A1.5 SOW.pdf
PDF 10 KB Posted
- Solicitation number
- N66001-18-Q-6252
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
NAVFAC HI ACS UPGRADE
26 JUNE 2018
I. TITLE: NAVFAC HI Utilities ACS Upgrade
II. STATEMENT OF WORK | DESCRIPTION OF WORK | TASKING | SCOPE:
SCOPE: SPAWAR Systems Center Pacific (SSC-PAC), Anti-Terrorism/Force Protection
(AT/FP) Branch Code H56C is looking for a CONTRACTOR to design, and integrate an upgrade to the electronic security system (ESS) for NAVFAC HI Utilities Department, Electrical, PRJ362. This consists of a standalone ACS (including server, software, reader, etc.), Intercom System (IS) for 3 entry control points, an
Intrusion Detection System (IDS) and CCTV. The respective CONTRACTOR, must already have base access to complete project on time.
DESCRIPTION OF WORK:
Site Survey: SSC-PAC and the CONTRACTOR will conduct several site assessments for various electrical utility sites and provide materials/design package. Sending the questions in advance is recommended, to ensure proper personnel and coordination is setup.
Designs: CONTRACTOR to produce engineering AutoCAD drawings and sketches for respective facilities. Sketches will include all phases of ESS and the integration of the components. Scale drawings to permit additions of details. This may require enlarging or reducing supplied drawings, providing
"blow-ups" of selected zones of drawings to show appropriate details. When required, perform sectioning of various views to show "hidden" details. CONTRACTOR to prepare engineering drawings or sketches of existing equipment or installations where original drawings are inadequate or non-existent. Provide scopes of work and cost estimates with assumptions for all recommendations made, where applicable, separated by different buildings. To be a part of the ATO and accredited, the type of equipment that should be specified in the designs is recommended to be:
ACS: Lenel
IDS: must integrate with Lenel software
CCTV: must integrate with Lenel software
Final Report: CONTRACTOR must submit draft final report and drawings by September 01, 2018 for
GOVERNMENT review. Final deliverable is by September 30, 2018.
III. DELIVERABLES: ACS Upgrade Design and Report for respective buildings (building 41, 1553, and 638).
Each submission shall include:
-Report with supporting documentation.
-CAD Drawings/Sketches, where applicable.
-Recommended advancements/improvements.
-Cost Estimates in Excel Format, where applicable.
-Response to Review Comments.
IV. REQUIRED BY | ESTIMATED COMPLETION DATE | PERIOD OF PERFORMANCE: 30 September 2018
V. PLACE OF PERFORMANCE | TRAVEL REQUIREMENTS: Buildings 41, 1553, and 638 on Joint Base Pearl
Harbor Hickam
File details come from the government source that posted it.