Amendment 2 - Clarifies prior RFI response, posts new RFI responses, changes bid validity period.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment1.pdf | ||
| Attachment_Bid_Form_REV1.pdf | ||
| Attachmen__5_Project_Specifications.pdf | ||
| Solicitation_N4008617B6134.pdf | ||
| Attachment_4_Repair_Location_Plan.pdf | ||
| Attachment_3_Structural_Steel_Reference_Drawings.pdf | ||
| Wage_Determination.pdf | ||
| Attachment_7_Lighting_Replacement_Plan.pdf | ||
| Attachment_8_Miscellaneous_Electrical_Requirements_and_Notes.pdf | ||
| Attachment_6_Typical_Concrete_Repair_Details.pdf | ||
| Attachment_1_Bid_Form.pdf | ||
| Attachment_2_Phasing_Plan.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ACQR4916901
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The bid date has not changed and remains August 29th, 2017 at 2:00 PM local time. Please note site visit request procedures apply to attend the bid opening for those w ho do not currently have base access.
The purpose of this amendment is as follow s:
1) Clarify RFI responses contained in Amendment 1
2) Post new RFI responses
3) Change the period bids are valid from 60 calendar days to 120 calendar days.
All other terms and conditions remain unchanged and in effect.
Bidders are reminded to acknow ledge this and all amendments w ith their bid submission.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 24-Aug-2017
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N4008517B6134
X 9B. DATED (SEE ITEM 11)
25-Jul-2017
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
24-Aug-2017
CODE
NAVFAC MID ATLANTIC
PWD MAINE - FEAD PORTSMOUTH
PORTSMOUTH NAVAL SHIPYARD
BLDG 59
PORTSMOUTH NH 03801-2032
N40085 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N4008517B6134
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
CLARIFICATION TO RFI RESPONSES
With regard to the question involving spec section 03 01 30.71-3.5 the following is the response that shall be used in establishing pricing and will be subsequently enforced upon contract award.
Question – Refer to spec section 03 01 30.71� 3.5.
a. Is a 3rd party inspection/testing firm required?
Response: No.
b. For all testing, please provide sampling sizes, qtys, etc Response: All testing shall be per the referenced ASTM specifications.
c. If Ktr is using a pre�mixed/bagged mix, are these field tests still required?
Response: No.
Responses to new RFIs:
Question – Will any of the steel framing repairs require shoring that must also support the weight of Building B343 above or do these horizontal members only support the concrete decks they are attached to?
Response: The Contractor is responsible for determining shoring requirements based on the Contractor's Means & Methods.
Question – During the creation of the ‘Repair Location Plans’, was a record kept that describes the expected repair types at each location, such as crack welding, patch required, or complete section replacement?
Response: No, the Contractor shall provide pricing for steel repairs based on the unit price for the quantity indicated on the plans & bid form.
(End of Summary of Changes)