J-1_SSP_032-19_NPTU_Work_Package.pdf
PDF 376 KB Posted
- Attached to
- NPTU BARGE (031-19) Federal contract opportunity
- Solicitation number
- N40027-18-R-0019
About this file
J-1
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| N40027-18-R-0020_NPTU_Barges_AMD_01.pdf | ||
| J-6__Past_Performance_Questionnaire.docx | DOCX document | |
| J-2_Request_for_Specification_Clarification.docx | DOCX document | |
| J-9_Additional_information_from_NPTU_c300.docx | DOCX document | |
| J-1_(ADD_01)_IX_516_ADDENDUM_ONE.pdf | ||
| N40027-18-R-0020_NPTU_Barges_RFP.pdf | ||
| J-7_Navy_NPTU_Charleston_Contractor_Special_Conditions.pdf | ||
| J-5_NPTU_IX-516_SSP_031-19_CDRLs.pdf | ||
| J-4,_Cost_Data_Break_Down_NPTU_031-19.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF THE NAVY
SPECIFICATIONS FOR WORK TO BE ACCOMPLISHED
SPECIFICATION NUMBER:
SHIP CHARACTERISTICS
FEET INCHESLENGTH OVERALL
FEET INCHESMAX. BEAM AT DESIGN WATERLINE
FEET INCHESEXTREME BEAM INCLUDING APPENDAGES
FEET INCHESDRAFT (MAX. NAVIGABLE) (FWD.)
FEET INCHESDRAFT (MAX. NAVIGABLE) (AFT.)
LONG TONLIGHT DISPLACEMENT
LONG TONFULL LOAD DISPLACEMENT
INCHESFEETHEIGHT OF MAST ABOVE DESIGN WATERLINE
INCLUDES ALL CHANGES THROUGH 8/31/2018
INDEX
SHIP: IX-516 (RMC 22275) SERM-031-19
ITEMS THAT ARE STRUCK OUT IN THIS INDEX DO NOT APPLY TO THIS CONTRACT.
CATEGORY I. FY-19 STANDARD ITEMS APPLICABLE TO THIS JOB ORDER WITHOUT FURTHER REFERENCE.
ITEM_NO. TITLE CHANGE DATE CHANGE
009-01 General Criteria; accomplish 05/03/2018 CH-3
009-02 Environmental Compliance Report for Material Usage; accomplish 05/03/2018 CH-3
009-03 Toxic and Hazardous Substance; control 10/01/2017 Original
009-04 Quality Management System; provide 10/01/2017 Original
009-06 Maintaining Protection and Cleanliness from Non-Radioactive Operations;
accomplish
03/20/2018 CH-1
009-07 Confined Space Entry, Certification, Fire Prevention and Housekeeping;
accomplish
10/01/2017 Original
009-08 Shipboard Fire Protection and Fire Prevention; accomplish 04/03/2018 CH-2
009-10 Asbestos-Containing Material (ACM); control 05/03/2018 CH-3
009-18 Mine Warfare Ships Magnetic Material; control 05/03/2018 CH-3
009-19 Provisioning Technical Documentation (PTD); provide 04/03/2018 CH-2
009-20 Government Property; control 10/01/2017 Original
009-21 Logistics and Technical Data; provide 04/03/2018 CH-2
009-23 Interference; remove and install 05/03/2018 CH-3
009-24 Authorization, Control, Isolation, Blanking, Tagging, and Cleanliness;
accomplish
05/03/2018 CH-3
009-29 CANCELLED 03/20/2018 CH-1
009-34 Fire Protection of Unmanned Vessel at Contractor Facility; accomplish 11/18/2016 Original
009-39 Technical Manual Contract Requirement (TMCR) for a New Technical Manual for Commercial Equipment/Component; accomplish
03/20/2018 CH-1
009-40 Contractor Crane, Multi-Purpose Machine and Material Handling Equipment at a Naval Facility; provide
04/03/2018 CH-2
009-60 Schedule and Associated Reports for Availabilities Over 9 Weeks in Duration;
provide and manage
05/03/2018 CH-3
009-61 Shipboard Use of Fluorocarbons; control 07/18/2014 Original
009-67 Integrated Total Ship Testing; manage 05/03/2018 CH-3
009-69 Heavy Weather/Mooring Plan; provide 05/03/2018 CH-3
009-70 Confined Space Entry, Certification, Fire Protection, Fire Prevention and Housekeeping for Unmanned Vessels; accomplish
04/03/2018 CH-2
009-72 Physical Security at a Private Contractor Facility; accomplish 10/01/2017 Original
009-73 Shipboard Electrical/Electronic Cable Procedure; inspect, test, install, remove, and repair
04/03/2018 CH-2
009-74 Occupational, Safety and Health Plan; accomplish 05/03/2018 CH-3
009-80 Ship Facilities; maintain 11/18/2016 Original
009-81 Compartment Closeout; accomplish 03/20/2018 CH-1
009-82 Installation of Equal Component Vice Specified Component; report 04/03/2018 CH-2
009-84 Threaded Fastener Requirements; accomplish 10/01/2017 Original
009-93 Emergency Planning and Community Right-to-Know Act (EPCRA) and Pollution Prevention Act (PPA) Information; provide
03/20/2018 CH-1
009-94 CANCELLED 04/03/2018 CH-2
Page 1 of 4 EXECUTING WORK
ITEM_NO. TITLE CHANGE DATE CHANGE
009-97 Cancelled 05/03/2018 CH-3
009-99 Ship Departure Report; provide 07/18/2014 Original
009-100 Ship's Stability; maintain 03/20/2018 CH-1
009-101 Ship Transit and Berthing; accomplish 04/03/2018 CH-2
009-102 CANCELLED 04/03/2018 CH-2
009-106 Work Authorization Form Coordinator (WAFCOR); provide 10/01/2017 Original
009-108 CANCELLED 03/20/2018 CH-1
009-109 Non-SUBSAFE Work on SUBSAFE-Certified Vessel; accomplish 10/01/2017 Original
009-110 Non-Nuclear Work on a Nuclear Vessel; accomplish 11/18/2016 Original
009-111 Schedule and Associated Reports for Availabilities 9 Weeks or Less in Duration; provide and manage
05/03/2018 CH-3
009-117 Combat Systems, Light-Off Suport; provide 04/03/2018 CH-2
009-118 CG Deck Loading; accomplish 07/18/2014 Original
009-120 Fact Finding and Critique of Unplanned Event; manage 03/20/2018 CH-1
009-122 Temporary Padeye; install and remove 10/01/2017 Original
099-01SE General Criteria for Mayport Naval Station (NAVSTA) Availabilities; accomplish 01/20/2017 Original
099-08SE Deleted 01/31/2018 Original
099-51SE Non-Hazardous Liquid Waste Removal Operations at Naval Station Mayport;
accomplish
02/12/2018 Original
099-53SE Temporary Hazardous Material (HM)/Hazardous Waste (HW)/Satellite Accumulation Point (SAP) Storage Units for Ship's Force Use; provide
01/31/2012 Original
099-55SE Cleaning and Pumping; accomplish (CMAV) 02/12/2018 Original
099-58SE Heavy Weather Plan for Naval Station Availabilities; provide 01/30/2017 Original
099-60SE General Environmental Requirements for Naval Station Mayport Availabilities;
accomplish
05/13/2013 Original
099-61SE Temporary Hazardous Material (HM)/Hazardous Waste (HW)/Satellite Accumulation Point (SAP) Storage Units for Ship's Force Use at Contractor's Facility; provide
01/27/2009 Original
099-74SE General Safety Requirements; accomplish 02/28/2018 Original
Page 2 of 4 EXECUTING WORK
CHANGE DATETITLEITEM NO.
CATEGORY II. FY-19 STANDARD ITEMS WHICH MAY BE INVOKED IN THE WORK ITEMS OF THIS JOB ORDER
CHANGE
009-09 Process Control Procedure (PCP); provide and accomplish
05/03/2018 CH-3
009-12 Weld, Fabricate, and Inspect; accomplish 05/03/2018 CH-3
009-25 Structural Boundary Test; accomplish 03/20/2018 CH-1
009-32 Cleaning and Painting Requirements; accomplish 04/03/2018 CH-2
009-36 Controller; repair 04/03/2018 CH-2
009-65 Polychlorinated Biphenyls (PCBs); control 04/03/2018 CH-2
009-71 Piping System; test 03/20/2018 CH-1
009-88 Collection, Holding and Transfer (CHT) and Motor Gasoline (MOGAS) Tanks, Spaces, and Piping, including Sewage or MOGAS-Contaminated Tanks, Spaces, and Piping; certify
11/18/2016 Original
Page 3 of 4 EXECUTING WORK
ITEM NO. TITLE
Deck House Exterior Siding; repair110-11-002
Electrical Distribution System; inspect and repair320-11-001
Ventilation Cleaning; accomplish514-21-001
Mooring Winch Motor Controller; repair582-11-001
Collection, Holding and Transfer (CHT) Piping System; chemically clean593-11-001
Exterior Superstructure, Siding and Deck; repair and preserve631-21-001
Page 4 of 4 EXECUTING WORK
SHIP: IX-516 (RMC 22275) ITEM NO: 110-11-002
COAR: 95 PCN: DK01-0943
CSWT FILE NO: 110-009 (MCM 1) CMP: NONE
REVISED: 07 Nov 2017 PLANNER: CORNWELL, RICHARD
SPIGELMYER, GLENN
UNDHEIM, DANNY
SSP: SERM-031-19 1 of 2 ITEM NO: 110-11-002
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
1. SCOPE:
1.1 Title: Deck House Exterior Siding; repair
1.2 Location of Work:
1.2.1 IX-516 Barge, Deck House Exterior and Roof Top
1.3 Identification:
1.3.1 Not Applicable
2. REFERENCES:
2.1 Standard Items
2.2 150-6396668 Rev 0, Roof Primary Framing Plan
2.3 150-6396662 Rev 0, 2nd and 3rd Floor Deck Layout
3. REQUIREMENTS:
3.1 Accomplish the following repairs in the location listed in 1.2, in accordance with 2.2 and 2.3, as designated by the SUPERVISOR:
3.1.1 Remove existing and install new a total of 500 EA CRES
fastener for deck house siding.
3.1.2 Remove existing and install new a total of 200 square feet of deck house siding.
3.1.3 Remove existing and install new the deck house siding sealing tape.
3.1.4 Template exact size, configuration, and location from existing condition.
3.2 Accomplish the requirements of 009-12 of 2.1, including Table 3, Column A and C, Line One through 7.
3.3 Accomplish the requirements of 009-25 of 2.1 for a water hose test of each new siding panel. Allowable leakage: None.
3.4 Accomplish the requirements of 009-32 of 2.1 for each new and disturbed surface.
4. NOTES:
4.1 None.
5. GOVERNMENT FURNISHED MATERIAL (GFM):
5.1 LLTM:
1. None.
5.2 PUSH MATERIAL:
1. None.
SHIP: IX-516 (RMC 22275)
SSP: SERM-031-19 2 of 2 ITEM NO: 110-11-002
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
5.3 KITTED MATERIAL:
SHIP: IX-516 (RMC 22275) ITEM NO: 320-11-001
COAR: 95 PCN: DK01-1029
CSWT FILE NO: 320-005 (LCU 1646) CMP: NONE
REVISED: 07 Nov 2017 PLANNER: CAMPBELL, TIMOTHY
MAYNARD, JAMES
SPIGELMYER, GLENN
UNDHEIM, DANNY
SSP: SERM-031-19 1 of 2 ITEM NO: 320-11-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
1. SCOPE:
1.1 Title: Electrical Distribution System; inspect and repair
1.2 Location of Work:
1.2.1 IX-516 Barge, Throughout the Vessel
1.3 Identification:
1.3.1 Quantity (23 EA), Electrical Power Panel, No. C, H, I-A, I-B, J, K, L-A, L-B, M, N-1, N-2, N-3, N-4, Q-1, Q-2, Q-3, R, S, T, U, X, Y, and Z
2. REFERENCES:
2.1 Standard Items
2.2 324-6396702 Rev 03, Electrical Panel Schedules
2.3 320-6396699 Rev B, Moored Training Ship IX 516 Power Plans Main Deck
2.4 320-6396701 Rev B, Moored Training Ship IX 516 Power Plans 02 Deck
2.5 300-6396691 Rev B, Moored Training Ship IX 516 One-Line Diagram
2.6 S9086-KC-STM-010 Rev 09, NSTM CH 300, Electric Plant - General
2.7 S9086-KY-STM-010 Rev 06, NSTM CH 320, Electric Power Distribution Systems
3. REQUIREMENTS:
(V) ""PRELMINARY OPERATIONAL TEST""
3.1 Accomplish a preliminary operational test of each power panel listed in 1.3 as directed by the SUPERVISOR, using 2.2 through 2.5 for guidance.
Report: TEST REPORT AVAIL START DATE (Key Event) + 1 day
3.1.1 Submit one legible copy, in hard copy or approved
transferrable media, of a report listing results of the requirements of 3.1 to the SUPERVISOR.
3.2 Accomplish an inspection of each power panel listed in 1.3 in accordance with Paragraph 300-4.8.1 of 2.6, using 2.7 for guidance.
3.2.1 Annotate and identify each damaged, defective, and missing, breaker, cable, connector, copper buss, fastener, fuse, gasket, label plate, lug, and wire marker.
SSP: SERM-031-19 2 of 2 ITEM NO: 320-11-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
Report: INSPECTION REPORT AVAIL START DATE (Key Event) + 3 days
3.2.2 Submit one legible copy, in hard copy or approved
transferrable media, of a report listing results of the requirements of 3.2 and 3.2.1 to the SUPERVISOR.
3.3 Repair each power panel as designated by SUPERVISOR.
3.3.1 Clean each power panel listed in 1.3 in accordance with Paragraph 300-4.8.2 of 2.6, using 2.7 for guidance.
3.4 Provide 92 mandays of labor and 6,900 dollars of material to accomplish work not previously identified in the Work Item, as directed by the SUPERVISOR. If the total cost is less than the authorized manday and dollar amount, remaining funding will be subject to recoupment. The contractor is not authorized to exceed this limit.
Report: EXPENSE REPORT AVAIL START DATE (Key Event) + 3 days
3.4.1 Submit one legible copy, in hard copy or approved
transferrable media, of a weekly report listing results of the requirements of 3.4 to the SUPERVISOR.
(V)(G) ""OPERATIONAL TEST""
3.5 Accomplish an operational test of each power panel listed in 1.3 as directed by the SUPERVISOR and in accordance with Paragraph 300-4.8.4 of 2.6, using 2.2 through 2.5 and 2.7 for guidance.
3.6 Accomplish the requirements of 009-32 of 2.1 for each new and disturbed surface.
4. NOTES:
4.1 None.
5. GOVERNMENT FURNISHED MATERIAL(GFM):
5.1 LLTM:
1. None.
5.2 PUSH MATERIAL:
1. None.
SHIP: IX-516 (RMC 22275) ITEM NO: 514-21-001
COAR: 95 PCN: DK01-1024
CSWT FILE NO: 514-001 (PC 1) CMP: NONE
REVISED: 07 Nov 2017 PLANNER: DELCAMBRE, STEVEN
UNDHEIM, DANNY
SSP: SERM-031-19 1 of 3 ITEM NO: 514-21-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
1. SCOPE:
1.1 Title: Ventilation Cleaning; accomplish
1.2 Location of Work:
1.2.1 IX-516 Barge, Throughout the Ship
1.3 Identification:
1.3.1 Quantity (One EA), Hold Deck Level HVAC Ventilation System
1.3.2 Quantity (One EA), Main Deck Level HVAC Ventilation System
1.3.3 Quantity (One EA), 01 Deck Level HVAC Ventilation System
1.3.4 Quantity (One EA), 02 Deck Level HVAC Ventilation System
2. REFERENCES:
2.1 Standard Items
2.2 S9086-RQ-STM-010/CH-510 Rev 7, Heating, Ventilating, And Air Conditioning Systems For Surface Ships
2.3 512-6396740 Rev 2, HVAC Plans Main Deck and Hold
2.4 512-6396741 Rev 01, HVAC Plans - 01 and 02 Decks
2.5 512-6396742 Rev 2, HVAC-Equipment Installation Details
2.6 512-6396743 Rev 2, HVAC Equipment Schedules
2.7 PM 230-126, SJAX, Ventilation Gasket Material
3. REQUIREMENTS:
3.1 Consider each material, debris, and/or residue associated with ventilation system to contain toxic/hazardous substance including but not limited to cadmium, chromium, and PCB's.
3.1.1 Accomplish the requirements of 009-65 of 2.1.
3.2 Schedule work on each HVAC system to ensure that at least one zone/level is in service at all times to ensure uninterrupted air conditioning during cleaning process, as directed by the SUPERVISOR.
3.3 Clean interior of each duct free of rust, dirt, grease, lint and other contamination, from each air handler to terminal end, using Appendix B of 2.2 for guidance. Remove, clean and reinstall each re-usable ventilation system air filter for each ventilation system listed in 1.3.
3.3.1 Matchmark, remove, and clean each damper, diverting/balancing plate, orifice plate, and access plate. Retain for reuse.
3.4 Clean interior of each air handler and air conditioning evaporator coil free of rust, dirt, grease, lint and other contamination, using Appendix B of 2.2 for guidance, for each ventilation system listed in
SSP: SERM-031-19 2 of 3 ITEM NO: 514-21-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
1.3.
(V)(G) "VENTILATION CLEANLINESS"
3.5 Accomplish a visual inspection of each cleaned interior surface of each ventilation branch for each ventilation system listed in 1.3 for cleanliness and completion of work prior to installation of each wire mesh screen, damper, orifice plate and access plate, in accordance with
2.2 through 2.5.
Report: CLEANINES INSPECTION RESULTS AVAIL START DATE (Key Event) + 2 days
3.5.1 Submit one legible copy, in hard copy or approved
transferrable media, of a report listing requirements of 3.5 to the
SUPERVISOR.
3.6 Install each damper, diverting/balancing plate, orifice plate and access plate removed in 3.3.1, using 2.3 through 2.7 for guidance.
3.6.1 Install new each gasket for each disturbed ventilation joint and access plate in accordance with 2.7.
3.6.2 Install a metal tag with contractor's name, date, and stating "PCB FREE" to each disturbed/new ventilation flange, access cover, and closure where each gasket is required.
3.7 Remove existing and install new 9 EA 2-1/2 inch IPS ball valve, for chilled water supply to each air conditioning unit, in accordance with
2.3 through 2.6.
3.7.1 Template exact size, configuration, and location from existing shipboard condition.
3.7.2 Accomplish the requirements of 009-12 of 2.1, including Table One, Column A and B, Line One through 10.
3.8 Accomplish the requirements of 009-71 of 2.1 for new and disturbed piping.
3.8.1 Ensure hydrostatic test pressure is 236 PSIG, using clean, fresh water, when the hydrostatic test option is selected.
(V)(G) "VOLUMETRIC TEST"
3.9 Accomplish an volumetric test for each ventilation system identified in 1.3, in accordance with 2.5.
3.9.1 Operate each ventilation system at system normal operating pressure to ensure ventilation joint tightness. Allowable leakage:
None.
3.10 Accomplish the requirements of 009-32 of 2.1 for each new and disturbed surface.
4. NOTES:
SSP: SERM-031-19 3 of 3 ITEM NO: 514-21-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
4.1 ESR SERM-18-0000-1017 applies.
5. GOVERNMENT FURNISHED MATERIAL (GFM):
5.1 LLTM:
1. None.
5.2 PUSH MATERIAL:
1. None.
SHIP: IX-516 (RMC 22275) ITEM NO: 582-11-001
COAR: 95 PCN: DE01-1089
DE01-1087
CSWT FILE NO: 582-002 (DDG 51) CMP: NONE
REVISED: 07 Nov 2017 PLANNER: CAMPBELL, TIMOTHY
SPIGELMYER, GLENN
SSP: SERM-031-19 1 of 2 ITEM NO: 582-11-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
1. SCOPE:
1.1 Title: Mooring Winch Motor Controller; repair
1.2 Location of Work:
1.2.1 IX-516 Barge, Main Deck, Forward and Aft
1.2.2 YFN-797 Barge, Main Deck
1.2.3 YC-1596 Barge, Main Deck
1.3 Identification:
1.3.1 Quantity (4 EA), Mooring Winch Motor Controller
2. REFERENCES:
2.1 Standard Items
2.2 331-6396715 Rev 01, Equipment Control Schematics
2.3 S9086-KE-STM-010 Rev 03, NSTM CH 302, Electrical Motors and Controllers
3. REQUIREMENTS:
3.1 Accomplish the requirements of 009-36 for each controller listed in
1.3 and located in 1.2, in accordance with 2.2, using 2.3 for guidance, as designated by the SUPERVISOR.
3.1.1 Accomplish the requirements of 009-32 of 2.1, including Table 2, Line One, Columns A, B, and C, for the foundation of the equipment listed in 1.3 and located in 1.2.
3.1.2 Accomplish the requirements of 009-32 of 2.1, including Table 5, Line 9 for the interior and exterior of the motor controller enclosure.
3.2 Provide 20 mandays of labor and 4000 dollars of material to accomplish work not previously identified in the Work Item, as directed by the SUPERVISOR. If the total cost is less than the authorized manday and dollar amount, remaining funding will be subject to recoupment. The contractor is not authorized to exceed this limit.
Report: EXPENITURE REPORT AVAIL START DATE (Key Event) + 1 day
3.2.1 Submit one legible copy, in hard copy or approved
transferrable media, of a weekly report listing results of the requirements of 3.2 to the SUPERVISOR.
3.3 Accomplish the requirements of 009-32 of 2.1 for each new and disturbed surface.
SSP: SERM-031-19 2 of 2 ITEM NO: 582-11-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
4. NOTES:
4.1 None.
5. GOVERNMENT FURNISHED MATERIAL(GFM):
5.1 LLTM:
1. None.
5.2 PUSH MATERIAL:
1. None.
SHIP: IX-516 (RMC 22275) ITEM NO: 593-11-001
COAR: 95 PCN: DK01-0944
CSWT FILE NO: 593-049 (DDG 51) CMP: NONE
REVISED: 07 Nov 2017 PLANNER: KRIMMER, DAVID
DELCAMBRE, STEVEN
UNDHEIM, DANNY
SSP: SERM-031-19 1 of 3 ITEM NO: 593-11-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
1. SCOPE:
1.1 Title: Collection, Holding and Transfer (CHT) Piping System;
chemically clean
1.2 Location of Work:
1.2.1 IX-516 Barge, Throughout the Ship
1.3 Identification:
1.3.1 None
2. REFERENCES:
2.1 Standard Items
2.2 MIL-STD-3026, Chemical Cleaning of Sewage Collection Piping Systems on Navy Surface Ships
2.3 528-6396762 Rev 2, Sewage Mechanical Flow Diagram
2.4 528-6396766, Sewage & Gray Water Piping Plans & Details
2.5 593-6396801 Rev 5, CHT Tank Assembly and Details
2.6 593-6396802 Rev 4, CHT Tank Assembly and Details
3. REQUIREMENTS:
3.1 Accomplish the requirements of 009-88 of 2.1.
3.1.1 Accomplish the requirements of 009-09 of 2.1 for the
certification process.
3.2 Accomplish the requirements of 009-09 of 2.1 for chemically cleaning and flushing with RYDLYME of the entire collection, holding and transfer (CHT) system up to and including the tank in accordance with 2.2, using
2.2 through 2.6.
3.2.1 Cover and seal each commode and urinal to prevent usage while system is secured for cleaning.
3.2.2 Accomplish a flush of the CHT sewage piping system, using clean, fresh water for a minimum of one hour and ensure piping system is leak free. Allowable external leakage: None.
3.2.3 Clear each vent pipe free of obstruction and foreign matter.
3.2.4 Accomplish corrosion test of each chemical cleaning product tested at the most concentrated state anticipated for shipboard application, in accordance with Paragraph 5.2 through 5.2.2 of 2.2 prior to the start of cleaning process.
3.2.4.1 Submit one legible copy, in hard copy or approved
transferrable media, of a report listing results of the requirements of 3.2.4 to the SUPERVISOR within 2 days prior to
SSP: SERM-031-19 2 of 3 ITEM NO: 593-11-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
start of cleaning process.
(V) "NEUTRALIZE FLUSH"
3.3 Neutralize the flushing chemical remaining in the sanitary waste system after the piping cleaning has been completed. Monitor each PH level during the neutralization process to ensure effluent solution PH level is between 6 and 8.
(V) "FLOW VERIFICATION "
3.4 Accomplish a full flow piping flush to the pier side holding tank upon completion of neutralization process using clean, fresh water to remove loose residue and each chemical.
(V)(G) "BORESCOPE INSPECTION"
3.5 Accomplish a borescope inspection of each internal surface of the CHT sewage piping system for buildup of calcium upon completion of chemical cleaning. Allowable calcium buildup: None.
Report: BORESCOPE INSPECTION RESULT AVAIL START DATE (Key Event) + 2 days
3.5.1 Submit one legible copy, in hard copy or approved
transferrable media, of a report listing borescope inspection result to the SUPERVISOR.
3.6 Remove existing and install new 40 LF of 6 inch IPS, 80 LF of 4 inch IPS, 40 LF of 3 inch IPS, 20 LF of 2 inch IPS, 80 LF of 1-1/2 inch IPS, 20 LF of 1-1/4 inch IPS, and 20 LF of one inch IPS, polyvinyl chloride (PVC) piping and each associated fitting, in accordance with 2.3 through 2.6, as designated by the SUPERVISOR:
3.6.1 Template exact size, configuration, and location from existing shipboard condition.
3.7 Provide 10 mandays of labor and 5000 dollars of material to accomplish work not previously identified in the Work Item, as directed by the SUPERVISOR. If the total cost are less than the authorized manday and dollar amounts, remaining funds will be subject to recoupment. The contractor is not authorized to exceed the limit.
3.7.1 Submit one legible copy, in hard copy or approved
transferrable media, of a weekly report to document labor and material expenditures to the SUPERVISOR.
3.8 Accomplish the requirements of 009-71 of 2.1.
(V)(G) "OPERATIONAL TEST"
3.9 Accomplish an operational test of the CHT sewage piping system under normal operation condition. Allowable external leakage: None.
SSP: SERM-031-19 3 of 3 ITEM NO: 593-11-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
3.10 Accomplish the requirements of 009-32 of 2.1 for each new and disturbed surface.
4. NOTES:
4.1 ESR SERM-18-0000-0992 applies.
5. GOVERNMENT FURNISHED MATERIAL (GFM):
5.1 LLTM:
1. None.
5.2 PUSH MATERIAL:
1. None.
SHIP: IX-516 (RMC 22275) ITEM NO: 631-21-001
COAR: 95 PCN: DK01-1030
CSWT FILE NO: 631-021 (DDG 51) CMP: NONE
REVISED: 07 Nov 2017 PLANNER: CORNWELL, RICHARD
SPIGELMYER, GLENN
UNDHEIM, DANNY
SSP: SERM-031-19 1 of 2 ITEM NO: 631-21-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
1. SCOPE:
1.1 Title: Exterior Superstructure, Siding and Deck; repair and preserve
1.2 Location of Work:
1.2.1 IX-516 Barge, Main Deck to 02 Level, Weather
1.3 Identification:
1.3.1 Each Exterior Surface of the Main Deck, 01 Level, 02 level, Including the Top of the 02 Level
1.3.2 Quantity (6 EA), Double Steel Door, 6 Feet by 6 Feet 8 Inch, RH, Section K, Sheet 2 of 2.6
2. REFERENCES:
2.1 Standard Items
2.2 801-6396642 Rev 3, General Arrangement Deck 02
2.3 801-6396641 Rev 3, General Arrangement Deck 01
2.4 801-6396640 Rev 4, General Arrangement Main Deck
2.5 150-6396673, Elevations
2.6 116-6396648 Rev 2, Barge Floor Plating and Access Way Details
3. REQUIREMENTS:
3.1 Accomplish the requirements of 009-32 of 2.1, including Table 2, Line One, Column A for surface preparation of each exterior surface of each area listed in 1.3.1 and located in 1.2.
3.1.1 Accomplish a visual inspection of each area of exterior structural and structural support for structural integrity, deterioration, pitting, cracking, and each area of damage or distortion.
3.1.1.1 Submit one legible copy, in hard copy or approved
transferrable media, of a report listing results of the requirements of 3.1.1 to the SUPERVISOR.
3.2 Accomplish the following repairs in the locations listed in 1.2, in accordance with 2.2 through 2.5, as designated by the SUPERVISOR:
3.2.1 Remove existing and install new a total of 24 linear feet of exterior structural support.
3.2.2 Remove existing and install new each exterior access door and door frame assembly listed in 1.3.2 and located in 1.2.
3.2.3 Template exact size, configuration, and location from existing shipboard condition.
(V)(G) "OPERATIONAL TEST"
SSP: SERM-031-19 2 of 2 ITEM NO: 631-21-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
3.3 Accomplish an operational test of each door. Test each door by fully opening, fully closing and fully opening each door twice.
3.4 Accomplish the requirements of 009-32 of 2.1, including Table 2, Line One, Column A, B, E and G preparation of surface and exterior superstructure listed in 1.3.1 and located in 1.2.
3.5 Accomplish the requirements of 009-32 of 2.1 for each new and disturbed surface.
4. NOTES:
4.1 None.
5. GOVERNMENT FURNISHED MATERIAL (GFM):
5.1 LLTM:
1. None.
5.2 PUSH MATERIAL:
1. None.