Kent ISD Addendum A - KAC & Main Campus Parking Lots.pdf

PDF 264 KB Posted

Attached to
2025 Kent ISD Parking Lots & Road Replacement
Solicitation number
RFP-KSD-250000001435-2
Issued by
Kent County, Grand Rapids City, Michigan

About this file

This is an Addendum A document for the Kent ISD Parking Lots & Road Replacement Project in Kent County, Michigan. The project involves parking lot and road replacements at multiple locations including the Kent Conference Center (KCC) Lot 3A, KCTC-East Lot 3, campus drives, and the Kent Aviation Center (KAC) parking lot. All work is scheduled to be performed between May 30, 2025 and June 30, 2025, with the KCC Lot 3A having a shorter completion window of May 31 to June 7, 2025. The contractor will coordinate the project schedule and sequence with Kent ISD staff.

The modified scope of work includes two key changes: an increase in the bituminous base course thickness from 1.5" to 2.5" for the campus drives, and the elimination of the service entrance on the west side of KCC leading to the dumpsters from the project scope. The document includes an aerial map showing the Kent ISD campus with highlighted areas indicating the project scope and specifically marks the eliminated service entrance area.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Kent ISD Parking Lots & Road Replacement Project

Addendum A

Work to be performed within the time frames listed below.

Contractor will work with Kent ISD Staff who will coordinate project schedule and sequence.

Main Campus Parking/Drives

• Kent Conference Center (KCC) Lot 3A – between May 31, 2025 and June 7, 2025

• KCTC-East Lot 3 – between May 31, 2025 and June 30, 2025

• Drives into the Kent ISD Campus – between May 31, 2025 and June 30, 2025

Kent Aviation Center (KAC) parking lot – between May 30, 2025 and June 30, 2025

MODIFIED SCOPE OF WORK:

• Drives into the Kent ISD Campus – increase bituminous base course from 1.5” thickness to 2.5” thickness.

• The service entrance on the west side of KCC leading to the dumpsters has been eliminated from the project. See updated map below: