Amendment_0001_-_Zeus_Rescue_Boat.pdf

PDF 42 KB Posted

Attached to
USNS ZEUS Rescue Boat and Davit System Federal contract opportunity
Solicitation number
N32205-16-T-4017
Issued by
Department of the Navy Military Sealift Command

About this file

Amendment 0001

View the file

Other files for this federal contract opportunity

Other files attached to USNS ZEUS Rescue Boat and Davit System, newest first.
File Type Posted
Zeus_Rescue_Boat_and_Davit_System_Bidders_Questions_6-8.docx DOCX document
Zeus_Rescue_Boat_and_Davit_System_Bidders_Questions.docx DOCX document
N32205-16-T-4017_Solicitation.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

N623876321N7002

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to change the follow ing:

1. Revise paragraph 2.5.1

2. Change the delivery date for the installation draw ings

3. Add three attachments (available upon w ritten request)

4. Revise instructions to offerors to provide a preliminary sketch of the rescue boat and davit system w ith their technical proposal.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 5

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 02-Feb-2016

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N32205-16-T-4017

X 9B. DATED (SEE ITEM 11)

22-Jan-2016

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

02-Feb-2016

CODE

MILITARY SEALIFT COMMAND NORFOLK

471 EAST C STREET, BLDG SP-64 NAVAL STATI

NORFOLK VA 23511-2419

N32205 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N32205-16-T-4017

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 1449 - CONTINUATION SHEET

The following have been added by full text:

SUMMARY OF CHANGES

Amendment 0001

USNS ZEUS RESCUE BOAT SYSTEM

Item Requirements List

Paragraph 2.5.1 has been changed from:

2.5.1 Transverse extent is 36 ft. from the deck edge to the inboard bulkhead. When stowed, the rescue boat and davit must not extend outboard of the deck edge. The transverse location of the complete and installed assembly shall provide clear fore and aft passage under or around the stowed rescue boat.

Paragraph 2.5.1 has been changed to:

2.5.1 Transverse extent is 17.5 ft. from the deck edge to the inboard bulkhead. When stowed, the rescue boat and davit must not extend outboard of the deck edge. The transverse location of the complete and installed assembly shall provide clear fore and aft passage under or around the stowed rescue boat.

Paragraph 9.1 has been changed from:

9.1 Mechanical, electrical, and structural installation requirements for the rescue boats, davits, and winches, as well as the interface drawings required shall be provided in PDF and Autocad to the TPOC no later than four weeks after contract award.

Paragraph 9.1 has been changed to:

9.1 Mechanical, electrical, and structural installation requirements for the rescue boats, davits, and winches, as well as the interface drawings required shall be provided in PDF and Autocad to the TPOC no later than two weeks after contract award.

The Deliverables/Deliverables Due Date Chart has been changed from:

The Deliverables/Deliverables Due Date

Section Deliverable Required Due Date 2.1, 2.2, 2.3 Documentation of USCG Approval Prior to Government Acceptance of the Davits and Winches and Boat

5.2 List of Recommended Spare Parts At Time of Delivery

6.3 Material Certification Documents At Time of Delivery of the System 7 Schedule of Pending Tests Four (4) Weeks After Contract Award

7.1.3 Test Certificates Four (4) Weeks After Factory Tests Are Conducted

8.1 Operation and Maintenance Manuals At Time of Delivery

8.2 Recommended Maintenance Plans At Time of Delivery

10.1 Installation Drawing(s) Two weeks after contract award

*NOTE - All deliverables shall be submitted as original paper certificates and PDF of same to the Technical Point of Contact (TPOC)

The Deliverables/Deliverables Due Date Chart has been changed to:

The Deliverables/Deliverables Due Date

Section Deliverable Required Due Date 2.1, 2.2, 2.3 Documentation of USCG Approval Prior to Government Acceptance of the Davits and Winches and Boat

5.2 List of Recommended Spare Parts At Time of Delivery

6.3 Material Certification Documents At Time of Delivery of the System 7 Schedule of Pending Tests Four (4) Weeks After Contract Award

7.1.3 Test Certificates Four (4) Weeks After Factory Tests Are Conducted

8.1 Operation and Maintenance Manuals At Time of Delivery

8.2 Recommended Maintenance Plans At Time of Delivery

10.1 Installation Drawing(s) Two weeks after contract award

*NOTE - All deliverables shall be submitted as original paper certificates and PDF of same to the Technical Point of Contact (TPOC)

Attachments have been changed from:

16. Attachments

Attachment 1: Available Lube Oil Products

Attachment 2: Logistics Support Requirements

Attachment 3: General Arrangement Drawings for USNS ZEUS (available by written request)

Attachment 4: General Arrangement Drawings for USNS ZEUS (available by written request)

Attachments have been changed to:

16. Attachments

Attachment 1: Available Lube Oil Products

Attachment 2: Logistics Support Requirements

Attachment 3: General Arrangement Drawings for USNS ZEUS (available by written request)

Attachment 4: General Arrangement Drawings for USNS ZEUS (available by written request)

Attachment 5: CAD Drawing of Deck for USNS ZEUS (available by written request)

Attachment 6: Photo #1 of Footprint Area for USNS ZEUS Rescue Boat (available by written request)

Attachment 7: Photo #2 of Footprint Area for USNS ZEUS Rescue Boat (available by written request)

The following have been modified:

52.212-1 (ADDENDUM) ADDITIONAL INSTRUCTIONS TO OFFERORS--COMMERCIAL ITEMS

After receipt of quotes, the Government may without notice, negotiate with and, if desired, seek a quote revision from as many or as few quoters as it, in its discretion, deems appropriate.

General Instructions

Quoters shall submit quotes:

Price Quote – Should be submitted separate from Technical.

Technical Quotes – Shall include preliminary sketch of rescue boat and davit system Past Performance

Price and Other Business Considerations

1. A separate unit price and extended price must be submitted for each line item in above CLINs.

2. Terms of any express warranty.

3. Any discount terms.

4. A completed copy of the representations and certifications at FAR 52.212-3 Alternate I and DFARS

252.212-7000 or a statement stating that they are available via the SAM website, https://www.sam.gov/portal/public/SAM/.

5. Remittance address, Tax Identification Number, DUNS number and Cage Code.

6. Quoter shall state its ability to meet the required delivery date of 31 August 2016.

7. Responses to this solicitation are due 23 February 2015 at 1000 local time, Norfolk, VA. LATE QUOTES

MAY NOT BE CONSIDERED FOR EVALUATION. Quotes may be e-mailed to thomas.j.martin2@navy.mil . Please reference the solicitation number on your proposal.

8. Quotes submitted in response to this solicitation shall not contain nor be subject to the quoter’s standard commercial terms and conditions. Any offer submitted in response to this solicitation which includes the quoter’s standard commercial terms and conditions may be considered a material defect and may be rejected as being non-responsive to the solicitation.

Technical Quotes

For Parts: Technical description of the items being offered in sufficient detail to evaluate compliance with the requirements in the solicitation. This may include product literature, or other documents, if necessary.

Past Performance

To be considered acceptable for past performance, a search of the PPIRS shall reveal no negative past performance information for the recent and relevant records or in the event that there are no recent and/or relevant PPIRS records, the quoter’s past performance record shall be considered “unknown.” In the context of acceptable or unacceptable, “unknown” past performance shall be considered “acceptable.” To be considered recent, the effort must have been completed within the previous three (3) years from date of this draft award notice. To be considered relevant the record should be similar in terms of scope, complexity, and magnitude. At the quoter’s discretion, additional past performance may be submitted with the quote as a supplement to PPIRS. If furnished, this submission will be evaluated in accordance with the procedures described above

BASIS FOR AWARD:

Award will be made to the responsible, technically acceptable quoter, whose quote, conforming to the Request for Quotation, offers the lowest evaluated price and has been determined to have acceptable past performance.

(End of Provision)