Service Building Roof Replacement J. Percy Priest 90% DQC Nashville, TN

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

1.1 SUBMITTALS

1.2 WORK COVERED BY CONTRACT DOCUMENTS

1.2.1 Project Description

1.2.2 Location

1.3 OCCUPANCY OF PREMISES

1.4 EXISTING WORK

1.5 Delivery Schedule

1.6 SALVAGE or REUSE MATERIAL AND EQUIPMENT

PART 2 PRODUCTS

PART 3 EXECUTION

-- End of Section Table of Contents --

SECTION 01 11 00 Page 1

SECTION 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

1.2 WORK COVERED BY CONTRACT DOCUMENTS

1.2.1 Project Description

Work items are detailed below. All incidental related work shall be included.

Contractor shall make detailed recordings of work and findings throughout supported with photographs

A. JPP Service Building Roof Replacement

Demolition -

- Contractor shall remove ballasted aggregate material from roofing to be appropriately stored on site as determined by COR.

- Contractor to remove built up roofing material EPDM / rigid insulation/ Vapor Barrier entirely and accossory materials to bare metal deck. Removed materials to become property of the contractor.

- Contractor shall seal and repair metal decking if necessary.

- Remove and replace wood 2x2"x4" treated lumber as necessary.

Coordinate efforts with COR.

- Clean and repair aluminum gravel guard to COR satisfaction.

- Areas around vents shall be cleaned and repaired if necessary.

- Contractor will not remove vents. Vents to remain in place.

Contractor to create water tight seal around all vents and roof penetrations.

Installation -

- Place treated wood that was previously removed (if necessary).

- Vapor Barrier to be placed over metal decking or as directed by manufacturer.

- Rigid Insulation to be installed loose laid as directed by product manufacturer recommendations.

- EPDM to be applied using a low rise adhesive per manufacturer specifications.

- All material sealing and lapping shall be per manufacturers guidance. Contractor shall verify system is waterproof around all seals.

- Contractor shall purchase and apply additional aggregate if necessary.

SECTION 01 11 00 Page 2

- Contractor shall place new vents if contractor damages vents.

- COR may request vent replacement if COR deems necessary. Contract will be adjusted accordingly.

- Contractor will ensure watertight seal around all roof penetrations, edges and joints.

1.2.2 Location

The work is located at J. Percy Priest Service Area located near Nashville, Tennessee. The exact location of work to be performed will be shown by the Contracting Officer.

1.3 OCCUPANCY OF PREMISES

Building(s) will be occupied during performance of work under this Contract. Occupancy notifications will be posted in a prominent location in the work area.

Before work is started, arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.

1.4 EXISTING WORK

In addition to FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements:

a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.

1.5 Delivery Schedule

Notify the Contracting Officer in writing at least 5 calendar days in advance of the date on which the materials and equipment are required.

Pick up materials and equipment no later than 30 calendar days after such date. When materials and equipment are not picked up by the 30th day, the Contractor will be charged for storage as determined by the Contracting Office Representative.

1.6 SALVAGE or REUSE MATERIAL AND EQUIPMENT

Items designated by the Contracting Officer to be salvaged remain the property of the Government. Segregate, itemize, deliver and off-load the salvaged property at the Government designated storage area located within 2 miles of the construction site. Items shall be stored above ground protected from ponding water.

Provide a salvage plan, listing material and equipment to be salvaged, and their storage location. Maintain property control records for material or equipment designated as salvage. Use a system of property control that is approved by the Contracting Officer. Store and protect salvaged materials and equipment until disposition by the Contracting Officer.

SECTION 01 11 00 Page 3

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Section --

SECTION 01 11 00 Page 4

JPP - Roof - Service Bldg - 90% DQC - Spec 9.pdf
JPP - Roof - Service Bldg - 90% DQC - Spec 10