This document is a Requirements / Specification Document for a Flexible High-Density Microwave Transmission Line assembly needed for a 4K cryostat being constructed. The requirements include a 16-channel flex-based transmission line assembly, with SMA connectors on both the 300K room temperature and 4K interfaces, a 55cm minimum length, 50ohm nominal impedance, 10GHz nominal bandwidth, -15dB transmission line loss, and -30dB crosstalk. The assembly must be a commercial product, able to connect to the 50K thermal stage. The related federal contract opportunity is a Sources Sought notice for this requirement, with a solicitation number of NB672060-24-01856. The document provides details on shipping, inspection, acceptance, training, warranty, calibration, maintenance, and travel requirements. No Government Furnished Material/Equipment is identified.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sources Sought.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Requirements / Specification Document
TITLE: Flexible High-Density Microwave Transmission Line for 4K Cryostat
Requesting Laboratory / Division / Group:
Communications Technology Laboratory RF Technology Division Superconductive Electronics Group (672.06)
General Statement of Need:
A specialized 4 Kelvin cryostat we are constructing requires a set of flex-based high-density transmission lines with 16 channels. The flex-based architecture is required to minimize the thermal load to the 50 K and 4 K stages of our cryocooler, while simultaneously providing a highly reliable microwave path from dc to 10 GHz with acceptable properties for transmission line loss, and crosstalk between lines.
Item Specifications and Quantities:
Item 1: 16 channel miniature microwave transmission line assembly Quantity: 1 Specifications: 1.1 The assembly must contain 16 independent microwave transmission lines, constructed utilizing a flex-based architecture for use in a cryocooled cryogenic system with a 50K first stage, and a 4K second stage.
1.2 The 16 connectors on the room temperature 300K interface
must be SMA, and the 16 connectors on the cold 4K interface must be SMA suitable for reliable operation at 4K.
1.3 The room temperature SMA connector module must be
mounted on an integrated KF-40 vacuum flange (or KF-25), that can bolt directly onto an aluminum baseplate KF-40 port in the typical configuration.
1.4 55 cm is the minimum transmission line length, measured from the vacuum side of the room temperature KF-40 flange (or KF-25) to the 4K interface module.
1.5 The nominal characteristic impedance of each transmission line is 50 ohms at operating temperature.
1.6 The nominal bandwidth is 10 GHz at operating temperature, or better.
1.7 The nominal transmission line loss on each channel (S21) at operating temperature is -15 dB, or better.
1.8 The nominal crosstalk between transmission lines is -30 dB at operating temperature, or better.
1.9 The flex transmission lines must be able to be thermally
connected to the 50K stage, at a user selectable location somewhere in the middle of the flex-based assembly.
1.10 This assembly must be a commercial product, complete and fully-developed from the 300K SMA connectors thru to the 4K SMA interface.
Procurement Support Information and Ancillary Services:
[Provide input for each section Below or Mark Not Applicable (N/A)]
Section Requirements/Specifications
Planning Considerations ☒ N/A
☐ List any visits required to allow potential vendors to see site specific constraints.
[Explain Requirements.] ☐ US citizen required on-site (foreign nationals require pre-registration 30 days prior to visit.)
☐ Vendor Representative On-Site more than three (3) days.
☐ Other Considerations:
[List other considerations to ensure an accurate quote.]
Shipping & Delivery ☐ N/A
Shipping Address:
☒ NIST-Boulder
ATTN: TBA
Mail Stop: TBA 325 Broadway Boulder, CO 80305
☐ NIST-Gaithersburg
ATTN:
Mail Stop:
100 Bureau Dr Gaithersburg MD 20899
☐ [Alternate Shipping Address]
Shipping Criteria:
☐ Partial Delivery Acceptable
☐ [Enter Shipping and Delivery information by item.] ☐ Direct Delivery to OU Building Required [Explain Need for Requirement]
Building /Room Number: [Enter Building/Room Number] ☐ Building has Loading Dock
Containerization Preference: [Enter Container Type] Other Requirements:
[List Any Other Requirement] Delivery Date Criteria:
☐ Delivery Shall Be Competed No Later Than:
Click or tap to enter a date.
☐ Delivery Shall Be Made No Earlier Than:
Click or tap to enter a date.
☐ Scheduled Deliveries:
Item Number Due Date
☐ Other:
[List Other Shipping, Delivery or Special Requirements.]
Electronic Media ☒ N/A
[Enter Electronic Media Requirements by Item.]
☐ Software ☐ Electronic Manuals ☐ License Key ☐ Other:
[List Any Other Electronic Media Requirements] ☐ US Government Email Address for Software Delivery:
[Enter Address]
Installation
[Enter Installation Requirements by Item]
☐ Vendor Technician on Site ☐ Rigging ☐ Uncrating / Unpackaging
☐ Removal of Packaging Material ☐ Equipment Set Up ☐ Start-Up Services ☐ Turnkey Installation ☐ Other:
[Enter Details] NOTE: SME shall be the coordination POC.
Facility / Utility Considerations ☒ N/A
[List Site Specific Utility Considerations by Item] ☐ OFPM Work Order Numbers
[List Work Order Numbers]
☐ Power Available
Voltage: [Enter voltage] (V) Maximum Current: [Enter max current draw] (A) Phase: [Choose Phase]
Frequency: [Typically 60Hz] (Hz) NEMA Plug Type: [Enter Plug Type] (i.e.: NEMA L5-20P) Environment: [Choose Environment] Other Power Considerations:
[List Any Other Power Considerations.]
☐ Utility Connections:
[List Relevant Available Utilities, Pressure(s) and Flowrate(s).]
☐ Other Considerations:
[List Other Considerations to Ensure an Accurate Quote.]
Inspection and Acceptance ☐ N/A
[Inspection Requirements Per Item (Who, When, What, Where)] ☒ On-Site
☐ Acceptance Not Expected to Exceed 7 Business Days
☒ Acceptance Expected to Exceed 7 Business Days:
30 days
☐ Inspection and Acceptance Plan:
[Explanation]
[Enter Other Requirements]
Training
Training Requirements (Who, When, What, Where)
☐ Number of Trainees: [Enter Number of Trainees] ☐ On-Site
☐ Off-Site Location: [Enter Location(s)] Is Trainee Travel Required: [Choose Answer] Scope of Training ☐ Operation ☐ Maintenance ☐ Troubleshooting
☐ Safety ☐ Other [Enter Other Scope of Training Requirements] ☐ Training Materials to be Provided by Government:
[Describe Materials] ☐ Training Materials to be Provided by Vendor:
[Describe Materials] ☐ Other [Enter Other Training Requirements] NOTE: SME shall be coordination POC.
Warranty ☐ N/A
Base Manufacturer Warranty is acceptable Warranty Length: [i.e. 3 - Years] What is included?
☒ Labor ☒ Parts ☐ Travel ☐ Cost and Liability for Returns
☐ Other [Enter Other Requirements]
☐ 1 Option Period ☐ 2 Option Periods ☐ 3 Option Periods ☐ 4 Option Periods (Maximum)
Calibration
[Describe Calibration Requirements Per Item] Calibration Plan Length: [i.e. 3 - Years] What is Included?
☐ Labor ☐ Spare Parts ☐ Consumables
☐ Travel ☐ Cost and Liability for Shipment ☐ Software Updates ☐ Manuals
☐ Other [Enter Other Requirements] ☐ Requirements:
[Enter Requirements] (i.e.: On-Site Within 72 hours, etc.)
☐ 1 Option Period
Length: [i.e. 1 – Year / 6 - Months] ☐ 2 Option Periods
Maintenance
[Describe Maintenance Requirements Per Item] Maintenance Plan Length: [i.e. 3 - Years] What is Included?
☐ Labor ☐ Spare Parts ☐ Consumables
☐ Travel ☐ Cost and Liability for Shipment ☐ Software Updates ☐ Manuals
☐ Other [Enter Other Requirements] ☐ Requirements:
[Enter Requirements] (i.e.: On-Site Within 72 hours, etc.)
☐ 1 Option Period
Length: [i.e. 1 – Year / 6 - Months] ☐ 2 Option Periods
Government Furnished Material / Equipment ☒ N/A
List Any Government Furnished Material / Equipment Per Item] ☐ Samples for Testing
☐ Equipment which will leave Government Site
Description:
Serial Number:
NIST Property Number:
[Enter Description] [Enter Serial Number] [Enter NIST Property Number]
☐ Other: [Enter Other Details]
Travel
[Describe any Travel Requirements Per Item] ☐ Explain:
[Enter Justification / Requirement]
[Enter Other Requirements]
NOTE TO VENDOR: To the maximum extent possible, include travel requirement estimates as part of pertinent sections above (Installation, Maintenance, Repair, etc.). Otherwise, Travel will be a separate line item, reimbursable per the Federal Travel Regulation.