COMMISSIONING PLAN
Weaver Mountain Fire Station
May 26, 2014 impact ● collaborate ● innovate
Ambient Energy
130 W 5th Ave
Denver, CO
80204
303.278.1532
Denver
Los Angeles
San Francisco ambient-e.com
2● Page
TABLE OF CONTENTS
Project Overview and Commissioning Goals
Commissioning Scope
Systems to be Commissioned
Heating Ventilation and Cooling (HVAC) Systems
Lighting Systems
Plumbing Systems
Project Team and Responsibilities
Owner/Owner's Representative
Design Team (A/E)
Commissioning Authority (CxA)
Construction Manager/General Contractor:
Subcontractors
Commissioning Team
Schedule of Cx Events by Phase of Project
Design Phase
Construction Phase
Acceptance Phase
Appendixes
Appendix A: Owner’s Project Requirements
Appendix B: Basis of Design
Appendix C: Commissioning Team List
Appendix D: Abbreviations and Definitions
3● Page
PROJECT OVERVIEW AND COMMISSIONING GOALS
The Weaver Mountain Fire Station (WMFS) is to be located at 33501 South Highway 89, Wickenburg, AZ on the BLM property. The WMFS will be constructed in two (2) phases.
Phase 1 is to construct the 3,748 sf Operations area. This area will house offices, training rooms, and locker rooms. Phase 2 is to construct the 2,593 sf Engine Bay area. This area will consist of two (2) engine bays, workshop, and mezzanine.
As proposed, key program elements include:
• The project is not pursuing a LEED certification;
• The project is seeking compliance with the Guiding Principles for Federal Leadership in
High Performance and Sustainable Buildings;
• Mechanical, electrical, and plumbing systems are to be designed to be as energy/water efficient as possible.
The HVAC systems in the Operations area comprises of one (1) energy recovery unit, three
(3) heat pumps with outdoor remote condensing units, and one (1) split-system air conditioning unit for the COMM Closet. The Engine Bay HVAC system comprises of one (1) exhaust air system with carbon monoxide and nitrogen dioxide controls, one (1) shop welding exhaust fans, three (3) infrared heaters, one (1) transfer fan, one (1) roof-mounted intake hood with a motorized damper, one (1) wall intake louvre with a motorized damper, one (1) roof mounted exhaust hood with a motorized damper, and one (1) evaporative cooler. All major HVAC equipment is to be controlled by DDC.
Commissioning Scope
Commissioning (Cx) is a systematic process of observing and documenting that a building’s systems installation, calibration, and performance meets both the Owner’s Project
Requirements (OPR) and the design team’s Basis of Design (BOD). For this project the schematic design documents and narratives will serve as the OPR and BOD. In order to achieve the maximum benefit from the Cx process, it is recommended that Cx begin during the design phase of the project to provide quality control of documentation for the systems to be commissioned and continue through construction, acceptance, and post-occupancy. In accordance with Guiding Principles for Federal Leadership in High Performance and
Sustainable Buildings, the commissioning process is intended to achieve specific goals in each phase of the project.
DESIGN PHASE: Commissioning during design is intended to achieve the following objectives:
• Review 100% design development documents prior to start of construction documents phase.
• Review construction documents, including OPR and MEP BOD, at 100% submittals.
• Incorporate the Cx requirements into the project by issuing the Cx specifications.
4● Page
• Develop the Commissioning Plan (Cx Plan).
CONSTRUCTION PHASE: Commissioning during the construction of this project is intended to achieve the following specific objectives:
• Review submittals of commissioned systems.
• Observe and document that equipment and systems are installed properly and receive adequate operational inspection by installing contractors.
• Observe and document performance of equipment and systems through normal and emergency operational modes necessary to meet design intent.
• Provide the owner with a final Commissioning Report that documents the commissioning process and results.
SYSTEMS TO BE COMMISSIONED
Heating Ventilation and Cooling (HVAC) Systems
• HVAC DDC System o Control Points o Control Sequences o Graphics
• Energy Recovery Units o ERV-1
• Heat Pump System o HP-1, 2, 3 o CU-1, 2, 3
• 100% EA Units o EF-1
• Evaporative Cooler EC-1
• Fans o EF-2 o TF-1
• Infrared Heaters o IRH-1, 2, 3
• Miscellaneous Equipment (Operations) o AC-1 and associated CU-4 o FH-1 o GM-1 o PR-1
• Miscellaneous Equipment (Engine Bay) o SL-1 Motorized Damper o FEA-1 o RH-1 Motorized Damper o IH-1 Motorized Damper
5● Page
Lighting Systems
• Daylighting controls
• Lights and lighting levels (interior)
• Lights and lighting levels (exterior)
• Lighting controls
Plumbing Systems
• Domestic Hot Water Heaters o DHW-1
• Domestic Hot Water Circulation Pumps o P-1
• Compressed Air System (Engine Bay) o C-1
PROJECT TEAM AND RESPONSIBILITIES
Owner/Owner's Representative
The owner and/or owner’s representative is responsible for authoring the owner’s project requirements (OPR) document (see Appendix A). The OPR is a document that defines what is important to Owner regards to the design, construction, appearance, and performance of the building. The owner provides for participation of the design and construction teams in the Commissioning process. The owner also provides facility staff to participate in equipment and operational training. Other responsibilities the owner will be required to provide are listed below.
• Review, direct and approve commissioning related tasks in relation to the contract documents.
• Coordinate facility staff and schedules to participate in Cx related activities.
• Provide direction to the Project Team on Cx issue resolution.
Design Team (A/E)
The design team (specifically the architect, mechanical, plumbing, and electrical engineers) is responsible for authoring the Basis of Design (BOD) document (see Appendix B). The BOD is a document that defines, in narrative format, the systems and equipment that will be utilized in the building to meet the OPR goals. The design team also produces the documentation, professional guidance, and specifications to the construction team so that the building is constructed in accordance with the OPR requirements and also complies with all local, state, and federal regulations. The design team will be required to perform the commissioning tasks listed below.
• Review and comment on commissioning documentation.
• Include commissioning requirements in the contract documents.
6● Page
• Address and recommend solutions to observations listed in the commissioning Master
Issues Log, as required by the owner.
• Review and approve submittals, incorporating Cx review comments.
• Assist in resolution of Cx related issues.
• Review and approve final TAB report.
• Review and approve O&M documentation.
• Participate in Cx meetings as required.
Commissioning Authority (CxA)
Ambient Energy, the commissioning authority (CxA), leads, reviews, and oversees the commissioning activities. This includes coordinating commissioning activities with the CM.
The CxA reports directly to the owner, typically, and acts as an unbiased third party advisor and owner advocate for the project. The CxA does not approve or accept; rather the primary role is to observe, report, and make recommendations.
Construction Manager/General Contractor:
The construction manager (CM) provides the means and methods to delegate responsibilities as defined in the contract documents. The CM will be responsible for distributing all documentation supplied by the subcontractors to the CxA, and from the CxA to the subcontractors. Other items to be provided by CM are listed below.
• Participate in the commissioning process and meetings as required.
• Provide contractors and subcontractors to perform and cooperate in their commissioning responsibilities.
• Notify the commissioning team and other participants two days in advance of delays in schedule regarding testing and site visits, otherwise travel and time expenses will be paid by the general contractor to those attending testing.
• Gather and coordinate all information from contractors, subcontractors, and suppliers needed to develop the systems manual; this information will be provided to the CxA in an electronic format.
• Review the commissioning plan and note any points of conflict in the commissioning plan and the contract documents. This shall include any items that need clarification in the commissioning plan.
• Aid in documenting of a Cx milestone schedule, which will be coordinated with the master construction schedule. The schedule should allow for functional testing to occur before owner occupancy and after substantial completion of the system installations.
• Notify (by email) the CxA and Design Team when site commissioning activities are to take place. The notification shall be seven days prior to when the systems are to be commissioned.
• Provide qualified contractors to calibrate equipment, tools, and space access to properly test systems and equipment as directed by the commissioning authority.
• Organize and coordinate activities requiring owner, design team, and CxA attendance so time is used efficiently while during site visits.
7● Page
• Coordinate all associated testing outside the commissioning plan; this includes fire alarm, life safety, emergency power, security, etc.
Subcontractors
The subcontractors include the mechanical, electrical, plumbing, and control trades that are constructing the building. The subcontractors are responsible for completing the prefunctional checklists and returning them to CM and the CxA. Other items the subcontractors will provide are as follows:
• Direct and coordinate participation of suppliers in the Cx process.
• Review and comment on the commissioning plan, prefunctional checklists and functional testing documentation.
• Participate in Cx meetings as required.
• Completing and signing prefunctional checklist and returning them to the CM and the
CxA prior to functional testing.
• Perform equipment start-up and provide CM with start-up reports for all equipment installed.
• Inform CM of any items that may affect commissioning activities or require CxA review.
• Perform all functional testing and controls verification as directed by the CxA.
• Perform all manufacturers’ maintenance procedures from construction to turn-over.
• Perform all fine tuning and troubleshooting as required to satisfy functional testing and design parameters.
• Responsible for O&M manuals and as-built information and providing these materials in a timely manner.
• Develop and provide equipment and system training. An outline of the training should be provided to CM and CxA for review prior to actual training.
• Perform functional testing and controls verification as directed by the CxA for of the ten month building walkthrough of equipment performance, if required.
COMMISSIONING TEAM
The contact list of the commissioning team members involved in the commissioning process is located in Appendix C of this document.
8● Page
SCHEDULE OF CX EVENTS BY PHASE OF PROJECT
As the construction of the building progresses, the CxA will update the schedule reflecting both slippage and recovery actions to maintain schedule milestones. Dates (start and completed) will be determined and included in Table 2.
TABLE 2: COMMISSIONING SCHEDULE.
Task Date Started Completed
Y/N Date Completed
Creation of Owner Project
Requirements Aug, 2014 Y Feb, 2015
Creation of Basis of Design
(BOD)
Sept, 2014 Y Feb, 2015
Design Development Review and Comment (50% CD drawings)
Feb 4, 2015 Y Mar, 2015
Issue Commissioning Plan Feb 2, 2015 Y May 12, 2015
Issue Commissioning
Specifications Dec, 2014 Y Feb, 2015
Construction Commissioning
Kick off Meeting N
Review Submittals N
Issue Pre-functional Checklists N
Construction Start Date N
Develop Master Issues Log N
Site Visits start N
Review of Prefunctional
Checklists completed by contractors
N
Review TAB Report N
Witness Functional Performance
Testing N
Construction completion Date N
Building Occupancy N
Issue Final Cx Report N
9● Page
COMMISSIONING PROCESS BY PHASE OF PROJECT
This project seeks to comply with the Guiding Principles for Federal Leadership in High
Performance and Sustainable Buildings.
Fig 1: Overview of the commissioning process.
Design Phase
During this phase the commissioning process includes the following:
• Review Design Development & Construction Documents: The CxA reviews the design development and construction documents as indicated in the scope of work, and provides comments to the design team. The CxA works with the design team to address any issues or concerns identified during the review. The comments, responses, and resolutions are documented in the design review log.
• Commissioning Specifications and Cx Plan: The commissioning specifications are written by the CxA and provided to the owner and design team to include in the project specifications. The specifications along with the Cx Plan define the commissioning requirements for the project.
Design Phase
OPR and BOD
Review/Quality Control
Design Documents Review/Quality Control
Construction Phase
Update Cx Plan;
Schedule Cx Activities;
Review Submittals
Review Submittal
Data;
Develop Pre-Functional
Checklists;
Conduct Site Visits;
Master Issues Log
Acceptance Phase
Functional Performance
Testing;
Issues Log Resolution;
Systems training sessions led by
Manufacturer’s Reps or
Contractors;
Review TAB and O&M
Manuals;
Document Functional
Performance testing results;
Document training session agendas and attendance;
Final Cx Report
10● Page
Construction Phase
The construction phase begins at the end of the design phase, during this phase the commissioning process includes the tasks below1:
• Review Submittals of Commissioned Systems: The CxA reviews submittal data related to the systems being commissioned, and provides comments to the design team and construction manager. The CxA works with the design team and construction manager to address any issues or concerns identified during the review. The comments, responses, and resolutions are documented in the submittal review log.
• Update the Cx Plan: The CxA updates the Cx Plan periodically throughout the design and construction of the project as needed.
• Commissioning Kick-off Meeting: The kick-off meeting occurs after contracts have been awarded prior to equipment installation. The meeting includes the CxA, design team, the contractor, and subcontractors, (including the mechanical, electrical and plumbing contractors); the owner is also encouraged to attend.
• Commissioning Schedule: The schedule is discussed at the Cx Kick-off meeting and dates for key commissioning activities are placed on the overall construction schedule.
• Review of Submittals: Submittals of the equipment to be commissioned are reviewed for compliance with the construction documents, OPR, BOD, and the ability to be commissioned. Comments are provided to the CM. Issues, if found, are documented on the Master Issues Log.
• Pre-functional Checklists: The CxA will create and complete pre-functional checklists for equipment to be commissioned on the project. These checklists are used to verify the equipment arrived on site, is the correct equipment and is installed per design and per manufacturer’s recommendations.
• Site Visits: Site visits are conducted by the CxA periodically throughout construction.
The goal of the site visit is to observe the installation of the equipment to be commissioned and observe that the equipment and systems meet the criteria of the OPR and BOD. The CxA will document observations and issues identified in a Site Visit
Report.
• Maintain Commissioning Log: The Master Issues Log (MIL) is developed and updated after each site visit and is included in the Site Visit Report.
• Review Prefunctional Checklists: Review and comment on prefunctional checklists that are completed by the contractors.
• Manufacturer Startup Reports: Manufacturer’s start-up of equipment occurs after the equipment is installed and ready for operation. Startup is intended to test the equipment and flush out any items that may have been changed during the installation process.
During startup, equipment parameters and performance is documented by a manufacturer’s or contractor’s qualified technician or representative. Pre-functional
1 The construction phase scope of work has not been awarded by the Owner. As such, this scope of work is subject to change based on negotiations between the
Owner and CxA.
11● Page checklists provided by the CxA are not a substitute for manufacturer’s checklists and startup procedures. The manufacturer checklists and startup procedures are provided the CxA and are included in the Cx Report.
• Create Functional Performance Tests: The CxA creates the functional performance tests based on submittal information and intended system operation. The systems are tested to perform as intended in normal and emergency modes of operation.
Acceptance Phase
The acceptance phase will begin toward the end of construction, when the systems are ready for testing, during this phase the commissioning process will provide the following2:
• System Testing Readiness: The installing contractor will be responsible for certifying that the commissioned systems are ready for functional performance testing. The Engineer of
Record’s punch list items will need to be accepted by the Engineer of Record. The
Engineer of Record will notify the CxA when their punch list has been accepted. The contractor will provide the completed prefunctional checklists, start-up reports, controls testing reports, and TAB report to the CxA for review prior to the CxA scheduling execution of the functional performance tests.
• Functional Performance Testing: Functional performance testing is conducted by the contractors, and witnessed and directed by the CxA. The testing includes the systems and equipment that are included in the commissioning process. The systems and equipment are tested to demonstrate compliance with the OPR, BOD, and construction documents. The systems are tested in normal operating mode as well as emergency operating mode, if applicable.
• Master Issues Log (MIL): At the end of the acceptance phase, the issues in the MIL will be either resolved, or a clear path to resolution has been identified and documented in the MIL.
• System Acceptance: After completion of the functional testing and MIL as noted above, the CxA will recommend acceptance of the commissioned systems to the Owner, Architect, and Engineer of Record.
• System Training: After the systems have been accepted by the Owner, the contractor will schedule system training with the Owner. The training should be conducted by the installing contractor and/or manufacturer’s representative. The training should be provided to the building’s operations and maintenance (O&M) staff. For each training session, the contractor and/or manufacturer’s representative will provide an agenda to the CxA for review prior to the meeting. Also, for each training session, the contractor and/or manufacturer’s representative will be responsible for documenting training attendance. Attendance sheets will be submitted to the CxA.
2 The acceptance phase scope of work has not been awarded by the Owner. As such, this scope of work is subject to change based on negotiations between the Owner and CxA.
12● Page
• Final Report: The CxA will develop a report that summarizes the commissioning activities accomplished during the Design, Construction, and Acceptance phases of the project.
The report typically includes the following (at a minimum):
o Executive Summary o Cx Plan o Design Review Comments o Site Observation Reports o Prefunctional Checklists o Functional Performance Tests o Master Issues Log
13● Page
APPENDIXES
Appendix A: Owners Project Requirements
Appendix B: Basis of Design
Appendix C: Commissioning Team List
Appendix D: Abbreviations and Definitions
14● Page
Appendix A: Owner’s Project Requirements
Owner’s Project Requirements for
Federal Guiding Principles for High Performance and
Sustainable Buildings
Project: Weaver Mountain Fire Station, L140D00737
Location: 33501 South Highway 89, Wickenburg, AZ 85390
Contacts: Stephen Cole, BLM National Operations Center, Denver, CO
303-236-1158
Introduction
The Owner’s Project Requirements (OPR) document is used to articulate the most important goals and objectives of the project from the point of view of the owner. The OPR is a detailed collection of the functional requirements of a project and the expectation of the building’s use and operation. This document is intended for use by the owner, design team, construction team, operation and maintenance staff, future renovation teams, and anyone who needs access to the original project information. The OPR forms the basis from which design, construction, operation and acceptance decisions are made. Each item of the OPR may have defined performance and acceptance criteria. Those that can be benchmarked should have the benchmark defined in specific terms and measurement.
During the course of design and construction, the OPR is updated to reflect changes to the original project goals. Updates to the OPR during the design and construction process are primarily the responsibility of the owner.
This OPR is a precursor and companion to the Basis of Design (BOD) document that provides detailed information on how the owner’s requirements are to be met through the development of the design documents, and/or implementation during construction, and/or operation. The
BOD is developed by the design team to reflect the requirements as specified in this OPR.
To meet BLM requirements, the owner’s intent is for the completed Fire Station to be compliant with the five Federal Guiding Principles for High Performance and Sustainable
Buildings. Requirements and strategies outlined in this document are driven by that goal.
Overview of Project
The Bureau of Land Management (BLM) has a strong commitment to high quality building construction, including sustainable design. In 2006, the BLM furthered their commitment to sustainability by pursuing compliance with the Federal Guiding Principles for High Performance and Sustainable Buildings (GP’s or Guiding Principles) on all new building projects.
The project referenced in this document will be the new Fire Station for the Weaver Mountain
BLM site. It will be a statement of commitment to the environment and a showcase for the community and the public that BLM serves.
The building designers should pursue sustainable objectives both within and outside the
Guiding Principles whenever possible. BLM’s commitment to sustainability is consistent with the desire to have integrated design and construction that exceeds industry standards both functionally and aesthetically.
The following items are described in this OPR:
• Owner Requirements
• Environmental and Sustainability Goals
• Energy Efficiency Goals
• Indoor Environmental Quality Requirements
• Equipment and System Expectations
• Building Occupant and O&M Expectations
1. Owner Requirements
A. Development of a 6,341 sf wildland fire station for use by BLM as outside of the city of Wickenburg, AZ.
B. The goal of the project is to provide a new fire station, consisting of an operations side and attached engine bays, reflecting the quality of development and professionalism that BLM purports. BLM has a commitment to sustainability for their new development projects and these needs must be reflected in this fire station project.
C. The conditioned office space will include a fully insulated and sealed envelope.
D. The design team may be asked to review or provide life cycle information where alternative systems are being evaluated that emphasize high value, long life and high efficiency.
E. Building envelope and structural components shall be designed for a longer than industry standard life cycle.
F. Mechanical. Electrical and Lighting equipment will be high efficiency with longer than average life cycle. Equipment will be selected based on long term value to the
Owner.
G. The design and construction team must provide an updated GP narrative completed in its entirety to BLM within 2 weeks after substantial completion is issued.
H. The design team is required to provide language in the specifications and/or the
General Notes of the Construction Drawings outlining the training requirements for each system. The design team is encouraged to work with the commissioning agent to collaborate on their reports and documents as there are commonalities. The minimum training requirements are as follows:
• Provide the trainees with a package that include the operating instructions, OPR, BOD, equipment submittals, Commissioning Report, construction drawings, testing procedures, functional checklists, maintenance schedules for equipment, and copies of warranties (equipment and maintenance).
• Include two trainings on the EMS system: one upon turning over the building and the second, 2-3 months after the building is in operation to resolve questions or issues.
• Contractors are required to balance and calibrate equipment, systems and controls and have the systems fully functional upon completion of the project.
They will make themselves available to answer questions that arise during the first year of operation.
I. Two levels of training shall be developed. One basic program for building occupants will include operating lighting, mechanical and security systems. Another more advanced level will be developed for a service contractor to be determined in the future. This will include operational procedures, maintenance, and control system programming.
J. Contractor shall videotape training and provide training DVDs to BLM.
2. Environmental and Sustainability Goals
A. Project shall comply with all Five Guiding Principles.
B. Project shall use an integrated project team and planning and design process.
C. Project shall employ appropriate commissioning practices in accordance with the requirements of Guiding Principle 1. The design team will work with the BLM to create a commissioning plan for the project.
D. Project shall not provide outdoor irrigation for landscaping. Hand watering will be used for newly landscaped areas during the establishment period only.
E. Project shall achieve an indoor water use reduction of at least 20% as compared to the baseline established by the Energy Policy Act of 1992. Water-saving plumbing fixtures to be used include pint flush urinals, low-flow toilets and low flow lavatory emitters and shower heads. These criteria are outlined in Guiding Principle 3. Use
EPA Watersense fixtures.
F. Project shall set a goal for a stormwater management plan that meets the criteria of
Guiding Principle 3.
G. Exterior lighting shall be reviewed by design team and owner to determine the options for meeting light pollution reduction goals without reducing the security of the facility.
3. Energy Efficiency Goals
A. Project shall achieve an energy cost savings of at least 30% compared to the baseline building performance rating per Guiding Principle 2.
B. Design team will provide the owner with different lighting options and packages to review and select based on features, performance, and first costs.
C. Daylighting controls will be installed for all exterior lighting and lighting in the fitness area.
D. Motion/Occupancy sensors shall be installed for lighting circuits in offices, training, fitness, work, locker, and storage rooms.
E. Additional energy efficiency measures that provide cost effective energy savings shall be included whenever feasible.
F. Design team will provide Energy Modeling Report (in accordance with the scope of work), that shows the Design meets EPAct 2005 with Guiding Principle 2 update as of 2008 (30% better than ASHRAE 90.1 2007)
4. Indoor Environmental Quality Requirements
A. Project shall meet the requirements of ASHRAE 62.1 – 2004, Ventilation for
Acceptable Indoor Air Quality and ASHRAE 55-2004, Thermal Environmental
Conditions for Human Occupancy in accordance with Guiding Principle 4.
B. Project shall meet Guiding Principle 4 requirements for Environmental Tobacco
Smoke (ETS) control.
C. The General Contractor shall develop an Indoor Air Quality Management Plan for the construction phase of the building according to Guiding Principle 4.
D. Project shall meet the requirements of Guiding Principle 4 concerning the use of low-emitting adhesives & sealants.
E. Daylight and Views are important and should be considered when designing the project.
F. HVAC controls will have simple override for after hour operation.
G. Special attention is to be paid to restroom and kitchen areas to guarantee that the air remains “fresh” and free of odors or stagnation.
5. Equipment and System Expectations
A. The project shall be fitted with a digital control system, integrating monitoring and control of energy consuming and monitoring equipment.
B. The building control system shall be of sufficient memory and configured to trend and alarm critical functions, values, and energy variables for a period of at least one
(1) year after system startup.
C. The MEP team will coordinate with BLM’s mechanical engineers to specify an energy management system designed to have the ability to be monitored remotely via internet connection.
D. HVAC equipment that uses CFC-based refrigerant is unacceptable. HVAC equipment and refrigerants shall be selected to meet the requirements of Guiding Principle 5.
E. Per Guiding Principles 2, building-level metering of energy use in accordance with the DOE guidelines issued under section 103 of the Energy Policy Act of 2005 is required for measurement and verification (M&V). Building-level natural gas and water meters only shall be provided to measure use and demand. The existing site electric meter shall be used to measure site electricity use and demand.
F. Set points shall be programmed assuming that facility hours of operation will be 6:00
AM - 6:00 PM Mon-Fri. Systems will be equipped with override options for use outside of regular occupancy schedule.
G. The design will provide for a room temperature setting of 65°F in the winter and
80°F in the summer when the spaces are unoccupied. The occupied setting will be
70°F in the winter and 75°F in the summer.
H. Solar shading and glass selection is important and BLM requires that the design team take into consideration Solar Heat Gain and glare when designing the exterior skin.
I. Energy related equipment must be accessible for maintenance, testing and balancing. No dampers or equipment shall located above a ceiling that is not easily accessible (i.e. concealed sheetrock/drywall; above a toilet or similarly difficult location to access.).
J. Energy related equipment will be configured with appropriate instruments as necessary to perform start-up, commissioning, ongoing maintenance and calibration.
6. Building Occupant and O&M Expectations
A. Day-to-day HVAC operation of occupant controls is to be provided in a simple, easy to use format.
B. Periodic HVAC maintenance shall be arranged for by the owner.
C. Lighting system maintenance will be arranged by the owner.
D. Training required for building occupants includes demonstration of applicable systems and instruction documents for these systems.
- End of OPR -
15● Page
Appendix B: Basis of Design
Weaver Mountain Fire Station - L14PD00737
100% Construction Document Submittal Revised, 26 January 2015 1
MKK Consulting Engineers, Inc. Design Narrative
CODES AND STANDARDS MEP:
• 2012 International Building Code
• 2012 International Fire Code
• 2012 International Mechanical Code
• 2012 International Plumbing Code
• 2012 International Energy Conservation Code
• 2012 International Existing Building Code
• 2012 International Fuel Gas Code
• NFPA 13 2010 Edition – Installation of Sprinkler Systems
• NFPA 14 2010 Edition – Installation of Standpipe and Hose Systems
• NFPA 20 2010 Edition – Centrifugal Fire Pumps
• NFPA 54 2009 Edition – National Fuel Gas Code
• NFPA 58 2009 Edition – Liquefied Petroleum Gas Code
• NFPA 70 2014 Edition – National Electrical Code
• NFPA 72 2010 Edition – National Fire Alarm Code
• NFPA 90A 2009 Edition – Installation of Air Conditioning and Ventilation Systems
• NFPA 101 2009 Edition – Life Safety Code
• Jurisdictional Utility Company Requirements
• State Department of Labor Requirements
• State Department of Health Requirements
• State and Federal Safety and Health Laws
• ASHRAE Standards including but not limited to 55, 62.1 and 90.1, applicable versions
DESIGN CONDITIONS:
Exterior Design Conditions:
Winter Summer Wet Bulb Project Elevation
19.7 o
F DB 110.8
o
F DB 70.7
o
F WB 2,070
Interior Design Conditions:
Mode Winter Summer
Occupied 70 o
F DB 75
o
F DB
Unoccupied 65 o
F DB 80
o
F DB
Active humidity control is not provided.
100% Construction Document Submittal Revised, 26 January 2015 2
MECHANICAL NARRATIVE
GENERAL MECHANICAL WORK
TAB Statement of Work
Test and balance the environmental systems including but not limited to air and water distribution systems and the equipment and apparatus connected thereto. The General Contractor will procure the services of an independent testing and balancing firm specializing in this work.
Commissioning Statement of Work
Provide commissioning services for the HVAC, plumbing and electrical equipment and systems outlined in the scope of work. The building shall also undergo a flush out procedure. A full report shall be issued to BLM at the end of the project.
Controls Statement of Work
Where noted in Building and System narratives below furnish and install a microprocessor based Direct
Digital Control (DDC) system for the monitoring and control of the mechanical and electrical equipment.
The DDC System will be of electronic components employing direct digital control to comprise a complete system, furnished and installed by the automatic temperature control contractor, Johnson
Controls, Inc. Provide a JCI NCE supervisory controller, equipment controllers and each HVAC unit with a
TEC network programmable thermostat capable of performing the control sequence of operations listed in the options below. HVAC equipment controls shall be field installed. The DDC system will have a protocol interface of BACnet IP. Control valves and actuators will be modulating except where noted otherwise below. The system will be complete in all respects, put in operation and calibrated and adjusted under occupied conditions. All temperature control work will be done by a single source responsibility.
General Mechanical Items
• Sheet metal duct systems gauges and installation requirements will be in accordance with
SMACNA HVAC Duct Construction Standards Manual. All round and oval ducts exposed to view will be spiral seam. Concealed round and oval ducts may be fabricated with lock type or welded longitudinal seams. All duct connections to motor driven equipment will be made with flexible connections. Make all radius elbows with radius of one and one half times the diameter or width of duct and an inside throat radius of one times the diameter or width.
Radius elbows are the preferred method for 90º duct turns. Provide manual balancing dampers at all takeoffs.
• All supply, return, exhaust and transfer ductwork will be galvanized steel. No fiberboard is allowed. All supply, return and transfer ductwork will be insulated with 1-1/2” fiberglass duct liner unless noted otherwise. Return air will be fully ducted from the space back to the
HVAC unit. All transfer ducts will have a minimum of two 90-deg elbows for sound attenuation.
• Fire dampers, smoke dampers, and combination fire/smoke dampers will be installed in ductwork where ducts penetrate rated assemblies where required by the Building Code.
Fire detection devices will be installed in all fan systems when required by the Building
Code.
100% Construction Document Submittal Revised, 26 January 2015 3
• All round outside air; return air and supply air ductwork shall have 2” thick fiberglass wrapped insulation, conforming to ASTM C553, Type 1, and “R” value of 8. Supply with vapor barrier foil-scrim-kraft (FSK) jacket.
• Smoke detectors installed in ducts and in listed air moving equipment shall be supervised by the building fire detection or alarm system when the building is equipped with such system.
• Provide vibration controls for equipment, piping and appurtenances.
• For refrigerant piping, provide flexible elastomeric or polyolefin insulation for fittings, flanges, valves and shall be pre-molded, pre-cut or job fabricated of the same thickness and conductivity. For flexible elastomeric: maximum K-value shall be 0.27 BTU-in/hr-SF/°F, flame spread/smoke developed indices shall be 25/50 or less for thickness 1 inch or less.
For flexible polyolefin: maximum K-value shall be 0.24 BTUH-in/hr-SF/°F, flame spread/smoke developed indices shall be 25/50 or less for thickness 1 inch or less. Insulate fittings with glass fiber blanket insulation. All exterior refrigerant piping shall be provided with a field mounted aluminum jacket.
• Provide ceiling access panels for all manual volume dampers and equipment access above hard lid ceilings.
• Provide sheet metal outside air, return and supply ductwork for each HVAC unit with insulation and duct sealant.
• Provide refrigerant liquid and suction piping with insulation.
• Provide low loss spin-in fitting with manual volume dampers to each grille and diffuser.
• Provide commercial grade grilles and diffusers, Titus or approved equal, for each room with a fully ducted return.
Stage 1 Operations Building Miscellaneous Systems
• Provide (1) 2-ton split system AC unit Mitsubishi Mr. Slim or equal for the Communications
Room. The indoor unit shall be wall mounted with a condensate pump. Route condensate to mechanical room floor drain with air gap and throttling ball valve. Provide refrigerant piping and insulation. The unit shall operate from a standalone thermostat.
• Provide (1) 925 CFM packaged plate type energy recover unit Renewaire or approved equal with ECM motor fans. The restroom and shower exhaust ductwork shall connect to the energy recovery unit and the supply discharge of the energy recovery unit shall connect to the heat pumps inside the mechanical room.
• Provide (1) aluminum roof intake hood rated for 925 CFM with sloped roof curb and insulated outside air ductwork down to the energy recovery unit in the mechanical room.
• Provide (1) louver above the mechanical room doors with bird screen for the exhaust discharge of the energy recovery unit.
• Provide (1) horizontal 500W electric unit heater for the mechanical room.
Site Conditions
• There are two existing 1,000 gallon propane tanks serving the existing building. Per the
March 13, 2013 propane bill and staff interviews at the project kickoff meeting, both tanks are filled once a year with starting level of 30% and a fill level of 80% totaling 955 gallons for both tanks. The total storage capacity of both tanks at 80% full is 1,600 gallons. Table 1 below compares the maximum equipment propane load by building.
Building Maximum Equipment Input Btuh
Existing Facility 809,000
100% Construction Document Submittal Revised, 26 January 2015 4
New Operations Building 400,000 (estimated)
New Operations Building & Future Engine Bay 800,000 (estimated)
Table 1 – Building Equipment Propane Load Comparison
Table 2 listed the diversity factor for various pieces of equipment per the NPGA Handbook.
Equipment Diversity Factor
Furnace 0.5
Radiant Heater 0.4
Water Heater 0.16
Dryer 0.15
Table 2 - Equipment Diversity Factors
Per the NPGA Handbook for a 1,000 gallon propane tank 25% full at 20°F ambient air temperature and 60% relative humidity, the vaporization rate is 157 MBH. For two 1,000 gallon tanks the vaporization rate is 314 MBH. Table 3 shows the demand of the buildings based on the diversity factors in Table 2.
Equipment Demand MBH
Existing Building 109
New Operations Building 118
New Engine Bay 160
Existing Building + Operations Building 227
Existing Building Plus Operations Building and Engine Bay 387
Table 3 - Equipment Diversity Factors
Based on the results of Table 3 and the total gallon usage listed in Table 1, an additional propane tank is not required for the New Operations Building. One additional propane tank may be required when stage 2, the Engine Bay is added.
• For base bid, the assumption is the facility at worst case will fill the tanks up twice a year instead of once a year. Therefore no additional propane tanks will be required.
• Provide alternate pricing for (1) additional 1,000 gallon propane tank leased and installed from the Flame Propane company. Provide concrete pad extension and additional bollards around the new tank. The additional tank will accommodate the New Operations Building with one propane fill a year.
• Provide (1) propane gas meter with a pulse BAS readout and secondary gas pressure regulator for the new Operations Building.
• Provide 1-1/2” propane piping from new meter, buried underground to existing propane tank header. The existing 1-1/2” propane pipe to the existing building shall remain.
• Replace propane gas meter serving the existing building with a new 1-1/2” gas meter with pulse BAS readout capability.
• Gas piping shall comply with the requirements of the International Fuel Gas Code and NFPA-
54 – National Fuel Gas Code.
100% Construction Document Submittal Revised, 26 January 2015 5
• Inside the building, the propane gas piping system will consist of schedule 40 black steel with threaded joints. The gas meter is to be located adjacent to the building and coordinated with the architect.
• Propane gas piping will be routed throughout the building to serve the domestic water heater, infrared heaters and furnaces.
• Gas pressure regulators shall be provided for at each piece of equipment.
Stage 1 Operations Building
HVAC System
• Provide (3) high efficiency, air-to-air heat pumps with auxiliary condensing propane furnaces to provide heating, cooling and ventilation for the Operations Building. Heat pumps shall be
Carrier or approved equal with SEER values equal to or greater than 16 and COP’s equal to or greater than 3.8.
• Heat pump HP-1 shall be 5-tons, HP-2 shall be 2-tons and HP-3 shall be 2-tons.
• Heat pumps and furnaces shall have 24V terminal strips for field installed controls.
• Provide heat pump with low ambient control down to 0°F.
• Provide each propane furnace with condensate neutralization kit and pipe to nearest floor drain.
• Provide heat pump manufacturer’s start-up.
Controls
• Provide a field mounted controller for each heat pump/furnace to enable/disable the heat pump and auxiliary propane furnace. An outside air setpoint shall switch the heating function from the heat pump to the propane furnace. The heat pump and propane furnace will not run simultaneously.
• The JCI NCE supervisory controller shall monitor heat pump alarms and status.
• Provide a space temperature sensor for the mechanical and alarm the BAS upon low temperature. Provide a line voltage thermostat to control the unit heater and do not connect the unit heater to the BAS.
• Provide a space temperature sensor for the IT room and alarm to the control system if the space temperature is above 85°F (adj.).
• The Operations Building energy recovery unit will enable/disable based upon occupied/unoccupied schedule. Provide the following air temperature sensor points:
outside air, exhaust air inlet, exhaust air outlet, supply air to heat pumps. Provide exhaust and supply fan start/stop and status points with failure alarm point. Provide 2-position outside air and exhaust air motorized dampers.
• For each new Operations Building heat pump unit, total of (3), the sequence will include, but will not be limited to, the following: Life/Unit safety including duct smoke detector shutdown if applicable, warm up, cool down, and occupied and unoccupied modes.
• For each new Operations Building heat pump unit, total of (3), provide the following points:
• Space temperature
• Return air temperature
100% Construction Document Submittal Revised, 26 January 2015 6
• Discharge air temperature
• Mixed air temperature
• Supply fan start/stop
• Gas furnace capacity staging (if applicable)
• Heat pump or DX coil modulation (if applicable)
• General alarm
Stage 2 Engine Bays (Provide Separate Pricing)
HVAC System
• Provide (1) indoor horizontal discharge Titan or approved equal evaporative cooling unit rated for 2,450 CFM each with non-combustible Glasdek media and 2-speed motors. Unit shall be supported from the roof structure with vibration isolators. Provide with factory disconnect switch, 24V auto fill and drain kit, glasdek evaporative media, hinged access doors, 2” aluminum mesh filter, premium efficiency motor, motor starter, and motorized outside air damper.
• Provide (1) roof intake hood with sloped roof curb for the evaporative cooling unit.
• Provide sheet metal outside air and supply air ductwork, grilles, manual balancing dampers and sealant for the evaporative cooling unit.
• Provide (1) roof mounted relief hood sized for 3,000 CFM with sloped roof curb and motorized backdraft damper.
• Provide (1) inline exhaust fan Greenheck VariGreen or approved equal with , motorized backdraft damper, disconnect switch, motor starter and ECM motor rated for 3,000 CFM at
0.4” ESP for engine bay exhaust. Fan shall be capable of receiving a 0-10V signal to vary the motor speed.
• Provide (3) infrared heaters Roberts Gordon or approved equal with direct vent configuration supported from the roof structure. Provide combustion air and flue pipe through the roof with roof jacks, propane piping, hangers, and gas cock and dirt leg for each unit heater.
• Provide (1) wall transfer fans for the air compressor room. Manufacturer shall be Broan
511MG or approved equal. Provide with disconnect switch, motor starter and line voltage thermostat.
• Provide welding fume arm extractor Ventaire Model SIFA4070 or approved equal for the shop area with 7’-0” work radius, painted steel tubing sections and flexible joints, gas spring supports, 360 degree rotation and 250 CFM of exhaust.
• Provide (1) wall mounted fume arm exhaust fan Ventaire PW-9 or approved equal with louver for side wall discharge , disconnect switch, motor starter and back draft damper.
Controls
• Provide a field mounted controller for the evaporative cooling unit to operate the fill and drain valves, sump pump, supply fan start/stop, supply fan status, alarm, outside air motorized damper, outside air temperature, and discharge air temperature.
• Provide (1) space temperature sensor for the evaporative cooling unit.
• Provide (1) space temperature sensor for each infrared heater. Provide dry contacts for start/stop and alarm control points. Provide current transducer for status control points.
100% Construction Document Submittal Revised, 26 January 2015 7
• Provide controls for each exhaust and transfer fan for start/stop, status and alarm points.
• Interlock garage exhaust fan with evaporative cooler and track the exhaust fan speed with the evaporative cooling .
• For each transfer fan provide a line voltage thermostat to enable/disable the fan based on space temperature setpoint.
• For the engine bay provide CO and NO2 sensors and controller to enable the garage exhaust fan and vary the fan speed and modulate the evaporative cooler outside air damper position based on gas detection concentration. Provide audio and visual alarms (horns and strobes) to alarm based on CO and NO2 high concentration setpoints. The controller shall have BACnet MS/TP interface for connection to the JCI NCE.
• The JCI NCE supervisory controller in the Operations Building shall monitor evaporative cooler, exhaust fan, transfer fans and infrared heater alarms and status points. All equipment in the Engine Bay shall be tied into the Operations Building control system.
PLUMBING NARRATIVE
Executive Summary/Overview
Stage 1 Operations Building and Stage 2 Engine Bay will be served by a new 1-/4” domestic cold water service line connected to the existing 2” domestic cold water line that serves the existing Crew
Headquarters Building. The domestic cold water entry assembly will include the building shut-off valve, and an indoor water meter with pulse BAS readout connected to the BAS. Provide a new water meter with BAS readout connected to the BAS for the existing Crew Headquarters building.
Existing Site Conditions
• An existing well with a submersible pump providing potable water to the site.
• There is an existing 2” line from the well to (1) 3,000 gallon above ground storage tank.
There is an existing inline solids separator on the inlet side of the storage tank.
• The outlet of the storage tank routes to the pump house with (1) 1.5 hp pump with the discharge routed to (2) 119 gallon hydro-pneumatic well tanks. The outlet of the well tanks is routed to a sand/solids separator, 1-1/2” water meter and then to the existing building.
• The existing pump operates on a 40/60 psi pressure switch.
• The existing well is assumed to have enough capacity to accommodate the existing building, Operations Building and Engine Bay.
• The total domestic water gpm demand for the existing Crew Headquarters Building is 52 and for the new Operations Building (including the Stage 2 Engine Bay) is 57. Because the total staff population will not increase and will just be divided up between the existing Crew
Headquarters Building and the new Operations Building, the existing well pump shall remain and a “T” be installed off the existing 2” cold water line to serve the new Operations
Building.
Domestic Cold Water Entry
• Backflow: Per the requirements of the International Plumbing Code and Authority Having
Jurisdiction, provide a reduced pressure principal backflow prevention device, assembly
100% Construction Document Submittal Revised, 26 January 2015 8 discharge piped to the building’s exterior with a TBD discharge line with a downspout nozzle on the building’s exterior. The device will be located in the water entry room.
Domestic Cold Water Distribution System
• Downstream of the water entry assembly described above, provide type K or L copper with soldered joints. Distribution piping will be routed to bathroom groups and individual fixtures including hose bibbs and…