B1510 Fire Protection Upgrades ADDENDUM 2.pdf
PDF 1 MB Posted
- Attached to
- BLDG 1510 FIRE PROTECTION IMPROVEMENTS Federal contract opportunity
- Solicitation number
- N4008022B9500
- Issued by
- Department of the Navy
About this file
This addendum modifies specifications and drawings for a solicitation seeking fire protection upgrades in Building 1510 at Naval Support Activity South Potomac in Dahlgren, Virginia. The scope of work includes replacement of an existing fire alarm system with a new fire alarm and mass notification system, along with acceptance testing, painting, cleanup and related work. Limited ceiling removal and replacement is required to accommodate the fire alarm installation. The addendum clarifies that work deferred to a future project includes replacement and upgrades to the wet pipe fire protection system, as well as extending fire alarm devices and circuits to new panels installed under the current project. It also specifies coordination needs, testing requirements, and provides a limited hazmat survey and references additional specification sections and a bid schedule attachment.
View the file
Other files for this federal contract opportunity
Show all 19
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Fire Protection Upgrades in Building 1510 Work Order Number: 1558920 NSA South Potomac, Dahlgren, VA
ADDENDUM #2: February 23, 2022
AMENDMENT TO DRAWINGS DATED AUGUST 08, 2019:
1. DRAWING FA-OO1:
a. General Note 28: Change the second paragraph to read as follows:
“A fire watch shall be provided when necessary by the Government at Government expense. Coordinate with the Government Contract Manager / Contract Engineer a minimum of 14 days in advance.”
2. DRAWING FX-OO1:
a. General Note 18.5: Change the note to read as follows:
“For the Fire Alarm Project, the Contractor shall provide the appropriate QUALIFIED PERSONNEL to perform incidental fire sprinkler outages as may be required for the connection of the new fire alarm system to the existing fire sprinkler system.”
AMENDMENT TO SPECIFICATIONS DATED AUGUST 08, 2019:
1. SECTION 01 11 00 “SUMMARY OF WORK”
a. THE FOLLOWING PARAGRAPHS MODIFY AND SUPPLEMENT THE SCOPE
OF WORK CLARIFICATIONS IDENTIFIED IN ADDENDUM # 1:
1.2.1 Project Description:
Contractors shall bid only on the replacement of the existing Fire Alarm System with a new Fire Alarm and Mass Notification System and Bid Option-1.
Work clarified to be included within current project includes:
Existing Fire Alarm Demolition and new fire alarm and mass notification installation, including acceptance testing, painting, cleanup and incidental related work.
o Limited ceiling removal and replacement as required to accommodate fire alarm work indicated.
o Coordinate new fire alarm device locations with existing ceiling systems and devices to remain, including lights, sprinklers, diffusers and registers.
o Wall and floor penetrations remaining unused after demolition shall be patched and sealed to match existing adjacent work.
o Above ceiling work and ceiling devices installed under this project shall be installed to accommodate the future fire sprinkler system and new ceiling heights referenced in the contract drawings.
Early detection and equipment shunt systems where indicated.
Interface with Elevators and elevator machine rooms.
Future interface with sprinkler components:
o Where sprinkler components are not currently available for connection due to deferred work, size panels and batteries for future circuits.
Demolition of Existing Halon System shall be performed with the fire alarm demolition/installation. (Halon System is currently not operational)
Work deferred to a future project includes:
Replacement and upgrades to wet pipe fire protection system.
Fire alarm devices and circuits extended back to panels installed under this current project.
Wholesale removal and re-installation of ceiling systems.
2. SECTION 01 14 00 “WORK RESTRICTIONS”
a. 1.2.3 “Work Outside Regular Hours”: ADD THE FOLLOWING TO
THE PARAGRAPH:
“Work requiring interruptions to existing building services, such as de-energizing electrical panels necessary to install new circuit breakers may take place outside of normal working hours.”
1.2.6 Building Access:
b. ADD THE FOLLOWING PARAGRAPH:
1.2.6 Building Access:
Initial Access: Through the front entrance for badging purposes.
Daily Access: Building access through the rear entrance near the loading dock will be coordinated with Building Security and escorts for badged individuals.
3. SECTION 02 82 16.00 20 “ENGINEERING CONTROL OF ASBESTOS
CONTAINING MATERIALS”
a. ADD THE FOLLOWING PARAGRAPH AND FIELD SURVEY:
1.1.1 Hazmat Survey: (See Attachment 1)
A limited field survey was performed and is included as an appendix to the specification. Should suspicious materials be encountered during the course of this project, they shall remain un-disturbed until tested and proven negative. Notify the Construction Manager immediately upon discovery and coordinate arrangements for appropriate testing.
4. SECTION 28 31 76 “INTERIOR FIRE ALARM AND MASS NOTIFICATION
SYSTEM”
2.1 Materials and Equipment: Add the following sub-paragraph:
a. Attic Stock: Furnish one spare of each type detection and notification device and turn over to the Government.
2.1.1 Standard Products: Ass the following sub-paragraph:
a. Interchangeability: Use off the shelf components which are physically, electrically and functionally interchangeable with equivalent components as complete items. Equivalent, replacement components must not require new or other component modification. Do not use custom designed, or one-of-a-kind items. Interchangeable components or modules must not require trial and error matching in order to =meet integrated system requirements, system accuracy, or restore complete system functionality.
3.4 Connection of New System: Add the Following to sub-paragraph b.:
1) Front Elevator: Obtain the services of an elevator contractor to upgrade controls to include elevator recall and fire department override system.
2) Loading Dock Elevator: Connect to existing elevator recall and fire department override.
3) Coordinate with the Government Construction Manager / Construction Engineer for assistance operating, inspecting and testing existing elevator systems.
3.4 Connection of New System: Add the Following to sub-paragraph c.:
1) Coordinate with the Government Construction Manager / Construction Engineer for assistance operating, inspecting and testing existing HVAC systems.
3.8.2.3 Final Testing: Add the Following:
Final Acceptance Test shall be scheduled only when the preliminary test reports have been approved by the Contractor’s Quality Control Fire Protection Engineer and the Government Fire Alarm Technician.
Final Acceptance Test: The Contractor’s Quality Control Fire Protection Engineer shall be present to facilitate the acceptance process with the Naval Facilities Engineering Command, Washington, Fire Protection Engineer.
5. ADD THE FOLLOWING SPECIFICATION SECTIONS REFERENCED IN ADDENDUM
#1(SEE ATTACHED):
01 31 23.13 20 ELECTRONIC CONSTRUCTION AND FACILITY SUPPORT CONTRACT
MANAGEMENT SYSTEM
01 57 19.01 20 SUPPLEMENTAL TEMPORARY ENVIRONMENTAL CONTROLS
01 58 00 PROJECT IDENTIFICATION
01 78 24.00 20 FACILITY ELECTRONIC OPERATION AND MAINTENANCE SUPPORT
INFORMATION (eOMSI)
6. ADD THE BID SCHEDULE REFERENCED IN ADDENDUM #1 (SEE ATTACHED):
ATTACHMENT – 1 LIMITED HAZMZT SURVEY: