M2.M3-Project Schedule-Final.pptx

PPTX presentation 41 KB Posted

Attached to
M2/M3 Motor Load Commutated Inverter Controls Upgrade/ Improve Transonic Plant Capabilities
Solicitation number
FA9101-20-R-0003
Issued by

About this file

This document contains a project schedule and related federal contract opportunity solicitation. The project schedule outlines the design review, delivery, installation, checkout, and documentation milestones for the M2/M3 Motor Load Commutated Inverter Controls Upgrade/Improve Transonic Plant Capabilities contract. Key dates include 30%, 60%, and 90% design reviews by March 2nd, 4th, and 7th; factory acceptance testing and delivery to the Air Force Materiel Command Test Center by March 9th and 10th; installation and checkout from March 11th through April 25th; and final documentation by December 7th.

The related federal contract opportunity solicitation FA9101-20-R-0003 seeks proposals from ABB, Inc. for the M2/M3 Motor Load Commutated Inverter Controls Upgrade/Improve Transonic Plant Capabilities to modernize controls at an Air Force test center. The sole source request for proposal is directed to the incumbent, ABB, Inc.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Schedule: M2/M3 Motor Load Commutated Inverter Controls Upgrade/Improve Transonic Plant Capabilities

Contract Award 0001:Design- Review

30%: 2MARO

60%: 4MARO

90%: 7MARO

0002: Delivery Factory Acceptance Testing: 9MARO Delivery to AAFB: 10MARO 0003: Install and Checkout Installation: 11MARO+11DARO Checkout: 11MARO+14DARO Uninstall & Dispose of Obsolete LCI control System: 11MARO+4DARO MARO= Months After Receipt of Order DARO= Days After Receipt of Order

100%: 7MARO+14DARO

Final Documentation: 12MARO