N3904021R0008- Statement of Work - Attachment 1.pdf
PDF 67 KB Posted
- Solicitation number
- N3904021R0008
About this file
This statement of work and solicitation are for the refurbishment of a Universal boring machine located at the Portsmouth Naval Shipyard. The statement of work provides extensive details on the required scope of work, which includes a complete disassembly, inspection, rebuilding and replacement of machine components as needed, restoration of alignments and accuracies to original specifications, and demonstration of capabilities. The period of performance is one year. The solicitation is a total small business set-aside with a response due date of August 31, 2021. Upon satisfactory completion, acceptance will be signed by the authorized government representative at Portsmouth Naval Shipyard.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| N3904021R00080001- Amendment.pdf | ||
| N3904021R00080001_RFQ - Conformed.pdf | ||
| N3904021R0008- 1449 RFQ.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK # xxxx
1. SCOPE: This Statement of Work (SOW) covers the rebuild of one UNIVERSAL Horizontal Boring Machine (Alpha ABG), S/N T3464.
2. BACKGROUND:
2.1. Location: Building 300 at the Portsmouth Naval Shipyard in Kittery, Maine.
2.2. Shipyard Point of Contact: The point of contact for this work will be Mark Lumino, mark.lumino@navy.mil, P 207.438.3841, C 207.994.0719
3. REQUIREMENTS:
3.1. General: Unless indicated otherwise in this SOW, the Contractor shall provide all equipment, tools, materials, parts, and other items and services necessary to perform the work specified herein and to return the machine to working order so that it performs as designed by the OEM. Used herein, “as needed” defines machine conditions that do not meet OEM specifications.
3.1.1 The Contractor shall perform the following work to the Universal boring machine:
Remove the machine from its current location and ship it to the contractor’s facility to perform the machine rebuild. Machine will have been electrically and pneumatically disconnected prior to Contractor’s arrival.
Contractor shall completely disassemble, catalog and inspect the entire machine assembly and a report of machine condition will be created and forwarded to the POC. Parts that can be reused shall be cleaned, painted (as required for preservation) and reused. Parts that need replacement shall be ordered, or when necessary, reverse engineered, manufactured, and installed.
Machine transmission is to be completely disassembled and all components evaluated. Any component (other than gears) not meeting OEM requirements will be replace with equivalent or better than OEM quality. All transmission gears evaluated and believed to be in acceptable condition shall be cleaned and reused as appropriate. If any gears are found to need replacing, Contractor will supply a separate quote for replacement gears.
All drive screws/nuts; racks/pinions and drive shafts will be removed and inspected. If parts are not up to OEM standards, components will be reground or replaced with equivalent or better than OEM quality.
Cross rail and saddle ways will be evaluated at the inspection. The ways will be reworked to an accuracy of .0002” per foot with an accumulated error no greater than .0007” in each axis of travel.
Repair method shall be noted on quote.
All other ways, gibs, taper shoes and liners shall be ground, machined or hand scraped to return the machine to its original machine geometry. If a shoe or liner is damaged beyond repair, the Contractor shall replace it.
All clamps and locks shall be completely rebuilt. All components found to be inadequate to be replaced with equivalent or better than OEM quality.
All ways shall be scraped to restore machine geometry and achieve a minimum of 80% contact.
All way wipers shall be replaced.
The lubrication system shall be completely rebuilt. All lines, gages, seals, filters, directional valves, etc.
shall be replaced with equivalent or better than OEM quality.
The hydraulic system shall be completely rebuilt. All components found to be inadequate shall be replaced with equivalent or better than OEM quality.
Headstock is to be completely disassembled and all components evaluated. Any component not meeting OEM requirements will be replaced with equivalent or better than OEM quality. Spindle taper will be ground to OEM specifications. Draw bar system to be completely rebuilt and brought back to OEM quality.
All bushings, bearings, seals and worn couplings shall be replaced as required.
All drive belts shall be replaced and re-tensioned. Pulleys shall be inspected and re-used unless damaged and not fit for use, in which case, pulleys shall be replaced with equivalent or better than OEM quality.
Hand wheels, hand cranks, levers and handles shall be inspected for looseness with their shaft, worn keys, cracks, breaks, distortion, damage, missing parts and other defects. Components shall be repaired or replaced as necessary.
All dials, scales, data plates and other tags shall be cleaned and restored to readable condition if possible.
All guards and covers shall be cleaned, inspected and repaired as needed.
All ram and counterweight components shall be inspected and repaired or replaced if necessary.
The contractor shall provide new internal electrical components for the existing panel, including a main disconnect, fuses, terminal strips, motor starters, contactors, relays to meet current electrical standards of NFPA 70 and 79.
All wiring and components on the machine shall be replaced to meet the current electrical standards of NFPA 70 and 79.
All electric motors shall be rebuilt or replaced.
All operator station buttons including the machine emergency stop shall be replaced.
The digital readout and scales shall be cleaned, inspected and replaced if found to not meet OEM requirements.
Machine alignments shall be restored to OEM specifications.
The Contractor shall assemble the machine in their facility to verify the alignment, accuracy and operation of the machine.
The Contractor shall perform basic machining operations to demonstrate that all above mentioned machine characteristics and capabilities meet or exceed OEM specifications.
The customer shall reserve the right to witness the rebuilt machine in operation at the Contractor’s facility.
Upon delivery to Portsmouth Naval Shipyard, the Contractor shall unload and reinstall the machine.
Upon completion of installation, the contractor shall verify the alignment, accuracy and performance of the machine and perform basic machining operations to demonstrate that all above mentioned machine characteristics and capabilities meet or exceed OEM specifications.
4 QUALITY ASSURANCE PROVISIONS:
4.1 Personnel Safety and health Requirements: Where applicable, all machine parts, components, mechanisms, and assemblies furnished on the unit shall comply with all specific requirements of “OSHA Safety and Health Standard (29CFR1910), General Industry”, ANSI/AMT B11.19, ANSI/AMT B11.22, and ANSI/AMT B11.23, and ANSI/AMT B20.1 that are applicable to the equipment itself. Covers, platforms, guard rails, belt guards, and safety devices shall be provided for all parts of the equipment that present a safety hazard. The safety devices shall not interfere with the operation or maintenance of the equipment. The safety devices shall be removable to facilitate inspection, maintenance, and repair of the part.
Additional safety and health requirements shall be as specified in other paragraphs of this specification.
4.2 OSHA Approved: Where applicable, the equipment specified herein shall be in compliance with the applicable OSHA regulations and be listed by one of the OSHA accredited laboratories or approved in accordance with CFR Title 29, Chapter XVII, Part 1910 and installed in accordance with applicable NEC/NFPA requirements. Approval shall be as specified under the “Approval” and “Acceptance” criteria in the OSHA regulations Subpart “O”, Machinery and Machine Guarding para. 1910.212 and Subpart “S” Electrical, para. 1910.303 and para.
1910.399. After equipment delivery and installation and prior to testing, the Contractor shall provide a signed written Manufactures Certification (paragraph 3.3.6.8) that equipment has been manufactured and installed to OSHA CFR 1910.399 (per definition of ‘acceptable’).
5 HAZARDOUS ENERGY CONTROL:
5.1 Contractors and non-PNS government agencies (NPGAs) are hereby informed that their employees or representatives present on property under Portsmouth Naval Shipyard cognizance must adhere to Federal OSHA requirements for hazardous energy control IAW 29 CFR 1915.89 and must follow Hazardous Energy Control (HEC) procedures as identified in NAVSEA’s Occupational Safety, Health, and Environment Corporate Manual (OSHECM) Chapter 250 (latest revision), Hazardous Energy Control (HEC) when performing work under PNS contract. All HEC work to be performed by Contractors and NPGAs requires that PNS Technical Points of Contact (TPOC) and/or Contracting Officer’s Representatives (CORs) be notified of the HEC scope of work prior to starting work. Any changes or deviations in the initial scope of HEC work requires the PNS Technical Points of Contact (TPOC) and/or Contracting Officer’s Representatives (CORs) be informed of the change/deviation. Appendix 250, B-1 through B-3 of OSHECM Chapter 250 for multiple employer work identifies when Contractors and NPGAs are required to assign their Lockout/Tags-Plus Coordinator (LOTC) to coordinate HEC work with the designated LOTC.
5.2 HEC locks shall have red bodies and meet the requirements of OSHECM Chapter 250 which includes having labels or tags affixed to the HEC locks to identify who installs the HEC lock(s) and also to provide a point of contact telephone number. HEC locks shall be provided by the Contractor or NPGA for their employees use. HEC tags used for Tags-Plus HEC work shall be provided by the designated PNS LOTC to the Contractor or NPGA for their use if machinery, equipment, or systems (MES) cannot be locked out. OSHECM Chapter 250 Tags-Plus procedures will be strictly followed.
5.3 Contractors and non-PNS government agencies (NPGAs) may obtain electronic copies of OSHECM Chapter 250 (latest revision) by using the following web site:
http://www.navsea.navy.mil/shipyards/norfolk/Shared%20Documents/Chapter%20250.pdf
5.4 For service and rental contracts involving hazardous energy control work, the contractor or Non-PNS Government Agency (NPGA) shall submit to the contracting officer a certification of compliance that their personnel who need to work under hazardous energy controls have been trained IAW 29 CFR 1915.89 and must follow Hazardous Energy Control (HEC) procedures as identified in NAVSEA’s Occupational Safety, Health, and Environment Corporate Manual (OSHECM) Chapter 250 (latest revision), Hazardous Energy Control (HEC) program requirements. Contractors and NPGAs shall ensure that all their employees present on property under Portsmouth Naval Shipyard cognizance are aware of HEC program requirements.
5.5 Names and contact information for PNS LOTCs and/or the Facility Custodian will be provided by PNS Technical Points of Contact (TPOC) and/or Contracting Officer’s Representatives (CORs) set forth elsewhere in the award document.
TPOC: Mark Lumino (mark.lumino@navy.mil) 207.438-3841; 207.994.0719 COR: needs to be assigned
6 PLACE OF PERFORMANCE:
6.1 The machine disassembly, reassembly, and final accuracy test will take place in Building 300 within the Portsmouth Naval Shipyard. All work to be performed between the hours of 0700 and 1530, Monday-Friday.
6.2 All other work shall be performed at the Contractors facility.
7 PERIOD OF PERFORMANCE:
7.1 The Contractor shall complete performance under this contract no later than one year after the date the contract is awarded.
8 SECURITY:
8.1 Building 300 is within the Controlled Industrial Area (CIA) of the Portsmouth Naval Shipyard.
Additionally, building 300 is a security island. No person not known to be an American citizen of good standing and repute shall be eligible for access to Portsmouth Naval Shipyard. Proof of citizenship is required.
9 DELIVERABLES:
9.1 Responsibility For Inspection: The Contractor is responsible for the performance of all inspection requirements as specified herein. The Contractor may utilize his own facility or any other commercial facility acceptable to the Government. The Government reserves the right to perform any of the inspections set forth in the specification where such inspections are deemed necessary to assure supplies and services conform to the prescribed requirements.
9.2 Final Acceptance: Upon satisfactory completion of inspection and test of the equipment, the authorized Government Representative (Portsmouth Naval Shipyard) will sign and forward the acceptance document(s) to the paying office.