J-2 Category A Items Rev 1.xlsx

XLSX spreadsheet 36 KB Posted

Attached to
USNS YUKON FY21 ROH Federal contract opportunity
Solicitation number
N3220520R4011
Issued by
Department of the Navy Military Sealift Command

About this file

This document contains a contractor price breakdown for category A items required for the regular overhaul of the USNS Yukon (T-AO-202). The contractor shall provide services including hull preservation and repairs, main propulsion and engine overhauls, electrical system maintenance and upgrades, auxiliary machinery services, habitability repairs, heating and ventilation system work, drydocking, and underway replenishment equipment refurbishment. The contractor will also be responsible for establishing and maintaining physical security conditions at its private facility, as well as continuing various services for 15 days after contract completion. Pricing is provided by line item number for labor hours, materials, subcontractors, and total costs for the category A work.

View the file

Other files for this federal contract opportunity

Other files attached to USNS YUKON FY21 ROH, newest first.
File Type Posted
N3220520R4011-0002.docx DOCX document
J-2 Category A Items Rev 2.xlsx XLSX spreadsheet
J-3 Category B Items REV 2.xlsx XLSX spreadsheet
N3220520R4011 0001.docx DOCX document
J-3 Category B Items REV 1.xlsx XLSX spreadsheet
J-9 DISCLOSURE OF LOBBYING ACTIVITIES.docx DOCX document
CDRL SWI-0010.pdf PDF
J-3 Category B Items.xlsx XLSX spreadsheet
N3220520R4011.docx DOCX document
CDRL SWI-006.pdf PDF
J-13 PAST PERFORMANCE QUESTIONNAIRE.docx DOCX document
CDRL SWI-0016.pdf PDF
CDRL SWI-0012.pdf PDF
CDRL SWI-0019.pdf PDF
J-11 Dry Dock Evaluation Form.docx DOCX document
CDRL SWI-0024.pdf PDF
CDRL SWI-0022.pdf PDF
CDRL SWI-001.pdf PDF
YUKON ROH 2021 GFP.xlsx XLSX spreadsheet
J-12 Past Performance Data.doc DOC document
CDRL SWI-0021.pdf PDF
CDRL SWI-004.pdf PDF
CDRL SWI-0018.pdf PDF
J-8 REQUEST FOR SPECIFICATION CLARIFICATION.docx DOCX document
CDRL SWI-0011.pdf PDF
CDRL SWI-0023.pdf PDF
CDRL SWI-0017.pdf PDF
CDRL SWI-0014.pdf PDF
J-7 MSC Ship Repair Facility Survey.docx DOCX document
J-14 Non-Disclosure Agreement.docx DOCX document
J-10 Interport Differential.docx DOCX document
CDRL SWI-0013.pdf PDF
CDRL SWI-005.pdf PDF
J-2 Category A Items.xlsx XLSX spreadsheet
CDRL SWI-0020.pdf PDF
CDRL SWI-0015.pdf PDF
Show all 36

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Cat A Items

CATEGORY “A” ITEMS
GENERAL REQUIREMENTPRIME ContractorSUB ContractorGovt Mandated Tech Rep / SubOTHER COSTSTOTAL PRICE
ITEM NO.TITLE CAT A ITEMPRIME L/HLABOR PRICEMATERIAL PRICESUB L/HLABOR PRICEMATERIAL PRICEGovt Mand TR/Sub PriceOTHER COSTSTOTAL LABOR HOURSTOTAL MATERIAL
CATEGORY "A"
000GENERAL REQUIREMENTS
001INTENT, SCOPE, GENERAL REQUIREMENTS, AND DEFINITIONS
002TECHNICAL AND MANUFACTURER’S REPRESENTATIVES
003APPROACH, BERTH, AND MOORING REQUIREMENTS
004TESTING AND QUALITY ASSURANCE
005ELECTRICAL SAFETY PROCEDURES REQUIREMENTS
006HEAVY WEATHER PLAN
010FURNISH OFFICE FOR OVERHAUL MANAGEMENT TEAM
011FURNISH GENERAL SERVICES (T-AO)
012TELEPHONE SERVICES
013PROJECT PLANNING AND PRODUCTION STAUS MONITORING REPORT
014PREPARATION OF WEIGHT AND MOMENT REPORT
015INTEGRATED LOGISTICS AND GFM SUPPORT RQUIREMENTS
016FIRE PROTECTION AND SHIP'S SAFETY PROGRAM
017HANDLING SHIP'S STORES
018DELIVERY AND REDELIVERY OF VESSEL
019SHIPBOARD ACCESS AND SECURITY
020GAS FREE CERTIFICATES
021CLEAN AND GAS FREE TANKS, VOIDS, COFFERDAMS AND SPACES
022DOCK TRIALS AND SEA TRIALS
023HAZARDOUR WASTE DISPOSAL AT A CONTRACTOR'S FACILITY
024PHYSICAL SECURITY AT PRIVATE CONTRACTOR'S FACILITY
026VESSEL FINAL CLEANING CAT B
090DAILY COVID 19 PREVNENTION AND CONTROL SERVICES
100HULL STRUCTURES
101NDT Kingposts (ABS & USCG)
102AFFF Sprinkler Piping Replacement
103Frame 56 Expanision Joint Replacement
10402 LVL Focsle Preservation
105Deck Preservation
106Potable Water Tank Preservation
107Flight Deck AFFF Piping Replacement
108Exterior Ladderway Repairs
109Flight Deck Preservation
110Fligh Deck Safety Nets
111Cargo Tiedown Replacement
112Close Up Survey
113Ultrasonic Gauging
114PIPING REPLACEMENT CAT B
115STEEL REPLACEMENT CAT B
116Flight Deck Tiedown Replacement
117Aft Ballast Tank Preservation
118Fore Peak Preservation
119Gravity Drain Line Replacement
120Tank Preservation, 1S, 1P and 3P
121Cargo Tank Preservation 2C
122Degaussing System Removal
123Garbage Chute Removal
162Water Tight Closure Inspection (5YR)
200MAIN PROPULSION
201Port Main Engine 24K Overhaul
202Main Engine Intercooler Cleaning
203Main Engine Fuel Injector Overhaul
204Maine Engine Industrial Assist
300ELECTRICAL
302Weather Deck Kick Pipes
303AC Motor Overhauls
304Annual Cargo Console Groom
305Annual PTO Groom
331Circuit Breaker Overhauls
351Switchboard Cleaning
352Motor Control Center Cleaning
353Thermographic Survey
354Generator Cleaning and Inpsection
401Dopppler Speed Log Maintenance
402Echo Sounder Service
403OE 82 UHF Satcom Antenna Overhaul
404New Radar and ECDIS Installation
451Annual Radar Service
452Annual Ecdis Service
453Annual Gyro Service
454Annual SVDR Certification
455Annual Radio Comm Equipment Recertification
456Magnetic Compass Service
457EPIRB SERVICE (5 YR)
458Antenna Maintenance Whip, Dipole and NGW
459URT-23(D) URR-2368A HF Set Groom
460Annual Inspection of Alarms
500AUXILIARY MACHINERY
501Installation of New Distillers
502EDG Overhaul
503Ship's Service Air Compressor Groom
504Hp Air Compressor Overhaul
505Start Air Compressor Overhaul and Groom
506MSD Tank Replacement
507Vacuum Sewage Collection Piping Acid Cleaning
508Purifier Maintenance - WESTFALIA
509SSDG Exhaust Insulation Renewal
510Roller Curtain Doors Replacement
511MARPOL ANNEX VI Sample Requirement Install
512Autopilot Replacement
513Pump Overhaul
517Annual Incinerator Service
524ER OWS and Cargo OCM Certification (1YR)
535ABS Auxiliary Boiler Survey and Hydro
556Inspect Deck Cranes
558Personnel Elevator Inspection
561Gauge Calibration (2YR)
562SCBA Annual Inspection (1 YR)
563SCBA Compressor and Fill Station Inspection (1YR)
565Fixed Gas Firefighting System Inspect and Test (1 YR)
567Fixed Foam Firefighting System Inspect and Test (1 YR)
569Fire and Smoke Detection System (1 YR)
570Portable Fire Extinguisher Service (1 YR)
571Annual Fire and Smoke Damper Service (1 YR)
572Deep Fat Fryer and Range Hood Ext System (1 YR)
573Fire Hoses (1 YR)
574Fire Doors and Shutters (1 YR)
600HABITABILITY
601Joiner Bulkhead and Shower Repairs
602Carpet and Tile Replacement
651Annual Lifeboat Davit Inspection
653Annual Rescue Boat Davit Inspection
655Immersion Suit Service
656Annual Liferaft Certirication
657Accomodation Ladder Inspect and Test (1 YR)
662Deep Fat Fryer Inspection
800HEATING, VENTILATION, AC
802Misc Lagging Insulation Renewal
803Renew Air Ducting
851Annual Galley Vent & Gaylord Hood Cleaning
852Annual Laundry Vent Cleaning
853Accomodation Vent Cleaning
900DRY DOCKING
901Dry Docking Undocking
902Propeller System Maintenance and OD Box Grrom
903Propeller Shaft Weardown
904Stern Tube Seal Servicing and Maintenance
905Bilge Keel Inspection
906Spur Line Cutter and Net Inspection
907Sea Chest and Stern Tube Zincs
908Hull Freeboard Cleaning and Painting
953Anchors and Chains (5 YR)
954Rudder and Stern Frame Exam and Repair
956Overhauling Sea Valves
960Underwater Hull Cleaning and Painting
962Cathodic Protection System
963Sea Chest Marine Growth Prevention System
966Shaft Alignment Bearing Reaction Checks
1000UNREP EQUIPMENT
1001Highline Cargo Winch and Electric Motor Refurbishment
1002Heavy SP Winch and Motor Refurbishment
1003Gauge and Thermometer Calibration
1004HP Air Relief Valves
1005Saddle Winch Motor Refurbishment and Shaft Replacement

TOTAL CATEGORY "A" ITEMS

USNS YUKON (T-AO 202)CONTRACTOR PRICE BREAKDOWN
&"Arial,Bold"CATEGORY "A" ITEMSN32205-18-R-4011

ATTACHMENT J-2

Sheet1

Cat B Items

25PHYSICAL SECURITY AT PRIVATE CONTRACTOR’S FACILITY IN FORCE PROTECTION CONDITIONS BRAVO - DELTATotalTotalTotalTotalTotalTotalTotalTotalTotalTotal
7.11Cost to Establish Condition Bravo1Days
7.12Cost to Establish Condition Charlie1Days
7.13Cost to Establish Condition Delta1Days
7.11Daily Rate to Maintain Condition Bravo1Days
7.12Daily Rate to Maintain Condition Charlie1Days
7.13Daily Rate to Maintain Condition Delta1Days
WI 025 SUBTOTAL
030CONTINUATION OF SERVICESTotalTotalTotalTotalTotalTotalTotalTotalTotalTotal
7.1Parent work item 010 “Overhaul Management Team Services”.15Days
7.2Parent work item 011” General Services for the Ship”15Days
7.3Parent work item 012 “Telephone Services15Days
7.4Parent work item 013 “Project Planning and Monitoring”15Days
7.5Parent work item 016 “Fire Protection and Ship’s Safety”15Days
7.6Shipboard Access and Security15Days
7.7Parent work item 020 “Gas Free Certificates”15Days
15Days
WI 030 SUBTOTAL

File details come from the government source that posted it. Updated .