MC-0322784_Project_Manual.pdf
PDF 7 MB Posted
- Attached to
- Emerson St. Sinkhole Repair
- Solicitation number
- MC-0322784, WP# N10346
- Issued by
- King County, Spokane City, Washington
About this file
Emerson St Sinkhole Repair – Project Manual and Bidding Documents
This is a Project Manual and bidding document package issued by the Port of Seattle for the Emerson St Sinkhole Repair project (MC-0322784, WP #N10346) located at 1795 W Emerson Street, Seattle, Washington 98119. The project involves the repair of a disconnect between the King County sewer line and the BNSF stormwater/sewer line under West Emerson Street through the demolition and replacement of approximately 125 feet of storm drain running under West Emerson Street and 16th Avenue West at depths up to 15 feet. Work includes sealing the existing King County connection point and creating a new connection requiring coordination with King County, installation of one new catch basin in Emerson Street, replacement of an existing catch basin on port property, asphalt excavation in the roadway, and roadway repaving with extensive traffic controls on a busy arterial street. The project requires substantial completion within 120 calendar days from contract execution. Electronic bids must be submitted by email to const-proposal@portseattle.org by October 26, 2026 at 2:00 p.m., with public bid opening via Microsoft Teams at 3:00 p.m. the same day. A pre-bid meeting is scheduled for October 5, 2026 at 11:00 a.m. via virtual attendance through Microsoft Teams or telephone conference.
The Engineer's estimate range for this project is $400,000 to $600,000. Bidders must submit a bid bond or other bid security equal to not less than 5 percent of the total bid amount. The successful bidder must provide Performance and Payment Bonds in the full amount of the contract sum and current insurance certificates prior to contract execution. A Women and Minority Business Enterprise (WMBE) utilization goal of 8 percent has been established for this contract. Bids will be evaluated on a lowest responsible bidder basis, with responsibility criteria including current Washington contractor registration, Washington unified business identifier number, Department of Revenue excise tax registration, workers' compensation coverage, compliance with prevailing wage and apprenticeship requirements, and no disqualification under RCW 39.06.010 or 39.12.065(3). The Port reserves the right to reject any or all bids, waive informalities, and cancel the award before contract execution. Protest procedures are available for interested parties within specified timeframes, with administrative appeals available for contracts exceeding $200,000 in value.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Issued by:
THE PORT OF SEATTLE COMMISSION
EMERSON ST SINKHOLE REPAIR
at 1795 W Emerson Street, Seattle, WA 98119
PROJECT MANUAL
Divisions 00-33
MC-0322784
WP# N10346
September 26, 2026
DIVISION 0 - BIDDING REQUIREMENTS, CONTRACT FORMS AND CONDITIONS OF THE CONTRACT
Document 00 00 00b - Attention to Bidders
MC-0322784 / WP #N10346 00 00 00b-1 Rev. 08/14/2025
ATTENTION TO BIDDERS
The following bid forms are included in the Bid Package and must be completed , signed and submitted as indicated below. This is only a checklist for your use and not required to be submitted as part of the bid.
Bid Submittal Requirements Checklist
Complete
1. Bid Form, Document 00 41 00 (submit with bid)
2. Acknowledge all addenda on the bid form
3. Bid Bond or other Bid Security (submit with bid)
4. Women and Minority Business Enterprise (WMBE) Commitment Plan Form (submit with bid or within one (1) hour after the published bid submittal time)
5. Verify Responsibility Criteria is met as listed in Document 00 20 00 Instructions to Bidders Section IB 6.03
Document 00 00 00c - Notice to Bidders
MC-0322784 / WP #N10346
Rev. 06/13/2024
NOTICE TO BIDDERS
NOTICE REGARDING DIVERSITY IN CONTRACTING
The Port is providing the following list to assist Bidder’s in locating subcontractors and suppliers from the Washington State Office of Minority and Women’s Business Enterprises (OMWBE) directory for this contract. The following list of North American Industry Classification System (NAICS) codes may not be inclusive of all trades that may be utilized for this work and should not be relied upon as the only source of completing the Inclusion Plan.
NAICS Number & Description
238910 - Site Preparation Contractors
237310 - Highway, Street, and Bridge Construction
561990 - All Other Support Services
532490 - Other Commercial and Industrial Machinery and Equipment Rental and Leasing
562212 - Solid Waste Landfill
NOTICE REGARDING PLANHOLDER LISTS
The Contractor’s list for this job is continually changing by the addition of new planholders. The planholders list is available at the Port’s VendorConnect website at https://hosting.portseattle.org/sops; click on “Current and Past Solicitations” and select this project, then select “Plan Holder”.
NOTICE REGARDING SITE INSPECTION
To register for the Pre-Bid Meeting, log into VendorConnect at https://hosting.portseattle.org/sops; click on “Current and Past Solicitations” and then on the solicitation of interest and click on the “Events” tab and then on “Login to RSVP.” The preferred method for registration is through the Port’s VendorConnect website. If a bidder does not have the capability to register on-line, then they may contact Marilynn Montenegro, Procurement Officer, at 206-886-9628 to register.
A Pre-bid Meeting will be held on the date, time and location indicated in Document 00 10 00 – Advertisement for Bids.
NOTICE REGARDING BID CLARIFICATIONS
To submit questions regarding Bidding Documents, log into VendorConnect at https://hosting.portseattle.org/sops/; click on “Current and Past Solicitations” and then on the solicitation of interest and “Ask a Question”. Vendors must be a Plan Holder to ask a question.
The preferred method for submitting questions is through the Port’s VendorConnect website. If a bidder does not have on-line capability, submit all questions to the address in Document 00 20 00, paragraph IB-04.02 B 1.
https://hosting.portseattle.org/sops https://hosting.portseattle.org/sops https://hosting.portseattle.org/sops/
TABLE OF CONTENTS
MC-0322784 / WP #N10346
Rev. 8/12/2024
Emerson St Sinkhole Repair
TABLE OF CONTENTS
DIVISION 0
BIDDING REQUIREMENTS, CONTRACT FORMS AND CONDITIONS OF THE CONTRACT
NUMBER DOCUMENT TITLE PREPARER
00 10 00 Advertisement for Bids POS 00 20 00 Instructions to Bidders POS 00 41 00 Bid Form POS 00 52 00 Agreement Forms POS 00 60 00 Bonds and Certificates POS 00 70 00 General Conditions POS 00 80 00 Supplementary Conditions POS 00 83 00 Civil Rights, Title VI, and Non-Discrimination POS 00 89 00 Women and Minority Business Enterprise Inclusion Plan POS
DIVISION 1
GENERAL REQUIREMENTS
NUMBER
SECTION TITLE PREPARER
01 11 00 Summary of Work POS 01 20 00 Measurement and Payment Procedures POS 01 25 00 Substitutions POS 01 31 00 Contractor’s Project Organization POS 01 31 13 Project Coordination POS 01 31 19 Project Meetings POS 01 32 16 Bar Chart Schedule POS 01 32 19 Preconstruction Submittals POS 01 33 00 Submittals POS 01 35 29 Safety Management POS 01 35 43 Environmental Regulatory Requirements POS 01 45 16.13 Contractor Quality Control POS 01 45 29 Independent Testing and Inspection Service POS 01 50 00 Temporary Facilities and Controls POS 01 55 16 Haul Routes POS 01 55 26 Traffic Control POS
Rev. 8/12/2024
DIVISION 1
GENERAL REQUIREMENTS
NUMBER
SECTION TITLE PREPARER
01 57 13 Temporary Erosion and Sediment Control (TESC) Planning and Execution POS
01 57 23 Pollution Prevention, Planning and Execution POS 01 59 00 Construction Water Management System POS 01 71 13 Mobilization/Demobilization POS 01 71 23.16 Surveying POS 01 73 29 Cutting and Patching/Removal and Re-Installation POS 01 74 00 Cleaning POS 01 74 19 Construction Waste Management POS 01 77 00 Construction Project Closeout POS 01 77 20 Public Works Project Closeout POS 01 78 23 Seaport Operations and Maintenance Documentation POS 01 78 29 As-Built Redline Documents POS 01 78 36 Warranties and Bonds POS 01 78 39 Contract Management System POS 01 79 00 Training POS 01 91 00.13 Commissioning Activities POS
DIVISION 2
EXISTING CONDITIONS
NUMBER SECTION TITLE PREPARER
02 41 13 Site Demolition CTR 02 61 13 Handling Contaminated Soil CTR 02 87 00 Fugitive and Silica Dust Control Procedures CTR
DIVISION 3
CONCRETE
NUMBER SECTION TITLE PREPARER
03 11 00 Concrete Forms CTR 03 30 00 Cast-in-Place Concrete CTR
Rev. 8/12/2024
DIVISION 31
EARTHWORK
NUMBER SECTION TITLE PREPARER
31 00 00 Earthwork CTR 31 23 19 Dewatering CTR 31 50 00 Trench Safety Systems CTR
DIVISION 32
EXTERIOR IMPROVEMENTS
NUMBER SECTION TITLE PREPARER
32 11 00 Base Course CTR 32 12 16.13 Bituminous Concrete Pavement CTR 32 16 13 Curbs and Gutters CTR 32 17 23 Pavement Markings CTR
DIVISION 33
UTILITIES
NUMBER SECTION TITLE PREPARER
33 41 00 Storm Drainage CTR
Table of Contents - Certification of Technical Specifications
MC-0322784 / WP #N10346
Rev. 01/14/14
CERTIFICATION OF TECHNICAL SPECIFICATIONS
Technical Specifications in this project manual were prepared by the design professionals whose initials appear opposite the Specification Division or Section in the Table of Contents.
Stamps, names and initials of the Design Professionals are:
NAME INITIALS
CTR
End of Document
09/01/2026
Document 00 10 00 - Advertisement for Bids
MC-0322784 / WP #N10346 0 00 10 00-1
Rev. 03/25/2026
MC-0322784 - EMERSON ST SINKHOLE REPAIR
Bids must be submitted via email to const-proposal@portseattle.org no later than October 26, 2026 2:00 p.m.
The public bid opening will be hosted via video conferencing and by telephone October 26, 2026 at 3:00 pm. The Port of Seattle is not responsible for any costs incurred in response to this Advertisement for Bids. Any bids received after the published bid submittal time will be rejected.
Join MSTeams Meeting Link to attend the Bid Opening (ctrl + mouse click) or join by phone
(833) 209-2690 and use Conference ID #: 298 712 452#.
Visit the Port’s Vendor Connect procurement site for further details and to access the bid documents: https://hosting.portseattle.org/sops/#/Dashboard A pre-bid meeting will be conducted on October 5, 2026 at 11:00 am. IF ATTENDING VIRTUALLY, join via MSTeams Meeting Link (ctrl + mouse click) or join by phone (833) 209- 2690 and use Conference ID #: 432 932 698#.
See Document 00 20 00 – Instructions to Bidders - IB 4.06 for more information.
This project is to repair a disconnect between the King County sewer line and the BNSF stormwater/sewer line under West Emerson Street. Work will entail demolition and replacement of roughly 125’ of storm drain that runs under West Emerson Street and 16th Avenue West. The depth will be up to 15’ at the deepest point. The existing connection point to the King County line will need to be sealed and a new connection will be made. Coordination with King County will be required. One new catch basin will be installed in Emerson Street, and an existing catch basin on port property will be replaced. This work will require asphalt excavation in the roadway and repaving of the roadway. The project requires considerable traffic controls (Impacts several lanes of traffic on a busy roadway) located at 1795 W Emerson Street, Seattle, WA 98119.
The Engineer’s estimate range for this project is $400,000 - $600,000.
The time limit for substantial completion is 120 calendar days.
The WMBE utilization goal is 8% for this contract.
By submission of a bid, the Bidder certifies they will comply with all local, state, federal, and other laws, rules, regulations, and other requirements applicable to its operations relating to environmental responsibility, worker safety, labor, anti-discrimination and anti-human trafficking.
The Bidder/Proposer is also acknowledging that it will adhere to the Values and Standards of the Port of Seattle. A copy of the Third-Party Expectations is included in Document 00 83 00.
TITLE VI SOLICITATION NOTICE
The Port of Seattle, in accordance with the provisions of Title VI of the Civil Rights Act of 1964 (78 Stat. 252, 42 U.S.C. §§ 2000d to 2000d-4), 28 CFR § 50.3, and 49 CFR Part 21, hereby notifies all bidders that it will affirmatively ensure that any contract entered into pursuant to this advertisement, all contractors will be afforded full opportunity to submit bids in response to this invitation and will not be discriminated against on the grounds of the owner’s race, color, national origin, sex, creed, age, or disability in consideration for an award.
Any such complaint must be in writing and filed with the Port’s Title VI Coordinator within one hundred, eighty (180) days following the date of the alleged discriminatory occurrence. Title VI Discrimination Complaint Forms may be obtained from the office of the Tittle VI Coordinator at no cost to the complainant by sending an email to TitleSixCoordinator@portseattle.org.
mailto:const-proposal@portseattle.org https://teams.microsoft.com/meet/298509858844744?p=7y4kPZ4EdpqoghupIP https://hosting.portseattle.org/sops/#/Dashboard https://teams.microsoft.com/meet/223983329633360?p=qyIHBJbABSaIKMReS6 mailto:TitleSixCoordinator@portseattle.org
Document 00 10 00 - Advertisement for Bids
MC-0322784 / WP #N10346 0 00 10 00-2
Rev. 03/25/2026
Dated at Seattle, Washington, September 25, 2026.
AUTHORIZED BY THE PORT COMMISSION OF THE PORT OF SEATTLE
Yanet Maldonado
Manager, Procurement, Central Procurement Office, PORT OF SEATTLE
First Publication: September 25, 2026 Final Publication: October 2, 2026
DIVISION 0 – BIDDING REQUIREMENTS, CONTRACT FORMS AND CONDITIONS OF THE CONTRACT
Document 00 20 00 – Instructions to Bidders
MC-0322784 / WP #N10346 00 20 00-1
Rev. 08/10/2026
CONTENTS
ARTICLE 1 - DEFINITIONS
IB-01.01 Definitions
ARTICLE 2 - QUALIFICATION OF BIDDERS
IB-02.01 General IB-02.02 Special Qualification Questionnaires
IB-02.03 RESERVED
IB-02.04 RESERVED
IB-02.05 Civil Rights, Title VI, and Non-Discrimination IB-02.06 Port of Seattle Values, Anti-Human Trafficking:
ARTICLE 3 – BIDDER’S REPRESENTATIONS
IB-03.01 General
ARTICLE 4 - BIDDING DOCUMENTS
IB-04.01 Availability IB-04.02 Interpretation and Clarification IB-04.03 Substitutions IB-04.04 Addenda IB-04.05 Additional Information Provided by the Port IB-04.06 Pre-Bid Meeting
ARTICLE 5 - BONDING & INSURANCE REQUIREMENTS
IB-05.01 Bid Bond IB-05.02 Performance and Payment Bond Costs IB-05.03 Contract Bonds and Insurance Certificates IB-05.04 Power of Attorney
ARTICLE 6 - EXECUTION OF BID
IB-06.01 Form of Bid IB-06.02 Irregular Bids IB-06.03 Responsible Bidder IB-06.04 Non-Responsive Bid
IB-06.05 RESERVED
MC-0322784 / WP #N10346 00 20 00-2
Rev. 08/10/2026
IB-06.06 State and Local Taxes
ARTICLE 7 - SUBMISSION OF BIDS
IB-07.01 Submission of Bid IB-07.02 Timely Delivery
ARTICLE 8 - WITHDRAWAL OR MODIFICATION OF BIDS
IB-08.01 Prior to Bid Opening IB-08.02 After Bid Opening IB-08.03 Resubmittal of Modified Bids
ARTICLE 9 - OPENING OF BIDS
IB-09.01
IB-09.02
IB-09.03
IB-09.04
IB-09.05
Public Opening Reading of Bids Evaluation of Bids
RESERVED
RESERVED
ARTICLE 10 - ACCEPTANCE OF BIDS (AWARD)
IB-10.01 Verification of Bid Prices IB-10.02 Return of Bid Security IB-10.03 Rights of the Port IB-10.04 Failure to Execute Contract IB-10.05 Notice of Intent to Award IB-10.06 Extension of Time IB-10.07 Signing of Contract IB-10.08 Cancellation of Award
ARTICLE 11 - PROTESTS
IB-11.01 Purpose IB-11.02 Timing IB-11.03 Contents of Protest IB-11.04 Administrative Appeal Procedures IB-11.05 Judicial Proceedings IB-11.06 Strict Compliance IB-11.07 Representation
MC-0322784 / WP #N10346 00 20 00-3
Rev. 08/10/2026
IB-11.08 Computation of Time IB-11.09 Acknowledgement
ARTICLE 12 - FORM OF AGREEMENT
IB-12.01 Form of Agreement
MC-0322784 / WP #N10346 00 20 00-4
Rev. 08/10/2026
ARTICLE 1: DEFINITIONS
IB-01.01 - DEFINITIONS
All definitions set forth in the General Conditions of the Contract, or other definitions within the Contract Documents are applicable to the Bidding Documents.
A. Alternate Bid: The sum stated in the Bid offered by the Bidder to be added to or deducted from the Base Bid for Work described as a change in the project. An Alternate Bid may change price, time, scope, materials, or methods of construction.
B. Base Bid: The sum stated in the Bid offered by the Bidder to perform the Work described as the base, to which Work may be added to or deducted from based upon the sum(s) of Alternate or Alternative bids accepted by the Port.
C. Bidding Documents: Bidding Documents include references therein, namely the Advertisement, Instruction to Bidders, Bid form, Sample forms, supplemental forms and the proposed Contract Documents including Addenda, if any, issued prior to the time specified for opening of the Bids.
D. Small Works: Construction contracts with a total cost less than $350,000.00.
E. Substitutions: The product, equipment, material, or method proposed by a Bidder or Contractor to be incorporated into this project in place of that specified.
Substitutions are not Alternative Bids. Substitutions shall not be considered prior to award.
F. Unit Price: An amount stated in the Bid as the price for a particular unit of the Work measured as described within the Contract Documents.
ARTICLE 2: QUALIFICATION OF BIDDERS
IB-02.01 - GENERAL
A. Generally, no prequalification requirements are imposed prior to submitting a Bid.
However, the Port of Seattle may make such investigations as they deem necessary to determine the ability of the Bidder to perform the Work. The Bidder shall furnish to the Port all such information and data for this purpose as the Port may request. The Port reserves the right to reject any Bid if the evidence submitted by, or investigation of, such Bidder fails to satisfy the Port that such Bidder is properly qualified to carry out the obligations of the contract and to complete the Work contemplated therein.
1. In accordance with RCW 39.04.380 effective March 30, 2012, the State of Washington is enforcing a Reciprocal Preference for Resident Contractors. Any public works bid received from a nonresident contractor from a state that provides an in-state percentage bidding preference, a comparable percentage disadvantage must be applied to the bid of that
MC-0322784 / WP #N10346 00 20 00-5
Rev. 08/10/2026 nonresident contractor. A nonresident contractor from a state that provides a percentage bid preference means a contractor that:
a) is from a state that provides a percentage bid preference to its resident contractors bidding on public works contracts; and
b) at the time of bidding on a public works project, does not have a physical office located in Washington.
The state of residence for a nonresident contractor is the state in which the Contractor was incorporated or, if not a corporation, the state where the contractor's business entity was formed. All nonresident contractors will be evaluated for out of state bidder preference. If the state of the nonresident contractor provides an in-state contractor preference, a comparable percentage disadvantage will be applied to their bid prior to contract award. This section does not apply to public works procured pursuant to RCW 39.04.155, 39.04.280, or any other procurement exempt from competitive bidding.
B. The Bidder must be familiar with all Federal, State and local laws, including RCW
18.27 Registration of Contractors, ordinances and regulations which in any manner might affect those engaged or employed in the Work, the materials, equipment or procedures used in the Work, or which in any other way would affect the conduct of the Work. It is assumed the Bidder is familiar with such laws and regulations, and no plea of misunderstanding or ignorance of the law will be considered.
C. The Bidder must be registered and licensed as may be required by the laws of the State of Washington at the time Bids are publicly opened.
IB-02.02 - SPECIAL QUALIFICATION QUESTIONNAIRES
Special qualification questionnaires, if any, shall be submitted as requested.
IB-02.03 – RESERVED
IB-02.04 - RESERVED
IB-02.05 - CIVIL RIGHTS, TITLE VI, AND NON-DISCRIMINATION:
A. Bidders are required to comply with Port policies, procedures and requirements relating to Resolution 3668 – Non-Discrimination and Equal Opportunity, a copy is included in Document 00 83 00.
IB-02.06 – PORT OF SEATTLE VALUES, ANTI-HUMAN TRAFFICKING:
A. The Proposer certifies they will comply with all local, state, federal, and other laws, rules, regulations, and other requirements applicable to its operations, including those relating to environmental responsibility, worker safety, labor, anti-discrimination, and anti-human trafficking. The Bidder/Proposer is also
MC-0322784 / WP #N10346 00 20 00-6
Rev. 08/10/2026 acknowledging that it will adhere to the Values and Standards of the Port of Seattle, refer to “Third Party Expectations” a copy is included in Document 00 83 00.
ARTICLE 3: BIDDER'S REPRESENTATION
IB-03.01 - GENERAL
Each Bidder, by submitting a Bid, represents that:
A. The Bidder has read and understands the Bidding Documents and that the Bid is made in accordance with all applicable documents.
B. The Bidder has inspected or investigated the site(s) of the Work (if a site investigation was offered) and has become familiar with the local conditions under which the Work is to be performed and has familiarized itself with the quantity and character of all materials to be demolished.
C. The Bid is based upon the Work described or presented within the Bidding Documents and described in detail in the Project Manual.
D. The failure or omission of the Bidder to examine all pertinent forms, instruments, applicable statutes, or other documents shall in no way relieve the Bidder from the contractual obligations required by the Bidding Documents.
E. The Bid submitted is unconditional in all respects.
ARTICLE 4: BIDDING DOCUMENTS
IB-04.01 - AVAILABILITY
A. Copies of the Project Manual and Drawings may be viewed on VendorConnect at:
https://hosting.portseattle.org/sops/.
B. Only complete sets of Bidding Documents shall be used in preparing bids. The Port of Seattle assumes no responsibility for errors or misinterpretations resulting from the use of incomplete sets of Bidding Documents.
C. Bidding Documents issued as stated above are for bidding purposes only. The Port does not confer a license or grant for any other use.
IB-04.02 - INTERPRETATION & CLARIFICATION
A. Bidders shall promptly notify the Port of ambiguities, inconsistencies, or errors, if any, which they may discover upon examination of the Bidding Documents or of the site and local conditions.
1. Every request for interpretation or clarification should be submitted using the Port’s VendorConnect website https://hosting.portseattle.org/sops/. If a Bidder does not have on-line capability, then submit in writing, addressed to the Bid Desk, Port of Seattle, 17900 International Blvd., Suite 400 B, MC-0322784 / WP #N10346 00 20 00-7
Rev. 08/10/2026
Sea-Tac, WA 98188. To be given consideration the request must be received seven (7) working days prior to the date fixed for the opening of the bids.
2. The Port’s responses, if there are any, which do not change the Scope of Work described in the contract documents may be mailed, delivered, telegraphed, faxed, or by other electronic means, to all plan holders of record, at the respective address furnished for such purposes, prior to the date fixed for the receipt of bids. Such letters of clarification shall not be considered part of the contract documents and therefore need not be acknowledged by the Bidders as part of the Bid Form. The Port will determine at its sole discretion whether or not any clarification or interpretation changes the Scope of Work and should be included in the Contract Documents.
3. Clarifications, interpretations, or supplemental instructions which do change the Scope of Work and or schedule described in the contract documents, will be issued only in the form of written addenda.
B. Oral interpretations or clarifications will be without legal effect.
IB-04.03 - SUBSTITUTIONS
A. The product, equipment, materials, or methods described or noted within the Bidding Documents, whether currently available or not, are to establish a standard of quality, function, appearance and dimension. A proposed substitution shall have equal attributes in all respects.
B. No substitution will be considered unless a written request for approval is submitted by the Contractor, after Award, in accordance with the applicable provisions of Section 01 25 00 of these specifications. Each such request shall describe the proposed substitution in its entirety including name of the material or equipment, drawings, catalog cuts, performance or test data and all other information required for an evaluation. The submittal shall also include a statement noting all changes required in adjoining, dependent or other interrelated work necessitated by the incorporation of the proposed substitute. The Bidder shall bear the burden of proof of merit of the proposed substitution. The Engineer’s decision of approval or disapproval of a proposed substitution shall be final.
IB-04.04 - ADDENDA
A. Addenda will be issued on the Port’s VendorConnect website https://hosting.portseattle.org/sops/. Bidder is required to sign up as a plan holder to receive addenda notifications prior to the date fixed for the receipt of bids.
B. Each Bidder shall acknowledge on Bid that it has obtained all addenda issued.
C. All addenda so issued shall become part of the Contract Documents.
MC-0322784 / WP #N10346 00 20 00-8
Rev. 08/10/2026
IB-04.05 - ADDITIONAL INFORMATION PROVIDED BY THE PORT
A. The following documents are available on the Port’s VendorConnect website for the Bidder’s inspection and information:
1. MC-0322784_REFERENCE_A_SDOT_StreetUsePermit
2. MC-0322784_REFERENCE_B_Seattle_SideSewerPermit
IB-04.06 – PRE-BID MEETING
A. A Pre-Bid Meeting will be conducted October 5, 2026 at 11:00 am at the following locations:
Virtual Via Microsoft Teams Meeting or via Telephone.
To attend the meeting, go to the following link via MSTeams Meeting Link (ctrl + mouse click) Meeting ID: 223 983 329 633 360
Passcode: Td6jb6EW
To join by phone by call (833) 209-2690.
Conference ID # 432932698#.
B. No site tour is scheduled for this project. The work site is accessible to the public.
Prior to the deadline for submission of bids, you may submit your questions through the Port’s VendorConnect website https://hosting.portseattle.org/sops/.
The prospective bidder further agrees to indemnify, and hold harmless, the Port of Seattle and its agents from any and all claims of personal injury arising from its examination of the work site.
ARTICLE 5: BONDING & INSURANCE REQUIREMENTS
IB-05.01 - BID BOND
Each Bid shall be accompanied by a Bid security, cashier’s check, money order, or surety bid bond, in the amount of not less than five percent (5%) of the total bid including Alternates, if any. A bid bond shall not be conditioned in any way to modify the minimum five percent (5%) required. Surety companies executing Bid Bonds must appear on the U.S. Treasury Department’s most current list (Circular 570 as amended) and be authorized to transact business in the State of Washington. In addition, the surety must be rated “A-, FSC (VI)”, or higher by A.M. Best Rating Guide. Checks shall be payable to the Port of Seattle.
IB-05.02 –BOND COSTS
The costs or premiums for all bonds shall be paid by the successful bidder.
https://teams.microsoft.com/meet/223983329633360?p=qyIHBJbABSaIKMReS6
MC-0322784 / WP #N10346 00 20 00-9
Rev. 08/10/2026
IB-05.03 - CONTRACT BONDS AND INSURANCE CERTIFICATES
A. Prior to the execution of the Contract, the successful bidder shall furnish Insurance Certificates, Performance Bond and a Payment Bond covering the faithful performance of the Contract and the payment of all obligations arising there under.
Each Performance and Payment bond shall be in the full amount of the Contract Sum. See Document 00 70 00 - General Conditions Article G-11 for more information.
B. FAILURE TO PROVIDE BONDS
1. Failure to provide timely Performance and Payment Bonds will result in non-Award and forfeiture of any Bid bond or Security to the Port.
2. The Port may, from time to time, require the Contractor’s Surety (or
Sureties) to appear and qualify themselves upon the bonds. If such Surety (or Sureties) refuse or fail to so appear and qualify, or if the Port determines that such Surety (or Sureties) are insufficient to fulfill the terms and conditions of the bonds, then the Port shall require the Contractor to furnish additional Surety (or Sureties) as may be necessary to fulfill the terms and conditions of the bonds.
3. If the Contract Sum is increased by Change Order, the Contractor agrees to provide the Port with such additional Performance and Payment Bonds as required to assure performance of any additional Work and payment for the labor and materials incidental to such Work.
IB-05.04 - POWER OF ATTORNEY
Attorneys-in-fact who sign Bid Bonds or Contract Bonds must file with each bond a certified and effectively dated copy of their Power of Attorney.
ARTICLE 6- EXECUTION OF BID
IB-06.01 - FORM OF BID
A. Bids shall be submitted on the forms provided by the Port.
B. All blanks on the Bid Form shall be filled in by computer or printed by hand in ink.
C. For lump sum Bids the total Contract lump sum price shall be submitted.
D. Where so indicated by the makeup of the Bid Form, sums shall be expressed in figures only.
E. For unit price Bids a price shall be submitted for each item of the Work, an extension thereof, and the total amount bid. Such prices shall be stated in clearly legible figures only and shall be in ink or typed.
F. Alterations, erasures, or interlineations, if any, shall be in ink and initialed by the signer of the Bid.
G. The Bidder shall make no additional conditions or stipulations on the Bid or qualify its Bid in any manner.
MC-0322784 / WP #N10346 00 20 00-10
Rev. 08/10/2026
H. The Bid Form shall include the legal name and registration number of the Bidder and a statement indicating whether Bidder is a sole proprietor, a partnership, a corporation, joint venture, or other legal entity. The Bid Form shall be signed by the person or persons legally authorized to bind the Bidder to a contract and shall be accompanied by satisfactory evidence of such authorization. A Bid submitted by an agent shall have a current Power of Attorney attached certifying agent’s authority to bind the Bidder.
I. The Bid Form shall not become a part of the Contract Documents except by inclusion into the Agreement.
IB-06.02 - IRREGULAR BIDS
A bid shall be considered irregular and may be rejected by the Port for any of the following reasons:
A. If the Bid Form furnished or authorized is not used or is altered;
B. If the Bid Form is incomplete or if any required supplemental documents contain any additions, deletions, unauthorized alternate bids, conditions, or otherwise fail to conform to the Port of Seattle requirements;
C. If the Bidder adds any provisions reserving the right to reject or accept the award, or enter into the contract;
D. If the Bid fails to include a unit price for every bid item;
E. If the Port deems any of the Bid prices to be excessively unbalanced either above or below the amount of a reasonable bid for the item of work to be performed to the potential detriment of the Port.
F. If Bid is not based on United States of America dollars;
G. If the Bid or Bid Bond is not properly executed, or shows an incorrect amount;
H. If the Port, for good cause, deems the Bid security inadequate.
IB-06.03 - RESPONSIBLE BIDDER
It is the intent of the Port to award a contract to the “lowest responsible Bidder”. Before award, the Bidder must meet the following Bidder responsibility criteria to be considered a responsible Bidder. The Bidder may be required by the Port to submit documentation demonstrating compliance with the criteria. The Bidder must:
A. Have a current certificate of registration as a contractor in compliance with chapter
18.27 RCW, and if applicable, a plumbing contractor license in compliance with chapter 18.106 RCW, an elevator contractor license in compliance with chapter
70.87 RCW, an electrical contractor license in compliance with chapter 19.28 RCW, which must have been in effect at the time of bid submittal.
B. Have a current Washington state unified business identifier (UBI) number.
MC-0322784 / WP #N10346 00 20 00-11
Rev. 08/10/2026
C. Have a Department of Revenue state excise tax registration number, as required in Title 82 RCW.
D. If applicable:
1. Have Industrial Insurance (workers’ compensation) coverage for the Bidder’s employees working in Washington, as required in Title 51 RCW.
2. Have a Washington Employment Security Department number, as required in Title 50 RCW.
E. Not be disqualified from bidding on any public works contract under RCW
39.06.010 or 39.12.065(3).
F. Not have a civil judgement entered by a court of limited or general jurisdiction of a willful violation, as defined by RCW 49.48.082, any provision of chapter 49.46, 49.48, or 49.52 RCW and no final and binding citation and notice of assessment issued by the Department of Labor and Industries (L&I).
G. If bidding on a public works project subject to the apprenticeship utilization requirements in RCW 39.04.320, not have been found out of compliance by the Washington state apprenticeship and training council for working apprentices out of ratio, without appropriate supervision, or outside their approved work processes as outlined in their standards of apprenticeship under chapter 49.04 RCW for the one-year period immediately preceding the date of the bid solicitation.
H. Have received training on the requirements related to public works and prevailing wage under Chapter 39.12 RCW. Bidders that have completed three or more public works projects and have had a valid business license in Washington for three or more years are exempt from this subsection.
I. Meet the minimum Women and Minority Business Enterprise (WMBE) requirements per Document 00 89 00.
J. Meet any supplemental criteria requirements, if applicable.
K. A Bidder may be deemed not responsible and its Bid rejected if:
1. More than one Bid on the same project from a Bidder under the same or different names.
2. Evidence of collusion with any other Bidder or Bidders. Participants in such collusion may be disqualified from submitting Bids on further work.
L. If requested, the apparent low Bidder must provide within two (2) business days of receiving the Port’s request:
1. Information demonstrating that the Bidder is responsible, consistent with the criteria set forth above. The Port may specifically request information addressing any of the items listed above. The Port reserves the right to request such documentation from other Bidders also.
MC-0322784 / WP #N10346 00 20 00-12
Rev. 08/10/2026
M. If the Port determines that the apparent low Bidder is not responsible, the Port will notify the Bidder of its preliminary determination in writing. Within two (2) days of receipt of the preliminary determination, the Bidder may either withdraw its bid or protest the Port’s determination by presenting additional information to the Port.
(Protest procedures are outlined in Document 00 20 00 IB-11.02 and IB-11.03.)
The Port will consider the additional information before issuing its final determination. If the final determination affirms that the Bidder is not responsible, the Port will not execute a contract with any other Bidder until two (2) business days after the Bidder determined to be not responsible has received the final determination.
IB-06.04 - NON-RESPONSIVE BID
A. For bids estimated at or above $1,000,000, a bid will we be declared non-responsive for failure to comply with the Subcontractor Work Listing Document 00 43 70.
IB-06.05 - RESERVED
IB-06.06 - STATE AND LOCAL TAXES
Bidders shall not add State and local retail sales taxes to any Bid Price except as may be provided for in the Bid Form Schedule of Prices.
ARTICLE 7: SUBMISSION OF BIDS
IB-07.01 - SUBMISSION OF BID
A. The Port is requiring electronic submission for this solicitation. Hard copy Bids will not be accepted. Bids and the required documents below must be delivered through email to: const-proposal@portseattle.org. Include the notation “BID ENCLOSED” and the Contract Number (MC-0322784) in the Subject line of the email. It is the responsibility of the Bidder to ensure timely delivery of Bids. The bid opening meeting will be hosted via Teams and by telephone. Please see document 00 10 00-Advertisement for Bids for bid opening details.
B. No Bid shall be considered which has not been received by the Director, Central Procurement Office before the time fixed for the opening of Bids in the published call for Bids.
C. Subcontractor Work Listing Document 00 43 70 shall be completed, if required, and submitted electronically with the Bid.
D. Document 00 89 00b – Women and Minority Business Enterprise Inclusion Plan Form shall be completed and submitted with the Bid or within one (1) hour after the published Bid submittal time.
E. Each bid must include a bid guarantee in the form of a cashier’s check, money order, or surety bid bond, in an amount not less than five percent (5%) of the total bid, made payable to Port of Seattle. A copy of the bid guarantee shall be
MC-0322784 / WP #N10346 00 20 00-13
Rev. 08/10/2026 provided electronically with your bid. Bid guarantees submitted in the form of Cashier’s Check, shall be sent to CPO Construction Bid Desk, Port of Seattle, 17900 International Blvd., Suite 400B, SeaTac, WA 98188 no later than 10 calendar days after the bid opening due date and time. Also, send email notification to const-proposal@portseattle.org of intent to mail Cashier’s Check.
F. The e-mail Bids shall include the solicitation number, title, due date and time in the subject line of the Bid’s e-mail.
G. The Port’s e-mail server will not accept files larger than 10 MB. If files are larger than 10MB, Proposers should send multiple e-mails with the information as set forth in the solicitation above as well as the total number of e-mails submitted by the Bidder.
H. The Port will use the time stamp on the Bidder’s e-mail to determine timeliness and Bidders are responsible for ensuring timely delivery of Bids. The Port is not responsible for Bidder’s technical difficulties in submitting electronically. Late Bids shall be rejected as non-responsive.
IB-07.02 - TIMELY DELIVERY
Bidder shall assume full responsibility for timely delivery at the location designated for receipt of Bids.
The Bid shall be submitted via email. The time the Bid is received shall be the Port of Seattle’s email server time.
ARTICLE 8: WITHDRAWAL OR MODIFICATION OF BIDS
IB-08.01 - PRIOR TO BID OPENING
Prior to the time and date designated for the receipt of Bids, a Bidder may withdraw or modify a Bid submitted earlier. Withdrawal, or modification, of the Bid shall be by written or electronic notice signed by the Bidder and received prior to the time and date designated for the receipt of Bids. Modifications submitted via electronic means shall be followed by written confirmation mailed and postmarked on or before the date set for receipt of Bids and shall include reasonable assurance of Bid security changes if applicable.
IB-08.02 - AFTER BID OPENING
A Bid may not be modified, withdrawn or canceled by the Bidder after the time and date set for the opening and for the period of time stipulated in the Bid Form. By submitting a Bid the Bidder agrees to the above conditions.
IB-08.03 - RESUBMITTAL OF MODIFIED BIDS
A Bid which has been withdrawn or modified prior to the time and date designated for the receipt of Bids may be resubmitted. The resubmitted Bid will be considered valid only if it is received prior to the date and time originally set for the receipt of Bids and contains the Bid security covering all modifications, and all documents requested in the original mailto:const-proposal@portseattle.org
MC-0322784 / WP #N10346 00 20 00-14
Rev. 08/10/2026 submittal, signed and initialed as mentioned heretofore. Bids shall be submitted electronically unless otherwise specified.
If the Bid is submitted via email multiple times, the latest responsive submission will govern.
ARTICLE 9: OPENING OF BIDS
IB-09.01 - PUBLIC OPENING
Bids will be opened and read publicly at the time indicated in the call for Bids unless the Port has changed through Addendum the date of opening Bids to another date, rejected any Bid or Bids, or has canceled the call for Bids. Bidders, their authorized agents, and other interested parties are invited to be present:
Refer to Document 00 10 00 Advertisement For Bids.
IB-09.02 - READING OF BIDS
Unless stated otherwise in the Advertisement, all Bids which have been properly identified and received will be publicly opened and read aloud. No evaluation of the Bids will be made at that time except for the announcement of the “Apparent Low Bidder,” if pertinent.
IB-09.03 - EVALUATION OF BIDS
After evaluation by the Director, Central Procurement Office and recommendation to the Port of Seattle Commission, the Port retains the right to reject any or all Bids.
IB-09.04 – RESERVED
IB-09.05 – RESERVED
ARTICLE 10: ACCEPTANCE OF BIDS (AWARD)
IB-10.01 - VERIFICATION OF BID PRICES
When Bids are opened and read, they will be checked for mathematical accuracy with respect to the extensions of unit bid prices and the total Bid price. If there is a discrepancy between a unit Bid price and the extended amount of any Bid item, the unit Bid price shall control. The total of extensions, corrected where necessary, will be used as the amount of the Bid for award purposes and will fix the amount of the Contract bonds.
IB-10.02 - RETURN OF BID SECURITY
As soon as Bid prices have been compared, the Director, Central Procurement Office will return the Bid security accompanying any Bids which would not be considered in making the award. All other Bid securities will be held until the Contract and bonds have been executed, after which all remaining Bid securities, except such as have been forfeited, will be returned to the Bidders.
MC-0322784 / WP #N10346 00 20 00-15
Rev. 08/10/2026
IB-10.03 - RIGHTS OF THE PORT
A. The Port shall have the right to waive any informality or irregularity in any Bid received.
B. The right is reserved to accept a Bid of the lowest responsible Bidder, to reject any or all Bids, republish the call for Bids, revise or cancel the work to be performed, or to do the work otherwise, if in the judgment of the Port Commission, the best interest of the Port is served thereby.
C. Bidders are advised that regulations governing the permit application and approval process are becoming so complex and uncertain as to results that this project may not receive the approval of all regulatory agencies and therefore may not be awarded to any Bidder, notwithstanding that the price offered is within the budget approved by the Commission.
D. The Port of Seattle may require the escrow of Bidder’s Bid Documentation, as well as the Bid Documentation of certain, key Subcontractors. Refer to General Condition’s paragraph GC-05.06, and Document 00 80 00, Supplementary Conditions, Paragraph SC-05.06, Review of Bid Documentation, for the requirements applicable to this contract.
IB-10.04 - FAILURE TO EXECUTE CONTRACT
If the Bidder awarded the Contract fails to execute the Contract and furnish satisfactory bonds within ten (10) days from receipt of the Notice of Intent to Award, or declares in writing its intent to not execute the Contract, the Bid deposit shall be forfeited to the Port and the Port Commission may provide Notice of Intent to Award to the second lowest responsible Bidder. If the second lowest responsible Bidder fails to enter into the Contract and furnish bonds within ten (10) days after receipt of the Notice of Intent to Award, forfeiture of its Bid deposit shall also be made and the Contract may be awarded to the third lowest responsible Bidder, and in like manner until the Contract and bonds are executed by a responsible Bidder to whom award is made, or further Bids are rejected or the number of Bids is exhausted.
IB-10.05 - NOTICE OF INTENT TO AWARD
A. The successful Bidder will receive a “Notice of Intent to Award” by email, certified mail, express mail, or courier. The letter will direct the Bidder to provide, in writing, an acknowledgement of receipt of the “Notice of Intent to Award”. It will also list out the contract submittals required for execution of the contract.
B. The successful Bidder is to submit Certificates of Insurance, and the required bonds for review and approval within ten (10) days after receipt of the “Notice of Intent to Award.”
C. The successful Bidder shall also submit an executed Agreement form, furnished by the Port Commission, within ten (10) days after receipt of the “Notice of Intent to Award.”
MC-0322784 / WP #N10346 00 20 00-16
Rev. 08/10/2026
IB-10.06 - EXTENSION OF TIME
If the Contract is not executed or not provided within the time required, and there appears circumstances which the Port Commission deems to warrant an extension of time, it may extend the time for execution of the Contract or for furnishing bonds for not to exceed ten
(10) additional days.
IB-10.07 - SIGNING OF CONTRACT
Copies of Contract Documents shall be signed by the Port Commission or Authorized Representative and the Contractor.
IB-10.08 - CANCELLATION OF AWARD
The Port reserves the right to cancel its Intent to Award of any Contract at any time before the execution of said Contract by all parties without liability to the Port.
ARTICLE 11: PROTESTS
IB-11.01 - PURPOSE
These protest procedures are included in this Solicitation to provide a prompt, fair and equitable administrative remedy to all interested parties regarding alleged substantive errors or omissions in the Solicitation or any decision by the Port of Seattle (hereinafter “Port”) to award the contract, to declare a proposal non-responsive, or to find a Proposer not responsible.
IB-11.02 - DEFINITIONS
Filed: Complete receipt of any document by the Port prior to the specified time indicated in these procedures. Documents received after the specified time indicated in these procedures shall be considered received the following business day.
Interested Party: An actual or prospective Bidder or Proposer whose direct, substantial economic interest would be affected by award of a contract or by the failure to award a contract.
11.03 TIMING
Any interested party for the purpose of filing a Protest under this Solicitation may Protest to the Port only in accordance with the procedures set forth below:
A. Protests Based on the Form or Content of the Solicitation: Any Protest based on the form or content of the Solicitation or any addendum thereto (including, but not limited to, any terms, requirements and/or restrictions therein) must be filed with the Port via email to Protests@portseattle.org. The email subject line must clearly identify the Solicitation number and be labeled as a “Protest.” No protest based on the content of the Solicitation will be considered if filed later than 5PM Pacific Time mailto:Protests@portseattle.org
MC-0322784 / WP #N10346 00 20 00-17
Rev. 08/10/2026
(i) five (5) business days prior to the specified proposal due date. Failure to timely file the protest will result in its rejection. It is the sole responsibility of the protestor to ensure the protest is timely filed.
B. Other Protests: Protests based on any other circumstances must be filed with the Port via email to protests@portseattle.org no later than 5 PM Pacific Time, within two (2) business days after the aggrieved person knew or should have known of the facts and circumstances upon which the protest is based. The email subject line must clearly identify the Solicitation number and be labeled as a “Protest.” No protest will be considered by the Port if all bids/proposals are rejected or if the protest is received after award of the Contract. Failure to timely file the protest will result in its rejection. It is the sole responsibility of the protestor to ensure the protest is timely filed.
IB-11.04 - CONTENTS OF PROTEST
To be considered, a Protest shall be timely, in writing, and shall include: (1) the name, street address, phone number and email address of the aggrieved party; (2) the Solicitation title and number under which the Protest is filed; (3) the direct economic interest of the aggrieved party in the contract to be awarded under the Solicitation; (4) a detailed description of the specific grounds for the Protest and any supporting legal and/or factual documentation; and (5) the specific ruling or relief requested. In the event the protesting party asserts the responsibility of any other Proposer as a ground for Protest, it must address in detail the specific responsibility criteria identified in the Solicitation.
IB-11.05 – ADMINISTRATIVE REVIEW
A. The Protest shall be promptly considered on the written submittal by the Port. In its sole discretion, the Port may give notice of the Protest to other entities and/or interested parties, including other Proposers. The Port reserves the right to resolve or to attempt to resolve any timely Protest that concerns the content of the Solicitation through written addenda thereto.
B. The Port will issue a written decision on the Initial Administrative Review following the timely filing of the Protest, stating the reasons for the action taken. In making its decision, the Port may consult with others and consider information relating to the Protest from any source, including other interested parties. A copy of the decision shall be provided to the aggrieved party, and any other party in the Port’s sole discretion, via email.
IB-11.06 - ADMINISTRATIVE APPEAL
A. Right of Appeal. For any Solicitation in which the value of the contract to be awarded is expected to exceed $200,000, the aggrieved party may appeal the decision of the Port by filing a Notice of Administrative Appeal via email to Protests@portseattle.org not later than 5PM Pacific Time two (2) business days after filing the initial Administrative Review decision. The Notice of Administrative mailto:protests@portseattle.org
MC-0322784 / WP #N10346 00 20 00-18
Rev. 08/10/2026
Appeal shall be timely, in writing and clearly labeled in the email subject line as a “Notice of Administrative Appeal.” A copy of the initial Protest shall be attached to the Notice of Administrative Appeal. The Port will provide a copy of the Notice of Administrative Appeal to other interested parties at the Port’s sole discretion.
Failure to timely file the Administrative Appeal will result in its rejection. It is the sole responsibility of the appellant to ensure the Administrative Appeal is timely filed.
B. Hearing. Promptly following the filing of the Notice of Administrative Appeal, an appeal hearing shall be conducted before a panel of at least two Port representatives (“the Panel”) normally consisting of the Director, Central Procurement Office (or designee) and a representative of the Port’s legal department. The hearing will generally be conducted within five (5) business days of the filing of the Notice of Administrative Appeal, and the aggrieved party and any other interested parties will be notified of the time and place of the hearing.
C. Conduct of Hearing. Except as the Panel may allow in its discretion, no discovery shall be available. At the Administrative Appeal Hearing, the aggrieved party will be given a reasonable opportunity to present relevant testimony and evidence and to make legal arguments. Other interested parties may also be given the opportunity to do so. The hearing will be recorded, and the Panel shall maintain an official record of all documentary evidence presented at the hearing. The Panel shall issue a written Final Decision. A copy of the Final Decision shall be provided to the aggrieved party, and any other party at the Port’s sole discretion, via email.
D. Standard of Review on Administrative Appeal: On Administrative Appeal the Panel will consider the Protest, de novo. The aggrieved party shall, however, be restricted from raising any matter or ground not reasonably within the scope of the materials placed before the Port.
IB-11.06 - STAY OF AWARD OF THE CONTRACT
The Port will stay award of the contract for two (2) business days following the issuance of its Final Decision.
IB-11.07 - JUDICIAL PROCEEDINGS
All judicial proceedings must be filed within two (2) business days of the issuance of the Port’s Final Decision. The stay provided by Section IB 11.06 is specifically intended to ensure that any request for judicial relief proceeds orderly and that the Port is provided advance notice thereof.
This is the start of the file's text. The full file is on GovTribe.