N55236-15-Q-0196

Section B - Supplies or Services and Prices

ITEM NO SUPPLIES/SERVICES ESTIMATED

QUANTITY

UNIT UNIT PRICE ESTIMATED AMOUNT

CLIN

Number

1 Lot

USS STERETT (DDG-104) 7MRB0608, -0609

FFP

Accomplish Boat Repairs and Alterations Update for the USS STERRETT (DDG-

104) in accordance with the enclosed Section C Statement of Work SSSD 0069-15 less CLIN 0002 (Option Item-1), and work item entitled, Hazardous Waste Produced on Naval Vessels; as amended.

FOB: Destination

PURCHASE REQUEST NUMBER: N5523615Q0196USSSTERRET

ESTIMATED

NET AMT

ITEM NO SUPPLIES/SERVICES ESTIMATED

QUANTITY

UNIT UNIT PRICE ESTIMATED AMOUNT

CLIN

Number

1 Lot

OPTION USS STERETT (DDG-104) 7MRB0608, -0609

FFP

Prepare for & Accomplish Paragraph 3.5.36 only of the enclosed Statement of Work in Section C

PURCHASE REQUEST NUMBER: N5523615Q0196USSSTERRET

ESTIMATED

NET AMT

CLAUSES INCORPORATED BY FULL TEXT

HQ B-2-0016 PROVISIONING TECHNICAL DOCUMENTATION – WITHHOLDING OF PAYMENT

(NAVSEA) (SEP 1990)

(a) For the purpose of paragraph (c) of the "PROGRESS PAYMENTS" clause of this contract, if included, the requirement that the Contractor develop and deliver Provisioning Technical Documentation (PTD) is considered to be a "material requirement of this contract," and Contractor failure to make adequate progress in the development of PTD, or to deliver acceptable PTD on a timely basis, may result in reduction or suspension of Progress Payments as provided in said paragraph.

(b) The PTD is considered to be a part of the "Technical Data" specified to be delivered under this contract for the purposes of the "TECHNICAL DATA--WITHHOLDING OF PAYMENT" (DFARS 252.227-7030) clause. The terms and conditions of the clause entitled "LIMITATION ON WITHHOLDING OF PAYMENTS (FAR 52.232-9), if included in this contract, shall not apply to withholding of payment for failure to make timely delivery of the PTD or delivery of deficient PTD.

HQ B-2-0022 CONTRACT SUMMARY FOR PAYMENT OFFICE (FIXED PRICE) (FEB 1997)

This entire contract is fixed price.

RMC B-2-0002 PROGRESS PAYMENT RATES

The progress payment rate for this contract is 80 percent for large business and 85 percent for small business.

Section C - Descriptions and Specifications

STATEMENT OF WORK

STATEMENT OF WORK

SHIP: USS STERETT (DDG 104) SSP: SSSD

0069-15

7MRB0608 & 7MRB0609

SURVEYOR: Rod Taliman

1. SCOPE:

1.1 TITLE: Boat Repairs and Alterations Update; accomplish

1.2 LOCATION: NBSD, California, Boat Lot-1

1.3 IDENTIFICATION:

1.3.1 Quantity (One EA), 7 Meter RHIB, Hull Identification Number (HIN): 7MRB0608

1.3.1.1 Main Propulsion Diesel Engine (MPDE) Serial Number: 464508073

1.3.2 Quantity (One EA), 7 Meter RHIB, Hull Identification Number (HIN): 7MRB0609

1.3.2.1 Main Propulsion Diesel Engine (MPDE) Serial Number: 46632757

2. REFERENCE:

2.1 FY15 NAVSEA Standard Items

2.2 180-5110620, Engine Mount Replacement (7MRB/44B)

2.2.1 90-866235, QSB 5.9 230 GS Drive Shaft Extension Kit

2.3 S9008-GG-BIB-010 7-METER RIGID INFLATABLE BOAT (RIB) HULLS 7MRB0601 THRU

7MRB0614

2.4 9233-ED-MMC-010, CUMMINS ENGINE, QSB5.9; VOLUME 1 TROUBLESHOOTING AND

REPAIR MANUAL

2.5 9233-ED-MMC-020, CUMMINS ENGINE, QSB5.9; VOLUME 2 TROUBLESHOOTING AND

REPAIR MANUAL

2.6 T9008-B4-MAN-010, Inspection and Repair Manual for Fiberglass Reinforced Plastic

Boats and Craft

2.7 S9AA-AB-GOS-010/GSO, General Specifications For Overhaul Of Surface Ships

2.8 LAR: GEN-1504, Alternative Paint Option For Navy Boats Applicable to Various Naval Boats

2.9 Attachment “A”, Management and Disposal of all Hazardous Waste

2.10 Attachment-“B”, Not Applicable NAVSEA Standard Items CAT I

3. REQUIREMENTS:

3.1 Accomplish the requirements of Boat Alteration 7MRB/44B on craft identified in 1.3.1 and 1.3.2, in accordance with 2.2, 2.2.1, and 2.3.

CHECK POINT: (V) (G) “GENERAL NOTES”

3.1.1 Accomplish the requirements of general notes 14 through 16 of 2.2.

3.1.2 Accomplish engine alignment, in accordance with 2.2.1.

3.2 Accomplish the following repairs and preservation to MPDE, QSB 5.9,230 Horse Power, on craft listed in 1.3.1 and 1.3.2, using 2.3 and 2.9 for guidance.

3.2.1 Remove existing MPDE, soda blast, re-paint in accordance with OEM specifications

(Cummins White), and reinstall.

3.2.1.1 Flexible hoses and fittings shall not be painted.

3.2.1.2 Preserve/paint driveshaft and support bearing cover (black).

3.2.1.3 Preserve/paint trim pump bracket (black).

3.3 Accomplish the preservation to hull exterior above and below waterline, interior, aft stowage console, control console, deck surfaces, transom and all other interior and exterior gel coated surfaces, on craft listed in 1.3.1 and 1.3.2.

3.3.1 Record the existing periphery lines, exact locations, painted stenciling, and colors and dimensions of painted coatings, and non-skid deck covering on each exterior surface of the craft from keel to the top of the cabin.

3.3.2 Surface preparation shall be accomplish by using high pressure wash to remove marine growth and loose light paint or touch-up, to ensure all surfaces to be painted are properly prepared, achieve a minimum of 95 % surface abrasion using a minimum of 320 grit sandpaper.

3.3.3 Fair any pit-holes and scratches/gouges in the painted surfaces to restore a like new finish.

3.3.4 Accomplish the preservation of the craft’s interior and exterior hulls and structures in its entirety, in accordance with 2.8.

3.3.4.1 Color shall be in accordance with the recorded data listed in 3.3.1.

3.3.4.2 Final painted surfaces shall be like-new finish free of grinding/sanding marks and surface defects such as orange peel, runs, sags, crazing, surface contaminates, and fish-eyes.

3.3.4.3 Preserve and paint compass black in color, in accordance with OEM instructions.

3.3.4.4 Repair fiberglass in and around console VHF mount prior to painting to ensure proper fit of VHF in console of craft listed in 1.3.1.

3.3.5 Ensure all unused, drilled holes are filled prior to painting.

3.3.6 Clean and polish in its entirety, each craft’s stainless steel and aluminum plating materials. Each of the following component below shall be free of corrosion:

3.3.6.1 Bow eye

3.3.6.2 Elephant trunk retainers

3.3.6.3 Aft transom cover

3.3.6.4 Forward and aft lifting gear

3.3.6.5 Forward deck cleats and bearing plates

3.3.6.6 Canopy bow / tie down rings

3.3.6.7 Forward towing bit

3.3.6.8 Aft stowage box hinges

3.3.6.9 Coxswain backrest rail and receiving hardware

3.3.6.10 Anchor stowage clips

3.3.6.11 Control console hinges

3.3.6.12 Stainless intake screens

3.3.6.13 Handrails

3.3.6.14 Security arch and receiving hardware

3.3.7 Clean and recondition all placards and ensure all stenciled letterings are restored and legible.

3.3.8 Prepare transom hull numbers location to ensure there are no cracks prior painting.

3.3.8.1 Paint hull numbers black color, in accordance with OEM instructions.

3.3.9 Remove existing and install new in its entirety, each non-skid onboard with edge sealer, in accordance with 2.3.

3.3.10 Reseal the removable deck after engine installation, reseal the transom and deck connections.

3.3.11 Paint the engine bay bilge area, aft bilge area, and inside of storage box along with the forward facing area of the transom match existing color scheme, in accordance with OEM instructions.

3.4 Remove existing, procure and install new in its entirety each of the following components and accomplish repairs on craft and engines identified in 1.3.1.1 and 1.3.2.1 using 2.4 and 2.5 for guidance.

3.4.1 Remove existing and install new High Pressure fuel pumps P/N: 5273441.

3.4.2 Quantity (One EA) Cummins fuel cooler P/N: 5288253

3.4.3 Provide and oil sample from a certified oil analysis testing facility to check for metal, debris or contaminants in engine oil removed form engine.

3.4.3.1 Submit a report in electronic format listing the results of 3.4.3 to the SUPERVISOR with 24 hours of testing.

3.4.4 Remove existing Diesel View and or Vessel View display’s and install new Vessel

View Displays to include necessary harnesses, fuses, and SIM cards.

3.4.5 Accomplish inspection and cleaning of existing engine wiring harnesses.

3.4.6 OEM shall accomplish troubleshooting and operational test to prove repairs are acceptable and that no alarms or codes are present during bay trial identified in 3.8.

3.5 Remove existing and install new in its entirety, each of the following components on craft identified in 1.3.1 and 1.3.2, using 2.3 through 2.9 for guidance.

3.5.1 Quantity (26 EA), engine and exhaust stainless steel hose clamps

3.5.2 Quantity (One EA), engine coolant thermostat

3.5.3 Quantity (2.7 Gallons), engine antifreeze/coolant plus 50% water mix

3.5.4 Quantity (15 Quarts), engine oil

3.5.5 Quantity (One EA), oil filter

3.5.6 Quantity (One EA), alternator belt

3.5.7 Quantity (One EA), raw water pump belt

3.5.8 Quantity (One EA), RACOR filter

3.5.9 Quantity (One EA), “Fuel” spin on filter

3.5.10 Quantity (15 LF), coxswains flat caulk

3.5.11 Quantity (8 EA), engine and storage box rubber securing latches

3.5.12 Quantity (One EA), GPS (Garmin echo Map 50s with transducer)

3.5.13 Quantity (One EA), storage box cushion (gray)

3.5.14 Quantity (One EA), engine box cushion (gray)

3.5.15 Quantity (2 EA), life ring brackets

3.5.16 Quantity (One EA), anchor hatch latch

3.5.17 Quantity (3 EA Bearings & One EA Seal), forward and aft support bearings and seal

3.5.18 Quantity (One EA), air filter

3.5.19 Quantity (One EA), raw water pump impeller

3.5.20 Quantity (5 Quarts), outdrive oil

3.5.21 Quantity (One EA), engine flex plate

3.5.22 Quantity (One EA), backrest cushion (gray)

3.5.23 Quantity (One EA), outdrive tilt sending unit.

3.5.24 Quantity (One EA), outdrive tilt limit switch.

3.5.25 Quantity (One EA), outdrive gimabal bearing and seal.

3.5.26 Quantity (One EA), MOBI post pin.

3.5.27 Quantity (One EA), coolant pre-heater breaker.

3.5.28 Quantity (One EA), oil stripper.

3.5.29 Quantity (One EA), fuel stripper.

3.5.30 Quantity (Two EA), Optima Blue top batteries.

3.5.31 Quantity (One EA), outdrive trim pump assembly.

3.5.32 Quantity (One EA), outdrive prop.

3.5.33 Quantity (Two EA), aft elephant trunks

3.5.34 Quantity (One EA), ignition switch

3.5.35 Quantity (One EA), battery barrel switch.

OPTION ITEM-1 (Paragraph 3.5.36 only)

3.5.36 Quantity (One EA), craft sponson and MBCS

3.5.37 Remove existing engine coolant level sensor from expansion tank and install new, 1 each (one /engine) ¼” aluminum pipe plug.

3.5.38 Install an electrical plug Cummins PN: 5265255, 1 each (one/engine) into coolant level sensor harness plug and secure harness out of the way.

3.5.39 Accomplish the following requirements to the after coolers and heat exchangers on engines identified in 1.3.1.1 and 1.3.2.1 and upon completion of the requirement of 3.2 in accordance with 2.4-2.5.

3.5.39.1 Remove existing after cooler and heat exchanger from engines.

3.5.39.2 Disassemble heat exchangers and after coolers.

CHECK POINT: (V) (G) VISUAL INSPECTION

3.5.39.3 Accomplish visual inspection of the heat exchangers and after coolers.

3.5.39.4 Accomplish the cleaning of heat exchangers and after cooler.

CHECK POINT: (V) (G) VISUAL INSPECTION

3.5.39.5 Accomplish visual inspection of the heat exchangers and after coolers with

SUPERVISOR

3.5.39.6 Reassemble heat exchangers and after coolers, using new gaskets, fasteners and zincs.

3.6 Accomplish the following repairs on craft listed in 1.3.1 and 1.3.2, using 2.3 through 2.9 for guidance.

3.6.1 Clean and remove corrosions, each battery cable connectors and terminals.

3.6.2 Adjust outdrive trim and tilt to OEM specifications.

3.6.3 Drain trim pump fluid in its entirety, replenish with new fluid in accordance with OEM specifications.

3.7 Accomplish the following repairs on craft listed in 1.3.2 using 2.3 through 2.9 for guidance.

3.7.1 Repair a total of 5 square feet of fiberglass on bow.

3.7.2 Replace MOBI control head and electrical connectors.

3.7.3 Install new hailer head microphone.

CHECK POINT: (V) (G) “OPERATIONAL TEST”

3.8 Perform a bay trial/operational test in San Diego Bay to crafts identified in 1.3.1 and 1.3.2 to prove each component installed in paragraph 3.1 through 3.7 are up to OEM standards and in accordance with 2.2 through 2.9.

3.8.1 Submit legible copies, one in hard and one in electronic format, with recommended repairs of any hull, mechanical, electrical, and accessory discrepancy found during the performance of 3.8 to the SUPERVISOR within 24 hours of completion of testing.

3.8.2 Contractor shall continue to accomplish 3.8 until a satisfactory result is achieved.

3.8.3 Provide 30 gallons of diesel fuel (DFM) for the performance of 3.8 on craft listed in

1.3.1 and 1.3.2.

3.8.4 Contractor to clean all bilges of foreign matter after successful completion of 3.8.

3.9 Contractor shall pick up and deliver crafts via trailers to contractor facility and back to NBSD upon completion of the availability.

3.9.1 Contractor shall pick up the craft listed in 1.3.1 and 1.3.2 within 24 hours after the awarding of contract.

3.9.2 Government will provide trailer for craft’s transport.

3.9.3 Contractor shall be responsible for moving of the crafts from government owned trailers to contractor facility and vice versa after the completion of availability.

3.9.4 Contractor shall be responsible for delivery to and from boat launch ramp for all necessary sea trials to prove all work has been completed in accordance with SOW.

3.10 Contractor shall ensure that only qualified, competent personnel carry out the tasks outlined in this SOW. Competent is defined as registered professional or, where registration is not applicable, trained, and /or certified in their respective field.

3.11 Primary and Sub-Contractor personnel shall be available for meetings at the Government’s facility throughout the performance of this availability.

3.12 Accomplish the requirements of Attachment-A listed in 2.11 for the management and disposal of all hazardous waste through completion of this availability.

3.13 Accomplish paint touch up to each new and disturbed surface to match the surrounding colors, in accordance with OEM instructions.

4 NOTES:

4.1 Paragraph 2.10 is the list of NAVSEA Standard Items Not Applicable to this SOW.

5 GOVERNMENT FURNISHED MATERIAL (GFM):

5.1 None.

ATTACHMENT-A

ITEM NO: 077-01-001

SSP: SSSD 0069-15

DATE: 07/29/15

1. SCOPE:

1.1 Title: Hazardous Waste Produced on Naval Vessels; control

1.2 Location of Work:

1.2.1Throughout the crafts

1.3 Identification:

2.1.1 Quantity (One EA), 7 Meter RHIB, Hull Identification Number (HIN): 7MRB0608

1.3.1.1 Main Propulsion Diesel Engine (MPDE) Serial Number: 464508073

2.1.2 Quantity (One EA), 7 Meter RHIB, Hull Identification Number (HIN): 7MRB0609

2.1.2.1 Main Propulsion Diesel Engine (MPDE) Serial Number: 46632757

2. REFERENCES:

2.1 Resource Conservation and Recovery Act (RCRA)

2.2 49 U.S.C. 5103, Federal Hazardous Materials Transportation Act

2.3 Applicable Hazardous Waste Manifest Form

2.4 10 U.S.C. 7311

3. REQUIREMENTS:

3.1 Manage and dispose of all hazardous waste listed in 3.5 in accordance with 2.1 through 2.2.

3.1.1 Consider marine paint/nonskid and abrasive blasting media to contain heavy metals (e.g., beryllium, cadmium, chromium, or lead), hexavalent chromium, crystalline silica and/or other toxic or hazardous substances.

3.1.1.1 Accomplish the requirements of NAVSEA Standard Items 009-03 (Toxic and

Hazardous Substances; control), 009-06 (Maintaining Protection and Cleanliness from Non-Radioactive Contaminate-Producing Operations;

accomplish), and 009-32 IAW SOW (Cleaning and painting Requirement;

accomplish).

3.1.2 When a Navy generator number is required by this Work Item, submit the original of copy of

2.3 to the SUPERVISOR for assignment of Environmental Protection Agency (EPA) or delegated state environmental agency identification number.

3.1.3 Manage and transport for Navy disposal, Navy-generated hazardous waste listed in 3.5 in accordance with 2.1 and 2.2, as designated by the SUPERVISOR.

3.1.4 Submit one legible copy, in hard copy or electronic media, of 2.3 signed by the owner or operator of the disposal facility to the SUPERVISOR within 48 hours of receipt from owner or operator of disposal facility.

3.2 Complete documentation required by 2.1 and 2.2, using EPA or delegated state environmental agency identification number in accordance with 2.4.

3.2.1 Documentation related to hazardous waste generated solely by the physical actions of Ship's

Force or Navy employees (termed Navy-Generated Hazardous Waste) on board the vessel shall only bear a generator identification number issued to the Navy pursuant to applicable law. The contractor shall obtain SUPERVISOR'S concurrence with the categorization of the waste as Navy-generated before completion of the manifest. The manifest prepared shall be presented to the SUPERVISOR for completion after the hazardous waste has been identified.

3.2.2 Documentation related to hazardous waste generated solely by the physical actions of contractor personnel (termed Contractor-Generated Hazardous Waste) shall bear a generator identification number issued to the contractor pursuant to applicable law. Regardless of the presence of other material in or on the shipboard systems or structure which may have qualified a waste stream as hazardous, where the contractor performs work on a system or structure using materials (whether or not the use of such materials was specified by the Navy) which by themselves would cause the waste from such work to be a hazardous waste, documentation related to such waste shall only bear a generator number issued to the contractor.

3.2.3 Documentation related to hazardous waste generated by the combined physical actions of Navy and contractor personnel (termed Co-Generated Hazardous Waste) shall bear a generator identification number issued to the contractor pursuant to applicable law and shall also cite in the remarks block a generator identification number issued to the Navy pursuant to applicable law. When the contractor merely drains a system and such drainage creates hazardous waste or the contractor performs work on system or structure using materials which by themselves would not cause the waste from such work to be hazardous waste but such work nonetheless creates a hazardous waste, documentation related to such waste shall bear a generator identification number issued to the contractor and shall also cite in the remarks block a generator identification number issued to the Navy. The contractor shall sign the generator certification on the Uniform Hazardous Waste Manifest whenever use of the manifest is required for disposal. The contractor shall obtain SUPERVISOR's concurrence with the categorization of the wastes as co-generated before completion of the manifest. Manifests prepared shall be presented to the SUPERVISOR for completion after the hazardous waste has been identified.

3.3 If the contractor, while performing work at a Government facility, cannot obtain a separate generator identification number from the state in which the availability will be performed, the contractor shall notify the SUPERVISOR within three business days of receipt of written notification by the state.

After obtaining approval of the SUPERVISOR, the contractor shall use the Navy site generator identification number and insert in the remarks block the contractor generator identification number issued for the site where his main facilities are located.

3.4 If, for availabilities at a contractor-owned or controlled facility, the Navy cannot obtain a separate generator identification number for use at a contractor facility, the Navy shall notify the contractor within three business days of receipt of notification by the state. The contractor shall dispose of hazardous waste in accordance with 2.1, 2.2, and 3.2.2.

3.5 Hazardous waste, as identified in 2.1, expected to be produced during performance of this Job Order:

3.5.1 Cleaning Solvents _____________ 2 Gallons

3.5.2 Spent Abrasive Blast media & Non-skid________________________ ___.5 Ton

3.5.3 Paints (enamel, latex, epoxy, thinners, oil based)_____________________15 LBS._

3.5.4 Engine Coolant _______________________ ____________ 15 Gallons

3.5.5 Rags (contaminated with known source) ______________ 10 LBS.

3.5.6 Residual contaminated bilge water __________________ 50 Gallons

3.5.7 Miscellaneous Chemicals_________________________________________8 LBS

3.5.8 Diesel Fuel ____________________________________ __40 Gallons

3.5.9 Sludge (Contaminated with a known hazardous waste) ____________10 Gallons

3.5.10 Insulation ___________________________________8 SQFT

3.5.11 Lube & Gear Oil_____________________________________________15 Gallons

3.6 Submit one legible copy, in hard copy or electronic media, of a report identifying type, amount, and disposal cost of waste listed in 3.5 that was removed during the performance of this Job Order to the

SUPERVISOR.

3.6.1 The report shall include analysis or other method used to identify the waste and state whether each listed waste was hazardous (with generator assignment), non-hazardous, or did not exist.

3.6.1.1 Chemical analysis shall be accomplished by laboratories with state or EPA approved quality assurance programs.

3.6.2 The contractor shall make an effort to minimize hazardous waste generation by reducing the volume or toxicity by neutralizing, recycling, or otherwise removing it from the requirements of Subtitle C of 2.1 and include a description of such efforts in the report.

3.7 Nothing contained in this Work Item shall relieve the contractor from complying with applicable federal, state, and local laws, codes, ordinances, and regulations, including the obtaining of licenses and permits in connection with hazardous waste handling and disposal in the performance of this contract.

4. NOTES:

4.1 The waste listed in 3.5 is based on the best information available at the time of preparation of the solicitation. Hazardous waste generated during the actual performance of the work may vary in type or amount from waste listed in 3.5 which may result in renegotiation pursuant to Paragraph (b) of 2.4. The contractor is expected to use best management practice to identify and dispose of all hazardous waste.

Some of the substances listed in 3.5 may be neutralized, recycled, or otherwise removed from the requirements of Subtitle C of 2.1. Inclusion of these substances in the waste listed in 3.5 does not preclude the contractor from taking action consistent with 2.1 to reduce or eliminate the hazardous constituents of any waste required to be disposed of under the contract in accordance with 2.2.

Processes that add hazardous constituents to the bilges may require that bilge water be disposed of as a hazardous waste.

4.1.1 The types and amounts of wastes listed in 3.5 are estimates of waste to be disposed of under this contract as required by 2.4. They are not estimates of the amount of the work involved in generating that waste. The work requirements of each individual Work Item specify the actual work to be accomplished.

4.2 Hazardous wastes are determined by one or more of the following methods:

4.2.1 Chemical analysis which shows that the material characteristics of ignitability, corrosively, reactivity, and/or toxicity (Toxicity Characteristic Leachate Procedure - TCLP) exceed the limits for that material in 40 CFR 261.20 Subpart C.

4.2.2 Reference to a Material Safety Data Sheet (MSDS).

4.2.3 Applying knowledge of the hazardous characteristics of the waste in light of the materials or the process used.

4.3 Asbestos, bilge water, oil/water including sludge, debris and other contaminants, sludge which includes solids and sludge from ballast tanks, CHT tanks, voids, oily waste tanks, fuel ballast tanks, fuel oil tanks, skegs (West coast), PCB's (Maryland), etc., apply only in those states listing them as hazardous waste. When availability is to be performed in a state where these items are hazardous waste, an estimate of the amount to be generated shall be included in 3.5.

5. GOVERNMENT FURNISHED MATERIAL (GFM):

5.1 LLTM:

ATTACHMENT-B:

SWRMC C370 SMALL BOATS & YARD CRAFTS NOT APPLICABLE NAVSEA STANDARD ITEMS

CAT-I

The following Category I NAVSEA STANDARD ITEMS are not applicable & will not be invoked:

009-02 Environmental Compliance Reports for Material Usage at Naval Facilities; provide 009-18 Magnetic Material; control 009-19 Provisioning Technical Documentation (PTD); provide 009-21 Logistics and Technical Data; provide 009-29 Asbestos-Free Pipe Hanger Liner Material; install 009-35 Confined Space Entry, Certification, Fire Prevention Utilizing Military Fire Watches, and Housekeeping;

accomplish 009-39 Technical Manual Contract Requirement (TMCR) for New Technical Manuals for Commercial

Equipment/Component; provide 009-40 Requirements for Contractor Cranes, Multi-Purpose Machines and Material Handling Equipment at Naval

Facilities; accomplish 009-59 Organotin Antifouling Materials; control 009-61 Shipboard Use of Fluorocarbons; control 009-64 Synthetic Fire Resistant Hydraulic Fluid; control 009-73 Shipboard Electrical/Electronic/Fiber Optic Cable; remove, relocate, repair, and install 009-77 Cofferdam Requirements; accomplish 009-80 Ship's Facilities; provide 009-84 Accountability of Temporary Fasteners; provide

009-87 Chlorination Procedures; accomplish 009-88 Collection, Holding, and Transfer (CHT) and Mogas Tanks, Spaces, and Piping, including Sewage or

Mogas-Contaminated Tanks, Spaces, and Piping; certify 009-89 Purchase and Inspection Requirements for Contractor Furnished Anodes; accomplish 009-95 Mechanically Attached Fittings (MAFs) for Piping Systems; install 009-100 Ship's stability process control procedure (PCP); maintain 009-101 Requirements for Mooring, Entry to, and Departure from Contractor's Facility; accomplish 009-106 Work Authorization Form Coordinator (WAFCOR); provide 009-108 Aircraft Carrier Requirements for Mooring, Entry to, Movement within & Departure from Contractor's

Facility; accomplish 009-109 Special Requirements for Non-SUBSAFE Work on SUBSAFE-Certified Vessels; accomplish 009-110 Special Requirements for Non-Nuclear work on Nuclear Vessels; accomplish 009-112 Prevention of Radiographic Inspection Ionizing-Radiation Hazards; accomplish 009-117 AEGIS Light-Off (ALO) Support for AEGIS Weapons Systems; provide 009-118 CG Deck Loading; accomplish 009-120 Fact Finding & Critiques of Unplanned Events; manage 009-121 Ship Assessment/Inspection Requirements; provide

HQ C-2-0003 ACCESS TO THE NAVY SUPPLY SYSTEM (NAVSEA) (MAR 2011)

(a) In compliance with the comparability requirement of 10 U.S.C. 7314, Public and Private Shipyards will be provided equal access to the Naval Supply System. Use by private yards is permissive, not mandatory.

(b) Pursuant to the clause of this contract entitled "GOVERNMENT SUPPLY SOURCES" (FAR 52.251-1) the Contracting Officer hereby authorizes the Contractor to place orders with the Navy Supply System for materials and equipment or other supplies necessary to perform the required work. The Naval Supply System shall process such orders in the same manner as it would for any other Navy supply user, and the Contractor shall make payment on account of materials and equipment and other supplies ordered and/or received in accordance with the normal requirements of the Naval Supply Systems Command, but in no event shall payment in full be any later than 30 days after receipt by the Contractor of each order. The Contractor shall pay the Naval Supply System any costs for materials, equipments, or other supplies obtained including any surcharges normally charged to any other Naval Supply System user.

(c) This job order has been priced on the basis that, except as specifically provided elsewhere in this contract with regards to Government furnished property, the Contractor shall provide all necessary materials, equipments and supplies for performance of this contract. If the Contractor uses the Naval Supply System, it has elected to use the system for its own convenience to meet its contractual obligations to perform the work under this contract. The Naval Supply System is considered to be an alternate source or vendor of contractor furnished material; therefore materials, equipments, or other supplies ordered and/or obtained from the Naval Supply System are specifically not considered to be Government furnished material, but are considered to be contractor furnished material. The Government makes no representation as to the availability of materials, equipments, or other supplies for the performance of the work required under this contract, nor shall unavailability, late delivery, delivery of non-conforming supplies, higher costs of the Naval Supply System (if any), or any failure of the Naval Supply System to meet the expectations or requirements of the Contractor constitute excusable delay or grounds for equitable or any other adjustment to the contract or relief from the requirement to perform in accordance with the terms of the contract.

HQ C-2-0004 ACCESS TO THE VESSEL(S) (AT) (NAVSEA) (JAN 1983)

Officers, employees and associates of other prime Contractors with the Government and their subcontractors, shall, as authorized by the Supervisor, have, at all reasonable times, admission to the plant, access to the vessel(s) where and as required, and be permitted, within the plant and on the vessel(s) required, to perform and fulfill their respective obligations to the Government. The Contractor shall make reasonable arrangements with the Government or Contractors of the Government, as shall have been identified and authorized by the Supervisor to be given admission to the plant and access to the vessel(s) for office space, work areas, storage or shop areas, or other facilities and services, necessary for the performance of the respective responsibilities involved, and reasonable to their performance.

HQ C-2-0005 ACCESS TO VESSELS BY NON U.S. CITIZENS (NAVSEA) (DEC 2005)

(a) No person not known to be a U.S. citizen shall be eligible for access to naval vessels, work sites and adjacent areas when said vessels are under construction, conversion, overhaul, or repair, except upon a finding by COMNAVSEA or his designated representative that such access should be permitted in the best interest of the United States. The Contractor shall establish procedures to comply with this requirement and NAVSEAINST

5500.3 (series) in effect on the date of this contract or agreement.

(b) If the Contractor desires to employ non U.S. citizens in the performance of work under this contract or agreement that requires access as specified in paragraph (a) of this requirement, approval must be obtained prior to access for each contract or agreement where such access is required. To request such approval for non U.S. citizens of friendly countries, the Contractor shall submit to the cognizant Contract Administration Office (CAO), an Access Control Plan (ACP) which shall contain as a minimum, the following information:

(1) Badge or Pass oriented identification, access, and movement control system for non U.S. citizen employees with the badge or pass to be worn or displayed on outer garments at all times while on the Contractor's facilities and when performing work aboard ship.

(i) Badges must be of such design and appearance that permits easy recognition to facilitate quick and positive identification.

(ii) Access authorization and limitations for the bearer must be clearly established and in accordance with applicable security regulations and instructions.

(iii) A control system, which provides rigid accountability procedures for handling lost, damaged, forgotten or no longer required badges, must be established.

(iv) A badge or pass check must be performed at all points of entry to the Contractor's facilities or by a site supervisor for work performed on vessels outside the Contractor's plant.

(2) Contractor’s plan for ascertaining citizenship and for screening employees for security risk.

(3) Data reflecting the number, nationality, and positions held by non U.S. citizen employees, including procedures to update data as non U.S. citizen employee data changes, and pass to cognizant CAO.

(4) Contractor’s plan for ensuring subcontractor compliance with the provisions of the Contractor's ACP.

(5) These conditions and controls are intended to serve as guidelines representing the minimum requirements of an acceptable ACP. They are not meant to restrict the Contractor in any way from imposing additional controls necessary to tailor these requirements to a specific facility.

(c) To request approval for non U.S. citizens of hostile and/or communist controlled countries (listed in Department of Defense Industrial Security Manual, DOD 5220.22 M or available from cognizant CAO), Contractor shall include in the ACP the following employee data: name, place of birth, citizenship (if different from place of birth), date of entry to U.S., extenuating circumstances (if any) concerning immigration to U.S., number of years employed by Contractor, position, and stated intent concerning U.S. citizenship. COMNAVSEA or his designated representative will make individual determinations for desirability of access for above group. Approval of ACP's for access of non-U.S. citizens of friendly countries will not be delayed for approval of non-U.S. citizens of hostile communist-controlled countries. Until approval is received, Contractor must deny access to vessels for employees who are non-U.S. citizens of hostile and/or communist-controlled countries.

(d) The Contractor shall fully comply with approved ACPs. Noncompliance by the Contractor or subcontractor serves to cancel any authorization previously granted, in which case the Contractor shall be precluded from the continued use of non-U.S. citizens on this contract or agreement until such time as the compliance with an approved ACP is demonstrated and upon a determination by the CAO that the Government's interests are protected. Further, the Government reserves the right to cancel previously granted authority when such cancellation is determined to be in the Government's best interest. Use of non-U.S. citizens, without an approved ACP or when a previous authorization has been canceled, will be considered a violation of security regulations. Upon confirmation by the CAO of such violation, this contract, agreement or any job order issued under this agreement may be terminated or default in accordance with the clause entitled "DEFAULT (FIXED-PRICE SUPPLY AND SERVICE)" (FAR 52.249-8), "DEFAULT (FIXED-PRICE RESEARCH AND DEVELOPMENT)" (FAR 52.249-9) or "TERMINATION (COST REIMBURSEMENT)" (FAR 52.249-6), as applicable.

(e) Prime Contractors have full responsibility for the proper administration of the approved ACP for all work performed under this contract or agreement, regardless of the location of the vessel, and must ensure compliance by all subcontractors, technical representatives and other persons granted access to U.S. Navy vessels, adjacent areas, and work sites.

(f) In the event the Contractor does not intend to employ non-U.S. citizens in the performance of the work under this contract, but has non-U.S. citizen employees, such employees must be precluded from access to the vessel and its work site and those shops where work on the vessel's equipment is being performed. The ACP must spell out how non-U.S. citizens are excluded from access to contract work areas.

(g) The same restriction as in paragraph (g) above applies to other non-U.S. citizens who have access to the Contractor's facilities (e.g., for accomplishing facility improvements, from foreign crewed vessels within its facility, etc.).

HQ C-2-0006 ADDITIONAL PROVISIONS RELATING TO GOVERNMENT PROPERTY (NAVSEA) (SEP 2009)

(a) For purposes of paragraph (h) of the clause entitled "GOVERNMENT PROPERTY" (FAR 52.245-1) in addition to those items of property defined in that clause as Government Property, the following shall also be included within the definition of Government Property:

(1) the vessel;

(2) the equipment on the vessel;

(3) movable stores;

(4) cargo; and

(5) other material on the vessel

(b) For purposes of paragraph (b) of the clause entitled "GOVERNMENT PROPERTY", notwithstanding any other requirement of this contract, the following shall not be considered Government Property:

(1) the vessel;

(2) the equipment on the vessel;

(3) movable stores; and

(4) other material on the vessel

HQ C-2-0007 APPROVAL BY THE GOVERNMENT (AT) (NAVSEA) (JAN 1983)

Approval by the Government as required under this contract and applicable specifications shall not relieve the Contractor of its obligation to comply with the specifications and with all other requirements of the contract, nor shall it impose upon the Government any liability it would not have had in the absence of such approval.

HQ C-2-0014 CONTRACTOR'S PROPOSAL (NAVSEA) (MAR 2001)

(a) Performance of this contract by the Contractor shall be conducted and performed in accordance with detailed obligations to which the Contractor committed itself in Proposal dated _________ in response to SWRMC Solicitation No. N55236-15-Q-0196.

(b) The technical volume(s) of the Contractor's proposal is incorporated by reference and hereby made subject to the provisions of the "ORDER OF PRECEDENCE" (FAR 52.215-8) clause of this contract. Under the "ORDER OF PRECEDENCE" clause, the technical volume of the Contractor's proposal referenced herein is hereby designated as item

(f) of the clause, following "the specification" in the order of precedence.

HQ C-2-0016 DEPARTMENT OF LABOR SAFETY AND HEALTH STANDARDS FOR SHIP REPAIR

(NAVSEA) (SEP 1990) (MODIFIED) (SEP 2012)

Attention of the Contractor is directed to the Occupational Safety and Health Act of 1970 (29 USC 651-678), and to the Safety and Health Regulations for Ship Repairing (29 CFR 1915), promulgated under Public Law 85-742, amending Section 41 of the Longshoremen's and Harbor Workers' Compensation Act (33 USC 941), and adopted by the Department of Labor as occupational safety or health standards under Section 6(a) of the Occupational Safety and Health Act of 1970 (See 29 CFR 1910.15). These regulations apply to all ship repair and related work, as defined in the regulations performed under this contract on the navigable waters of the United States including any dry dock and marine railway. Nothing contained in this contract shall be construed as relieving the Contractor from any obligations which it may have for compliance with the aforesaid regulations.

HQ C-2-0018 DISPOSAL OF SCRAP (NAVSEA) (JAN 2008)

(a) All Government scrap resulting from accomplishment of any job order is the property of the Contractor to be disposed as it sees fit. Scrap is defined as property that has no reasonable prospect of being sold except for the recovery value of its basic material content. The determination as to which materials are scrap and which materials are salvage, will be made, or concurred in, by the duly appointed Property Administrator for the cognizant SUPSHIP or RMC Office.

(b) As consideration for retaining the Government's scrap, the Contractor's price for the performance of the work required herein shall be a net price reflecting the value of the Government scrap.

(c) This requirement is not intended to conflict in any way with the clauses of this contract entitled "PERFORMANCE" (DFARS 252.217-7010) or "GOVERNMENT PROPERTY" (FAR 52.245-1) under the Master Contract in effect at the time of job order award, nor does it relieve the Contractor of any other requirement under such clauses.

HQ C-2-0023 EXCLUSION OF MERCURY (NAVSEA) (MAY 1998)

Mercury or mercury containing compounds shall not be intentionally added or come in direct contact with hardware or supplies furnished under this contract.

HQ C-2-0028 GOVERNMENT SURPLUS PROPERTY (NAVSEA) (SEP 1990)

No former Government surplus property or residual inventory resulting from terminated Government contracts shall be furnished under this contract unless (i) such property is identified in the Special Contract Requirements or (ii) is approved in writing by the Contracting Officer. Notwithstanding any such identification in the Special Contract Requirements or approval by the Contracting Officer, the Contractor agrees all items or components described in this requirement shall comply in all respects with the specifications contained herein.

HQ C-2-0029 HEAVY WEATHER PLAN (NAVSEA) (JUN 1999)

In order to ensure that Naval vessels and material are protected during gales, storms, hurricanes and destructive weather, the Contractor is required to have a written Heavy Weather Plan (HWP) which assigns responsibilities and prescribes actions to be taken on the approach of and during heavy weather conditions as delineated in NAVSEA Standard Item (SI) 009-69. In accordance with SI 009-69, the Contractor shall furnish to the cognizant Shipbuilding, Conversion and Repair, U.S. Navy, a copy of such HWP, and shall make such changes in the plan as the Supervisor considers necessary and reasonable to protect and care for vessels and machinery and equipment to be installed therein.

In the event the Supervisor directs the Contractor to implement the HWP pursuant to SI 009-69 the Contractor may submit to the Contracting Officer a request for reimbursement for costs resulting from such actions together with any documentation that the Contracting Officer may reasonably require. The Government shall reimburse the Contractor for all reasonable, allowable and allocable costs resulting from the Contractor's implementation of the HWP based on such Government direction.

HQ C-2-0030 INFORMATION AND DATA FURNISHED BY THE GOVERNMENT (FIXED-PRICE) (NAVSEA)

(SEP 2009)

(a) Contract Specifications. The Government will furnish, if not included as an attachment to the contract, any unique contract specifications set forth in Section C.

(b) Contract Drawings and Data. The Government will furnish contract drawings, design agent drawings, ship construction drawings, and/or other design or alteration data cited or referenced in Section C or in the contract specification as mandatory for use or for contract performance.

(c) Government Furnished Information (GFI). GFI is defined as that information essential for the installation, test, operation, and interface support of all Government Furnished Material enumerated on NAVSEA Form 4205/19 or Schedule A, as applicable, attached to the contract. The Government shall furnish only the GFI identified on the NAVSEA Form 4340/2 or Schedule C, as applicable, attached to the contract. The GFI furnished to the contractor need not be in any particular format. Further, the Government reserves the right to revise the listing of GFI on the NAVSEA Form 4340/2 or Schedule C, as applicable, as follows:

(1) The Contracting Officer may at any time by written order:

(i) delete, supersede, or revise, in whole or in part, data listed or specifically referenced in NAVSEA Form 4340/2 or Schedule C, as applicable; or

(ii) add items of data or information to NAVSEA Form 4340/2 or Schedule C, as applicable; or

(iii) establish or revise due dates for items of data or information in NAVSEA Form 4340/2 or Schedule C, as applicable.

(2) If any action taken by the Contracting Officer pursuant to subparagraph (1) immediately above causes an increase or decrease in the costs of, or the time required for, performance of any part of the work under this contract, the contractor may be entitled to an equitable adjustment in the contract price and delivery schedule in accordance with the procedures provided for in the clause of this contract entitled "CHANGES--FIXED-PRICE"

(FAR 52.243-1).

(d) Except for the Government information and data specified by paragraphs (a), (b), and (c) above, the Government will not be obligated to furnish the Contractor any specification, standard, drawing, technical documentation, or other publication, notwithstanding anything to the contrary in the contract specifications, the GFI listed on the NAVSEA Form 4340/2 or Schedule C, as applicable, the clause of this contract entitled "GOVERNMENT PROPERTY" (FAR 52.245-1) or "GOVERNMENT PROPERTY INSTALLATION OPERATION SERVICES " (FAR 52.245-2), as applicable, or any other term or condition of this contract.

(e) Referenced Documentation. The Government will not be obligated to furnish Government specifications and standards, including Navy standard and type drawings and other technical documentation, which are referenced directly or indirectly in the contract specifications set forth in Section C and which are applicable to this contract as specifications. Such referenced documentation may be obtained:

(1) From the ASSIST database via the internet at http://assist.daps.dla.mil/; or

(2) By submitting a request to the Department of Defense Single Stock Point (DoDSSP) Building 4, Section D 700 Robbins Avenue Philadelphia, Pennsylvania 19111-5094 Telephone (215) 697-6396 Facsimile (215) 697-9398.

Commercial specifications and standards, which may be referenced in the contract specification or any sub-tier specification or standard, are not available from Government sources and should be obtained from the publishers.

HQ C-2-0034 MINIMUM INSURANCE REQUIREMENTS (NAVSEA) (SEP 1990)

In accordance with the clause of this contract entitled "INSURANCE--WORK ON A GOVERNMENT INSTALLATION" (FAR 52.228-5), the Contractor shall procure and maintain insurance, of at least the kinds and minimum amounts set forth below:

(a) Workers' Compensation and Employer's Liability coverage shall be at least $100,000, except as provided in FAR 28.307(a).

(b) Bodily injury liability insurance coverage shall be written on the comprehensive form of policy of at least $500,000 per occurrence.

(c) Automobile Liability policies covering automobiles operated in the United States shall provide coverage of at least $200,000 per person and $500,000 per occurrence for bodily injury and $20,000 per occurrence for property damage. The amount of liability coverage on other policies shall be commensurate with any legal requirements of the locality and sufficient to meet normal and customary claims.

HQ C-2-0038 PERMITS AND RESPONSIBILITIES (NAVSEA) (SEP 1990)

The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses and permits, and for complying with any applicable Federal, State, and Municipal laws, codes, and regulations, in connection with any movement over the public highways of overweight/overdimensional materials.

HQ C-2-0044 PROTECTION OF THE VESSEL (NAVSEA) (SEP 1990)

(a) The Contractor shall exercise reasonable care, as agreed upon with the Supervisor, to protect the vessel from fire, and shall maintain a system of inspection over the activities of its welders, burners, riveters, painters, pipe fitters, and similar workers, and of its subcontractors, particularly where such activities are undertaken in the vicinity of the vessel's magazines, fuel oil tanks, or store rooms containing inflammable materials. All ammunition, fuel oil, motor fuels, and cleaning fluids shall have been off-loaded and the tanks cleaned, except as may be mutually agreed upon between the Contractor and the Supervisor prior to work on the vessel by the Contractor. Fire hose lines shall be maintained by the Contractor ready for immediate use on the vessel at all times while the vessel is berthed alongside the Contractor's pier or in dry dock. All tanks under alteration or repair shall be cleaned, washed, and steamed out or otherwise made safe to the extent necessary, and the Contractor shall furnish the vessel's Gas Free Officer and the Supervisor with a "Gas Chemists' Certificate" before any hot work is done. The Contractor shall maintain a fire watch aboard the vessel in areas where the Contractor is working. All other fire watches aboard the vessel shall be the responsibility of the Government.

(b) Except as otherwise provided in contractually invoked technical specifications or NAVSEA furnished directives, while the vessel is at the Contractor's plant and when the temperature becomes as low as thirty-five degrees Fahrenheit, the Contractor shall assist the Government when requested in keeping all pipe-lines, fixtures, traps, tanks, and other receptacles on the vessel drained to avoid damage from freezing, or if this is not practicable, the vessel shall be kept heated to prevent such damage. The vessel's stern tube and propeller hubs shall be protected by the Contractor from frost damage by applied heat through the use of a salamander or other proper means.

(c) The work shall, whenever practicable, be performed in such manner as not to interfere with the work performed by military personnel attached to the vessel, and provisions shall be made so that personnel assigned shall have access to the vessel at all times, it being understood that such personnel will not unduly interfere with the work of the Contractor's workmen.

(d) The Contractor shall at all times keep the site of the work on the vessel free from accumulation of waste material or rubbish caused by its employees, or the work performed by the Contractor in accordance with this contract, and at the completion of such work shall remove all rubbish from and about the site of the work, and shall leave the work in its immediate vicinity "broom clean", unless more exactly specified by the Supervisor.

HQ C-2-0045 QUALIFICATION OF CONTRACTOR NONDESTRUCTIVE TESTING (NDT) PERSONNEL

(NAVSEA) (APR 2004)

(a) The Contractor and any Nondestructive Testing (NDT) subcontractor shall utilize for the performance of required NDT, only Level I, II and III personnel currently certified in accordance with NAVSEA Technical

Publication T9074-AS-GIB-010/271, ACN Notice 1 of 16 Feb 99. Documentation pertaining to the qualification and certification of NDT personnel shall be made available to the Contracting Officer for review upon request.

(b) These requirements do not apply with respect to nuclear propulsion plant systems and other matters under the technical cognizance of SEA 08. Because of health and safety considerations, such matters will continue to be handled as directed by SEA 08.

HQ C-2-0051 SPECIFICATIONS AND STANDARDS (NAVSEA) (AUG 1994)

(a) Definitions.

(i) A "zero-tier reference" is a specification, standard,…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .