McGarity 0.9 Million Gallon Ground Storage Tank (Specs).pdf
PDF 7 MB Posted
- Attached to
- McGarity 0. 9 Million Gallon Ground Storage Tank
- Solicitation number
- 25-2208 RFP#046-026
- Issued by
- Collin County, Texas
About this file
This is a specifications document for a Texas water infrastructure project involving the removal and replacement of a ground storage tank. The project requires the removal of an existing 200,000-gallon ground storage tank and the construction of a new 0.9 million-gallon welded steel ground storage tank. The scope of work encompasses foundation preparation, excavation, backfill, installation of piping and supports, tank overflow funnel, equipment installation, exterior painting, shrouding, tank accessories, and all related appurtenances necessary for full operational capability.
The specifications document details the technical requirements and construction standards for the welded steel tank, including material specifications, welding procedures, quality assurance testing, and installation protocols. The project requires compliance with applicable industry standards and codes for water storage tank construction. Pricing and contract terms, award timelines, site visit requirements, and bidder conference details are not specified within this specifications document, as it serves primarily as a technical reference for design and construction standards that bidders must meet when submitting proposals for this infrastructure improvement project.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CITY OF LUCAS, TEXAS
PUBLIC WORKS CONSTRUCTION PROJECT
McGarity 0.9 Million Gallon
Ground Storage Tank
RFP#046-026
-i-
TABLE OF CONTENTS
ARTICLE I; THE CONTRACT AND THE CONTRACT DOCUMENTS 1
1.1 The Contract 1
1.2. The Contract Documents 1
1.3 Entire Contact 1
1.4 No Privity with Others 1
1.5 Intent and Interpretation 1
1.6 Ownership of Contract Documents 2
ARTICLE II; THE WORK 2
2.1 The Work Generally 2
2.2 Work 2
ARTICLE III; CONTRACT TIME 3
3.1 Time and Liquidated Damages 3
3.2 Substantial Completion 4
3.3 Time is of the Essence 4
ARTICLE IV; CONTRACT PRICE 5
4.1 The Contract Price 5
ARTICLE V; PAYMENT OF THE CONTRACT PRICE 5
5.1 Schedule of Values 5
5.2 Payment Procedure 5
5.3 Withheld Payment 6
5.4 Unexcused Failure to Pay 7
5.5 Certificate of Substantial Completion 7
5.6 Completion and Final Payment 7
ARTICLE VI; THE CITY 8
6.1 Information, Services and Things Required from City 8
6.2 Right to Stop Work 9
6.3 City's Right to Perform Work 9
ARTICLE VII; THE CONTRACTOR 9
7.1 Must Follow Contract 9
7.2 Prosecution of Work 9
7.3 Warranty 10
7.4 Permits; Fees; Licenses 10
7.5 Supervision 10
7.6 Work Schedule 10
7.7 On-Site Drawings 10
7.8 Record Drawings/Plans, As-Built Plans, Shop Drawings, Product Data, and Samples 11
7.9 Cleaning the Site and the Project 11
7.10 Access to Work and Inspections 11
7.11 Indemnity and Disclaimer 11
7.12 Nondiscrimination 12
7.13 Prevailing Wage Rates 12
7.14 Job Site Safety Precautions 12
7.15 Warning Devices and Barricades 12
7.16 Protection of Utilities and Other Contractors 13
ARTICLE VIII; CONTRACT ADMINISTRATION 13
8.1 The Engineer 13
8.2 Engineer's Administration 13
-ii-
8.3 Claims by the Contractor 14
8.4 Extra Work 15
8.5 Claims for Additional Costs or Time; Contract Price Increase 15
8.6 Field Orders 15
8.7 Mediation 16
ARTICLE IX; SUBCONTRACTORS 16
9.1 Definition 16
9.2 Award of Subcontracts 16
ARTICLE X; CHANGES IN THE WORK 16
10.1 Changes Permitted 16
10.2 Change Order Defined 17
10.3 Changes in the Contract Price 17
10.4 Minor Changes 17
10.5 Effect of Executed Change Order 17
10.6 Notice to Surety; Consent 17
ARTICLE XI; UNCOVERING AND CORRECTING WORK 18
11.1 Uncovering Work 18
11.2 Correcting Work 18
11.3 City May Accept Defective or Nonconforming Work 18
ARTICLE XII; CONTRACT DEFAULT AND TERMINATION 18
12.1 Termination by the Contractor 19
12.2 Termination by the City 19
12.3 Use of Third-Party Oversight or Construction Manager 20
ARTICLE XIII; INSURANCE 20
13.1 Contractor Shall Maintain Insurance 20
13.2 Types and Amounts of Contractor’s Insurance 21
13.3 Additional Insured 22
13.4 Written Notification 22
13.5 Premiums and Assessments; Subrogation 22
13.6 Certificate of Insurance 22
13.7 Primary Coverage 22
13.8 Subrogation 22
13.9 Worker's Compensation Insurance Coverage 22
ARTICLE XIV; MISCELLANEOUS 24
14.1 Laws and Ordinances 24
14.2 Governing Law 24
14.3 Successors and Assigns 24
14.4 Surety Bonds 24
14.5 Severability 25
14.6 Amendments 25
14.7 Force Majeure 25
14.8 Notices 25
14.9 Immunities; Defenses 25
14.10 No Rights in Third Parties 26
14.11 Prohibitions 26
ATTACHMENTS
Advertisement for Bids Bid Schedule Geotechnical Report
-1-
City of Lucas, Texas
This Agreement is made by and between the City of Lucas, Texas, a home-rule municipality (hereinafter referred to as the "City") and [ENTER CONTRACTOR LEGAL NAME], a [ENTER STATE OF INCORPORATION] [ENTER LEGAL ENTITY TYPE] (hereinafter referred to as the "Contractor") for construction of McGarity 0.9 Million Gallon Ground Storage Tank, (hereinafter referred to as the "Project"), the City and the Contractor hereby agreeing as follows:
ARTICLE I
THE CONTRACT AND THE CONTRACT DOCUMENTS
1.1 THE CONTRACT
1.1.1 The Contract between the City and the Contractor, of which this agreement (sometimes referred to herein as the “Contract”) is a part, consists of the Contract Documents. It shall be effective on the date this Contract is executed by the last party to execute it.
1.2. THE CONTRACT DOCUMENTS
1.2.1 The Contract Documents consist of this Contract, the General Conditions, the Invitation to Bid/Request for Proposal/Advertisement for Bids (attached), Plans and Drawings, Bid Schedule (attached), all Change Orders and Field Orders issued hereafter, any other amendments hereto executed by the parties hereafter, together with the following (if any):
In the event of a conflict in terms among any of the Contract Documents, the provisions of this Contract will prevail.
In order of priority in resolving conflicts outside of this Contract, the City’s Invitation to Bid/Request for Proposal, the Contractor’s Bid or Best and Final Offer, and the Specifications and Drawings shall, in that order, prevail.
Irreconcilable conflicts that cannot be resolved by Field Order shall be resolved by written Change Orders. Documents not enumerated in this paragraph 1.2.1 are not Contract Documents and do not form part of this Contract.
1.3 ENTIRE CONTRACT
1.3.1 This Contract, together with the Contractor's performance and payment bonds for the Project, all General Conditions, Special Conditions, Plans and Specifications, and Addenda attached thereto, constitute the entire and exclusive agreement between the City and the Contractor with reference to the Project. Specifically, but without limitation, this Contract supersedes any bid documents and all prior written or oral communications, representations, and negotiations, if any, between the City and Contractor not expressly made a part hereof.
1.4 NO PRIVITY WITH OTHERS
1.4.1 Nothing contained in this Contract shall create, or be interpreted to create, privity or any other contractual agreement between the City and any person or entity other than the Contractor.
1.5 INTENT AND INTERPRETATION
1.5.1 The intent of this Contract is to require complete, correct and timely execution of the Work. Any Work that may be required, implied, or inferred by the Contract Documents, or any one or more of them, as necessary to produce the intended result shall be provided by the Contractor for the Contract Price.
1.5.2 This Contract is intended to be an integral whole and shall be interpreted as internally consistent. What is required by any one Contract Document shall be considered as required by the Contract.
-2-
1.5.3 When a word, term or phrase is used in this Contract, it shall be interpreted or construed, first, as defined herein; second, if not defined, per its generally accepted meaning in the construction industry; and third, if there is no generally accepted meaning in the construction industry, per its common and customary usage.
1.5.4 The word “City” includes the City of Lucas, Texas, a municipal corporation, and its public officials, officers, employees, agents, and employees. The word “Contractor” includes the Contractor and its officers, employees, agents, and representatives. The word "include", "includes", or "including", as used in this Contract, shall be deemed to be followed by the phrase, "without limitation".
1.5.5 The specification herein of any act, failure, refusal, omission, event, occurrence, or condition as constituting a material breach of this Contract shall not imply that any other, non-specified act, failure, refusal, omission, event, occurrence, or condition shall be deemed not to constitute a material breach of this Contract.
1.5.6 Words or terms used as nouns in this Contract shall be inclusive of their singular and plural forms unless the context of their usage clearly requires a contrary meaning.
1.5.7 The Contractor shall have a continuing duty to read, carefully study and compare each of the Contract Documents, the Shop Drawings, the Product Data, and any Plans and Specifications, and shall give written notice to the City of any inconsistency, ambiguity, error, or omission which the Contractor may discover with respect to these documents before proceeding with the affected Work. The issuance, or the express or implied approval by the City or the Engineer of the Contract Documents, Shop Drawings, or Product Data, shall not relieve the Contractor of the continuing duties imposed hereby, nor shall any such approval be evidence of the Contractor's compliance with this Contract. The City has requested the Engineer to only prepare documents for the Project, including the Drawings, Plans, and Specifications for the Project, which are accurate, adequate, consistent, coordinated, and sufficient for construction. HOWEVER, THE CITY MAKES NO REPRESENTATION OR WARRANTY OF ANY NATURE WHATSOEVER TO THE CONTRACTOR CONCERNING SUCH DOCUMENTS. By the execution hereof, the Contractor acknowledges and represents that it has received, reviewed, and carefully examined such documents, has found them to be complete, accurate, adequate, consistent, coordinated, and sufficient for construction, and that the Contractor has not, does not, and will not rely upon any representation or warranties by the City concerning such documents as no such representation or warranties have been or are hereby made. Further, the Contractor represents and warrants that it has had a sufficient opportunity to inspect the Project site and assumes any and all responsibility for inadequacies or ambiguities in the plans, drawings, or specifications as well as for latent conditions of the site where the work is to be performed, subject to the terms and conditions of Subparagraph 8.3.3.
1.5.8 As between numbers and scaled measurements on the Drawings and in the Design, the numbers shall govern, as between larger scale and smaller scale drawings, the larger scale shall govern.
1.5.9 Neither the organization of any of the Contract Documents into divisions, sections, paragraphs, articles, (or other categories), nor the organization or arrangement of the Design, shall control the Contractor in dividing the Work or in establishing the extent or scope of the Work to be performed by Subcontractors.
1.6 OWNERSHIP OF CONTRACT DOCUMENTS
1.6.1 The Contract Documents, and each of them individually and collectively, shall remain the property of the City. The Contractor shall have the right to keep one record set of the Contract Documents upon completion of the Project; provided, however, that in no event shall Contractor use, or permit to be used, any or all of such Contract Documents on other projects without the City's prior written authorization.
-3-
ARTICLE II
THE WORK
2.1 The Contractor shall perform all the Work required, implied or reasonably inferable from, this Contract.
2.2 WORK
2.2.1 The term "Work" shall mean whatever is done by or required of the Contractor to perform and complete its duties under this Contract, including the following: construction of the whole or a designated part of the Project;
furnishing of any required surety bonds and insurance, and the provision or furnishing of labor, supervision, services, materials, supplies, equipment, fixtures, appliances, facilities, tools, transportation, storage, permits and licenses required of the Contractor, power, water, fuel, heat, light, cooling and all other utilities as required by this Contract.
The Work to be performed by the Contractor is shown in the plans and itemized in the attached Bid Schedule.
2.2.2 The Contractor shall be responsible for paying for and procuring all materials and labor and furnishing all services necessary or appropriate for the full performance of the Work and for the full completion of the Project. All materials shall be new, and materials and workmanship shall be of good quality. Upon request, the Contractor shall furnish satisfactory proof of the type, kind, and quality of materials.
ARTICLE III
CONTRACT TIME
3.1 TIME AND LIQUIDATED DAMAGES
3.1.1 The Contractor shall commence the Work within ten (10) days of receipt of a written Notice to Proceed and shall achieve Substantial Completion of the Work no later than 200 calendar days from the date specified in the Notice to Proceed. The parties acknowledge that time is of the essence in the performance of the terms of this Contract. The term “calendar days” shall mean all days of the week or month, no days being excepted. It is contemplated by the parties that the progress of the Work may be delayed by certain conditions beyond the control of the parties; these delays have been contemplated by the parties and considered in the time allotted for performance specified herein and includes, but is not limited to delays occasioned on account of adverse weather, temporary unavailability of materials, shipment delays, and the presence and potential interference of other contractors who may be performing work at the Project site unrelated to this Contract.
The number of calendar days from the date on which the Work is permitted to proceed, through the date set forth for Substantial Completion, shall constitute the "Contract Time".
3.1.2 The Contractor shall pay the City the sum of 500.00 per day for each and every calendar day of unexcused delay in achieving Substantial Completion beyond the date set forth herein for Substantial Completion of the Work.
Any sums due and payable hereunder by the Contractor shall be payable, not as a penalty, but as liquidated damages representing an estimate of delay damages likely to be sustained by the City, estimated at or before the time of executing this Contract, and represent City’s sole remedy for delay damages in the event of unexcused delay. When the City reasonably believes that Substantial Completion will be inexcusably delayed, the City shall be entitled, but not required, to withhold from any amounts otherwise due the Contractor an amount then believed by the City to be adequate to recover liquidated damages applicable to such delays. If and when the Contractor overcomes the delay in achieving Substantial Completion, or any part thereof, for which the City has withheld payment, the City shall promptly release to the Contractor those funds withheld, but no longer applicable, as liquidated damages.
3.1.3 In the event that the Contractor achieves certification by the Engineer of Final Completion prior to the date set for Substantial Completion, the City shall pay to the Contractor the sum of $0.00 per day for each calendar day that Final Completion is certified in advance of the scheduled Substantial Completion date, as that date may be
-4-modified by written change order. However, early completion bonuses shall not, in the aggregate, exceed the total sum of $0.00. Any reduction in the scope of work, evidenced by written change order, shall commensurately reduce the Contract Time.
3.1.4 No claim shall be made by the Contractor to the City, and no damages, costs, or extra compensation shall be allowed or paid by the City to the Contractor for any delay or hindrance from any cause in the progress or completion of the Work or this Contract. The Contractor’s sole remedy in the event of any delay or hindrance shall be to request time extensions by written change orders as provided for hereinafter. Should the Contractor be delayed by an act of the City, or should the City order a stoppage of the Work for sufficient cause, an extension of time and extended General Conditions shall be granted by the City by written authorization upon written application, which time extension and extended General Conditions shall not be unreasonably denied, to compensate for the delay.
3.1.5 The City shall have the authority to suspend the Work wholly or in part for such period or periods of time as it may deem appropriate due to unsuitable conditions considered unfavorable for the proper prosecution of the Work or for the failure of the Contractor to carry out instructions from the City or City’s representative. During any period in which the Work is stopped or during which any of the Work is not actively in progress for any reason, Contractor shall properly protect the site and the Work from damage, loss or harm.
3.2 SUBSTANTIAL COMPLETION
3.2.1 "Substantial Completion" shall mean that stage in the progression of the Work when the Work is sufficiently complete in accordance with this Contract that the City can enjoy beneficial use or occupancy of the Work and can utilize the Work for its intended purpose, even though minor miscellaneous work and/or adjustment may be required.
3.3 TIME IS OF THE ESSENCE
3.3.1 The scheduled completion date is based on public necessity. The scheduled completion date is factored into and is a material component of the Contract Price. All limitations of time set forth in the Contract Documents are of the essence of this Contract.
3.3.2 TIME IS OF THE ESSENCE IN THE PERFORMANCE OF THE WORK AND THE COMPLETION OF
THE PROJECT ON OR BEFORE THE SCHEDULED COMPLETION DATE. THE SCHEDULED COMPLETION
DATE IS A DEADLINE. THE CITY EMPLOYS A ZERO-TOLERANCE POLICY REGARDING THE TIME FOR COMPLETION. The time for completion is an essential and material term of this Contract and the Contractor’s failure to achieve substantial completion on the date stated herein, to comply with work schedules, or achieve milestones in approved construction schedules, shall be a material breach and default of this Contract.
3.3.3 The City shall have the authority to suspend the Work wholly or in part for such period or periods of time as it may deem appropriate due to unsuitable conditions considered unfavorable for the proper prosecution of the Work or for the failure of the Contractor to carry out instructions from the City or City’s representative. During any period in which the Work is stopped or during which any of the Work is not actively in progress for any reason, Contractor shall properly protect the site and the Work from damage, loss, or harm. The Contractor shall not be compensated for periods of delay caused by a suspension of the work by the City. If work is suspended due to unsuitable conditions through no fault of the Contractor, an extension of time shall be granted by the City by Change Order upon written application, which extension shall not be unreasonably denied, to compensate for the delay.
3.3.4 The Contractor shall not have or assert any claim against the City for damages or back-charges of any kind for any reason, including but not limited to claims for Extra Work, damages, economic loss, additional costs, unknown latent site conditions, and refusals by the City to grant extensions of time, unless supported and authorized by a written Change Order or separate agreement signed by all parties. The Contractor, in entering into this Contract, hereby waives, releases, quitclaims, discharges, and holds harmless the City from and against any and all claims, damages, liabilities and losses, save and except those arising under Paragraph 12.1 of this Contract.
-5-
ARTICLE IV
CONTRACT PRICE
4.1 THE CONTRACT PRICE
4.1.1 The City shall pay, and the Contractor shall accept, as full and complete payment for all of the Work required herein, the fixed sum of $ [ENTER CONTRACT AMOUNT]. The sum set forth in this Paragraph 4.1 shall constitute the Contract Price which shall not be modified except by written Change Order as provided in this Contract.
ARTICLE V
PAYMENT OF THE CONTRACT PRICE
5.1 SCHEDULE OF VALUES
5.1.1 Within ten (10) calendar days of the effective date hereof, the Contractor shall submit to the City and to the Engineer a Schedule of Values allocating the Contract Price to the various portions of the Work. The Contractor's Schedule of Values shall be prepared in such form, with such detail, and supported by such data as the Engineer or the City may require to substantiate its accuracy. The Contractor shall not imbalance its Schedule of Values nor artificially inflate any element thereof. The violation of this provision by the Contractor shall constitute a material breach of this Contract. The Schedule of Values shall be used only as a basis for the Contractor's Applications for Payment and shall only constitute such basis after it has been acknowledged and accepted in writing by the Engineer and the City.
5.2 PAYMENT PROCEDURE
5.2.1 The City shall pay the Contract Price to the Contractor as provided below.
5.2.2 PROGRESS PAYMENTS - Based upon the Contractor's Applications for Payment submitted to the Engineer and upon Certificates for Payment subsequently issued to the City by the Engineer, the City shall make progress payments to the Contractor on account of the Contract Price.
5.2.3 APPLICATION FOR PAYMENT - On or before the 25th day of each month after commencement of the Work, the Contractor shall submit an Application for Payment for the period ending the 15th day of the month to the Engineer in such form and manner, and with such supporting data and content, as the City or the Engineer may require. The Contractor may request payment for that portion of the Contract Price properly allocable to Contract requirements properly provided and to labor, materials and equipment properly incorporated in the Work, less retainage and less the total amount of previous payments received from the City. Such Application for Payment shall be signed by the Contractor and shall constitute the Contractor's representation that the Work has progressed to the level for which payment is requested in accordance with the Schedule of Values, that the Work has been properly installed or performed in full compliance with this Contract, and that the Contractor knows of no reason why payment should not be made as requested. Thereafter, the Engineer will review the Application for Payment and may also review the Work at the Project site or elsewhere to determine whether the quantity and quality of the Work is as represented in the Application for Payment and is as required by this Contract. The Engineer shall determine and certify to the City the amount properly owing to the Contractor. The City shall make partial payments on account of the Contract Price to the Contractor within thirty (30) days following the Engineer's receipt and approval of each Application for Payment. The amount of each partial payment shall be the amount certified for payment by the Engineer less such amounts, if any, otherwise owing by the Contractor to the City or which the City shall have the right to withhold as authorized by this Contract. The Engineer's certification of the Contractor's Application for Payment shall not preclude the City from the exercise of any of its rights as set forth in Paragraph 5.3 hereinbelow.
-6-
5.2.4 Each Application for Payment shall include a Statement of Delay showing the number of days lost due to inclement weather, conflicts with other City contractors, utilities, or design specifications, or other proper reasons.
The failure to submit the Statement of Delay shall be a waiver of any claim for additional days or extensions of the scheduled completion date.
5.2.5 If the Contract Price set forth in Subparagraph 4.1.1 is between $50,000 and $1,000,000, the City shall withhold retainage of ten (10) percent; if between 1,000,001 and $2,000,000, the City shall withhold retainage of seven and one-half (7½) percent; if over $2,000,000, the City shall withhold retainage of five (5) percent. If a different percentage is set forth in the Invitation to Bid/Request for Proposal, then that percentage shall apply. Retainage shall be withheld from each progress payment to secure performance of the Contract. The City shall deposit in an interest-bearing account that portion of any retainage withheld that exceeds five (5) percent of the progress payment. Interest earned on retainages in excess of five (5) percent of progress payments shall be paid to the Contractor with the final payment.
5.2.6 The Contractor warrants that title to all Work covered by an Application for Payment will pass to the City when installed at the Project site, regardless of the time of payment. The Contractor further warrants that upon submittal of an Application for Payment, all Work for which payments have been received from the City shall be free and clear of liens, claims, security interest or other encumbrances in favor of the Contractor or any other person or entity whatsoever.
5.2.7 The Contractor shall promptly pay each Subcontractor out of the amount paid to the Contractor on account of such Subcontractor's Work, the amount to which such Subcontractor is entitled. In the event the City becomes informed that the Contractor has not paid a Subcontractor as herein provided, the City shall provide written notice to the Contractor. If the Contractor fails to cure such payment issues within ten (10) days of receipt of City’s notice, the City shall have the right, but not the duty, to issue future checks in payment to the Contractor of amounts otherwise due hereunder naming the Contractor and such Subcontractor as joint payees. Such joint check procedure, if employed by the City, shall create no rights in favor of any person or entity beyond the right of the named payees to payment of the check and shall not be deemed to commit the City to repeat the procedure in the future.
5.2.8 No progress payment, nor any use or occupancy of the Project by the City, shall be interpreted to constitute an acceptance of any Work not in strict compliance with this Contract.
5.3 WITHHELD PAYMENT
5.3.1 The City may decline to make payment, may withhold funds, and, if necessary, may demand the return of some or all of the amounts previously paid to the Contractor, to protect the City from loss because of:
(a) defective Work not remedied by the Contractor or, in the opinion of the City, likely to be remedied by the Contractor;
(b) claims of third parties against the City or the City's property;
(c) failure by the Contractor to pay Subcontractors or others in a prompt and proper fashion, subject to Contractor’s right to cure;
(d) evidence that the balance of the Work cannot be completed in accordance with the Contract for the unpaid balance of the Contract Price,
(e) evidence that the Work will not be completed in the time required for substantial or final completion (final completion meaning the full and final completion of all work called for by this Contract and final acceptance by the Engineer and the City);
(f) persistent failure to carry out the Work in accordance with the Contract;
(g) damage to the City or a third party to whom the City is, or may be, liable.
-7-
(h) failure to submit an updated project schedule in accordance with Subparagraph 3.2.3.
(i) failure to submit record drawings in accordance with Subparagraph 7.9.1.
In the event that the City makes written demand upon the Contractor for amounts previously paid by the City as contemplated in this Subparagraph 5.3.1, the Contractor shall promptly comply with such demand. The City shall have no duty to third parties to withhold payment to the Contractor and shall incur no liability for a failure to withhold funds.
5.4 UNEXCUSED FAILURE TO PAY
5.4.1 If within fifteen (15) days after the date established herein for payment to the Contractor by the City, the City, without cause or basis hereunder, fails to pay the Contractor any amount then due and payable to the Contractor, then the Contractor may after ten (10) additional days' written notice to the City and the Engineer, and without prejudice to any other available rights or remedies it may have, stop the Work until payment of those amounts due from the City have been received. Late payments shall not accrue interest or other late charges.
5.5 CERTIFICATE OF SUBSTANTIAL COMPLETION
5.5.1 When the Contractor believes that the Work is substantially complete, the Contractor shall submit to the Engineer a list of items to be completed or corrected. When the Engineer and the City on the basis of an inspection determine that the Work is in fact substantially complete, the Engineer will prepare a Certificate of Substantial Completion which shall establish the date of Substantial Completion, shall state the responsibilities of the City and the Contractor for Project security, maintenance, heat, utilities, damage to the Work, and insurance, and shall fix the time within which the Contractor shall complete the items listed therein. In no event, however, shall the date of Final Completion be delayed. Guarantees required by the Contract shall commence on the date of Substantial Completion of the Work; however, the maintenance bond required herein, and the assurances given thereunder, shall commence of and from the date of final acceptance of the work by the City. The Certificate of Substantial Completion shall be submitted to the City and the Contractor for their written acceptance of the responsibilities assigned to them in such certificate.
Upon Substantial Completion of the Work, and execution by both the City and the Contractor of the Certificate of Substantial Completion, the City shall pay the Contractor an amount sufficient to increase total payments to the Contractor to one hundred percent (100%) of the Contract Price less three hundred percent (300%) of the reasonable cost as determined by the City and the Engineer for completing all incomplete Work, correcting and bringing into conformance all defective and nonconforming Work, and handling all unsettled claims.
5.6 COMPLETION AND FINAL PAYMENT
5.6.1 When all of the Work is finally complete and the Contractor is ready for a final inspection, it shall notify the City and the Engineer thereof in writing. Thereupon, the Engineer will make final inspection of the Work and, if the Work is complete in full accordance with this Contract and this Contract has been fully performed, the Engineer will promptly issue a final Certificate for Payment certifying to the City that the Project is complete and the Contractor is entitled to the remainder of the unpaid Contract Price, less any amount withheld pursuant to this Contract. If the Engineer is unable to issue its final Certificate for Payment and is required to repeat its final inspection of the Work, the Contractor shall bear the cost of such repeat final inspection(s) which cost may be deducted by the City from the Contractor's final payment.
5.6.1.1 If the Contractor fails to achieve final completion within thirty (30) days of Substantial Completion, the Contractor shall pay the City the sum set forth hereinabove as liquidated damages per day for each and every calendar day of unexcused delay in achieving final completion beyond the date set forth herein for final completion of the Work. Any sums due and payable hereunder by the Contractor shall be payable, not as a penalty, but as liquidated damages representing an estimate of delay damages likely to be sustained by the City, estimated at or before the time of executing this Contract. When the City reasonably believes that final completion will be inexcusably delayed, the City shall be entitled, but not required, to withhold from any amounts otherwise due the Contractor an amount then
-8-believed by the City to be adequate to recover liquidated damages applicable to such delays. If and when the Contractor overcomes the delay in achieving final completion, or any part thereof, for which the City has withheld payment, the City shall promptly release to the Contractor those funds withheld, but no longer applicable, as liquidated damages.
5.6.2 The Contractor shall not be entitled to final payment unless and until it submits to the Engineer its affidavit that all payrolls, invoices for materials and equipment, and other liabilities connected with the Work for which the City, or the City's property might be responsible, have been fully paid or otherwise satisfied; releases and waivers of lien from all Subcontractors of the Contractor and of any and all other parties required by the Engineer or the City;
consent of Surety, if any, to final payment. If any third party fails or refuses to provide a release of claim or waiver of lien as required by the City, the Contractor shall furnish a bond satisfactory to the City to discharge any such lien or indemnify the City from liability.
5.6.3 The City shall make final payment of all sums due the Contractor within thirty (30) days of the Engineer's execution of a final Certificate for Payment.
5.6.4 Acceptance of final payment shall constitute a waiver of all claims against the City by the Contractor except for those claims previously made in writing against the City by the Contractor, pending at the time of final payment, and identified in writing by the Contractor as unsettled at the time of its request for final payment.
5.6.5 Under no circumstance shall Contractor be entitled to receive interest on any payments or monies due Contractor by the City, whether the amount on which the interest may accrue is timely, late, wrongfully withheld, or an assessment of damages of any kind.
ARTICLE VI
THE CITY
6.1 INFORMATION, SERVICES AND THINGS
REQUIRED FROM CITY
6.1.1 The City shall furnish to the Contractor, at the time of executing this Contract, any and all written and tangible material in its possession concerning conditions below ground at the site of the Project. Such written and tangible material is furnished to the Contractor only in order to make complete disclosure of such material and for no other purpose. By furnishing such material, the City does not represent, warrant, or guarantee its accuracy either in whole, in part, implicitly or explicitly, or at all, and shall have no liability therefor. The City shall also furnish surveys, legal limitations and utility locations (if known), and a legal description of the Project site.
6.1.2 Excluding permits and fees normally the responsibility of the Contractor, the City shall obtain all approvals, easements, and the like required for construction and shall pay for necessary assessments and charges required for construction, use or occupancy of permanent structures or for permanent changes in existing facilities.
6.1.3 The City shall furnish the Contractor, free of charge, two copies of the Contract Documents for execution of the Work.
6.2 RIGHT TO STOP WORK
6.2.1 If the Contractor persistently fails or refuses to perform the Work in accordance with this Contract, if the Contractor fails to meet milestones set forth in approved construction schedules, if the City has sufficient reason to believe that the Contractor is not and will not complete the Project by the scheduled completion date, or if the best interests of the public health, safety or welfare so require, the City may order the Contractor to stop the Work, or any described portion thereof, until the cause for stoppage has been corrected, no longer exists, or the City orders that Work be resumed. In such event, the Contractor shall immediately obey such order.
-9-
6.3 CITY'S RIGHT TO PERFORM WORK
6.3.1 If the Contractor's Work is stopped by the City under Paragraph 6.2, and the Contractor fails within seven
(7) days of such stoppage to provide adequate assurance to the City that the cause of such stoppage will be eliminated or corrected, then the City may, without prejudice to any other rights or remedies the City may have against the Contractor, proceed to carry out the subject Work. In such a situation, an appropriate Change Order shall be issued deducting from the Contract Price the cost of correcting the subject deficiencies, plus compensation for the Engineer's additional services and expenses necessitated thereby, if any. If the unpaid portion of the Contract Price is insufficient to cover the amount due the City, the Contractor shall pay the difference to the City.
ARTICLE VII
THE CONTRACTOR
7.1 MUST FOLLOW CONTRACT
7.1.1 The Contractor is again reminded of its continuing duty set forth in Subparagraph 1.5.7. The Contractor shall perform no part of the Work at any time without adequate Contract Documents or, as appropriate, approved Shop Drawings, Product Data, or Samples for such portion of the Work. If the Contractor performs any of the Work knowing it involves a recognized error, inconsistency, or omission in the Contract Documents without such notice to the Engineer, the Contractor shall bear responsibility for such performance and shall bear the cost of correction.
7.2 PROSECUTION OF WORK
7.2.1 The Contractor shall perform the Work strictly in accordance with this Contract.
7.2.2 The Contractor shall supervise and direct the Work using the Contractor's best skill, effort and attention. The Contractor shall be responsible to the City for any and all acts or omissions of the Contractor, its employees and others engaged in the Work on behalf of the Contractor.
7.2.3 The Contractor shall give adequate attention to the faithful prosecution of the Work and the timely completion of this Contract, with authority to determine the manner and means of performing such Work, so long as such methods insure timely completion and proper performance.
7.2.4 The Contractor shall exercise all appropriate means and measures to insure a safe and secure jobsite in order to avoid and prevent injury, damage or loss to persons or property.
7.2.5 The City will not interfere with the Contractor’s manner and means of performing the Work. However, the City’s insistence on strict compliance with the Contract shall not be regarded as an interference with the Contractor’s manner and means. In the event that any part of the Work is not in strict compliance with the Contract, the Contractor is and shall be estopped from claiming any interference by the City or Engineer with the Contractor’s manner and means of performing that part of the Work.
7.3 WARRANTY
7.3.1 The Contractor warrants to the City that all labor furnished to progress the Work under this Contract will be competent to perform the tasks undertaken, that the product of such labor will yield only first-class results, that materials and equipment furnished will be of good quality and new unless otherwise permitted by this Contract, and that the Work will be of good quality, free from faults and defects and in strict conformance with this Contract. All Work not conforming to these requirements may be considered defective. THE CONTRACTOR WARRANTS AND
GUARANTIES THAT IT SHALL COMPLETE THE WORK AND ACHIEVE SUBSTANTIAL COMPLETION
BY THE SCHEDULED COMPLETION DATE, STRICTLY IN ACCORDANCE WITH THIS CONTRACT.
-10-
DEFECTIVE WORK OR MATERIALS SHALL BE FIXED, REPAIRED OR REPLACED FREE OF CHARGE OR
COST TO THE CITY.
7.4 PERMITS; FEES; LICENSES
7.4.1 The Contractor shall obtain and pay for all permits, fees, and licenses necessary and ordinary for the Work.
The Contractor shall comply with all lawful requirements applicable to the Work and shall give and maintain any and all notices required by applicable law pertaining to the Work.
7.5 SUPERVISION
7.5.1 The Contractor shall employ and maintain at the Project site only competent supervisory personnel. Absent written instruction from the Contractor to the contrary, the superintendent shall be deemed the Contractor's authorized representative at the site and shall be authorized to receive and accept any and all communications from the City or the Engineer.
7.5.2 Key supervisory personnel assigned by the Contractor to this Project are as follows:
NAME FUNCTION
So long as the individuals named above remain actively employed or retained by the Contractor, they shall perform the functions indicated next to their names unless the City agrees to the contrary in writing. In the event one or more individuals not listed above subsequently assume one or more of those functions listed above, the Contractor shall be bound by the provisions of this Subparagraph 7.5.2 as though such individuals had been listed above.
7.6 WORK SCHEDULE
7.6.1 The Contractor, within fifteen (15) days of commencing the Work, shall submit to the City and the Engineer for their information, the Contractor's schedule for completing the Work. The Contractor's schedule shall be revised no less frequently than monthly (unless the parties otherwise agree in writing) and shall be revised to reflect conditions encountered from time to time and shall be related to the entire Project. Each such revision shall be furnished to the City and the Engineer. Failure by the Contractor to strictly comply with the provisions of this Section 7.6 shall constitute a material breach of this Contract.
7.7 ON-SITE DRAWINGS
7.7.1 The Contractor shall continuously maintain at the site, for the benefit of the City and the Engineer, one record copy of this Contract marked to record on a current basis changes, selections and modifications made during construction. Additionally, the Contractor shall maintain at the site for the City and Engineer the approved Shop Drawings, Product Data, Samples, and other similar required submittals. Upon final completion of the Work, all of these record documents shall be delivered to the City.
7.8 RECORD DRAWINGS/PLANS, AS-BUILT PLANS, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES
7.8.1 Shop Drawings, Product Data, Samples, and other submittals from the Contractor do not constitute Contract Documents. Their purpose is merely to demonstrate the manner in which the Contractor intends to implement the Work in conformance with information received from the Contract Documents.
-11-
7.9.2 The Contractor shall not perform any portion of the Work requiring submittal and review of Shop Drawings, Product Data, or Samples unless and until such submittal shall have been approved by the Engineer. Approval by the Engineer, however, shall not be evidence that Work installed pursuant thereto conforms with the requirements of this Contract.
7.9 CLEANING THE SITE AND THE PROJECT
7.9.1 The Contractor shall keep the site reasonably clean during performance of the Work. Upon final completion of the Work, the Contractor shall clean the site and the Project and remove all waste, rubbish, temporary structures, and other materials together with all of the Contractor's property therefrom. Contractor shall dispose of all refuse at a Texas Natural Resource Conservation Commission approved landfill. The Contractor shall further restore all property damaged during the prosecution of the Work and shall leave the site in a clean and presentable condition.
No additional payment shall be made by the City for this work, the compensation having been considered and included in the contract price.
7.10 ACCESS TO WORK AND INSPECTIONS
7.10.1 The City and the Engineer shall have access to the Work at all times from commencement of the Work through final completion. The Contractor shall take whatever steps necessary to provide access when requested.
When reasonably requested by the City or the Engineer, the Contractor shall perform or cause to be performed such testing as may be necessary or appropriate to insure suitability of the jobsite or the Work’s compliance with the Contract requirements.
7.11 INDEMNITY AND DISCLAIMER
7.11.1 CITY SHALL NOT BE LIABLE OR RESPONSIBLE FOR, AND SHALL BE
INDEMNIFIED, DEFENDED, HELD HARMLESS AND RELEASED BY CONTRACTOR
FROM AND AGAINST ANY AND ALL SUITS, ACTIONS, LOSSES, DAMAGES, CLAIMS,
OR LIABILITY OF ANY CHARACTER, TYPE, OR DESCRIPTION, INCLUDING ALL
EXPENSES OF LITIGATION, COURT COSTS, AND ATTORNEY'S FEES, FOR INJURY OR
DEATH TO ANY PERSON, INJURY OR LOSS TO ANY PROPERTY, OR ECONOMIC LOSS,
RECEIVED OR SUSTAINED BY ANY PERSON OR PERSONS, INCLUDING THE
CONTRACTOR, OR PROPERTY, DIRECTLY OR INDIRECTLY ARISING OUT OF, OR
OCCASIONED BY THE PERFORMANCE OF CONTRACTOR UNDER THIS CONTRACT,
INCLUDING CLAIMS AND DAMAGES ARISING IN WHOLE OR IN PART FROM THE
NEGLIGENCE OF CITY, WITHOUT WAIVING THE CITY’S GOVERNMENTAL,
SOVEREIGN OR OTHER IMMUNITIES OR DEFENSES AVAILABLE TO THE CITY
UNDER TEXAS LAW AND WITHOUT WAIVING ANY DEFENSES OF THE PARTIES
UNDER TEXAS LAW. IT IS THE EXPRESS INTENT OF THE PARTIES TO THIS
CONTRACT THAT THE INDEMNITY PROVIDED FOR HEREIN IS AN INDEMNITY
EXTENDED BY CONTRACTOR TO INDEMNIFY AND PROTECT CITY FROM THE
CONSEQUENCES OF THE CONTRACTOR’S AS WELL AS THE CITY'S NEGLIGENCE,
WHETHER SUCH NEGLIGENCE IS THE SOLE OR PARTIAL CAUSE OF ANY SUCH
INJURY, DEATH, OR DAMAGE.
The provisions of this indemnification are solely for the benefit of the parties hereto and not intended to create or grant any rights, contractual or otherwise, to any other person or entity.
7.11.2 The Contractor will secure and maintain contractual liability insurance to cover this indemnification agreement that will be primary and non-contributory as to any insurance maintained by the City for its own benefit, including self-insurance. In addition, Contractor shall obtain and file with City a standard form Certificate of Insurance and copies of policy endorsements evidencing the required coverage.
-12-
7.11.3 In claims against any person or entity indemnified under this Paragraph 7.11 by an employee of the Contractor, a Subcontractor, anyone directly or indirectly employed by them or anyone for whose acts they may be liable, the indemnification obligation under this Paragraph 7.11 shall not be limited by a limitation on amount or type of damages, compensation, or benefits payable by or for the Contractor or a Subcontractor under workers' compensation acts, disability benefit acts or other employee benefit acts.
7.12 NONDISCRIMINATION
7.12.1 The Contractor shall not discriminate in any way against any person, employee or job applicant on the basis of race, color, creed, national original, religion, age, sex, or disability where reasonable accommodations can be effected to enable the person to perform the essential functions of the job. The Contractor shall further insure that the foregoing nondiscrimination requirement shall be made a part and requirement of each subcontract on this Project.
7.13 PREVAILING WAGE RATES
7.13.1 The Contractor shall comply in all respects with all requirements imposed by any laws, ordinances, or resolutions applicable to the Project with regard to the minimum prevailing wage rates for all classes of employees, laborers, subcontractors, mechanics, workmen, and persons furnishing labor and services to the Project. The City has adopted a Prevailing Wage Rate Schedule, available to the Contractor by request (or attached to this contract as a part of the exhibits), which specifies the classes and wage rates to be paid to all persons. The Contractor shall pay not less than the minimum wage rates established thereby for each class, craft, or type of labor, workman, or mechanic employed in the execution of this Contract. The failure of the Contractor to comply with this requirement shall result in the forfeiture to the City of a sum of not less than Sixty Dollars ($60.00) for each person per day, or portion thereof, that such person is paid less than the prevailing rate. Upon request by the City, Contractor shall make available for inspection and copying its books and records, including but not limited to its payroll records, account information and other documents as may be required by the City to insure compliance with this provision.
7.14 JOB SITE SAFETY PRECAUTIONS
7.14.1 The Contractor shall at all times exercise reasonable precautions for the safety of its employees, laborers, subcontractors, mechanics, workmen, and others on and near the jobsite and shall comply with all laws, ordinances, regulations, and standards of federal, state, and local safety laws and regulations. The Contractor shall provide such machinery guards, safe walk-ways, ladders, bridges, and other safety devices as may be necessary or appropriate to insure a safe and secure jobsite and shall require its subcontractors to comply with this requirement. The Contractor shall immediately comply with any and all safety requirements imposed by the Engineer during the progress of the Work.
7.15 WARNING DEVICES AND BARRICADES
7.15.1 The Contractor shall furnish and maintain such warning devices, barricades, lights, signs, pavement markings, and other devices as may be necessary or appropriate or required by the Engineer to protect persons or property in, near, or adjacent to the jobsite. No separate compensation shall be paid to the Contractor for such measures. Where the Work is being conducted in, upon or near streets, alleys, sidewalks, or other rights-of-way, the Contractor shall insure the placement, maintenance, and operation of any and all such warning devices as may be required by the City and shall do so until no longer required by the City. Such devices shall be in compliance with and conform to the manual and specifications for the uniform system of traffic control devices adopted by the Texas Department of Transportation.
7.16 PROTECTION OF UTILITIES AND OTHER CONTRACTORS
7.16.1 The Contractor shall use best efforts to leave undisturbed and uninterrupted all utilities and utility services provided to the jobsite, or which presently exists at, above, or beneath the location where the Work is to be performed.
In the event that any utility or utility service is disturbed or damaged during the progress of the Work, the Contractor shall forthwith repair, remedy or restore the utility at Contractor’s sole expense. The Contractor shall coordinate any
-13-utility conflicts with the owner of the utility and no extension of time will be requested or given if adequate coordination is not provided by Contractor.
7.16.2 The Contractor understands and acknowledges that other contractors of the City or of other entities may be present at the jobsite performing other work unrelated to the Project. The Contractor shall use best efforts to work around other contractors without impeding the work of others while still adhering to the completion date established herein. In the event that the Contractor’s work is or may be delayed by any other person, the Contractor shall immediately give notice thereof to the City and the Engineer and shall request a written Change Order in accordance with the procedures set forth by this Contract. The Contractor’s failure to provide such notice and to request such Change Order shall constitute a waiver of any and all claims associated therewith.
ARTICLE VIII
CONTRACT ADMINISTRATION
8.1 THE ENGINEER
8.1.1 When used in this Contract the term “Engineer” does not necessarily denote a duly licensed, trained or certified engineer; as used herein, the term shall be used interchangeably and shall mean a designated Engineer, Architect, or Contract Administrator (who may not be an architect or engineer) for the City, said person to be designated or…