This document contains an amendment to a solicitation for a 25,000-pound vertical universal testing machine with a two-range load cell. The amendment provides answers to five questions from industry. The first question regards flexibility in the 300mm ram stroke specification to accommodate unique testing needs such as for polyester. The second specifies the minimum acceptable specimen length as 10 feet. The third clarifies that the ramp-up speed of 1% per second and cycle testing speed of 120-150% are both requirements. The fourth confirms a horizontal machine is an acceptable alternative to the specified vertical one. The fifth advises that direct delivery must be to Bahrain, as the Navy facility in Portsmouth, Virginia is no longer accepting deliveries.

View the file

Other files

File Type Posted
Past Performance Information.docx DOCX document
N4033923RF023-0002.pdf PDF
N4033923RF023.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

N4891523RC00FFB

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this Solicitation Amendment is to answ er industry questions as show n herein.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 04-Sep-2023

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X N4033923RF023

X 9B. DATED (SEE ITEM 11)

30-Aug-2023

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

04-Sep-2023

CODE

NAVSUP FLC BAHRAIN CODE 200

SHORE SUPPORT DIVISION PSC 851, BOX 430

FPO AE 09834-0005

N40339 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N4033923RF023

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 1449 - CONTINUATION SHEET

The following have been added by full text:

INDUSTRY QUESTIONS AND ANSWERS

Question #1: The specification mentions a ram stroke of 300mm. However, for testing polyester, this stroke length might not be sufficient. Could you confirm if the 300mm stroke length is a strict requirement or if there is any flexibility in this specification?

Answer #1: 0-300mm stroke length is not a strict requirement, flexibility in certain specifications to accommodate unique testing needs.

Question #2: The solicitation states that the maximum and minimum specimen length is 15 feet. Could you please specify the minimum acceptable specimen length?

Answer #2: Minimum specimen length is 10 feet.

Question #3: The specification mentions a ramp-up speed of 1% per second, which seems to differ from the cycle testing speed of 120-150%. Could you clarify which speed requirement takes precedence or if both are necessary?

Answer #3: Response: 1% Speed per second at 120% Cycle testing speed. Ramp-Up Speed of 1% per Second:

This speed requirement is typically used during the initial phase of testing, especially when conducting tests that involve gradually increasing load or stress levels. A ramp-up speed of 1% per second ensures a controlled and gradual application of force or stress to the test specimen. It's essential for accurately observing how the specimen responds to increasing stress levels over time. Cycle Testing Speed of 120-150%: This speed requirement refers to the speed at which the machine operates during the main testing cycles. It's crucial for simulating real-world conditions or specific use cases where the specimen may experience rapid changes in load or stress. This higher cycle testing speed allows for the evaluation of the specimen's performance under dynamic conditions.

Question #4: The solicitation specifies a vertical machine, which would require assembling the test object 6-7 meters in the air for a 15-foot specimen. We are considering proposing a horizontal version for practicality. Is a horizontal machine an acceptable alternative?

Answer #4: Absolutely, proposing a horizontal machine as an alternative to the specified vertical one is a practical and viable solution. A horizontal machine can still effectively fulfill the testing requirements while offering greater convenience and safety, making it a suitable alternative for consideration.

Question #5: Reference to subjected solicitation, can we make the delivery to the US at any of the Navy facilities, or do you need delivery at Bahrain? Please advise.

Answer #5: Direct delivery to Bahrain. NNSY Portsmouth Virginia is not accepting the deliveries anymore.