Solicitation Questions Answered.docx
DOCX document 22 KB Posted
- Attached to
- Chevalier Lathe Federal contract opportunity
- Solicitation number
- N00167-21-Q-0076
About this file
This document contains a solicitation for a Chevalier lathe and answers to questions about the solicitation. The Naval Surface Warfare Center Carderock Division is seeking a firm fixed price purchase order for a Chevalier Model FBL-530A MC lathe. The solicitation incorporates FAR and DFARS clauses. Quotes are due by April 14, 2021 and the Navy will award a contract to the responsible offeror submitting the lowest priced technically acceptable quote representing the best value. The government will provide a chuck, CNC program, and tooling for testing and the power requirement of 225 amps at 220 volts is acceptable.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment 3 - Machine Foundation Footprint.pdf | ||
| Attachment 2 - Shop Layout.pdf | ||
| Attachment 5 - Sample Requirements.pdf | ||
| Attachment 1 - Chevalier Lathe Specs.docx | DOCX document | |
| Attachment 4 - Acceptance Checklist.docx | DOCX document | |
| JA REDACTED.pdf | ||
| N00167-21-Q-0076.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Question 1 Paragraph 10.1 Acceptance Testing - There is no chuck required in this request, however the test cannot be conducted without one, will the end user be providing the chuck?
Answer 1 Yes, the Government will provide for use an existing chuck. The chuck that we will be using is an (A2-15 32” Manual 4-Jaw chuck with a 7.7” bore).
Question 2 Is the Government providing the program and tooling for this fabricated test part?
Answer 2 Yes, the Government will provide the CNC program and tooling for a test part.
Question 3 Paragraph 4.1 Power Requirement lists maximum amperage of 100 Amps at 220V. However, the Chevalier Model FBL-530A MC draws 225 amps @ 220 volts. Please advise if you will be amending this specification, or how we should address this in our offering.
Answer 3 225 Amps @ 220 volts is acceptable. The Government has power readily available at the installation location.