J.2 Summary of Work 01010_02.pdf

PDF 133 KB Posted

Attached to
CLRD Fort Collins Admin Storage Building Federal contract opportunity
Solicitation number
1282AT20R0003
Issued by
Department of Agriculture Forest Service R2-Rocky Mountain Region

View the file

Other files for this federal contract opportunity

Other files attached to CLRD Fort Collins Admin Storage Building, newest first.
File Type Posted
0. 1282AT20R0003-0002 TermsB-M.pdf PDF
QA-1282AT20R0003_07302020FE.pdf PDF
1282AT20R0003-0002_ SF1442.pdf PDF
1282AT20R0003-0002_SF30.pdf PDF
1282AT20R0003_0001_ SF1442.pdf PDF
1282AT20R0003_0001_SF30.pdf PDF
Pre-BidMtgMins-1282AT20R0003FE.pdf PDF
0. 1282AT20R0003, SF1442andTermsB-M.pdf PDF
J.1 SOI, 1282AT20R0003 (Fill-In).xlsx XLSX spreadsheet
J.4 WD CO20200024 v2, 01242020.pdf PDF
J.9 SAMProofofRegistration.docx DOCX document
J.6 Fire Plan, 08202018.pdf PDF
J.3 Work Restrictions 01140_02.pdf PDF
J.8 FS 6300-11_SubkApp.doc DOC document
J.5 WD CO20200002 v1, 01312020.pdf PDF
J.7 1282AT20R0003_TechProposalForm.docx DOCX document
Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01010 - 1

SUMMARY OF WORK

SECTION 01010

SUMMARY OF WORK

PART 1 - GENERAL

1.1 SUMMARY

A. Work for this project consists of the labor and materials to construct one 23’6” X 60’ wood framed storage building onto an existing concrete slab foundation.

1.2 LOCATION

A. This project is located in Fort Collins, Colorado.

Fort Collins Administrative Site 300 Hemlock St.

Fort Collins, CO 80524

4.1 USE OF PREMISES

A. General: Contractor shall have full use of premises for construction operations, including use of Project site, during construction period. Contractor's use of premises is limited only by the Government's right to perform work or to retain other contractors on portions of Project. The use of Forest Service restroom facilities will not be allowed. The contractor will be required to provide restroom facilities for it’s employees.

B. Contractor shall at all times conduct his operations to ensure the least inconvenience to the public and employees. Confine storage of materials to areas as approved by the

CO.

C. Contractor shall provide adequate signing and barricades and take necessary safety measures to protect the public and Forest Service Employess during all construction operations. Contractor shall minimize disturbance of all undisturbed areas.

D. Preservation of Natural Features: Confines all operations to work limits of the project.

Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.

1. Provide temporary barriers to protect existing trees and plants and root zones.

2. Do not remove, injure, or destroy trees or other plants without prior approval.

Consult with CO and remove agreed-on roots and branches that interfere with construction.

3. Do not fasten ropes, cables, or guys to existing trees.

4. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.

01010 - 2

SUMMARY OF WORK

E. Existing Utilities: Notify CO and utility companies of proposed locations and times for excavation.

1. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.

2. Interruption of Existing Utility Service: Notify CO, 48 hours in advance of any interruption of existing utilities.

4.2 MEALS AND LODGING

A. Meals and lodging are commercially available in the City of Fort Collins.

4.3 CONSTRUCTION SEQUENCE

A. There is no specified construction sequence or season for this project.

B. Depending on conditions, normal fire restrictions may apply to activities associated with this project.

4.4 FIELD VERIFICATION

A. Field verify all new and existing dimensions affecting the work of this contract before ordering products.

4.5 PERMITS

A. Special permits for permits required by County, State, or Federal laws or regulations shall be obtained by the Contractor.

END OF SECTION 01100

1.
1.1 summary
A. Work for this project consists of the labor and materials to construct one 23’6” X 60’ wood framed storage building onto an existing concrete slab foundation.
1.2 location
A. This project is located in Fort Collins, Colorado.
2.
3.
4.
Fort Collins Administrative Site
300 Hemlock St.
Fort Collins, CO 80524
4.1 USE OF PREMISES
A. General: Contractor shall have full use of premises for construction operations, including use of Project site, during construction period. Contractor's use of premises is limited only by the Government's right to perform work or to retain other ...
B. Contractor shall at all times conduct his operations to ensure the least inconvenience to the public and employees. Confine storage of materials to areas as approved by the CO.
C. Contractor shall provide adequate signing and barricades and take necessary safety measures to protect the public and Forest Service Employess during all construction operations. Contractor shall minimize disturbance of all undisturbed areas.
D. Preservation of Natural Features: Confines all operations to work limits of the project. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
1. Provide temporary barriers to protect existing trees and plants and root zones.
2. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with CO and remove agreed-on roots and branches that interfere with construction.
3. Do not fasten ropes, cables, or guys to existing trees.
4. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.
E. Existing Utilities: Notify CO and utility companies of proposed locations and times for excavation.
1. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.
2. Interruption of Existing Utility Service: Notify CO, 48 hours in advance of any interruption of existing utilities.
4.2 MEALS AND LODGING
A. Meals and lodging are commercially available in the City of Fort Collins.
4.3 construction sequence
A. There is no specified construction sequence or season for this project.
B. Depending on conditions, normal fire restrictions may apply to activities associated with this project.
4.4 Field verification
A. Field verify all new and existing dimensions affecting the work of this contract before ordering products.
4.5 permits
A. Special permits for permits required by County, State, or Federal laws or regulations shall be obtained by the Contractor.