N32253_02088.22_BETA.SAM.pdf
PDF 174 KB Posted
- Attached to
- OHIO Class Submarine Emergency Diesel Generator Crankshaft Replacement Federal contract opportunity
- Solicitation number
- N32253-20-P-0029
About this file
This document contains a Justification and Approval (J&A) for other than full and open competition and the related federal contract award notice. The J&A approves increasing the value of an existing contract awarded to Fairbanks Morse, LLC for emergency diesel generator crankshaft replacement on an Ohio Class submarine. The contract was awarded on a limited competition basis due to an unusual and compelling urgency, as a loss of emergency diesel generator capability would degrade the vessel's operational readiness and the Navy's mission. The J&A was amended multiple times to increase the contract value as additional work requirements were identified. The contract was awarded and administered by Pearl Harbor Naval Shipyard and Intermediate Maintenance Facility and involved repair and maintenance services required from March to May 2020.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| N32252_02088.20_BETA.SAM.pdf | ||
| N32252_02088.18_BETA.SAM.pdf | ||
| N32253_02088.16_BETA.SAM.pdf | ||
| N32253_02088.14_BETA.SAM.pdf | ||
| N32253_02088.7_BETA.SAM.pdf | ||
| 13. N32253_02088.3_BETASAM.pdf | ||
| N32253_02088_BETASAM.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF THE NAVY
PEARL HARBOR NAVAL SHIPYARD
AND INTERMEDIATE MAINTENANCE FACILITY
667 SAFEGUARD ST SUITE 100
JBPHH, HAWAII 96860-5033
IN REPLY TO:
J&A No.: 02088.22 Code: 410.2 P.R. No.:
N3225320RC12278
Date: 09SEP2020
JUSTIFICATION AND APPROVAL
FOR USE OF OTHER THAN FULL AND OPEN COMPETITION
FAR 6.303
1. Contracting activity
Pearl Harbor Naval Shipyard & Intermediate maintenance Facility (PHNS & IMF), Contracts Division Code 400.
2. Description of the action being approved
a. Increase of value on a contract that was awarded on a limited sources basis for emergent repair actions to ’s (
) emergency diesel generator. Diesel generator overhaul includes installation of new upper and lower crankshafts. This requirement was first identified on 14FEB2020.
b. Original J&A 02088 was approved on 28FEB2020 for $2,520,352.
c. Revised J&A 02088.3 was approved on 03APR2020 for $3,367,138.
d. Revised J&A 02088.7 was approved on 15MAY2020 for $4,679,014.
e. Revised J&A 02088.11 was approved on 02JUL2020 for
$5,543,248.65.
f. Revised J&A 02088.14 was approved on 21JUL2020 for
$6,116,744.88.
g. Revised J&A 02088.16 was approved on 13AUG2020 for
$6,555,306.76.
h. Revised J&A 02088.18 was approved on 27AUG2020 for
$6,952,873.48.
i. Revised J&A 02088.20 was approved on 03SEP2020 for
$7,094,533.88.
j. This amendment increases the J&A value by $17,061, from
$7,094,533.88 to $7,111,594.88.
3. Description of supplies/services
(b) (1) (A) (b) (1) (A)
J&A No.: 02088.22
a. Diesel generator overhaul onboard the including replacement of both upper and lower crankshafts.
b. The total estimated dollar value: $7,111,594.88.
c. Period of performance: – or until work completed.
d. The basic contract was awarded for $2,470,918.88 with J&A 02088 which was approved up to $2,520,352. After award there was $49,433.12 remaining ceiling for the J&A.
i. RCC 1G two subcontractor representatives 14 day restriction of movement, $49,026
ii. Remaining balance $407.12
e. J&A 02088.3 increased the J&A value to $3,367,138 by adding
$846,379. The following in-scope RCCs were settled under its approved ceiling. These RCCs did not increase the cumulative contract value beyond J&A 02088.3 price of $3,367,138, thus a revised J&A was not required to settle the RCCs:
i. RCC 2G, weld repair and quarantine, $61,932.24
ii. RCC 4G, additional material, $67,410.74
iii. RCC 5G, prime contractor quarantine, $60,688
iv. RCC 7G, additional material, $4,761.16
v. The above RCCs total $194,792.14 that after execution left $651,586.86 remaining on the approved J&A ceiling.
f. J&A 02088.7 increased the J&A value to $4,679,014 an increase of $1,311,876 to the previously remaining $701,426.98 for a combined remaining balance of $1,963,462.86. The following in-scope RCCs were settled under its ceiling.
i. RCC 8G, for additional material, subcontractor machining and welding support, and prime labor, $1,066,850.54
ii. RCC 9G for additional prime labor have been issued to the contractor, $639,475.72
iii. RCCs 8G and 9G extended the contract performance from to .
iv. RCC 11G for additional material, $4,836.89
v. The above RCCs total $1,711,163.15 that after execution left $252,299.71 remaining on the approved J&A ceiling.
g. J&A 02088.11 increased the J&A value to $5,543,248.65. The following in-scope RCC was settled under its ceiling.
i. RCC 10G for additional subcontractor welding support, $347,865.
ii. RCC 12G for additional prime contractor, prime material, and subcontractor machining support, $621,100.06.
(b) (1) (A)
iii. The above RCCs total $968,965.06 that after execution left $148,383.42 on the approved J&A ceiling.
h. J&A 02088.14 increased the J&A by $573,496.23 to $6,116,744.88. The following in-scope RCC was settled under its ceiling.
i. RCC 13G for additional prime labor and material and additional subcontractor machinists, $640,834.01.
ii. After execution of RCC 13G, $81,045.64 was left on the approved J&A ceiling.
i. J&A 02088.16 increased the J&A by $438,561.88 to $6,555,306.76. The following in-scope RCC was settled under its ceiling.
i. RCC 14G for additional prime labor and material and additional subcontractor machinists, $429,290.92.
ii. After execution of RCC 14G, $90,316.60 was left on the approved J&A ceiling.
j. J&A 02088.18 increased the J&A by $397,566.72 to $6,952,873.48. The following in-scope RCCs were settled under its ceiling.
i. RCC 3G, prime contractor and subcontractor standby, and subcontractor expedited work schedule, $272,206.72.
ii. RCC 15G, additional prime labor and material, $137,582.
iii. After execution of RCC 3G and RCC 15G, $78,094.60 was left on the approved J&A ceiling.
k. J&A 02088.20 increased the J&A by $141,660.40 to $7,094,533.88. The following in-scope RCC was settled under its ceiling.
i. RCC 16G, prime contractor labor, $194,318.
ii. After execution of RCC 16G, $25,437 was left on the approved J&A ceiling.
l. The current J&A 02088.22 is to increase the J&A by $17,061 to account for an in-scope growth RCC that is necessary to complete the basic contract.
i. RCC 17G, prime contractor labor, estimated $42,498.
4. Statutory authority permitting other than full and open competition
10 U.S.C. 2304(c)(2). Unusual and Compelling Urgency.
5. Rationale justifying use of cited statutory authority
The Repair and Overhaul identified in Paragraph 3 above is supporting an underway limiting CASREP. The is a forward deployer supporting real world events. If urgency is not
(b) (1) (A) applied there will be an impact to the operator’s mission causing a degradation in our Navy’s defense capabilities. The Emergency Diesel Engine is an integral submarine component. Loss of Emergency Diesel Engine capability would degrade and limit operational capability and maneuvers required of a forward deployer.
The customer identified the additional requirement for RCC 17G on 08SEP2020. RCC 17G results from schedule delay caused by the Government production team. RCC 17G is with-in the scope of the base contract because the work covered is necessary to complete the work on contract. It was not possible to foresee or plan for these additional costs without incurring significant financial risk by paying for a worst case scenario up front.
6. Description of efforts made to solicit offers from as many sources as practicable
Per PHNS & IMF Engineering and Planning Department (EPD), Fairbanks-Morse owns the necessary equipment and is experienced in performing the appropriate procedures and services identified in Paragraph 3a. They are currently the only known vendor that has performed this particular repair, are the Original Equipment Manufacturer of Emergency Diesel Engine on the class submarines, and are the only known source capable of meeting this urgent requirement.
A sources sought (ID N32253-20-Q-0024) was posted on the Government Point of Entry (GPE), beta.sam.gov, on 13FEB2020. The posting sought sources “that are interested and capable of providing technical assistance for the reassembly, possible repairs, and testing of an class submarine diesel engine.”
No responses were received.
7. Determination of fair and reasonable cost.
The Contracting Officer will use cost and price analysis, including historical cost estimating relationships from previous diesel engine repair requirements to determine the final price to the Government is fair and reasonable.
8. Actions to remove barriers to future competition
PHNS & IMF will continue to solicit offers from as many sources as practicable under the circumstances of each requirement. PHNS & IMF plans to issue a Sources Sought notice for future requirements.