N0025318Q0236_AMEND_3_NDT_CERT-TRNG.pdf
PDF 26 KB Posted
- Attached to
- NDT Training and Certification
- Solicitation number
- N0025318Q0236
About this file
NDT CERT AND TRAINING AMEND 3 - EXTEND CLOSING DATE
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to provide questions, answ ers and clarif ications regarding Statement of Work and extend the closing date.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 4
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 13-Aug-2018
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N0025318Q0236
X 9B. DATED (SEE ITEM 11)
27-Jul-2018
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
13-Aug-2018
CODE
NAVAL UNDERSEA WARFARE CENTER
ATTN: MELISSA REMIGIO
MELISSA.REMIGIO@NAVY.MIL
610 DOWELL ST BLDG 206
KEYPORT WA 98345-7610
N00253 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N0025318Q0236
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
VENDOR'S QUESTIONS AND ANSWERS
QUESTIONS:
1. Comment: Administration of the Level II training and testing can be accomplished in a condensed period, but the experience will take considerable time. An individual cannot be certified until all SNT-TC-1A requirements are met:: 1) vision exam, 2) training, 3) experience, 4) general exam, 5) specific exam, and 6) practical exam. All but
#3 "experience" can be accomplished in a tight window. The experience will take a longer period for the Level II candidate.
2. SOW Pargraph 2.7. (SF 1449, Item 1) Tech pub 271 requires ANST-TC-1A but says MIL-STD-410 (NAS410) is equivalent.. SOW Para 2.7 says ASNT-TC-1A and NAS 410. The requirements in NAS 410 are more stringent.
Is the individual to be trained from trainee to Level II, or is the individual a current Level I going to Level II?
Training hour requirements in the two documents are not the same. Assuming an individual is going from trainee to
Level II. For Penetrant, SNT-TC-1A requires 12 hours, while NAS410 requires 32 hours.. For Magnetic Particle, SNT-TC-1A requires 20 hours, while NAS410 requires 32 hours. If done strictly to SNT-TC-1A, it would be possible to complete in 6 days. For NAS410, each method would require 5 days to complete training and testing necessitating 2 weeks (10 business days). Once I know which you specifically need, then I can provide a price for on-site (Washington), or at my facility.
You are probably aware, but I just want to ensure you know experience hours for the two documents are also slightly different as well. SNT-TC-1A requires 400 NDT hours for Level II of which 210 must be in penetrant.
NAS410 Rev 4 requires all 400 hours in PT. For MT, SNT-TC-1A requires 530 hours of NDT experience for Level
II of which 280 hours in MT, while NAS410 requires all 530 hours in MT. Will there be someone who is a current
Level II, to oversee the work of the trainee or Level I obtaining the necessary NDT experience.
3. SOW 2.7.3 (SF 1449, Item 2). Is this just for MT and PT methods? Is this strictly intended for certification records, or are you looking for an audit of the program including process control. A program audit (certification records, processes to ) would take substantially more time 5 days vs 1 or 2.
4. SF 1449, Item 3. Missing Exhibit A. CDRL For 1423-1.
5. SF 1449, Item 4. Is the Level III training to be in both Penetrant and Magnetic particle? Is this to be conducted at your facility or the vendor's.
6. SF 1449, Item 5. Is this the same individual or another separate from Item 4 above.
7. SF 1449, Item 6. Three (3) oversights to be done for $2500.00 or is this each? Travel and one day would take up
$2500.00.
ANSWERS:
We are soliciting for NDT Level II Training and Certification including Level III Oversight (correction applied on
FBO posted description). Also, the SF 1449, item 5 should state; Provide firm fixed price for Level II Training and
Certification (correction applied).
1) The individual is currently a certified Level II with all experience hours met.
2) The individual is currently a certified Level II with all experience hours met. Requesting refresher training and recertification (2.7.1, 2.7.2)
3) PT & MT methods only. Level III annual review shall include NDT quality assurance and quality control processes, procedures, certification and record keeping (2.7.3)
4) SF 1449, ITEM 3 is not missing. Exhibit A. / CDRL is a separate attachment and was posted in FBO as a separate document.
5) Level II Training and Certification only with Level III Oversight. All Training, Certification and Oversight shall be conducted at NUWC Keyport facility.
6) Level II Training/Certification will be limited to (1) one individual (SF 1449, item 5).
7) Not to exceed $2500 for each year the service is performed (SF 1449, item 6).
SECTION SF 1449 - CONTINUATION SHEET
SOLICITATION/CONTRACT FORM
The required response date/time has changed from 13-Aug-2018 02:00 PM to 17-Aug-2018 02:00 PM.
SUPPLIES OR SERVICES AND PRICES
CLIN 0003
The CLIN extended description has changed from:
Data in accordance with Exhibit A. Contract Data Requirements List, DD Form 1423-1
To:
Data in accordance with Exhibit A. Contract Data Requirements List, DD Form 1423-1*** EXHIBIT A. CDRL document was posted through www.fbo.gov
CLIN 0005
Provide firm fixed price for Level III Training and Certification for (1) one government employee, IN
ACCORDANCE WITH ATTACHED STATEMENT OF WORKThis is an Option Item only and in no way are purchased or guaranteed under the resulting contract. Work cannot be started or performed under the Option Items without Option Exercise by the Contracting Officer in accordance with FAR Clause 52.217-7.
Provide firm fixed price for Level II Training and Certification for (1) one government employee, IN
ACCORDANCE WITH ATTACHED STATEMENT OF WORKThis is an Option Item only and in no way are purchased or guaranteed under the resulting contract. Work cannot be started or performed under the Option Items without Option Exercise by the Contracting Officer in accordance with FAR Clause 52.217-7.
CLIN 0006
Provide annual Oversight in accordance with the attached Statement of Work. Exact amount for additional oversight service if any is unknown; however, the total cost will not exceed $2,500.00. At the time it is exercised, the
Government will identify the exact amount required at the time of option exercise. FAR Clause 52.213-3 applies only to this CLIN. If option is exericsed, pricing will become Firm Fixed Price.This is an Option Item only and in no way are purchased or guaranteed under the resulting contract. Work cannot be started or performed under the Option
Items with Option Exercise by the Contracting Officer in accordance with FAR Clause 52.217-7.
Provide annual Oversight in accordance with the attached Statement of Work. Exact amount for additional oversight service if any is unknown; however, the total cost will not exceed $2,500.00. At the time it is exercised, the
Government will identify the exact amount required at the time of option exercise. FAR Clause 52.213-3 applies only to this CLIN. If option is exericsed, pricing will become Firm Fixed Price.*** NOT TO EXCEED $2500 FOR
EACH YEAR THE SERVICE IS PERFORMED***This is an Option Item only and in no way are purchased or guaranteed under the resulting contract. Work cannot be started or performed under the Option Items with Option
Exercise by the Contracting Officer in accordance with FAR Clause 52.217-7.