This document contains information from a government file regarding an industry day presentation and federal contract opportunity for the SPAWAR Shore Global Command, Control, Communications, Computer, Intelligence, Surveillance and Reconnaissance (C4ISR) Installations Contract.

The industry day presentation provides an overview of the SPAWAR Shore GIC SE4 contract, which will provide for C4ISR and other electronic systems installations across the Pacific and Atlantic areas of responsibility. It consolidates installation efforts and promotes competition at the task order level. Offerors must meet experience requirements to be considered, and proposals are due 1 May 2018, with award anticipated in January 2019. The presentation details evaluation factors such as technical capability, past performance, and small business participation. It also provides instruction on proposal submissions and oral presentations.

The federal contract opportunity notice identifies the solicitation as N00039-18-R-0060 for the SPAWAR Ashore Global C4ISR Installations Contract. The final RFP is anticipated for release on 26 March 2018, with an industry day to follow approximately three weeks later. The contract will support shore-based C4ISR and electronic systems installations for the Department of the Navy's Space and Naval Warfare Systems Command.

View the file

Other files for this federal contract opportunity

Other files attached to SPAWAR ASHORE GLOBAL C4ISR INSTALLATIONS CONTRACT, newest first.
File Type Posted
Q and A - N00039-18-R-0060 - Shore - 02 MAY 2018.pdf PDF
SE4 - Attachment 8 - Small Business Participation Data (01MAY2018).xlsx XLSX spreadsheet
N00039-18-R-0060-0005.pdf PDF
Q and A - N00039-18-R-0060 - Shore - 01 MAY 2018.pdf PDF
Q and A - N00039-18-R-0060 - Shore - 27 APR 2018.pdf PDF
Q and A - N00039-18-R-0060 - Shore - 26 APR 2018.pdf PDF
N00039-18-R-0060-0004.pdf PDF
Q and A - N00039-18-R-0060 - Shore - 20 APR 2018.pdf PDF
N00039-18-R-0060-0003.pdf PDF
SE4 - Attachment 5 - QASP (29MAR2018).pdf PDF
SE4 - Exhibit A - DD 1423 (11APR2018).pdf PDF
N00039-18-R-0060-0002.pdf PDF
INDUSTRY DAY II Sign In Sheet 20180402.pdf PDF
Q and A - N00039-18-R-0060 - Shore - 05 APR 2018.pdf PDF
SE4 - Attachment 3 - Statement of Work (SOW) 11APR2018.pdf PDF
Q and A - N00039-18-R-0060 - Shore - 12 APR 2018_FINAL.pdf PDF
N00039-18-R-0060-0001.pdf PDF
Q and A - N00039-18-R-0060 - Shore - 26 MAR 2018.pdf PDF
SE4 - Attachment 14 - Price Risk Math Model 26 MAR 2018.pdf PDF
SE4 - Exhibit A - DD 1423 (13MAR2018).pdf PDF
SE4 - Attachment 9 - Past Performance Questionnaire.docx DOCX document
SE4 - Attachment 10 - Proposal Checklist.pdf PDF
SE4 - Attachment 1B - Final Fee or Profit Determination Formula (09NOV2017).xlsx XLSX spreadsheet
SE4 - Attachment 1A - Incentive Plan 24OCT2017.pdf PDF
SE4 - Attachment 11 - Proposal Ratings Guide.pdf PDF
N00039-18-R-0060.pdf PDF
SE4 - Attachment 13 - CENTCOM Clauses Afghanistan (JAN 2018).pdf PDF
SE4 - Attachment 5 - QASP (03NOV2017).pdf PDF
SE4 - Attachment 7 - Reference Information Sheet (RIS).docx DOCX document
SE4 - Attachment 4 - DD 254.pdf PDF
SE4 - Attachment 8 - Small Business Participation Data (22FEB2018).xlsx XLSX spreadsheet
SE4 - Attachment 12 - Gate Review Matrix.xlsx XLSX spreadsheet
SE4 - ATTACHMENT 6 - Ceiling Distribution Proposal (26JAN2018).xlsx XLSX spreadsheet
SE4 - Attachment 3 - Statement of Work (SOW) 09MAR2018.pdf PDF
SE4 - Attachment 2 - Personnel Qualifications (06NOV2017).pdf PDF
Industry_Day_2_Information.pdf PDF
Q and A - N00039-18-R-0060 - Shore - 13 MAR 2018.pdf PDF
Q and A - N00039-18-R-0060 - Shore - 14 FEB 2018.pdf PDF
Q and A - N00039-18-R-0060 - Shore - 14 FEB 2018.pdf PDF
Q and A - N00039-18-R-0060 - Shore - 10 JAN 2018.pdf PDF
Q and A - N00039-18-R-0060 - Shore - 10 JAN 2018.pdf PDF
Show all 41

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SPACE AND NAVAL WARFARE SYSTEMS COMMAND

(SPAWAR)

SHORE GLOBAL

COMMAND, CONTROL, COMMUNICATIONS, COMPUTER,

INTELLIGENCE, SURVEILLANCE AND RECONNAISSANCE (C4ISR) INSTALLATIONS CONTRACT

N00039-18-R-0060

INDUSTRY DAY

02 APRIL 2018

DISTRIBUTION D. Distribution authorized to Department of Defense and U.S. DoD contractors only; Export Controlled; 02 April 2018. Other request for this document shall be referred to SPAWAR FRD 200

Agenda Industry Day Administration Mr. Daryl Smith – Global Installation Contract Re-Compete Manager

FRD 200 Opening Remarks Ms. Cheryl Carlton – Deputy Program Manager, Installation Program Office, Fleet Readiness Directorate

SPAWAR 2.0 Contracts Directorate Remarks Mr. Christopher Thompson – Procurement Contracting Officer, SPAWARSYSCOM

Question & Answer Session Mr. Christopher Thompson – Procurement Contracting Officer, SPAWARSYSCOM

SPACE AND NAVAL WARFARE SYSTEMS COMMAND

(SPAWAR)

FLEET READINESS DIRECTORATE

OPENING REMARKS

02 APRIL 2018

Ms. Cheryl Carlton Deputy Program Manager Installation Program Office Fleet Readiness Directorate

DISTRIBUTION D. Distribution authorized to Department of Defense and U.S. DoD contractors only; Export Controlled; 02 April 2018. Other request for this document shall be referred to SPAWAR FRD 200

Opening Remarks Welcome Industry Day is conducted during an open solicitation Purpose is to allow contractors to gain understanding of the RFP Maintain fair and open competition and aid the government in communication of requirements

Caution – no communications with any government person or agency during this open period outside of the Contracting Officer Christopher Thompson

Customer Perspective Installation work requires application of effective program management skills and tools As the government moves aggressively toward identifying, assessing and mitigating cost drivers, effective use of Program Management skills and tools are imperative to efficient contract execution and reporting

The Work Breakdown Structure defined in this solicitation seeks to establish a common vocabulary between government and industry in reporting cost and performance in the execution of Shore requirements

Shore GIC Goals/Overview Provides for one consistent methodology for Shore installation execution across the SPAWAR Enterprise (PEO C4I, PEO EIS, PEO SPACE, SSC Pacific and SSC Atlantic) Allows for greater efficiencies by combining installation efforts across Pacific and Atlantic AORs Promotes competition at the task order level, ensuring best value for the Government Ensures alignment of SSC PAC and SSC LANT procedures through the Fleet Readiness Directorate (FRD)

Program Management Reviews Program Management Reviews (PMRs) will be held semi-annually to allow contractors to communicate overall cost, schedule and performance

Goal from PMRs:

Review active and completed task orders during the review period Discuss status and effects of significant actions taken that affected cost, schedule, and/or performance Hold constructive dialog that could result in actions to improve processes and performance Enhance contractor performance and maintain quality of installations

Customer/Industry Relationship Navy/Industry team perspective A unified team delivers quality products to the Navy on time and within cost A team approach overcomes challenges more successfully than a segmented approach A cooperative environment is conducive to problem solving

SPAWAR is committed to being a good customer Businesses thrive and provide value to the Navy The Fleet needs the capabilities that you deliver!

SPAWAR SHORE GLOBAL C4ISR* INSTALLATION CONTRACT (GIC)

SEA ENTERPRISE 4 (SE4)

Chris Thompson Procurement Contracting Officer SPAWARSYSCOM

02 April 2018

* Command, Control, Communications, Computers, Intelligence, Surveillance & Reconnaissance

DISTRIBUTION D. Distribution authorized to Department of Defense and U.S. DoD contractors only; Export Controlled; 02 April 2018. Other request for this document shall be referred to SPAWAR FRD 200

Bottom Line Up Front If you have any questions – ask (BEFORE the solicitation closes), don’t assume

Prepare your proposal, then have someone (not the preparer) check the proposal against the solicitation requirements

Submit your proposal ON TIME: DO NOT WAIT UNTIL THE LAST MINUTE TO UPLOAD YOUR PROPOSAL

Agenda Acquisition Timeline RFP Information General Advice Q&A

Acquisition Timeline

RFP Release:16 March 2018
Second Industry Day02 April 2018
Proposals Due:01 May 2018
Anticipated Contract Award:January 2019

N00039-18-R-0060 RFP Information

3/30/2018 Entry Criteria – Relevant Organizational Experience Gate Offerors must meet minimum requirements for relevant (C4ISR or other like electronic systems) shore installation experience to be considered

Cumulative value of installation related tasks performed after 30 January 2012 must equal or exceed the following:

$95 million of shore installation work

Program Office Support Services experience for the work under the key areas of the SOW will not be considered acceptable, and will not count towards the cumulative value of installation experience.

Entry Criteria – Relevant Organizational Experience Gate (Cont.)

Offerors shall demonstrate relevant organizational experience in performing on-site work in all three of the below key SOW areas. The key SOW areas are listed in descending order based on the anticipated amount of work to be performed under the prospective contract:

(A) Experience in SOW Para 3.4 (inclusive of all subparagraphs)

(B) Experience in SOW Para 3.3 (inclusive of all subparagraphs)

(C) Experience in SOW Para 3.5 (inclusive of all subparagraphs)

Entry Criteria – Extent of Participation of Small Business At least 10% of the total acquisition value is required to be subcontracted to small business*

At least 5% of the total acquisition value is required to be attributable to small business* direct labor

*Small Business includes Small Disadvantaged Businesses, Women-Owned Small Businesses, Veteran-Owned Small Businesses, Service-Disabled Veteran-Owned Small Businesses, HUBZone Small Businesses and Historically Black Colleges or Universities and Minority Institutions.

Volume I, Section A Relevant Organizational Experience Each referenced contract (10 contracts maximum) shall be described using separately completed copies of RFP Attachment 7, Reference Information Sheet

Each Reference Information Sheet can be accompanied by a maximum of two additional pages One acronym list (not to be evaluated) of not more than one page may be submitted and is not counted toward the page count requirement

Each offeror shall submit one (1) completed RFP Attachment 12, Gate Review Matrix

Each offeror shall submit the cover sheet from each letter of commitment with each proposed subcontractor.

Volume I, Section B Organizational Past Performance Offerors shall provide information on no more than ten (10) previous relevant Government contracts; the contracts provided should have been performed after 30 January 2012

If the Offeror has not had ten (10) Government contracts for work performed after 30 January 2012, information on relevant subcontracts and/or commercial contracts may be submitted instead, however, the total number of submissions shall not exceed ten (10) references.

This information shall be provided by the submission of Attachment 7 “Reference Information Sheet” for each contract

Volume I, Section B Organizational Past Performance (Cont.)

Offerors shall contact their past performance references and request that each reference complete Attachment 9 “Past Performance Questionnaire” and e-mail the completed survey form BEFORE the RFP closes

Government reserves the right to use past performance information obtained from sources other than those identified by the offeror

Begin doing this now

Volume I, Section C Extent of Participation of Small Business All Prime Offerors (Large AND Small businesses) shall submit a completed Small Business Participation Data, (RFP Attachment 8)

In addition to RFP Attachment 8, each prime contractor (whether a small or large business) shall submit the cover sheet from each letter of commitment with each proposed small business subcontractor.

The small business subcontracting plan, which is only required from large businesses, is a separate requirement and is in addition to the information required to evaluate this factor.

Offerors will be evaluated on the extent of participation of small businesses in terms of the total acquisition value of this contract

Volume II, Cost Related Information Offerors shall submit a completed RFP Attachment 6, Ceiling Distribution Proposal. Attachment 6 shall be used by the offeror to annotate the distribution of ceiling amongst the prime and all subcontractors.

Offerors are required to provide the report(s) for the prime and any subcontractors that will utilize CPFF, FPIF, CPIF, or Cost-reimbursement pricing showing the Government’s determination of the offeror’s accounting system adequacy. If unavailable, other information pertinent to accounting system adequacy may be submitted.

All subcontractors with an accounting system that has not been deemed adequate by the Government shall be proposed as a FFP proposal, and identified in Attachment 6 as FFP.

Volume III, Offeror Information Failure or refusal to assent to any of the terms and conditions of the RFP, the imposition of additional conditions, or any material omission may constitute a deficiency which may render an offer unacceptable, and which may only be corrected through discussions (see FAR 15.306(d))

The Government intends to award a contract without discussions as permitted by FAR 15.306(a) and 52.215-1. Therefore, offerors are advised against submitting an offer which takes exception to any term or condition of this RFP or imposes any additional condition or omits any required information, without first consulting the Contracting Officer.

Volume III, Offeror Information ALL OFFERORS SHALL SUBMIT THE FOLLOWING, REGARDLESS OF POTENTIAL OCI DETERMINATION: Offerors shall identify and describe any contractual support they or any affiliate, joint venture or subcontractor under this solicitation are presently providing to PEO C41, SPAWAR, SPAWAR Systems Center (SSC) Atlantic, SSC Pacific, or any other activity, where that support relates to C4I installation support services. The offeror shall include: (1) the name of the contractor, joint venture, affiliate, or subcontractor; (2) the contracting agency; (3) contract number; (4) a short description of the work; and (5) whether the offeror believes that the support results in an OCI. Offerors shall specifically address why they believes no OCI exists (if applicable).

Source Selection The Government intends to make a contract award to each and all qualifying offerors. “Qualifying offeror” is defined as an offeror that is determined to be a responsible source, submits a technically acceptable proposal that conforms to the requirements of the solicitation, and the contracting officer has no reason to believe would be likely to offer other than fair and reasonable pricing.

In accordance with Class Deviation 2018-O0006, which implements Section 825 of the National Defense Authorization Act (NDAA) for Fiscal Year 2017, the Government will not evaluate cost or price for the IDIQ contract. Cost or price to the Government will be considered in conjunction with the issuance of a task or delivery order under any contract awarded hereunder.

Source Selection Evaluation Factors Factor 1: Technical and Management Capability Written submission Oral presentation Factor 2: Organizational Past Performance Factor 3: Extent of Participation of Small Business

Under each evaluation factor, specified individual evaluation sub-factors are weighted equally.

Factor 1: Technical and Management Capability Evaluation Written submittals and Oral presentations will be evaluated to determine each offeror’s technical and management capability

Oral Presentations will be used to evaluate how offerors would respond to more complex installation questions dealing with:

Shore installations Global Task Orders Consolidated (multiple system) installations

Capability Evaluation (Cont.)

The Government will evaluate the extent to which the offeror demonstrates the breadth and depth of its technical and management capability relative to its Key Personnel, staffing, tasking, processing, executing, reporting and managing consolidated task orders for shore-based installations of C4ISR or other like shore electronic systems installations.

The Government will also evaluate the offeror’s relevant experience, qualifications, and knowledge with regard to the requirements of the Statement of Work.

Capability Evaluation – Written Submission (Cont.)

Three questions that require written answers will be provided with the invitation for the oral presentation

Offerors will have 7 calendar days to submit their written answers electronically. Offerors will be allowed a maximum of 2 pages to respond to each question

Offerors who do not meet the Gate requirement will not receive an invitation to participate in oral presentations and will not receive the questions for the written portion of the Technical and Management Capability Factor

Capability Evaluation – Oral Presenation (Cont.)

Offerors will be given at least two (2) weeks notice for oral presentations

Offerors will make their oral presentations in person in the greater San Diego area

Offerors will be provided written questions. The questions will address general and specific facets of shore installations.

Each oral presentation is expected to last approximately six (6) hours

Capability Evaluation – Oral Presentation (Cont.)

Presentation teams will not be allowed to bring notes, references, communication devices or other presentation materials for use during the caucus session or the presentation

The Government will not provide any computer hardware and/or software, nor will the offeror be permitted to bring any computer hardware and/or software

Personnel shall not attend more than one oral presentation or caucus session for oral presentations resulting from this solicitation

FACTOR 1: Technical and Management Capability Evaluation – Oral Presentation (Cont.)

During oral presentations, offerors shall present information that clearly demonstrates its knowledge and understanding of the technical requirements of the solicitation’s Statement of Work (SOW), as well as the technical issues, problems, challenges and possible solutions associated with the envisioned work A maximum of seven (7) personnel representing each prime/subcontractor team may participate in the oral presentation Only the two (2) key personnel will be authorized to brief the Government team Each of the seven (7) personnel participating in the oral presentation shall be proposed as one (1) Full Time Equivalent (FTE) committed to this contract, and specifically named in Attachment 6.

One (1) additional person may attend and participate in the ten (10) minute introductory period prior to the oral presentation; however, the additional person will not be able to participate in any part of the oral presentation or caucus session

FACTOR 2: Organizational Past Performance Evaluation Three aspects of Past Performance Recency Relevance Quality

Evaluation of an offeror’s proposal shall be based on the information presented in the proposal and information available to the contracting office from sources deemed appropriate

Factor Level Rating – One Performance Confidence Rating Based on the aggregate of the individual experience performance confidence ratings

A Neutral rating will be assigned if no record of past performance exists

FACTOR 3: Extent of Participation of Small Business This factor will assess the extent to which offerors commit to small business performance (whether as a prime or subcontractor) in terms of the total acquisition value.

For this FACTOR only, small businesses identifying as more than one socioeconomic category may be counted to meet more than one of the minimum proposed percentages for socioeconomic purposes.

Offerors shall not be permitted to use small businesses more than once for the Extent of Participation of Small Business “Minimum Gate Requirement”.

Outstanding: Offeror proposes at least 20% of total acquisition value for small business. Of the proposed twenty (20) percent at least fifteen (15) percent of the total acquisition value shall be attributable to direct labor hours. Additionally, the extent of participation of small business shall meet, at a minimum, three (3) of the four (4) minimum proposed goals listed in the table below.

Good: Offeror proposes at least 17% of total acquisition value for small business. Of the proposed seventeen (17) percent at least twelve (12) percent of the total acquisition value shall be attributable to direct labor hours. Additionally, the extent of participation of small business shall meet, at a minimum, two (2) of the four (4) minimum proposed goals listed in the table below.

Socio-economic CategoryMinimum Proposed Goal*
SDB6.35%
SDVOSB3.00%
WOSB5.00%
HUBZone3.00%

Acceptable: Offeror proposes at least 15% of total acquisition value for small business. Of the proposed fifteen (15) percent at least ten (10) percent of the total acquisition value is attributable to direct labor hours.

Marginal: Offeror proposes at least ten (10) percent of total acquisition value for small business. Of the proposed ten (10) percent at least five (5) percent of the total acquisition value is attributable to direct labor hours.

Unacceptable: Offeror proposes less than 10% of total acquisition value for small business.

General Advice

Understand the Ground Rules Federal regulations require the acquiring activity to inform all offerors of the criteria, and their relative importance, that will be used to evaluate proposals (Section M)

Government evaluators may only evaluate the proposal against the criteria listed in Section M

Government evaluators may only evaluate a proposal using the information provided within the proposal itself The only exception is information relating to past performance

Follow the Instructions Section L tells you how the Government expects you to put your proposal together (e.g., how many volumes, what to put into those volumes, how many pages, etc.)

This is not the time to get creative – if information is requested in Section 1 of Volume 2, please put it there

Ensure that you complied with any page limitations - Government evaluators are not allowed to review any pages in excess of the limitation These pages are removed before giving the proposal to the technical evaluators to ensure they are not reviewed

Understand the “Grading System” Read Section M very carefully It contains the criteria that will be used to evaluate your proposal It specifies the relative importance of those criteria It (frequently) provides information on how the criteria will be applied (e.g., what constitutes an outstanding vice satisfactory rating)

Use this information when deciding where and how to focus the efforts of your proposal team

Writing Your Proposal Determine who is going to write the proposal (an individual, a team?)

Ensure that everyone involved with the proposal understands the requirements, the evaluation factors and the proposal instructions If you are unsure of something in the solicitation, get clarification, in writing, from the PCO BEFORE the solicitation closes

Decide how you are going to allocate time and resources (use the evaluation criteria as your guide)

Make sure your proposal is submitted ON TIME

Writing Your Proposal (cont.)

Put your best effort forward the first time – never assume that you will be given an opportunity to have discussions/fine tune your proposal

Taking exception or putting conditions on your proposal is risky and may make your proposal unacceptable

Have someone who was not involved with writing/assembling the proposal review it against the solicitation to ensure that ALL of the requirements of the solicitation were addressed

Ensure your proposal is signed and that it includes an acknowledgement of the receipt and acceptance of all the solicitation amendments (Review the Checklist)

After the Award Decision Request a debriefing To ensure that you get a debriefing, it must be requested, in writing, within 3 days of being notified of the award decision

Debriefings can be a learning opportunity Solicit information on what you can improve on for next time

Follow The Final RFP If necessary, any differences between this brief and the RFP shall be clarified through questions

Key Points-of-Contact Chris Thompson - (858) 537-0306 - chris.thompson1@navy.mil

Sharla van Bramer - (619) 524-7389 - sharla.vanbramer@navy.mil

Question & Answer Session image3.jpeg image4.jpeg image5.png image6.jpeg image7.jpeg image17.jpeg image1.jpeg image2.jpeg image8.png