STATEMENT OF WORK

1. Scope: The purpose of this requirement is to remove existing and install new, previously purchased vanities and equipment in building 25003 for Andersen Gateway Inns & Suites. These items are for AGIS Guests staying on Andersen AFB, Guam.

2. SCOPE OF WORK:

A.

Removal and Disposal Works

Existing vanity and sink120 each
Existing facial mirrors120 each
Existing light fixtures120 each
Existing outlet and Switch cover240 each

Installation of Owner-Furnished Materials Install vanity counter with sink 120 each Install combo facial mirror with light fixture

(No major electrical work will be done)120 each
Install flexible hoses (Minor Plumbing)240 each

Supply and install wood filler and shims as required on all vanities and Combo facial mirror with light fixture

Supply and install backsplash on back wall 120 each

Supply and install outlet and switch covers (Must be matching) 240 each

Supply and Touch-up paint around vanity area 120 each

Miscellaneous Works Supply and install angle valves (Minor plumbing) 240 each

Demobilize and final clean-up

B.

Any damage done to existing structures will be the responsibility of the contractor to repair. The condition of existing structures must be left the same quality found at the commencement of installation or better.

Touch up paint must be done around removed and placed items to match the existing color. Any screw or mount holes in the walls must be filled prior to paining.

Minor plumbing and electrical work will be completed during installation. Air Force Form 103 will be provided to the Civil Engineering Squadron upon commencement of work.

There are 2 sizes of rooms to be worked on, one with a slightly larger vanity space than the other. The contractor must provide plans to the Civil Engineering Squadron of how they will fill the spaces in between the countertops and the walls. Spaces range from 1/2 inch on each side to 1 inch on each side of the countertop.

Contractor must provide and install backsplash. Backsplash must be ceramic tile, 8” tall, and be a earth tone color. Backsplash will only be installed on the back wall.

3. SITE VISIT:

A site visit will be scheduled for Friday, September 21st, 2012 at 1pm local time. This site visit is not mandatory, but highly recommended. Contractors that will need temporary base passes should meet at the Visitor Center at 12:30pm.

4. LOCATION:

Andersen Navy Gateway Inns & Suites
Building 25003/ 120 VAQ rooms
Telephone
Front Desk 671-979-5501
Operation Manager 671-979-5513

5. PERFORMANCE PERIOD

Completion time is 60-120 calendar days depending on occupants as well as work schedule.

Requested Start Date: 1 November 2012