A17.0 Solicitation Q A's_2_answered.pdf
PDF 98 KB Posted
- Attached to
- 150-Ton Chiller Lease Federal contract opportunity
- Solicitation number
- N4523A23Q1333
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| A17.0 Solicitation Q A's_2_answered.pdf | ||
| A17.0 Solicitation Q & A answered.pdf | ||
| A17.0 Solicitation Q & A answered.pdf | ||
| C08.0 N4523A23Q1333 Solicitation.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. What is the flow rate of the existing system…GPM?
Paragraph 2.1.1 states the system is to be capable of supply at least (minimum) of 300gpm
2. What temperature do they plan on setting the machine at? (Supply Temp) Paragraph 2.1.2 states a temperature of 42ºF with a temperature difference (Delta T) of 10ºF
3. What temperature do they expect to see back after it runs through the system? (Return Temp) Paragraph 2.1.2 states a temperature of 42ºF with a temperature difference (Delta T) of 10ºF
4. What is the site Temporary Piping Connection (Vic or Flange)?
4” Camlock fittings
5. What is the site Temporary Piping Connection Size (4,6,8”)?
4”
6. What is the site Temporary Electric Breaker Voltage (208 or 460/480)?
Paragraph 2.2.1 states suitable for 460-volt, 3 phase power supply
7. What is the site Temp Electric Breaker Amp.?
A breaker required for the chiller will be provided
8. What is the location of temporary unit in relationship to Piping and Electrical (within 50’ within 100’)?
100’
9. Does the site have the fork lift or crane available to offload the unit off a trailer? To what capacity?
Yes, there is more than enough lifting capacity
10. Will they require a tech for quarterly maintenance?
Not directly specified for quarterly but maintenance and repairs shall be the responsibility of the vendor
11. Will they require a tech for startup and training?
Yes as stated in paragraph 2.4.3
12. Is there site training for a tech to be onsite?
Paragraph 2.4.3 states the training shall be conducted the day of, or the next day after the chiller and associated components are delivered, setup and operational. Training shall require no more than one instructor and shall last no longer than one workday.