Amendment_0007_to_Solicitation_N0010417RK091.pdf

PDF 366 KB Posted

Attached to
Cable Assembly, ADCAP F/MK48 MODS 6&7
Solicitation number
N0010417RK091
Issued by

About this file

Amendment 0007 to solicitation N0010417RK091

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

N5006316NA034

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

1) Section F, Deliveries of Performance and Section E Production Lot Test Samples(GOV’T TESTING) (March 2014) are revised as show n on the continuation page.

2) The hour and date specif ied for receipt of offers is extended to 2:00 PM local time on 19 January 2018.

3) All other terms and conditions remain unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 7

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 16-Jan-2018

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N0010417RK091

X 9B. DATED (SEE ITEM 11)

28-Jul-2017

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

16-Jan-2018

CODE

NAVSUP WEAPON SYSTEMS SUPPORT

KIRSTEN BARNES, CODE N742.13

5450 CARLISLE PIKE

P.O. BOX 2020

MECHANICSBURG PA 17055

N00104 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N0010417RK091

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION A - SOLICITATION/CONTRACT FORM

The required response date/time has changed from 17-Nov-2017 02:00 PM to 19-Jan-2018 02:00 PM.

SECTION E - INSPECTION AND ACCEPTANCE

The following have been modified:

SECTION E

PRODUCTION LOT TEST SAMPLES (GOV’T TESTING) (March 2014)

1. Test samples are required from each production lot. A production lot shall consist of: Net deliverable quantity, plus additional units for Lot Acceptance Test, in accordance with Section B. The performance, tests, and/or other characteristics, which the sample units must meet, shall be in accordance with the requirements of Section C of this contract.

2. The production lot(s) must be manufactured and presented to the Government Quality Assurance Representative (QAR) with all documentation required by section B. The documentation (WAWF-RRs and Ammunition Data Card printed from WARP) accompanying the production lot test samples shall contain the contract number, item, lot number identification, DODIC, NSN, and serial numbers. The presentation of the lot shall be made to the QAR 270 calendar days after date of contract to select the production test samples. If FAT is required then presentation of lot samples shall be made IAW timetable in Section F. The samples shall be selected, at random, from each production lot, by the QAR within 48 hours for resident QARs, and 7 calendar days for non-resident QARs after presentation of the lot.

NOTE 1: Sample units removed for testing from different lots shall not be commingled.

NOTE 2: The Contractor shall submit a Certificate of Compliance IAW 6894560 REV B, Para 6.5., as specified in the Contract Data Requirements List (DD Form 1423, sequence number A004).

3. After the selection of the production lot samples and all required data, the samples shall be furnished and shipped by the Contractor to the testing activity set forth in Section F within 15 calendar days of selection at no additional charge to the Government. The production lot test samples shall not be considered received until all data necessary to evaluate the samples is received.

4. The following activities will conduct production lot testing: NAVAL UNDERSEA WARFARE CENTER DIVISION KEYPORT IAW Table II of 6894520 REV C. Shock testing will be conducted by NAVAL UNDERSEA WARFARE CENTER DIVISION NEWPORT IAW 6894520 REV C and 6894560 REV B.

5. Disposition of Production Lot Test Samples - Units submitted for Production Lot Testing are subject to destructive testing. These units cannot be used to meet fleet support requirements. Samples tested will not be returned to the Contractor. However, in the event there is a failure, or samples are rejected for some other reason, the Contractor may request the return of units not destroyed during testing and/or residual material for disposition/examination. The written request to return rejected units/material shall be received by the Contracting Officer, with a concurrent copy to the testing activity, within 15 calendar days after notification of rejection. Any units/material returned will be at the Contractor's expense.

6. All other contractual requirements, such as acceptance, shipment, and payment will not be accomplished until the production lot test samples have been tested, approved, and released for service use. The Contractor shall not make shipment of the production lot until receipt of written notification of approval by the Contracting Officer.

7. The only valid and contractually binding notification of production lot approval, conditional approval, or disapproval shall be in writing and issued by the Contracting Officer. This notification shall be made to the

Contractor within 60 calendar days after receipt of the production lot test samples and all necessary data are received by the Government Testing Activity. Upon receipt of written notice accepting a production lot, shipment shall be made as soon as possible and no later than 15 calendar days after receipt of such notice.

a) Any notice of approval or conditional approval shall not relieve the Contractor from complying with all requirements of the specifications and all other terms and conditions of this contract.

b) A notice of conditional approval shall state any further action required of the Contractor. In the event the test sample fails to meet the requirements of the specification or drawing, the Contractor shall submit a Failure Analysis and Corrective Action Report (DD Form 1423, sequence number, A003) with all associated costs and expenses to be borne solely by the Contractor.

c) A notice of disapproval shall cite reasons for such. If any production lot test sample(s) is disapproved by the Government and at the Contractor’s sole cost and expense, the Contractor may be required, at the option of the Government, to submit an additional production lot test sample(s) for test. After each notification by the Contracting Officer to submit an additional production lot test sample(s), the Contractor shall - at no additional cost to the Government - make any necessary changes, modifications, or repairs to the production lot or the Government QAR may be required to select another test sample for testing. Such additional test sample(s) shall be furnished to the Government under the terms and conditions and within the time specified in the notification. The Government shall take action on this test sample(s) within 60 calendar days after receipt. The cost of each additional approval, and all costs and expenses related to such test(s) shall be borne solely by the Contractor.

Retest Cost for Item 0001 is: $64,000.00 (per lot) to perform A-Cable testing. Shock testing will be conducted by NUWC Newport for a cost of $5,000.00 (per lot). The Government reserves the right to require an equitable decrease of the contract price for any extension of the delivery schedule necessitated by additional tests.

INSPECTION AND ACCEPTANCE OF TEST PLANS / PROCEDURES

1. The Contractor shall submit a test plan/procedure for Government approval/disapproval as specified in the Contract Data Requirements List (DD Form 1423, sequence number, A001). The test plan shall be submitted within 60 calendar days after contract award date. The Acceptance Test Plan shall identify that test fixtures are available for use at the Contractor’s Facility.

2. Notification of test plan approval, conditional approval, or disapproval shall be in writing and issued by the Contracting Officer. This notification shall be made to the Contractor within 15 calendar days after receipt of the plan/procedure.

3. The notice of approval or conditional approval shall not relieve the Contractor from complying with all requirements of the specifications and all other terms and conditions of this contract.

4. A notice of conditional approval shall state any further action required of the Contractor.

5. A notice of disapproval shall cite the reasons for such. If the plan or procedure is disapproved by the Government, the Contractor may be required, at the option of the Government, to submit a revised plan or procedure for evaluation. After each notification by the Government to submit a revised plan or procedure, the Contractor shall, at no additional cost to the Government, make any necessary revisions or modifications to the plan or procedure. Such revisions shall be furnished in accordance with terms and conditions and within the time specified in the notification. The Government shall take action on the resubmitted plan or procedure within the time specified above. The Government reserves the right to require an equitable adjustment of the contract price for any extension of the delivery schedule necessitated by resubmission of the plan or procedure.

6. If the Contractor fails to deliver the plan or procedure within the time specified, or if the Contracting Officer disapproves any plan or procedure, the Contractor shall be deemed to have failed to make delivery within the meaning of the "Default" clause of this contract, and this contract shall be subject to termination for default.

However, failure of the Government in such an event to terminate the contract shall not relieve the Contractor of the responsibility to meet all requirements of the contract including delivery of any first article sample(s), data requirements, and/or production quantities.

7. There is hereby created an option for the Government to waive the requirement for submission of a plan or procedure. If the offeror has had its plan previously approved by the Government, the following information shall be furnished:

Approved by__________________________ Date of approval___________________

Contract number and contractor under which plan/procedure was approved__________________.

Test Plan number, revision date and NSN for which the item was previously approved_____________.

8. If the submission of the plan or procedure is waived, the previously approved plan or procedure shall apply to the contract.

INSPECTION AND ACCEPTANCE

Production Quality Assurance of all items to be furnished hereunder shall be made by the cognizant Government Inspector at the contractor's or sub-contractor's plant. Quality Assurance Inspection System to be in accordance with ISO-9001, ANSI/ASQC or

MIL-I- 45208.

NOTE:

Acceptance or rejection shall be accomplished by the cognizant GQAR based upon his own inspection(s) and the results of the First Articles or Periodic Production and/or Acceptance Samples from the testing activity to the GQAR via Procurement Contracting Officer (PCO).

QUALITY ASSURANCE REQUIREMENTS

An inspection lot shall consist of items manufactured under essentially the same conditions and at essentially the same time. Prior to submittal of each inspection lot to the Government Representative, the contractor shall provide inspection/or test records that assure the units presented have passed all inspections and tests required by the applicable drawings, specifications and quality assurance documentation. Unless specified otherwise, as a minimum this inspection and testing shall be in accordance with MIL-STD-105 (MIL-STD-1916), latest revision at issue date of solicitation, inspection Level II, with 100% inspection for critical characteristics, 1.0 AQL (Acceptance Quality Level), for major characteristics and 2.5 AQL for all other characteristics. All defects of the same class will be considered collectively when determined compliance with applicable AQL.

SECTION F - DELIVERIES OR PERFORMANCE

The following have been modified:

SECTION F

DELIVERIES OF PERFORMANCE

Unless otherwise indicated in this contract, accelerated deliveries are desirable and acceptable at no additional cost to the Government. The addresses for the activities designated to receive supplies are listed below:

LINE / SUBLINE ITEM and QTY SHIP TO:

0001AB 4 EA (FAT)

NUWC Keyport

UIC: N00253

ATTN: Darioush Sarraf

610 Dowell Street

Keyport, WA 98345-7610

After completion of Keyport testing then ship to:

NUWC Newport

UIC: N66604

ATTN: Mike Cullinane/George Kotas

1176 Howell Street

Newport, RI 02841

0001AC 4 EA (LAT)

NUWC Keyport

UIC: N00253

ATTN: Darioush Sarraf

610 Dowell Street

Keyport, WA 98345-7610

After completion of Keyport testing then ship to:

NUWC Newport

UIC: N66604

ATTN: Mike Cullinane/George Kotas

1176 Howell Street

Newport, RI 02841

0001AD TBD TBD

NOTES:

Please contact NAVSUP WSS Contracting Officer (Code N742.13) 60 days prior to shipment to confirm delivery destination. QAR is not authorized to approve items for shipment; approval for shipment is only authorized after the test validation reports have been reviewed and approved by the NAVSUP WSS PCO.

Shipment/Performance Notice Distribution - The cognizant DCMA office shall provide automated

Shipment/Performance Notice (PJJ card) to the Commanding Officer, Attn: Code 4511, NAVSUP

Logistics Operations Center, Mechanicsburg, PA 17055-0735 DOD Address Code N49935

(Routine ID Code NCB), (Communications ID RUSAACM), in support of the Ordnance Information

System-Wholesale (OIS-W, formerly CAIMS).

FAR 52.211-8 TIME OF DELIVERY

(a) The Government requires delivery to be made according to the following schedule:

FIRST ARTICLE REQUIRED DELIVERY SCHEDULE

Item Quantity Days Item Quantity Days

0001AB 4 EA (FAT) 270 DAC A001 (Test Procedure)

1 Set 60 DAC

0001AC 4 EA (LAT) 360 DAFATA A002 (Test Report) Per Lot A/R

0001AD 30 EA 457 DAFATA A003 (Failure Analysis)

A/R A/R

0001AE 30 EA 457 DAFATA A004 (Certificate of Compliance)

Per Lot A/R

0001AF 40 EA 457 DAFATA A005 (Progress Reports)

Monthly A/R

KEY: DAC = Days After Contract DAFATA = Days After First Article Test Approval

FIRST ARTICLE WAIVED DELIVERY SCHEDULE

0001AC 4 EA (LAT) 270 DAC A001 (Test Procedure)

1 Set 60 DAC

0001AD 30 EA 367 DAC A002 (Test Report) Per Lot A/R

0001AE 30 EA 367 DAC A003 (Failure Analysis)

A/R A/R

0001AF 40 EA 367 DAC A004 (Certificate of Compliance)

Per Lot A/R

A005 (Progress Reports)

Monthly A/R

KEY: DAC = Days After Contract

The Government will evaluate equally, as regards time of delivery, offers that propose delivery of each quantity within the applicable delivery period specified above. Offers that propose delivery that will not clearly fall within the applicable required delivery period specified above will be considered non-responsive and rejected. The Government reserves the right to award under either the required delivery schedule or the proposed delivery schedule, when an offeror offers an earlier delivery schedule than required above. If the offeror proposes no other delivery schedule, the required delivery schedule above will apply.

OFFERORS PROPOSED DELIVERY SCHEDULE – FIRST ARTICLE REQUIRED DELIVERY SCHEDULE

KEY: DAC = Days After Date of Contract DAFATA = Days After First Article Test Approval

OFFERORS PROPOSED DELIVERY SCHEDULE – FIRST ARTICLE WAIVED DELIVERY SCHEDULE

KEY: DAC = Days After Date of Contract

(b) Attention is directed to the Contract Award provision of the solicitation that provides that a written award or acceptance of offer mailed, or otherwise furnished to the successful offeror, results in a binding contract. The Government will mail or otherwise furnish to the offeror an award or notice of award not later than the day award is dated. Therefore, the offeror should compute the time available for performance beginning with the actual date of award, rather than the date the written notice of award is received from the Contracting Officer through the ordinary mails. However, the Government will evaluate an offer that proposes delivery based on the Contractor's date of receipt of the contract or notice of award by adding (1) five calendar days for delivery of the award through the ordinary mails, or (2) one working day if the solicitation states that the contract or notice of award will be transmitted electronically. (The term "working day" excludes weekends and U.S. Federal holidays.) If, as so computed, the offered delivery date is later than the required delivery date, the offer will be considered non-responsive and rejected.

(End of Summary of Changes)