This document is a U.S. Coast Guard Justification for Other Than Full and Open Competition for Simplified Acquisition Procedures. The Coast Guard intends to purchase two specialized pieces of equipment directly from Fatigue Technology Inc. (FTI): a Medium Brute Hydraulic Offset (MBHO) Puller (MBHO-20) and an FT-200D Hydraulic Powerpak. These tools are specifically designed for FTI's patented Cold Expansion (Cx™) technology, which improves the fatigue life of metal structures, particularly for H60 helicopters.

The procurement is being conducted on a sole-source basis under FAR 13.106-1(b)(1) because FTI is the only source reasonably available. The company owns all technical data and rights to the equipment, and the government does not possess the ability to reverse engineer or develop alternative sources. A combined synopsis/solicitation will be posted on SAM.gov, allowing all responsible sources to submit capability statements or quotations. The anticipated award is planned for around 10 June 2025, with a required delivery of 24 weeks after receipt of order. The total procurement is considered an unrestricted requirement with a NAICS code of 336413 and a small business size standard of 1,250 employees.

View the file

Other files

File Type Posted
Terms and Conditions.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Last Updated 11/01/24

U.S. COAST GUARD JUSTIFICATION FOR OTHER THAN FULL AND OPEN COMPETITION

SIMPLIFIED ACQUISITION PROCEDURES (SAP) FOR FAR 13.106-1(b)

PURCHASE REQUEST OR REQUISITION NUMBER:

2025140-CC01

ESTIMATED TOTAL VALUE, INCLUDING OPTIONS:

(Over Micro-Purchase Threshold, but up to the SAT)

AUTHORITY JUSTIFICATION TYPE

☒ 13.106-1(b)(1) ONLY ONE SOURCE REASONABLY AVAILABLE (e.g., urgency, exclusive licensing agreements, or industrial mobilization).

☐ FAR 5.102(a)(6), FAR

11.105, FAR 13.106-1

(b) (1)

BRAND NAME – Items peculiar to one manufacturer: The particular brand name, product, or feature is essential to the Government’s requirements, and market research indicates other companies’ similar products, or products lacking the particular feature, do not meet, or cannot be modified to meet, the agency’s needs.

BRIEF DESCRIPTION OF SUPPLIES OR SERVICES REQUIRED AND THE INTENDED USE:

The United States Coast Guard (USCG) intends to purchase the equipment shown in the table below on a sole source basis directly from the Original Equipment Manufacturer (OEM) – Fatigue Technology Inc. (CAGE Code: 51439), hereinafter referred to as FTI.

Line Item Nomenclature/Description Part Number (PN) Quantity

1 Medium Brute Hydraulic Offset (MBHO) Puller MBHO-20 1 each

2 FT-200D Hydraulic Powerpak FT-200D 1 each

The MBHO Puller is a specialized tool specifically designed for use with FTI’s patented Cold Expansion™ (Cx™) technology. The Puller is designed to pull a mandrel through a hole with the pre-lubricated stainless steel split sleeves used in this process. The puller is also compatible with other FTI processes including ForceMate®, FleXmate®, GromEx®, etc

The Hydraulic Powerpak is used to operate the MBHO Puller. The Powerpak consists of an air-operated hydraulic pump that generates up to 10,000 (±500) psi.

SUGGESTED SOURCE NAME, ADDRESS, & UNIQUE ENTITY IDENTIFIER (UEI):

Fatigue Technology Inc. (CAGE Code: 51439)

401 Andover Park East

Tukwila, WA 98188-7605

UEI: GPXBJDWPLNH7

RATIONALE FOR JUSTIFICATION TYPE SELECTED ABOVE TO INCLUDE RELEVANT INFORMATION GAINED

THROUGH YOUR MARKET RESEARCH TO SUPPORT THE JUSTIFICATION TYPE:

The equipment to be purchased under this acquisition is highly specialized and is specifically designed for use with FTI’s Cold Expansion

(Cx™) fastener systems. This process greatly improves the fatigue life of metal structures, particularly around fastener holes, and has been approved by USCG Engineering for use on all H60 helicopters.

As the OEM, FTI owns all rights to the technical data, specifications, and drawings required for the manufacture of this equipment. The rights to the technical data necessary to acquire this equipment from sources other than the OEM or an OEM approved source are not owned by the Government, and it has been determined that it is uneconomical to purchase these rights. The equipment must meet critical safety, durability, and reliability requirements, the achievement of which require extensive and/or sophisticated testing. The Government does not own or possess any rights to the relevant technical data, specifications, and drawings required to develop an adequate purchase description. In addition, the Government has not developed the technical data required to reverse engineer this equipment and has no plans to do so.

This equipment is not available from any required or optional source of supply IAW FAR 8.002. A combined synopsis/solicitation will be posted to the Contract Opportunities section of the web site at www.sam.gov. All responsible sources may submit a capability statement, proposal, or quotation which shall be considered by the agency.

https://www.acquisition.gov/far/13.106-1 https://www.acquisition.gov/far/5.102 https://www.acquisition.gov/far/11.105 https://www.acquisition.gov/far/11.105 https://www.acquisition.gov/far/13.106-1 https://www.acquisition.gov/far/13.106-1 http://www.sam.gov/

Last Updated 11/01/24

CONTRACTING OFFICER - FAIR AND REASONABLE PRICE DETERMINATION METHODS:

☐ MARKET RESEARCH

☒ COMPARISON OF PROPOSED PRICE WITH PRICES FOUND REASONABLE ON PREVIOUS PURCHASES

☐ CURRENT PRICE LIST

☒ COMPARISON WITH SIMILAR ITEMS IN A RELATED INDUSTRY

☐ COMPARISON TO IGCE

CONTRACTING OFFICER’S PERSONAL KNOWLEDGE (EXPLAIN)

☐ OTHER (EXPLAIN)

SIGNATURE AND TITLE OF TECHNICAL AND REQUIREMENTS POC

DATE

SIGNATURE OF CONTRACTING OFFICER

DATE

File details come from the government source that posted it. Updated .