ladot 196-01 4400035774 signed proposal.pdf
PDF 4 MB Posted
- Attached to
- LA 14: Ditch Cleaning and Grading
- Solicitation number
- 4400035774
- Issued by
- Calcasieu Parish, Louisiana
About this file
This is a signed Letter Bid Proposal from the Louisiana Department of Transportation and Development (LA DOTD) for State Project No. 4400035774, Control Section 196-01, involving ditch cleaning and grading work on LA 14 in Calcasieu Parish. The project encompasses 0.658 miles of roadway and includes ditch cleaning, pipe cleaning, regrading, and side drain replacement along LA 14 from LM 9.333 to LM 9.991. The work must be completed within 45 working days, with a 30-calendar-day assembly period permitted prior to commencement of contract time. Electronic bids were submitted through www.bidx.com prior to the September 17, 2026 bid opening at 10:00 a.m. at LA DOTD District 07 Headquarters in Lake Charles, Louisiana. Contractors must be licensed under LA R.S. 37:2150-2192 for Highway, Street, and Bridge Construction and must register with the Department prior to bidding. Bidders assume responsibility for accessing apparent and final bid results on the Construction Letting Information webpage to confirm award status. The contract requires compliance with the 2026 Louisiana Standard Specifications for Roads and Bridges, as amended by the project's special provisions and supplementary specifications.
The estimated cost range for the project is $250,000.00 to $500,000.00, with actual bid prices evaluated based on the final estimate value published at bid opening for award determination. The contractor must furnish all necessary machinery, tools, and materials and perform all work according to contract specifications in exchange for compensation calculated as the sum of products of work quantities and respective unit prices. Insurance requirements include Workers Compensation with employer liability of at least $1,000,000 for work over water, Commercial General Liability with aggregate limits based on contract amount, separate Owner's and Contractor's Protective Liability coverage, and Business Automobile Liability Insurance, with all policies maintained with A.M. Best rated carriers (A-: VI or higher). Contract time adjustments may be granted for adverse weather days exceeding allowable monthly thresholds documented by the Engineer, though no direct cost reimbursement is provided for excess adverse weather days. Lane closures are limited to Monday through Friday, 8:00 a.m. to 4:00 p.m., with all lanes required open during specified holiday periods and weather events. The Department will reimburse actual Owner's and Contractor's Protective Insurance premium costs without markup upon submission of invoices and sworn affidavits from the insurance producer.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATE OF LOUISIANA
DEPARTMENT OF TRANSPORTATION AND
DEVELOPMENT
LETTER BID PROPOSAL
FOR
DOTD
PARIMENTd
PARTMENT OF
TRANSPORTATION & DEVELOPMENT
STATEOF LOUISIANA
TRENT W.W. HARGRAVE
PROPESSIONAI ENOINCERPROCCense No. 45182
STATE PROJECT NO. 4400035774
CONTROL SECTION NO. 196-01
LA 14: DITCH CLEANING AND GRADING
ENGRTERI
NG
9/721
ROUTE: LA 14
CALCASIEU PARISH
A-1
B-1
STATE PROJECT NO. 4400035774
TABLE OF CONTENTS
Page No.
Title Sheet ..................................................................................................................A-1 Table of Contents .......................................................................................................B-1 Notice to Contractors .................................................................................................C-1 thru C-3 Special Provisions ......................................................................................................D-1 thru D-75 Plans (13 sheets) ........................................................................................................E-1 thru E-13 Construction Proposal Information:
Title Sheet ...........................................................................................................F-1 Bid Bond .............................................................................................................G-1 Schedule of Items ...............................................................................................H-1 thru H-3 Construction Proposal Signature and Execution Form .......................................I-1 thru I-2
NOTICE TO CONTRACTORS
C-1
Electronic bids and electronic bid bonds for the following project will be downloaded by the Louisiana Department of Transportation and Development (LA DOTD), District 07 on Thursday, September 17th, 2026. Paper bids and paper bid bonds will not be accepted. Electronic bids and electronic bid bonds must be submitted through www.bidx.com prior to the electronic bidding deadline. Beginning at 10:00 a.m., all bids will be downloaded and posted online at http://wwwapps.dotd.la.gov/engineering/lettings/. No bids are accepted after 10:00 a.m. The electronic bid download process is held in LA DOTD District 07 Headquarters Design Building, 5827 HWY 90E, Lake Charles, LA, and is open to the public.
STATE PROJECT NO. 4400035774
CONTROL SECTION NO. 196-01
DESCRIPTION: LA 14: DITCH CLEANING AND GRADING
Non-NHS Route
ROUTE: LA 14
PARISH: CALCASIEU
LENGTH: 0.658 miles.
TYPE: DITCH CLEANING, PIPE CLEANING, REGRADING, SIDE DRAIN
REPLACEMENT
LIMITS: CONTROL SECTION 196-01: LA 14 (LM 9.333 – LM 9.991)
ESTIMATED COST RANGE: $250,000.00 TO $500,000.00
The estimated cost range is for informational purposes only and may be subject to change.
The bid prices received from bidders will be evaluated based on the actual estimate value, which will be published at bid opening, for award determination.
PROJECT ENGINEER: JACOB BLACKMER, P.E., (337) 437-9200
PROJECT MANAGER: TRENT HARGRAVE, P.E., (337) 437-9110
Bids must be prepared and submitted in accordance with Section 102 of the 2026 Louisiana Standard Specifications for Roads and Bridges as amended by the project specifications, and must include all information required by the proposal.
PROJECT CLASSIFICATION
Bids shall be accepted from Contractors who are licensed under LA R.S. 37:2150-2192 for the classification of Highway, Street, and Bridge Construction.
All parties interested in bidding on this project must register with Ms. Kallie Broussard at (337) 437-9225 or by e-mail at Kallie.Broussard@la.gov.
C-2
First time bidders who are not registered with LA DOTD shall do so prior to bidding any work with the Department. The New Vendor Registration site may be accessed via the Internet at wwwsp.dotd.la.gov. From the LA DOTD home page, select the following link options:
BUSINESS Working with DOTD, then Projects Scheduled, then Construction Letting Information. Once the Construction Letting Information page appears, select Online Bidder Registration. On the Bidder Registration Log In page, select Companies not on file with LA DOTD, found at the bottom of the page. Fill out the required information and submit. You will be notified by email or phone of your ID within two (2) business days. Once your company receives confirmation of a successful registration, contact Ms. Kallie Broussard to finalize your company’s registration as a bidder or an information only plan holder for this project.
When approved for bidding, the bidder’s name will be placed on the “List of Prospective Bidders” located on the LA DOTD Internet website. It is the bidder’s responsibility to review the “List of Prospective Bidders” to ensure approval to bid. If a bidder does not register for a project, the bid will not be accepted by LA DOTD. As per 102.04.5 of the 2026 edition of the Louisiana Standard Specifications for Roads and Bridges, no bidders will be approved for bid registration within 24 hours before the bid opening. All bidders must register to bid before that deadline.
Plans and proposals are available in electronic format ONLY. All Plans, Proposals, Letters of Clarification, and Withdrawal Notices will be posted online. Paper notices will not be distributed.
Construction proposal information may be accessed via the Internet at wwwsp.dotd.la.gov. From the LA DOTD home page, select the following options: BUSINESS Working With DOTD, then Project Letting Info. Once the Construction Letting Information page appears, find the Notice to Contractors box. From the drop down menu, select the appropriate letting date and press the “Go To” button to open the page, which provides a listing of all projects to be let and a Construction Proposal Documents link for each project. All project specific notices are found here. It will be the responsibility of the bidder to check for updates. Additionally, plans and specifications may be seen at the Project Engineer's office. Upon request, the Project Engineer will show the project site.
All questions concerning the plans shall be submitted via the Electronic Plans Distribution Center known as Falcon. All submitted questions will be forwarded by email to the Project Manager and the Project Engineer. Questions submitted within a period of 96 hours prior to the advertised time for the opening of bids, excluding Saturdays, Sundays, and any other legal holidays, may not be answered prior to bidding. Falcon may be accessed via the Internet at wwwsp.dotd.la.gov. From the home page, select BUSINESS Working With DOTD, then select Project Letting Info. On the Construction Letting Information page, select the link, DOTD Plans Room (Falcon); Login to Falcon (or request an ID if a first-time user). Once logged in, you will have access to view Project Information, submit a question concerning the project, and view the plans. To avoid any suggestion that a potential bidder is using the Falcon system to communicate with other potential bidders, DOTD will not post any question or any statement of fact or opinion not made for the purpose of seeking clarification of plans and/or specifications. Any non-questions posted on falcon will be limited to the statement of an issue considered unresolved by a previous DOTD response.
C-3
Bidders assume the responsibility for accessing the Apparent Bid Results and final Bid Results on the Construction Letting Information web page located at wwwapps.dotd.la.gov/engineering/lettings/ to confirm whether they are the apparent low bidder for any given project. The award of the contract will be electronically submitted to the successful low bidder on each project.
The U. S. Department of Transportation (DOT) operates a toll free "Hotline" Monday through Friday, 8:00 a.m. to 5:00 p.m., Eastern Time. Anyone with knowledge of possible bid rigging, bidder collusion, or other fraudulent activities should call 1-800-424-9071. All information will be treated confidentially and caller anonymity will be respected.
SPECIAL PROVISIONS
D-1
S.P. CONTRACT TIME (01-26):
The entire contract shall be completed in all details and ready for final acceptance in accordance with 105.17.020 within FORTY-FIVE (45) WORKING days.
Prior to assessment of contract time, the contractor will be allowed 30 calendar days from the date stipulated in the Notice to Proceed to commence with portions of the contract work including but not limited to assembly periods, preparatory work for materials fabrications such as test piles, or other activities which hinder progress in the beginning stages of construction. Prior to issuance of the Notice to Proceed, the Department will consider extending the assembly period upon written request from the contractor justifying the need for additional time.
The contractor shall be responsible for maintenance of traffic from the beginning of the assembly period. During the assembly period, the contractor will be allowed to do patching and other maintenance work necessary to maintain the roadway with no time charges when approved by the engineer.
If the contractor begins regular construction operations prior to expiration of the assembly period, the assessment of contract time will commence at the time construction operations are begun.
S.P. GENERAL BIDDING REQUIREMENTS (01-26):
The specifications, contract and bonds governing the construction of the work are the 2026 Edition of the Louisiana Standard Specifications for Roads and Bridges, together with any supplementary specifications and special provisions attached to this proposal.
Bids shall be prepared and submitted in accordance with Section 102 of the Standard Specifications.
The plans herein referred to are the plans approved and marked with the project number, route and Parish, together with all standard or special designs that may be included in such plans.
The bidder declares that the only parties interested in this proposal as principals are those named herein; that this proposal is made without collusion or combination of any kind with any other person, firm, association, or corporation, or any member or officer thereof; that careful examination has been made of the site of the proposed work, the plans, Standard Specifications, supplementary specifications and special provisions above mentioned, and the form of contract and payment, performance, and retainage bond; that the bidder agrees, if this proposal is accepted, to provide all necessary machinery, tools, apparatus and other means of construction and will do all work and furnish all material specified in the contract, in the manner and time therein prescribed and in accordance with the requirements therein set forth; and agrees to accept as full compensation therefore, the amount of the summation of the products of the quantities of work and material incorporated in the completed project, as determined by the engineer, multiplied by the respective unit prices herein bid.
It is understood by the bidder that the quantities given in this proposal are a fair approximation of the amount of work to be done and that the sum of the products of the approximate quantities
D-2 multiplied by the respective unit prices bid shall constitute gross sum bid, which sum shall be used in comparison of bids and awarding of the contract.
The bidder further agrees to perform all extra and force account work that may be required on the basis provided in the specifications.
The bidder further agrees that within 15 calendar days after the contract has been transmitted to him, he will execute the contract and furnish the Department satisfactory surety bonds.
If this proposal is accepted and the bidder fails to execute the contract and furnish bonds as above provided, the proposal guaranty shall become the property of the Department; otherwise, said proposal guaranty will be returned to the bidder; all in accordance with 103.4.
S.P. DEFINITIONS AND TERMS (DOTD RECEIVES BIDS) (01-26):
101.3 of the 2026 Louisiana Standard Specifications for Roads and Bridges is amended to include the following:
Contracting Agency. A city, levee board, police jury or other governing authority of a parish, state office, agency, board, commission, public corporation or other political subdivision of the State, in whose name the contract will be executed. Whenever the term "Department" is used as Owner, it shall mean the Contracting Agency. Whenever the term "Department" is used as Engineer, it shall mean the Engineer.
S.P. MAINTENANCE OF TRAFFIC (01-26):
Section 104.3 of the 2026 Louisiana Standard Specifications for Roads and Bridges is amended to include the following:
Lane closure and work hour restrictions shall be as follows:
Lane closures shall be limited to Monday through Friday, from 8:00 AM to 4:00 PM.
No work shall be allowed and all lanes shall be open during New Year’s, Mardi Gras, Easter, Memorial Day, Independence Day, Labor Day, Thanksgiving, Christmas holiday periods, and other events as directed by the Engineer. No work shall be allowed and all lanes shall be open in preparation for weather events such as hurricanes, ice storms, etc, as deemed necessary, or during hurricane evacuation and contra flow operations. These periods shall be considered excusable, non-compensable.
S.P. PLANS AND SUBMITTALS (06-26):
Section 105.2 of the 2026 Louisiana Standard Specifications for Roads and Bridges has been amended to delete and replace the first paragraph as follows:
D-3
105.2 PLANS AND SUBMITTALS
Conform to 801.3.010 for format of plans and submittals.
S.P. PERMITS, LICENSES, TAXES AND INSURANCE (01-26):
Section 107 of the 2026 Louisiana Standard Specifications for Roads is Bridges is amended as follows:
107.2 is deleted and replaced with the following:
107.2 PERMITS, LICENSES, TAXES AND INSURANCE.
Contractors shall procure temporary permits and licenses for the work, pay charges, fees, and taxes, and give notices necessary for lawful prosecution of the work. Contractor, and its subcontractors, shall maintain all licenses and certifications necessary to accomplish the work in accordance with contract requirements and applicable law.
The contractor shall maintain, at a minimum, the following insurance coverage until final acceptance of the contract:
a) Workers Compensation in compliance with state law, with the exception that the contractor’s
Employer liability is to be at least $1,000,000 when work is to be over water and involves maritime exposures. For the coverage provided in this subpart the contractor’s Insurer will have no right of recovery or subrogation against the State of Louisiana or the Louisiana
Department of Transportation and Development.
b) For Commercial General Liability Insurance with a combined single limit per occurrence for bodily injury and property damage, the aggregate loss limit must be on a per project basis. This insurance shall include coverage for bodily injury and property damage, and include coverage for Premises-Operation; Broad form Contractual Liability; Products and Completed Operation;
Use of Contractors and Subcontractors; Personal Injury; Broad form Property Damage; and
Explosion, Collapse and Underground (XCU) coverage. The required combined single limit amount of insurance shall be as provided in Table 107.2-1.
When a railroad is within the project limits, the combined single limit amount of Commercial
General Liability Insurance shall be as required by the railroad or as provided in Table 107-1, whichever is greater.
c) A separate Owner’s and Contractor’s Protective Liability (OCP) Policy shall be furnished by the contractor naming the Louisiana Department of Transportation and Development as the named insured. The policy period of the OCP insurance shall extend through final acceptance of the project. The required combined single OCP limit amount shall be as provided in Table
107.2-1.
d) For Business Automobile Liability Insurance with a combined single limit per occurrence for bodily injury and property damage, this insurance shall include bodily injury and property damage coverage for owned automobiles, hired automobiles and non-owned automobiles. The required combined single limit amount of insurance shall be as provided in Table 107.2-1 below.
D-4
Table 107.2-1
Insurance Requirements1
Initial Contract
Amount
Occurrence
Minimum Aggregate
Ultrahazardous
Aggregate
Up to $1 $1 $2 $3
From >$1 to $2 $2 $4 $6
Over $2 $5 $10 $15 1 $ in millions.
Aggregate coverage for projects with ultrahazardous activities shall be triple the occurrence minimum. Ultrahazardous activities include pile driving; transportation, use, storage, or removal of explosives, radioactive materials, or particularly hazardous or volatile chemicals; and asbestos or lead paint abatement; but does not include vibratory installation of sheet piles.
Each policy shall include provisions stipulating that the insurance company(ies) shall have no recourse against the State of Louisiana and the Department for payment of any premiums or for assessments under any form of the policy and that any and all deductibles in the above described insurance policy(ies) shall be assumed by and be at the sole risk of the contractor.
Insurance is to be placed with insurance companies authorized in the State of Louisiana with an
A. M. Best’s rating of A-: VI or higher. This rating requirement may be waived for Workers
Compensation coverage only.
Should any policies be canceled, the contractor shall immediately notify the Department.
Upon failure of the contractor to furnish, deliver and maintain such insurance for itself as required, this contract, at the election of the Department, may be immediately declared suspended, discontinued or terminated. Upon failure of the contractor to maintain OCP insurance at any time prior to final acceptance of the project, work on this contract shall be immediately suspended until proof of such insurance is presented to and accepted by the Department’s Project Control unit.
During a suspension caused by the lack of any required insurance, contractual time charges will continue to be assessed against contract time, as will any assessment of stipulated damages, without interruption.
Failure of the contractor to maintain any required insurance shall not relieve the contractor from any liability under the contract, nor shall the insurance requirements be construed to conflict with the obligations of the contractor concerning indemnification under 107.17.
The contractor is responsible for requiring and verifying that all subcontractors working on the project maintain appropriate types and levels of insurance coverage.
Purchases related to work performed for this Project are exempt from sales and use taxes. Prior to claiming the exemption, the general contractor or its subcontractor shall obtain a certificate of exemption from the secretary of the Department of Revenue at Louisiana Department of Revenue, Taxpayer Compliance - SES Division, Phone: (855) 307-3893, Email:
LDRSales.ExemptionApplications@la.gov.
D-5
107.2.010 REIMBURSEMENT OF OCP INSURANCE:
Contractor may submit the direct cost of OCP insurance (only) to the Department for reimbursement. The provisions of 109.4 shall not apply to this reimbursement. The cost of all other required insurance must be included in contractor’s overhead applied to all other bid items.
The Department will reimburse the actual cost of OCP coverage as shown on an invoice produced by the insurance company or broker issuing the invoice in the amount of the premium due for the OCP policy: a) without a markup for profit or indirect costs including indirect costs associated with procurement of the OCP insurance; and b) less charges in the amount of a tax from which the Department is exempt and other related incidental fees. Contractor will be responsible for submitting a written request for reimbursement of the amount of the OCP policy premium invoice less all such charges including surplus lines taxes and other incidental fees.
The Contractor shall contact the Louisiana Department of Insurance, ldi.la.gov, to receive additional guidance.
Contractor must also submit an original sworn affidavit from the insurance producer/agent in which that person attests that the submitted invoice is for the required OCP coverage only, and that the invoice accurately reports the cost to contractor of that coverage. The invoice and affidavit may be submitted at the preconstruction conference or thereafter for inclusion with a partial estimate.
There will be no reimbursement for any purchase of OCP insurance policy extensions necessitated by concurrent; non-excusable; or excusable, non-compensable delays in completion of the project, whenever such delays occur, or for claimed utility delays where such days were not added to Contract Time by change order. Any policy extensions necessitated by excusable, compensable delays will be reimbursed on a pro-rata monthly basis.
S.P. DETERMINATION AND EXTENSION OF CONTRACT TIME (CALENDAR DAY)
(05-26):
Subsection 108.7, Determination and Extension of Contract Time, is amended to include the following:
The contractor shall document for each month of scheduled construction, the occurrence of adverse weather conditions having an impact on controlling items of work. An adverse weather day is a previously scheduled or normally scheduled work day on which rainfall, wet conditions or cold weather will prevent construction operations on the controlling work activity from proceeding for at least 5 continuous hours of the day or 65 percent of the normal work day, whichever is greater, with the normal working force engaged in performing the controlling item of work. If the contractor submits a written request for additional contract time due to adverse weather conditions, the contractor’s request will be considered only after the Department agrees with the days and then only for adverse weather days in excess of the allowable number of days per month stated below.
Adverse weather days will be documented by the Engineer and agreed upon monthly. Adverse weather days will be prorated for partial months when a work order or final inspection is issued other than the first or last of the month and agreed to by the Department. If the contractor is being considered for disqualification by the Department, an equitable adjustment in contract time may
D-6 be made at the end of the original contract period, including all days added by approved change orders. Contract time will be adjusted by comparing the actual number of adverse weather days to the statistical number of adverse weather days over the specific time period per the table below.
The resulting number of adverse weather days will be multiplied by 1.4 to convert to calendar days. Adjustments for adverse weather cannot result in a contract time reduction. Once adjusted, a new adverse weather day accounting will begin using the adverse weather conditions having an impact on the controlling items of work, in excess of the allowable number of days per month stated below. A second and final contract time adjustment will then be done at the final acceptance of the project. An adjustment in the contract time due to adverse weather will not be cause for an adjustment in the contract amount. There will be no direct or indirect cost reimbursement for excess adverse weather days.
The following are anticipated adverse weather days that the contractor shall include in each month of his calendar day construction schedule.
January 10 days May 5 days September 4 days
February 9 days June 6 days October 3 days
March 8 days July 6 days November 7 days
April 7 days August 5 days December 7 days
S.P. COMPENSATION FOR ALTERATIONS OF THE CONTRACT (07-26)
109.4 of the 2026 Louisiana Standard Specifications for Roads and Bridges is amended as follows:
109.4.030.B. is deleted and replaced with the following:
B. Direct Materials
For materials accepted by the engineer and used, the contractor shall receive the actual cost of such materials delivered to the work, including transportation charges if applicable and sales taxes subject to the requirements of 107.2.
109.4.030.C.3. is deleted and replaced with the following:
3. Operating Cost
When internal rates are used for cost recovery, equipment operating cost will be reimbursed for the actual hours used in work. Intermittent breaks throughout the day will not be deducted while the equipment is dedicated solely to the force account work. When using guide book rental rates, only the operating cost will be
D-7 reimbursed at an hourly rate over 8-hours per day. Reimbursement will stop when the equipment is no longer needed.
Pickups for superintendents and employee transport are non-compensable; when directly used in performance of the work, pickups will be reimbursed at $150/day with no markup.
The cost of service trucks and other support equipment will be considered compensable.
Standby will be reimbursed as follows, with a maximum reimbursement of 8-hours per day, 40-hours per week, and 22-days per month:
∗ (𝑎𝑔𝑟𝑒𝑒𝑑 𝑟𝑎𝑡𝑒 − 𝑜𝑝𝑒𝑟𝑎𝑡𝑖𝑛𝑔 𝑐𝑜𝑠𝑡𝑠)
Standby will not be reimbursed for periods when the equipment would ordinarily be idle (weekends, holidays, adverse weather, periods of repair and maintenance)
S.P. PAYMENT FOR STOCKPILED OR STORED MATERIAL (01-26)
Section 109 of the 2026 Louisiana Standard Specifications for Roads and Bridges is amended as follows:
109.6.010 is deleted and replaced with the following:
109.6.010 GENERAL
Payment for stockpiled or stored material will be considered only for materials anticipated to be stored for periods in excess of 30 calendar days. When approved, advance payments may be made for fabricated or natural materials that are to be incorporated in the project when stockpiled materials are stored on the project or in a dedicated stockpile at an approved site outside the limits of the project within the State of Louisiana. Payments shall be limited to durable materials described herein and shall represent a significant portion of the project cost.
Perishable articles and small warehouse items are not included. These materials shall meet the requirements of the specifications. Payment for stockpiled or stored materials will not constitute acceptance. It shall be the contractor's responsibility to protect the material from damage while in storage.
Payment for materials stored outside the State of Louisiana will be considered, subject to approval of the Chief Engineer. This will generally be limited to adjacent states, except in cases where it will be in the best interest of the Department to pay for these materials. If payment for stockpiled materials outside the State will affect the bid price for an item, the contractor shall submit a written request to the Chief Engineer prior to bidding.
Payment may be made for the invoice price for the materials, which shall not exceed 85 percent of the contract price for the items where the materials are to be incorporated. For fabricated materials purchased from commercial sources and delivered to approved storage, partial payment may be the invoice price plus freight and taxes subject to the requirements of 107.2.
D-8
The quantity of material for payment will not exceed the total estimated quantity required to complete the project.
The amounts advanced on stockpiled or stored materials will be recovered by the Department through deductions made on payments as the materials are incorporated in the work.
Partial payment for stockpiled materials shall be requested by the contractor in writing and the following documents shall be furnished:
a) A copy of the invoices from supplier or manufacturer verifying the cost and quantity of material.
b) If storage is on private property, a copy of the lease or agreement granting the Department right of entry to property.
Within 30 calendar days after payment by the Department, the contractor shall submit a certified copy of invoices from the supplier for each item for which payment has been made. All such invoices submitted shall state the amount received by the supplier as payment in full for the materials. If this certification of payment is not presented within the 30 day period, the advanced payment will be deducted from future progress payments.
Title and ownership of materials for which advancements have been made by the Department shall not vest in the Department until such materials are incorporated in the work and the work accepted by the Department. The making of advancements by the Department shall not release the contractor from the responsibility for any portion thereof.
S.P. (SEC 203.3.060) SETTLEMENT PLATE INSTALLATION AND SETTLEMENT
MONITORING (02-26):
Section 203.3.060.D. of the 2026 Louisiana Standard Specification for Highway Roads and
Bridges is deleted and replaced with the following:
D. Settlement Plate Installation and Settlement Monitoring
Install settlement plates prior to placement of fill. Unless specified otherwise, install settlement plate on natural ground on a level surface.
Maintain a vertical, accessible, and undamaged riser pipe during embankment placement and compaction. Replace any settlement plates damaged during construction at no cost to the Department.
Provide all elevations to have a precision of ±0.01 feet. Document the date and time of all survey readings.
Survey and document riser pipe elevations immediately before and immediately after riser pipe extension.
Survey and document settlement plate elevation readings immediately after installation of the plate, just prior to fill placement, and weekly during fill placement. Survey immediately after the final lift is placed and compacted, twice weekly for the first month of the settlement monitoring period, and weekly for five months thereafter. Restart settlement monitoring period if any additional fill placement or surcharge is required.
D-9
Unless specified otherwise, the settlement monitoring period begins after all fill has been placed and compacted. All surveying during fill placement does not count as part of the settlement monitoring period.
Record the embankment elevation and surcharge height for each settlement plate reading. Submit settlement plate readings to the Project Engineer. The Project Engineer and Geotechnical Engineer will verify the initial and final elevations for acceptance. Do not install foundations through, upon, or beneath new fill within 100 feet of a settlement plate prior to acceptance of the fill elevations.
Remove riser pipe and casing three feet below base course upon acceptance.
S.P. (SEC 502) ASPHALT CONCRETE MIXTURES (06-26):
Section 502 of the 2026 Louisiana Standard Specification for Highway Roads and Bridges is revised as follows:
Section 502.3.100.D. is deleted and replaced with the following:
D. Correction of Deficient Areas
Correct areas as required in 502.3.100.B. and 502.3.100.C. and those not meeting Table
502.3-4. Correct wearing and binder courses as defined in this subsection at no direct pay. In lieu of grinding, the Project Engineer may penalize the contractor $1,000.00 per individual bump specified in Table 502.3-4 or per “Ripple” as defined in 502.3.100.B.
1. Deficiencies in Mainline Wearing Course
Correct deficiencies in the final wearing course by:
a) by diamond grinding and applying a light tack coat; or
b) by furnishing and placing a supplemental layer of wearing course mixture at least 1½ inches compacted thickness for the full width of the roadway meeting specification requirements; or
c) by removing and replacing mixture.
If the supplemental layer does not meet specification requirements of Table 502.3-
4, remove and replace or correct it by other methods approved by the Project
Engineer.
For areas that will not be improved by grinding such as minor dips, extreme vertical curves, or other areas that are not exempt as measured with a 10 feet metal static straight edge, the Project Engineer may waive the requirement to grind as specified in 502.3.100.D.
2. Deficiencies in Mainline Binder Courses
Correct deficiencies in binder course: longitudinal, transverse, cross slope, and grade to meet specification requirements by diamond grinding, by milling, or by
D-10 removing and replacing mixture. Make corrections before subsequent courses are constructed.
3. Deficiencies in Minor Mixes
Correct deficiencies in minor mixes by diamond grinding or approved method at the
Project Engineer’s direction.
S.P. (SEC 601) PORTLAND CEMENT CONCRETE PAVEMENT (09-26)
Section 601 of the 2026 Louisiana Standard Specification for Highway Roads and Bridges is revised as follows:
Section 601.2 is deleted and replaced with the following:
601.2 Materials
Provide materials as specified in the following sections and subsections.
Portland Cement Concrete 901, 1001
Aggregates 1003
Joint Materials 1005
Reinforcing Steel 1009.1
Dowel Bars 1009.3
Curing Materials 1011.1
Admixtures 1011.2
Epoxy Resin Systems 1017
Water 1018.1
Hydrated Lime 1018.2
Non-Shrink Grout 1018.4
Geotextile Fabric 1019
Furnish PCCP concrete. Use the same type of concrete throughout the project, unless otherwise authorized in writing.
Account for delayed and fluctuating set times and strength gain characteristics when utilizing supplemental cementitious materials in PCCP.
601.2.010 HIGH FLEXURAL STRENGTH CONCRETE
Use the maturity method for flexural strength determination according to ASTM C1074. If any of the mix components change (material sources or mix proportions change by more than ±5%;
admixture dosages change by more than ±20%), a new maturity curve must be developed and verified. Submit the mix design, trial batch results, and maturity curves to the District
Laboratory Engineer for review.
D-11
Verify by trial batch that the proposed mixture achieves the flexural strength specified in Table
601.3.140-1, and the appropriate early opening strength specified in 601.3.130 within the time frame specified in the contract documents.
Trial batch requirements may be waived, with written approval from the District Laboratory
Engineer, for previously approved mix designs when all materials and proportions of the proposed design exactly match the previously approved mix design materials.
Section 601.3.060 is deleted and replaced with the following:
601.3.060 PLACING AND CONSOLIDATING CONCRETE
Deposit concrete on a surface-moist base or subgrade with a minimum of handling. Base course must be less than 120°F immediately prior to concrete placement. Place concrete continuously between transverse joints. Use appropriate tools for necessary hand spreading. Place concrete as close to joints as possible without disturbing them. Ensure workers wear footwear clean of foreign matter.
Except for concrete sawing equipment, restrict operation of mechanical equipment on the pavement until obtaining a minimum compressive strength of 3,000 psi in accordance with
DOTD TR-230. When high flexural strength is specified, restrict operation of mechanical equipment, except for concrete sawing equipment, on the pavement until obtaining a minimum flexural strength of 480 psi in accordance with ASTM C1074.
Pave adjacent lanes only after a minimum elapse of 1-day with no observable marring of the surface.
Rain protection along with hot and cold weather limitations of 901.3.090 shall apply.
Complete the surface finish as specified in 601.3.090.G. Texture the surface as specified in
601.3.090.H.
Cure the surface and edges as specified in 601.3.100.
A. Slip-Form Method
At the option of the contractor, the slip-form paving method may be used.
Place concrete with an acceptable slip-form paver designed to spread, consolidate, screed and float finish freshly placed concrete in one pass of the machine with only a minimum amount of hand finishing necessary to provide a dense, homogeneous pavement in conformance with plans and specifications. Equip the machine with vibrators conforming to 601.3.010.F.1. Vibrate concrete for the full pavement width and depth for complete consolidation. Hold sliding forms rigidly together laterally to prevent spreading of forms.
Provide concrete of a uniform consistency exhibiting minimal bleed water and laitance.
Operate the slip-form paver with as nearly a continuous uniform forward movement as possible. Coordinate mixing, delivering and placing of concrete to provide uniform progress. Concrete plants shall have sufficient mixing capacity to provide such continuous delivery of concrete to enable the paver to advance at a minimum rate of 1.5 feet per minute. If it is necessary to stop forward movement of the paver, also
D-12 immediately stop the vibrator and tamping elements. If forward movement of the paver is delayed for a period, the engineer may direct fogging of fresh concrete. See 601.3.080 for construction joint requirements. Apply no outside tractive force to the machine except as controlled from the machine.
B. Stationary Side-Form Method
Deposit concrete as near as possible to forms and joints assemblies without disturbing the form or joint assembly.
Use vibrators to consolidate concrete against and along the faces of all forms and the length and both sides of all joint assemblies. Limit vibrator operation to 5 seconds in any one location.
Section 601.3.110 is deleted and replaced with the following:
601.3.110 SURFACE TOLERANCE (IRI)
A. General
This subsection outlines the measurement of surface roughness, quality control requirements, corrective actions, and acceptance criteria for PCCP. Use the
International Roughness Index (IRI) to determine the amount of roughness in a measured longitudinal profile. In the direction of travel, measure the longitudinal surface profile in inches per mile and report as the IRI; all in accordance with DOTD
TR 644.
B. Equipment
In accordance with TR 644, furnish a DOTD certified inertial profiler for quality control and acceptance testing. A listing of DOTD certified profilers can be found on the DOTD
Materials and Testing Section website. The inertial profiler shall measure both wheel paths simultaneously with laser height sensing equipment at a constant speed within the certified range. Due to the surface texture of PCCP, lasers with a footprint greater than a single point are recommended for accurate readings.
Furnish a 10-foot metal static straightedge for quality control and acceptance testing for transverse cross slope, grade, and individual longitudinal bumps in excess of 1/4 inch in 10 feet. Additionally, bumps are not to exceed 1/4 inch in 10 feet for non-IRI pavements including but not limited to bike paths, detour roads, parking areas, sidewalks, turning lanes, turn outs, and shoulders.
C. Quality Control
1. Longitudinal Smoothness
Run the certified profiler and evaluate the raw IRI data using ProVAL to identify deficient areas for each wheelpath.
D-13
Any individual bump, which is more than 1/4 inch when tested with a 10-foot metal static straightedge, is a deficiency, which requires correction. Excessive rippling of the pavement surface will not be accepted. Ripples are small bumps (less than ¼ inch) in the pavement surface which usually appear in groups in a frequent and regular manner. No more than 12 ripples or peaks will be allowed in any 100-foot section. Rippling indicates a problem with the paving operation or mix that requires immediate corrective action by the contractor.
Modify operations to ensure the overall ride and individual bump requirements are met. Ensure the following quality requirements are met:
a) Produce IRI which meets the requirements for 100 percent pay in accordance with Table 601.3.110-1. Pavement operations resulting in continued surface tolerance penalties will not be allowed.
b) Correct all individual bumps which are more than ¼ inch when tested with a 10-foot metal static straightedge. The Rolling Straightedge Simulation in ProVAL may be used to help identify these bumps.
c) Correct ripples to the satisfaction of the Project Engineer. Report the Rolling
Straightedge Simulation for areas with 12 or more small, regular (less than 1/4 inch) bumps in a 100-foot section or for any areas in question.
Submit quality control IRI results to the Engineer for assessment as requested.
2. Correction of Deficient Areas
Correct deficient areas to meet the requirements of 601.3.110.C.1. Correct transverse, cross slope, or grade deficiencies to meet specifications. Make corrections by removing and replacing the PCCP full depth, or by diamond grinding and reestablishing surface texture and depth. Make corrections at no direct pay. In lieu of grinding, the Project Engineer may penalize the contractor $1,000.00 per individual bump or per localized area of excessive rippling.
For areas that will not be improved by grinding such as minor dips, extreme vertical curves, or other areas, the Project Engineer may waive the requirement to grind. In such cases, submit to the Engineer a written request to waive the requirement to grind and accept as constructed, along with a justification including a ProVAL screen shot for the area showing the Rolling Straightedge Simulation. Although omitted from corrective action, these areas still contribute to the overall IRI results.
D. Acceptance
1. Longitudinal Surface Tolerance Acceptance
Measure each mainline travel lane continuously from start to finish in the direction of travel for the project’s entire length. Perform the measurement under the observation and in the presence of the certified DOTD inspector. For projects that qualify for 102 percent pay, in accordance with Table 601.3.110-1, the Materials and Testing Section will verify the testing results. Measure the surface tolerance for acceptance at the completion of the project after all corrective actions.
D-14
Profiler system parameter settings shall be verified before and during each run by the DOTD inspector. The inspector will witness and document the daily setup procedure and pre-operation tests performed by the contractor in accordance with the manufacturer’s procedures and DOTD TR 644. A copy of the manufacturer’s setup, pre-operation, and general operating procedures for measuring surface tolerance, along with a copy of DOTD TR 644, shall be available at all times during measurement. Place a start and stop mark at the beginning and end of each travel lane so that the Department can rerun measurements.
The mainline longitudinal surface tolerance IRI specification requirements are in
Table 601.3.110-1.
The Department will view the mainline PCCP’s IRI raw data with ProVAL to identify deficient areas as defined by 601.3.110.C.1. Submit to the engineer for approval the locations and screen shots for any allowed uncorrected deficiencies in accordance with 601.3.110.C.2. Although grinding for some areas may be deemed unnecessary by the engineer the measured roughness for such areas will still contribute to the total IRI for the project. In addition, the Department will check for
1/4 inch bumps and excessive rippling at locations determined by the engineer.
Correct deficiencies in accordance with 601.3.110.C.2.
A DOTD inspector will be present for the acceptance testing and will immediately receive a copy of the raw data, the “*.erd” file and any files with information about the project, the operator, the equipment, the settings, daily pre-operation results, and a copy of the IRI results via USB flash drive. In addition to the data transferred by
USB storage device, provide the engineer a paper copy of the IRI report. Acceptance for the project will be in accordance with Table 601.3.110-1. The Department may elect to perform and utilize independent ride quality test results for acceptance at any time.
2. Exclusions
Take the IRI acceptance measurement in its entirety, without exclusions. The
Department will then review the profile report obtained for each lane. The project engineer will isolate or exclude sections of the profile that adversely affect the average IRI beyond the contractor’s reasonable control. These include the following:
a) Bridge ends and sections within 150 feet of bridge ends
b) Wheelpaths adjacent to curb and gutter sections
c) Wheelpaths adjacent to existing pavements
d) Manholes, catch basins, valve and junction boxes
e) Intersections or railroad crossings affecting the mainline roadway profile
f) Structures located in the roadway which cause abrupt deviations in the profile
g) Ramps less than 1,500 feet and turn lanes
D-15
h) Sections within 200 feet of the project limits if the limits begin or end at an intersection
i) Other sections where the project engineer determines that attaining smoothness is beyond the contractor’s reasonable control.
The roughness in excluded areas will not be included in the total IRI used for pay determination, but shall meet the requirements of 601.3.110.C.
The quantity represented by the roadway length excluded will not receive any bonus pay adjustment for surface tolerance.
Table 601.3.110-11
Payment Adjustment Schedule for
Mainline Longitudinal Surface Tolerance, Maximum International Roughness
Index, inches per mile
Percent of Contract
Unit Price 102% 100% 98% 80%
50% or
Remove and
Replace2
Category I: Design Speed
≥60 mph, IRI in/mi ≤65 ≤75 76-90 91 - 105 >105
Category II: Design
Speed ≥45 mph and <60 mph, IRI in/mi
≤75 ≤85 86-100 101 -
>115
Category III:
Design Speed <45 mph, IRI in/mi
N/A ≤115 116-
131 -
>145
1 Applies to each travel lane for the entire project’s length.
2 At the option of the Chief Engineer.
Section 601.3.130 is deleted and replaced with the following:
601.3.130 OPENING TO TRAFFIC
Allow traffic on the pavement after 14 days or when test specimens, complying with 601.3.070, attain a compressive strength of 3,000 psi when tested in accordance with DOTD TR 230, or when high flexural strength is specified, a flexural strength of 480 psi when tested in accordance with ASTM C1074. Saw initial stress relief joints and clean the pavement prior to opening to traffic. If full width joints are cut, seal before opening to traffic.
601.3.140 ACCEPTANCE REQUIREMENTS
A. General
Conduct sampling for DOTD testing on each pavement lot for thickness, concrete strength, and surface tolerance. Sample in accordance with the DOTD Sampling
D-16
Manual. Correct all pavement that is obviously defective, or remove and replace to full depth, to the satisfaction of the engineer. Times and locations will be established by the engineer.
A pavement lot is an identifiable area of approximately 4,000 square yards paid under the same item. The final area of pavement placed is a lot if it is at least 2,000 square yards; otherwise, it will be included in the previous lot. The engineer may redefine the lot limits when sequences of construction prevent timely sampling and testing.
Consider intersections, entrances, crossovers, ramps, and any other identifiable placement as separate lots.
B. Concrete Strength and Thickness
1. Compressive Strength
Determine the 28-day compressive strength and thickness of pavements from hardened cores. The Department, in accordance with DOTD TR 225, will identify random concrete core locations and determine the diameter, thickness, and strength.
Cut the cores in the presence of a DOTD representative between 14 days and 26 days after concrete is placed. The DOTD representative will take immediate possession of the cores for thickness and strength determinations. Notify the District
Laboratory Engineer at least five days prior to the start of coring operations.
The engineer will divide each pavement lot into five equal sections. Obtain one core from each section after meeting surface tolerances. Provide additional cores required by the Department to isolate thickness, strength or other pavement deficiencies, or for recutting of deficient cores at no direct pay. Patch all core holes using an approved pavement or structural concrete mixture meeting the requirements of
Section 901. Patch the core holes immediately after coring operations. Finish the surface of the patch to match the surrounding pavement. Include the cost of patching the core holes in the bid price of the concrete coring.
When the average strength for the lot is less than 4,000 psi, the contract unit price will be adjusted in accordance with Table 601.3.140-1. When an individual core indicates compressive strength less than 3,000 psi, remove, and replace the entire deficient section with concrete of the specified quality. If the Chief Engineer determines that the concrete may be left in place, payment for the quantity of concrete represented by the deficient core will be made at 50 percent of the contract unit price. Payment for the remainder of the lot will be made in accordance with
Table 601.3.140-1 based on the average compressive strength of the remaining sections.
D-17
Table 601.3.140-1
Payment Adjustment Schedule
Property
Payment
(Percent of Contract Unit Price/Lot)1
100 95 80 50 or Remove and Replace2
Deficiency in Average
Thickness of 5 cores/lot, inches
0 to
0.13
0.14 to
0.25
0.26 to
0.5 Over 0.50
Average Compressive
Strength, psi (28 to 31 days) ≥4,000
3,500 to
3,999
3,000 to
3,499 Below 3,000
Average Flexural Strength, psi
600 & over 599-530 529-480 Below 480
1 Payment adjustment shall be cumulative.
2 At the option of the Chief Engineer.
2. High Flexural Strength
When high flexural strength (modulus of rupture) is specified, submit a contractor-controlled curing and delivery plan to the engineer for approval.
Determine the flexural strength using the maturity method according to ASTM
C1074. The pavement lot shall be divided into five equal segments, and a minimum of two maturity sensors will be placed in each segment. The Department, in accordance with DOTD TR 225, will identify random locations to place the maturity sensors.
When the average flexural strength for the lot is less than 600 psi, the contract unit price will be adjusted in accordance with Table 601.3.140-1. When a maturity sensor indicates flexural strength less than 480 psi, remove, and replace the entire deficient section with concrete of the specified quality. If the Chief Engineer determines that the concrete may be left in place, payment for that segment will be made at 50 percent of the contract unit price. Payment for the remainder of the lot will be made in accordance with Table 601.3.140-1 based on the average flexural strength of the remaining sections.
To verify the sensor results, one beam per every 3 lots or every 10…