ROADWAY SURFACING MATERIAL
1. Station: ___Sam D. Hamilton Noxubee NWR___________ Date:_____03/22/2022 Contact:_Travis Carpenter_Telephone No.:662-226-8286___________
Material Description (i.e., gravel, aggregate, etc.): __#610 crushed limestone_(Crush N Run)_____________________________________
| Specification Section/Paragraph/No. (Reference applicable State |
| Department Standard and Specification, if known):_Mississippi Department of Transportation (MDOT) Standards Specification 703.04.3 Gradation, reference chart: Table of Sizes and Gradation of Crushed Stone Aggregate. |
2. Total Tons/Yards Required: _approximately 1600 tons to be tailgate spread on Section Line Road on the Sam D. Hamilton Noxubee NWR._____
3. Check one or more: ____ Stock Piled (spot dumped) __X___ Tail Gate Spread Thickness: __approx 4 inches_______ The Fish & Wildlife Service will provide the equipment to spread limestone.
4. Maximum/Minimum Amount to be delivered daily: __12/10 trucks per day__________ ***The minimum of 10 trucks/day is critical on this large of a gravel project.
5. Attach a delivery and/or local site map.
6. Are there State certified scales in the area? __X__ Yes ____ No
| NOTE: If yes, weight tickets are required for each delivery. | |
| If no, delivery must be by cubic yards. |
7. Required commencement date for delivery:
___(Flexible)_____________
8. Last date for delivery: ___10/1/2022___________________
9. Local conditions (bridge restrictions, weather conditions, water levels, road flooding, etc.) that may affect delivery: ___Weather could delay project due to access into Refuge. _______________
The following shall be attached to the acquisition request:
(A) A completed Roadway Surfacing Material Form
(B) Applicable Map
(C) List of suggested vendors with names, addresses and phone numbers
Then forward the acquisition package to:
| (1) | Appropriate Regional Office Supervisor |
| Contracting and General Services |
File details come from the government source that posted it. Updated .