Text version
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
The following items are applicable to this modification:
The purpose of this amendment is to correct Section L to incorporate additional tables.
1. Section L – Instructions, Conditions, and Notices to Bidders is hereby corrected to add additional tables.
From:
3.
ODC's - Offerors are instructed to use the travel and material/supplies as specified below, to generate their cost proposals. If the contractor contemplates charging directly to this contract, any other direct costs besides the material defined herein, they must include an explanation and estimate of such costs in their proposal. This includes acquisition, lease, depreciation, usage charges, etc. of any Government Property, office equipment or Automated Data Processing Equipment.
TABLE 2
Other Direct Costs
| Other Direct Costs (ODC’s) |
| Base Year |
| Option One |
| Option Two |
| Option Three |
| Option Four |
| Travel (Not-to-exceed)* |
| $29,149.80 |
| $30,024.29 |
| $30,925.02 |
| $31,852,77 |
| $32,808.35 |
| Material/Supplies (Not-to-exceed)* |
| $8,208,000.00 |
| $6,998,460.00 |
| $9,233,715.00 |
| $6,996,750.00 |
| $8,336,409.60 |
| Total |
| $8,237,149.80 |
| $7,028,484.29 |
| $9,264,640.02 |
| $7,028,602.77 |
| $8,369,217.96 |
*Inclusive of any associated indirect rates
To:
3.
Materials - Offerors are instructed to use the material/supplies as specified below, to generate their cost proposals. If the contractor contemplates charging directly to this contract, any other materials besides the material defined herein, they must include an explanation and estimate of such costs in their proposal. This includes acquisition, lease, depreciation, usage charges, etc. of any Government Property, office equipment or Automated Data Processing Equipment.
TABLE 2
Materials
| Materials |
| Base Year |
| Option One |
| Option Two |
| Option Three |
| Option Four |
| Material/Supplies (Not-to-exceed)* |
| $10,157,400.00 |
| $7,698,306.00 |
| $10,157,086.50 |
| $7,696,425.00 |
| $9,170,050.56 |
| Total |
| $10,157,400.00 |
| $7,698,306.00 |
| $10,157,086.50 |
| $7,696,425.00 |
| $9,170,050.56 |
4. ODC's - Offerors are instructed to use the travel as specified below, to generate their cost proposals. If the contractor contemplates charging directly to this contract, any other direct costs besides the defined herein, they must include an explanation and estimate of such costs in their proposal. This includes acquisition, lease, depreciation, usage charges, etc. of any Government Property, office equipment or Automated Data Processing Equipment.
Table 3
Other Direct Costs
| Other Direct Costs (ODC’s) |
| Base Year |
| Option One |
| Option Two |
| Option Three |
| Option Four |
| Travel (Not-to-exceed)* |
| $29,149.80 |
| $30,024.29 |
| $30,925.02 |
| $31,852,77 |
| $32,808.36 |
| Total |
| $29,149.80 |
| $30,024.29 |
| $30,925.02 |
| $31,852,77 |
| $32,808.36 |
2. Additionally, the Cost Summary Format called out in Section J is hereby provided.
3. All other terms and conditions of the solicitation remain the same.
4.
Direct any questions or concerns to Yolanda Riley at yolanda.riley@navy.mil or 301-744-6656.
File details come from the government source that posted it. Updated .