Amendment 0001 PPI Response.pdf

PDF 414 KB Posted

Attached to
Temporary Structure - Naval Station Norfolk - Amendment 002 Federal contract opportunity
Solicitation number
N0016721R0017
Issued by
Department of the Navy Naval Sea Systems Command

View the file

Other files for this federal contract opportunity

Other files attached to Temporary Structure - Naval Station Norfolk - Amendment 002, newest first.
File Type Posted
Amendment 0002.pdf PDF
N00016721R0017 Amendment 0001.pdf PDF
Attachment A - Pre Proposal Inquiries.xlsx XLSX spreadsheet
Attachment B - Safety Data Sheet.docx DOCX document
Attachment C - Price Proposal Form.xlsx XLSX spreadsheet
N0016721R0017.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GOVERNMENT RESPONSE

Doc Sec / Page Question

N0016721R0017 -

Solicitation

SF 1442-

12 A

I see that in 12 A., “Yes” is marked for the performance and payment bonds. What are the bond requirements? (owner, liquidated penalties, & maintenance term)

For Payment/ Performance Bonds FAR 52.228-15(b) states

Amount of required bonds. Unless the resulting contract price is valued at or below the threshold specified in

Federal Acquisition Regulation 28.102-1(a) on the date of award of this contract, the successful offeror shall furnish performance and payment bonds to the

Contracting Officer as follows:

(1) Performance bonds (Standard Form 25). The penal amount of performance bonds at the time of contract award shall be 100 percent of the original contract price.

(2) Payment Bonds (Standard Form 25A). The penal amount of payment bonds at the time of contract award shall be 100 percent of the original contract price.

N0016721R0017 -

Solicitation

52.228-

15/ p. 26

Performance/Payment Bond amount is 100%? Performance bonds (Standard Form 25). The penal amount of performance bonds at the time of contract award shall be 100 percent of the original contract price.

Attachment B Is Attachment B an older version? Would you all want EMR, DART, and TRC rates from the last three years (18’ – 20’)?

EMR, DART and TRC rates shall not be submitted for subcontractors.

N0016721R0017 -

Solicitation

Page 3/

Section D

Is the proposal submission only via email OR is it submitted through email & CDROM

(physical mailing)?

Email

N0016721R0017 -

Solicitation

Page 3/

Section C

On SAM.gov, it is stated that the proposal is due on Nov. 4 at 2 PM. However, the due time in the RFP is 10 AM. What is the correct Due time?

The due date is November 4th at 10:00 a.m.

N0016721R0017 -

Solicitation

Is there a separate RFP to provide heat to this structure? There is not a separate RFP to provide heat to the structure. Heating the structure is not required.

Electricity will be run to the structure and connected to the structure after the structure is erected, and is covered by a separate effort. This RFP does not require running electricity to the structure.

RFP Questions - Sustainment, Restoration and Repair (SRM) Services

File details come from the government source that posted it. Updated .