This Special Conditions document establishes requirements for McQueen's Trail Restoration project in unincorporated Chatham County, Georgia, adjacent to US 80. The project involves restoration and repair of a pedestrian/bike trail constructed over an old railroad bed that is surrounded by saltwater marsh on both sides. The trail features a soil cement surface course and has sustained hurricane damage requiring restoration along the northern edge of the western route. Bidders must submit a pre-construction conditions video emphasizing the condition of Fort Pulaski Road, the trail from Fort Pulaski Road to the work area, existing wooden bridges, and improvements within 100 feet of project limits. The contract deliverables include mobilization, replacement of crushed limerock and riprap, replacement of structural fill areas, installation of additional tiebacks to existing timber bulkheads, installation of new timber bulkhead retaining systems, and installation of temporary manatee signs. Work hours are limited to 7:00 a.m. to 7:00 p.m., Monday through Friday, excluding weekends and holidays unless otherwise approved. McQueen's Trail shall be closed to the public during construction with the contractor responsible for all signage and traffic control measures.
The contractor must prepare a detailed plan of operations identifying equipment and material staging locations outside wetlands to the extent practicable, with preference for staging on McQueen's Trail or at specified coordinates. Material delivery may occur via haul routes from Fort Pulaski Road or by barge, with the contractor responsible for structural inspections of existing wooden bridges to accommodate additional loads and for repairs of any damage incurred. Payment items are unit priced based on actual quantities, with mobilization not to exceed 5 percent of total contract price. The contractor bears responsibility for all erosion and sedimentation control compliance and carries a $500 per day fee for improper operation of the erosion control plan plus $300 per calendar day in liquidated damages for failure to complete work within the contract period. The county will pay for materials testing by an independent lab but the contractor pays for failed tests. A Field Condition Allowance belongs to the county and may be designated for unforeseen work; bidders must include this allowance in their base bid with unused amounts reverting to the county.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| McQueens Trail Restoration Plans.pdf | ||
| Bid 26_0048_5.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
01600 - 1
MCQUEEN’S TRAIL RESTORATION
SPECIAL CONDITIONS
SECTION 01600
PART 1 – PROJECT DESCRIPTION
The project is in unincorporated Chatham County on McQueen’s Trail adjacent to US 80.
McQueen’s Trail consists of a pedestrian/bike trail constructed over an old railroad bed surrounded on both sides by saltwater marsh. The trail material is constructed using a soil cement surface course over the existing rail bed sub-base. This trail has been impacted by hurricanes. This project will restore/repair specific areas along the northern edge of the western route of the trail.
PART 2 – CONTRACT DOCUMENTS
2.1 Drawings:
1 Cover Sheet 2 Plan of Restoration Areas 3 Notes and Details
PART 3 – PRE-CONSTRUCTION INSPECTIONS
The contractor is responsible for a pre-construction conditions video. Special emphasis shall be given to recording pre-disturbance condition of Fort Pulaski Road, McQueen’s Trail from Fort Pulaski Road to the work area, existing wooden bridges, and other improvements located within and 100 feet adjacent to the project limits.
PART 4 – STAGING AND STORAGE
The contractor shall prepare a plan of operations showing proposed locations of vehicle/equipment/material staging and storage. Construction activities, equipment staging, and equipment storage activities are not to be located within or adjacent to any wetlands to the extent practicable to construct the bulkheads. All materials and equipment should be staged outside of the wetlands on McQueen’s trail or on the dirt patch at coordinates (32.040481, -80.944474).
Documentation of compliance will be required at closeout. Delivery of materials shall be accomplished by either hauling from Fort Pulaski Road along McQueen’s Trail or by barge to a point along the trail and be offloaded. If using McQueen’s Trail to haul materials, the Contractor shall be responsible for inspections to each of the existing wooden bridges to ensure the bridges are structural sound for the additional loads. Any damage to the bridges will be corrected at the Contractor’s expense.
PART 5 – DOCUMENTATION
In addition to the documentation described elsewhere in the Contract Documents, the Contractor shall submit with each request for payment the following:
01600 - 2
1. Copies of material delivery tickets. The Contractor shall be responsible for collecting these documents at the time of delivery. The delivery tickets shall not relieve the Contractor of his responsibility to ensure the materials are in accordance with the contract with the contract documents. Missing or incomplete documentation of delivered materials may be cause for delay/denial of payment.
2. Prior to submitting a request for payment, the Contractor shall review the extent of work completed with the County’s representative for accuracy and completeness.
PART 6 – EROSION AND SEDIMENTATION CONTROL
The Contractor shall be fully responsible for compliance with the Georgia Water Quality Control Act and compliance with the approved sediment and erosion control plan contained in the contract documents.
1. The design engineer shall accomplish the initial inspection of the Best Management
Practice (BMP) system installation. The Contractor shall perform no land disturbing activities (other than that which is necessary for installation of the BMPs) until after the design engineer has provided to the owner a letter stating approval of the initial BMP installations.
2. The Contractor shall be responsible for all inspections of the BMP system (Excluding the initial inspections as described above) and for maintaining records at the site for inspection.
3. The Contractor shall provide the Owner copies of all inspection reports and other records which occur during a pay period with the pay request.
4. The Contractor shall be responsible for preparing plans, applying for, and obtaining erosion control permit for any impacted areas or lay down areas proposed by the contractor that are not included in the current plan documents.
PART 7 – FINES AND LIQUIDATED DAMAGES
1. A $500 per day fee shall be assessed against the Contractor and withheld from the
Contract Price for each day that the erosion and sedimentation control plan is not in proper operation. This fee shall be in addition to any penalties or assessments made against the Contractor for non-compliance with the Georgia Water Quality Control Act.
2. Liquidated Damages shall be assessed at $300 per calendar day for work not completed within the Contract period. The full amount of liquidated damages will be deducted from the final payment to the Contractor.
PART 8 – ALLOWANCE
The Field Condition Allowance shown on the bid sheet shall belong to Chatham County. The purpose of this Allowance is to allow the County to designate actions associated with completion of the project which are not indicated on the plans, but which are dictated by field conditions.
Bidders shall not use this Allowance to assume any Contractor costs known or unknown at the bidding. Chatham County must approve use of the Allowance. All bidders shall include this Field
01600 - 3
Condition Allowance within their base bid. Any unused allowance shall revert to Chatham County.
PART 9 – SPECIAL REQUIREMENTS OF CONSTRUCTION
1. The County will pay for all materials testing as required by the contract. Testing will be performed by an independent testing lab that is hired by the County. The County will not pay for testing in support of contractor operations/schedule. The contractor will be required to pay for failed tests.
2. Clearing debris may not be chipped and spread on the project site.
3. It is understood that the location and nature of the project will result in some soil migration to pavement. This is to be kept to a minimum and cleaned up on a regular basis.
4. The Contractor shall comply with all local, state, and federal regulations as they pertain to construction activities (erosion control, etc.).
5. Work hours shall be limited to 7:00 am to 7:00 pm Monday through Friday and shall exclude weekends and holidays unless otherwise approved by Chatham County.
6. The Contractor shall obtain an Encroachment permit from the Department of Public
Works prior to any work within County rights of way. All work is to be performed within the existing rights of way and easements as shown on the plans unless coordinated with others.
7. A detailed construction schedule for the project shall be provided to and approved by Chatham County prior to beginning construction.
8. McQueen’s Trail shall be closed to the public during construction. The contractor is responsible for providing all signage and measures of traffic control as deemed necessary. The County reserves the right to add additional traffic control measures for public safety.
9. The Contractor shall ensure all storage materials are secure in the event of a king tide or hurricane. Any material lost during these events will be at the Contractor’s expense.
PART 10 – MEASUREMENT AND PAYMENT
1. Measurement
The items listed in the proposal shall be considered as sufficient to complete the work in accordance with the drawings and specifications. Any portion of the work not listed in the bid form shall be deemed to be a part of the item which it is associated with and shall be included in the cost of the unit shown on the bid form. Payment for the unit shown on the bid form shall be considered to cover the cost of all labor, material, equipment and performing all operations necessary to complete the work in place. The unit of measurement shall be the unit shown on the bid form. Payment for unit price items shall be based upon the actual quantity multiplied by the unit prices. Where work is to be performed at a lump sum price, the lump sum shall include all operations and elements necessary to complete the work. No payment will be made for any material wasted, unused, rejected or used for the convenience of the Contractor.
2. Payment
The following items listed correspond to the items on the bid schedule.
01600 - 4
A. Mobilization Mobilization of equipment and commencement of project. Payment shall be based on the lump sum price in the Bid Proposal and shall not to exceed 5% of the total price bid for the project.
B. Replace Crushed Limerock
Payment shall be at the unit price in the Bid Proposal and shall include all labor, materials, and equipment required to replace crushed limerock in the same location as shown on the plans or as directed by the owner. Measurement shall be based on the actual number of cubic yards replaced.
C. Replace Riprap Payment shall be at the unit price in the Bid Proposal and shall include all labor materials and equipment required to install the riprap as shown on the plans or as directed by the owner. Filter fabric underlay is included. Measurement shall be based on the actual number of cubic yards of riprap installed.
D. Replace Structural Fill Areas materials, and equipment required to replace structural fill in the areas as shown on the plans or as directed by the owner. Measurement shall be based on the actual number of cubic yards replaced.
E. Install Additional Tiebacks to the Existing Timber Bulkhead materials, and equipment required to install piles, drag timber, and anchor rod per detail. Payment shall also include all disturbance and repair to the trail caused by the installation of these tiebacks. Measurement shall be based on the actual linear feet of trail where the tiebacks were installed.
F. Install New Timber Bulkhead Retaining System materials, and equipment required to install piles, drag timber, anchor rod, timber sheets, walers, filter fabric, and fasteners per detail, Payment shall also include all disturbance and repair to the trail caused by the installation of this retaining system. Measurement shall be based on the actual linear feet of trail where the tiebacks were installed.
G. Install Temporary Manatee Signs Payment shall be made at the contract unit price for each sign installed. Payment should include all labor, material, and equipment required to install the signs in accord with the contract documents. Measurement shall be based on the actual number of signs installed.