUCATION (the “Board”), pursuant to the provisions of O.C.G.A. § 36-91-1, et. seq., herein seeks competitive Proposals from contractors for the “A
New Field House for Hammond Creek Middle School”, located at 330 Pleasant Grove Dr., Dalton, GA
30720 (the “Project”).
The requirements for construction of the Project, and the duties and responsibilities of the contractor whose Proposal is accepted, are set forth in the Contract Documents which include the Instructions to
Proposers; Contract for Construction and Incorporated General Conditions (the “Contract”);
supplementary and other conditions; the drawings; the specifications; and any addenda issued by the
Architect. In general, the project includes the construction of a new middle school athletic field including bleachers, field lighting, concessions, utilities, concrete, restrooms, press box, fencing, paving and other improvements, all in accordance with the Contract Documents. Contractors interested in submitting
Proposals must obtain copies of the Contract Documents by contacting the Project Architect, KRH
Architects, 855 Abutment Road, Suite 4, Dalton, Ga. 30721, Ph 706-529-5895. A non-refundable deposit in the amount of $25.00 is required for each set of the Contract Documents. Documents will be issued in
PDF format. Payment must be made by company check, or cashier’s check, issued by a responsible bank or trust company, payable to the Architect. Any contractor submitting a Proposal must procure a complete set of the Contract Documents from the Project Architect. The Architect will also make available the Proposal Form as well as the Contractor’s Qualification Statement, all of which must be fully completed and submitted with any Proposal. All documents are available for inspection by the public at the office of the Architect identified above. The Contract Documents require, among other things, the furnishing of all materials, labor, and equipment for construction of the Project. The Board reserves the right to make available other relevant documents or information concerning the Project.
Any Contractor who intends to submit a Proposal is required to attend a Pre-Proposal Meeting, which will be held on the 6th day of January 2022, at 10:00 a.m. at the Project Site. Any contractor arriving more than 5 minutes late will not be permitted to attend.
Any Proposal submitted in response to this Request should comply strictly with all requirements set forth in the Instructions to Proposers. Any such Proposal must contain the completed Proposal Form setting forth the contractor’s proposed lump sum contract price for full and complete construction of the Project in conformity with all requirements of the Contract Documents. Any Proposal must include a fully executed Bid Bond in the amount of five percent (5%) of the proposed lump sum contract price (exclusive of any alternates and unit prices) in the form required by the Instructions to Proposers. As noted above, any contractor submitting a Proposal must also complete and submit the required Contractor’s
Qualification Statement. For any work requiring a specialty or professional license, only licensed subcontractors may be submitted for consideration.
In evaluating Proposals, the Board may seek additional information from any contractor concerning such contractor’s Proposal or its qualifications to construct the Project.
The Board intends to award the construction contract to the responsible and responsive contractor whose
Proposal is determined in writing to be the most advantageous to the Board, taking into consideration the following evaluation factors which are listed in their order of relative importance:
A. The contractor’s prior experience and references in constructing and completing similar projects on schedule and within budget including at least two projects comparable in size and scope to this project. For purposes of this factor, the Project should not be more than 30 percent greater in scope or cost than the similar projects identified by contractor. (40 Points)
B. The contractor’s proposed lump sum contract price for full and complete construction of the Project in conformity with all requirements of the Contract Documents. (40 Points)
C. The contractor’s history of successfully constructing and completing projects without unnecessary contractual disputes, claims, arbitration, or litigation. (10 Points)
D. The completeness and accuracy of proposals. (10 Points)
RFP responses will be received by the Board, in the Office of the Dalton Public Schools
Maintenance and Operations Dept., located at 412 S. Hamilton Street, Dalton, GA 30720, until 2:00 p.m. local time on the 21st day of January 2022. A total of 3 proposals in notebooks are required.
Please tab each section/form individually. The Board will receive such Proposals at such time and place. Proposals received after said time will not be accepted. At the discretion of the Board, and in conformity with the applicable provisions of Georgia Law, the Board may afford contractors an opportunity for subsequent discussion, negotiation, and revision of Proposals. The Board reserves the right to reject any or all Proposals and to waive any technicalities or formalities.
Please note: All allowances included in Section 01020 and listed on the Proposal form shall be used only as directed by the Owner and Architect for additional work that is not already included in the contract documents. The Owner will assume full control of these funds throughout the project. At the conclusion of the project, the contract value will be reduced by the amount of any unused allowances.
Contractors are responsible for ensuring Proposals comply with Georgia law, including but not limited to all state and local laws, rules, regulations, ordinances, and policies. Any Proposal must include an affidavit meeting all requirements of O.C.G.A. § 13-10-91 verifying compliance with applicable Federal work authorization program. The form for such affidavit is attached as an exhibit to the Instructions to
Proposers.
Any Proposal submitted in response to this Request shall remain open for acceptance by the Board, and same shall be honored by the contractor, for a period of sixty (60) days from the date set forth hereinabove for the receipt of Proposals.
Any questions or comments concerning this Request for Proposals should be addressed in writing to the
Architect at the address as set forth hereinabove.
Contractor must have minimum Worker’s Comp and General Liability Insurance in full force and effect.
No proposal will be considered unless it is accompanied by satisfactory evidence that the Bidder holds any and all necessary or required Federal, State or local licenses and/or permits. Pursuant to O.C.G.A. §
13-10-91, all contractors and sub-contractors performing work within the State of Georgia on a contract with a public employer must register and participate in a federal work authorization. The Board will require certification for contractor that this requirement has been met. Each Respondent shall submit with its proposal a copy of current Business License &/or Occupational Tax Certificate issued in the state it resides. If bidder cannot provide this License, it will be required to obtain one from the City of Dalton if it is the Awarded Respondent.
DALTON PUBLIC SCHOOLS,
BOARD OF EDUCATION
Other files
| File | Type | Posted |
|---|---|---|
| Award Information | — |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .