This document is a comprehensive Technical Specifications file for the Eastmonte Park Restroom Facility project, issued by the City of Altamonte Springs, Florida. The project involves designing and constructing a turn-key prefabricated precast modular building restroom facility, which includes precast walls with form liner finish, precast floor, doors, door frames, door hardware, painting, toilet accessories, toilet partitions, signage, skylights, LED lighting, mechanical, electrical, and plumbing work. The City is open to considering alternate designs and is requesting qualified vendors to submit comprehensive specifications and drawings for evaluation. Potential bidders are advised that site visits can be arranged by appointment with Johan Hendricks via email or telephone, with requests for site appointments accepted until 4:30 PM on Thursday, October 10, 2024.

The technical specifications provide extensive details about the project's requirements, including specific materials, construction methods, electrical and mechanical systems, and accessory installations. The building will feature ADA-compliant fixtures, a ductless split system air conditioning unit, exhaust fans, LED lighting, and various specialized components such as toilet partitions, grab bars, hand dryers, and signage. The project emphasizes compliance with Florida Building Code, accessibility guidelines, and includes comprehensive engineering requirements for structural, electrical, and mechanical systems. The specifications outline rigorous standards for materials, installation processes, and performance expectations, indicating a thorough and detailed approach to the restroom facility's design and construction.

View the file

Other files for this state and local contract opportunity

Other files attached to EASTMONTE PARK RESTROOM FACILITY (RE-BID), newest first.
File Type Posted
ITB-25-006-RS__Notice_of_Intended_Action_Reject_-_Cancel_Bid.pdf PDF
ITB-25-006-RS_Solicitation_Document_Final.pdf PDF
VendorLink_Online_Submittal_Instructions_(as_of_03-30-2020).pdf PDF
ITB-25-006-RS_Attachment_B_-_Drawings_Final.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

INVITATION TO BID

DOCUMENTS

ITB-25-006-RS

EASTMONTE PARK RESTROOM FACILITY

ATTACHMENT A-

TECHNICAL SPECIFICATIONS

CITY OF ALTAMONTE SPRINGS

City Hall, Suite 1030 Procurement Division

225 Newburyport Avenue Altamonte Springs FL 32701-3697

For Contract Information & Updates go to https://www.myvendorlink.com/cityofaltamontesprings/searchcontracts.aspx https://www.myvendorlink.com/cityofaltamontesprings/searchcontracts.aspx

** THIS PAGE LEFT INTENTIONALLY BLANK **

Section 00 01 00-1

SIGNATURE SHEET/TABLE OF CONTENTS 2020.011.H

TECHNICAL SPECIAL PROVISION

for

City of Altamonte Springs Eastmonte Park Restroom Bentley Project #: 2020.011.H

This item has been electronically signed using a Digital Signature. Printed copies of this document are not considered signed and sealed and the signature must be verified on any electronic copies.

Approved By:

STRUCTURAL This item has been digitally signed and sealed by:

Professional Engineer: Brenton Daily, PE Date: September 21, 2023 Fla. License No.: 81028

On the date indicated here.

ARCHITECTURE This item has been digitally signed and sealed by:

Registered Architect: Gary Kranston, RA Date: September 21, 2023 Fla. License No.: 11541 Certificate of Authorization: AAC002023

On the date indicated here.

Date: September 21, 2023 Firm Name: Bentley Group, Inc.

Firm Address: 651 West Warren Ave., Suite 200 City, State, Zip Code: Longwood, FL 32750 Certificate of Authorization: 5898 & AAC002023 Pages: 1-98

Section 00 01 00-2

TABLE OF CONTENTS

THE FOLLOWING SPECIFICATION SECTIONS SHALL GOVERN “LUMP SUM”

CONSTRUCTION WORK FOR THE PROJECT.

THE LISTED SPECIFICATIONS WERE PREPARED UNDER THE DIRECT

SUPERVISION OF THE PERSON SIGNING AND SEALING THE COVER SHEET OF

THESE TECHNICAL SPECIAL PROVISIONS FOR THEIR RESPECTIVE

DISCIPLINES INDICATED.

SECTION TITLE DISCIPLINE PAGES PAGE

NO.

PROCUREMENT AND CONTRACTING REQUIREMENTS

DIVISION 00 -- PROCUREMENT AND CONTRACTING REQUIREMENTS

00 01 10 SIGNATURE SHEET/TABLE OF CONTENTS Not Applicable 1-3 1

TECHNICAL SPECIAL PROVISIONS

DIVISION 01 -- GENERAL REQUIREMENTS

01 10 00 SUMMARY Architectural 1 4

01 23 00 ALTERNATES Architectural 1 5

01 25 00 SUBSTITUTION PROCEDURES Architectural 1-3 6

01 30 00 ADMINISTRATIVE REQUIREMENTS Architectural 1-4 9

01 40 00 QUALITY REQUIREMENTS Architectural 1-3 13

01 50 00 TEMPORARY FACILITIES AND CONTROLS Architectural 1-2 16

01 60 00 PRODUCT REQUIREMENTS Architectural 1-3 18

01 70 00 EXECUTION REQUIREMENTS Architectural 1-7 21

01 78 00 CLOSEOUT SUBMITTALS Architectural 1-4 28

01 79 00 DEMONSTRATION AND TRAINING Architectural 1-3 32

Section 00 01 00-3

SECTION TITLE DISCIPLINE PAGES PAGE

NO.

DIVISION 02 THROUGH 06

NOT USED

DIVISION 07 -- THERMAL AND MOISTURE PROTECTION

07 52 00 MODIFIED BITUMINOUS MEMBRANE

ROOFING Architectural 1-15 35

07 92 00 JOINT SEALANTS Architectural 1-7 50

DIVISION 08 -- OPENINGS

08 71 00 DOOR HARDWARE Architectural 1-13 57

DIVISION 9 --THROUGH 12

NOT USED

DIVISION 13 – SPECIAL CONSTRUCTION

13 04 60 PREFABRICATED MODULAR BUILDING Architectural/ Structural 1-26 70

DIVISION 26 THROUGH 30

NOT USED

DIVISION 31 -- EARTHWORK

31 31 16 TERMITE CONTROL Architectural 1-2 96

DIVISION 33 -- UTILITIES

NOT USED

APPENDIX

Appendix A GEOTECHNICAL REPORT Structural 1-1 98

END OF SECTION

01 10 00 - 1

SUMMARY EASTMONTE PARK RESTROOM

SECTION 01 10 00

SUMMARY

PART 1 GENERAL

1.1 PROJECT

A. Project Name: EASTMONTE PARK RESTROOM B. Owner's Name: CITY OF ALTAMONTE SPRINGS C. The Project consists of the design and construction of a turn-key prefabricated precast modular building restroom facility including all review and permit fees. The turn key building includes but is not limited to the following: Precast walls with formliner finish, precast floor, doors, door frames, door hardware, painting, toilet accessories, toilet partitions, signage, skylights, LED lighting, mechanical, electrical and plumbing work.

The completed facility will be fully functional, and meet all the operational requirements of the Owner and local, state, and federal regulatory requirements.

D. Permits, Reports, and Forms:

1. St Johns River Water Management District

2. City of Altamonte Springs Building Permit and Electrical Permit

1.2 CONTRACT DESCRIPTION

A. Contract Type: A single prime contract based on a Stipulated Price.

1.3 OWNER OCCUPANCY

A. Owner will occupy the project site throughout the project.

B. Contractor and sub-contractors shall follow all security procedures as set forth by The

City of Altamonte Springs.

C. Cooperate with Owner to minimize conflict and to facilitate Owner's operations.

D. Schedule the Work to accommodate Owner occupancy.

1.4 CONTRACTOR USE OF SITE AND PREMISES

A. Provide access to and from site as required by law and by Owner:

1. Emergency Routes During Construction: Keep all routes required by code open during construction period; provide temporary signs if routes are temporarily altered.

2. Do not obstruct roadways, sidewalks, or other public ways without permit.

1.5 WORK SEQUENCE

A. Coordinate construction schedule and operations with Owner.

01 23 00 - 1

ALTERNATES EASTMONTE PARK RESTROOM

SECTION 01 23 00

ALTERNATES

PART 1 GENERAL

1.1 SECTION INCLUDES

A. Description of Alternates.

B. Procedures for pricing Alternates.

1.2 ACCEPTANCE OF Alternates

A. Alternates quoted on Bid Forms will be reviewed and accepted or rejected at Owner's option. Accepted Alternates will be identified in the Owner-Contractor Agreement.

B. Coordinate related work and modify surrounding work to integrate the Work of each

Alternate. City has added a section within the PBF for the vendor to quote on an alternate.

1.3 SCHEDULE OF Alternates

A. Alternate No. One - Door Hardware:

1. Include all labor, materials, wiring conduit, circuiting, door and frame preparation and equipment for a complete installation of timers, and power supplies as indicated in the door hardware schedule. Installed hardware shall be complete and functional allowing owner to schedule the locking and unlocking of the doors based on park operating hours.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION - NOT USED

01 25 00 - 1

SUBSTITUTION PROCEDURES EASTMONTE PARK RESTROOM

SECTION 01 25 00

SUBSTITUTION PROCEDURES

PART 1 GENERAL

1.1 SECTION INCLUDES

A. Procedural requirements for proposed substitutions.

1.2 DEFINITIONS

A. Substitutions: Changes from Contract Documents requirements proposed by Contractor to materials, products, assemblies, and equipment.

1. Substitutions for Cause: Proposed due to changed Project circumstances beyond

Contractor's control.

2. Substitutions for Convenience: Proposed due to possibility of offering substantial advantage to the Project.

a. Substitution requests offering advantages solely to the Contractor will not be considered.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION

3.1 GENERAL REQUIREMENTS

A. A Substitution Request for products, assemblies, materials, and equipment constitutes a representation that the submitter:

1. Has investigated proposed product and determined that it meets or exceeds the quality level of the specified product, equipment, assembly, or system.

2. Agrees to provide the same warranty for the substitution as for the specified product.

3. Agrees to coordinate installation and make changes to other work that may be required for the work to be complete, with no additional cost to Owner.

4. Waives claims for additional costs or time extension that may subsequently become apparent.

5. Agrees to reimburse Owner and Architect for review or redesign services associated with re-approval by authorities.

B. Document each request with complete data substantiating compliance of proposed substitution with Contract Documents. Burden of proof is on proposer.

1. Note explicitly any non-compliant characteristics.

C. Content: Include information necessary for tracking the status of each Substitution Request, and information necessary to provide an actionable response.

1. No specific form is required. Contractor's Substitution Request documentation must include the following:

a. Project Information:

b. Substitution Request Information:

1) Discrete and consecutive Substitution Request number, and descriptive subject/title.

2) Indication of whether the substitution is for cause or convenience.

01 25 00 - 2

3) Issue date.

4) Reference to particular Contract Document(s) specification section number, title, and article/paragraph(s).

5) Description of Substitution.

6) Reason why the specified item cannot be provided.

7) Differences between proposed substitution and specified item.

8) Description of how proposed substitution affects other parts of work.

c. Attached Comparative Data: Provide point-by-point, side-by-side comparison addressing essential attributes specified, as appropriate and relevant for the item:

1) Physical characteristics.

2) In-service performance.

3) Expected durability.

4) Warranties.

5) Other salient features and requirements.

6) Include, as appropriate or requested, the following types of documentation:

(a) Product Data:

(b) Samples.

(c) Certificates, test, reports or similar qualification data.

(d) Drawings, when required to show impact on adjacent construction elements.

d. Impact of Substitution:

1) Savings to Owner for accepting substitution.

2) Change to Contract Time due to accepting substitution.

D. Limit each request to a single proposed substitution item.

1. Submit an electronic document, combining the request form with supporting data into single document.

3.2 SUBSTITUTION PROCEDURES DURING CONSTRUCTION

A. Submit request for Substitution for Cause within 14 days of discovery of need for substitution, but not later than 14 days prior to time required for review and approval by Architect, in order to stay on approved project schedule.

B. Submit request for Substitution for Convenience immediately upon discovery of its potential advantage to the project, but not later than 14 days prior to time required for review and approval by Architect, in order to stay on approved project schedule.

1. In addition to meeting general documentation requirements, document how the requested substitution benefits the Owner through cost savings, time savings, greater energy conservation, or in other specific ways.

2. Document means of coordinating of substitution item with other portions of the work, including work by affected subcontractors.

3. Bear the costs engendered by proposed substitution of:

a. Owner's compensation to the Architect for any required redesign, time spent processing and evaluating the request.

01 25 00 - 3

b. Other unanticipated project considerations.

C. Substitutions will not be considered under one or more of the following circumstances:

1. When they are indicated or implied on shop drawing or product data submittals, without having received prior approval.

2. Without a separate written request.

3.3 RESOLUTION

A. Architect may request additional information and documentation prior to rendering a decision. Provide this data in an expeditious manner.

B. Architect will notify Contractor in writing of decision to accept or reject request.

1. Architect's decision following review of proposed substitution will be noted on the submitted form.

3.4 ACCEPTANCE

A. Accepted substitutions change the work of the Project. They will be documented and incorporated into work of the project by Change Order, Construction Change Directive, Architectural Supplementary Instructions, or similar instruments provided for in the Conditions of the Contract.

3.5 CLOSEOUT ACTIVITIES

A. Include completed Substitution Request Forms as part of the Project record. Include both approved and rejected Requests.

01 30 00 - 1

ADMINISTRATIVE REQUIREMENTS EASTMONTE PARK RESTROOM

SECTION 01 30 00

ADMINISTRATIVE REQUIREMENTS

PART 1 GENERAL

1.1 SECTION INCLUDES

A. Electronic document submittal service.

B. Preconstruction meeting.

C. Progress meetings.

D. Construction progress schedule.

E. Coordination drawings.

F. Submittals for review, information, and project closeout.

G. Number of copies of submittals.

H. Submittal procedures.

1.2 1RELATED REQUIREMENTS

A. Section 01 7800 - Closeout Submittals: Project record documents.

PART 2 PRODUCTS -NOT USED

PART 3 EXECUTION

3.1 ELECTRONIC DOCUMENT SUBMITTAL

A. All documents transmitted for purposes of administration of the contract are to be in electronic (PDF) format and transmitted electronically to the Architect.

B. Besides submittals for review, information, and closeout, this procedure applies to requests for information (RFIs), progress documentation, contract modification documents (e.g. supplementary instructions, change proposals, change orders), applications for payment, field reports and meeting minutes, and any other document any participant wishes to make part of the project record.

C. All other specified submittal and document transmission procedures apply, except that electronic document requirements do not apply to samples or color selection charts.

3.2 PRECONSTRUCTION MEETING

A. Attendance Required:

1. Owner.

2. Architect.

3. Contractor.

B. Agenda:

1. Execution of Owner-Contractor Agreement.

2. Submission of executed bonds and insurance certificates.

3. Distribution of Contract Documents.

4. Submission of list of Subcontractors, list of Products, schedule of values, and progress schedule.

5. Designation of personnel representing the parties to Contract and Architect.

01 30 00 - 2

6. Procedures and processing of field decisions, submittals, substitutions, applications for payments, proposal request, Change Orders, and Contract closeout procedures.

7. Scheduling.

8. Contractor to record minutes and distribute copies within two days after meeting to participants, with copies to Architect, Owner, participants, and those affected by decisions made.

3.3 PROGRESS MEETINGS

A. Schedule and administer meetings throughout progress of the Work at maximum bi-monthly intervals.

B. Attendance Required: Job superintendent, Contractor's Project Manager, Owner, Architect, as appropriate to agenda topics for each meeting.

C. Agenda:

1. Review minutes of previous meetings.

2. Review of Work progress.

3. Field observations, problems, and decisions.

4. Identification of problems that impede, or will impede, planned progress.

5. Review of submittals schedule and status of submittals.

6. Maintenance of progress schedule.

7. Corrective measures to regain projected schedules.

8. Planned progress during succeeding work period.

9. Maintenance of quality and work standards.

10. Effect of proposed changes on progress schedule and coordination.

11. Other business relating to Work.

D. Record minutes and distribute copies within two days after meeting to participants, with copies to Architect, Owner, participants, and those affected by decisions made.

3.4 CONSTRUCTION PROGRESS SCHEDULE

A. Within 10 days after date of the Agreement, submit preliminary schedule defining planned operations for the first 60 days of Work, with a general outline for remainder of Work.

B. If preliminary schedule requires revision after review, submit revised schedule within 10 days.

C. Within 20 days after review of preliminary schedule, submit draft of proposed complete schedule for review.

D. Within 10 days after joint review, submit complete schedule.

E. Submit updated schedule with each Application for Payment.

3.5 SUBMITTALS FOR REVIEW

A. When the following are specified in individual sections, submit them for review:

1. Product data.

2. Shop drawings.

3. Samples for selection.

4. Samples for verification.

01 30 00 - 3

B. Submit to Architect for review for the limited purpose of checking for conformance with information given and the design concept expressed in the contract documents.

C. Samples will be reviewed only for aesthetic, color, or finish selection.

D. After review, provide copies and distribute in accordance with SUBMITTAL

PROCEDURES article below and for record documents purposes described in Section 01 7800 -Closeout Submittals.

3.6 SUBMITTALS FOR INFORMATION

A. When the following are specified in individual sections, submit them for information:

B. Design data.

C. Certificates.

D. Test reports.

E. Inspection reports F. Manufacturer's instructions.

G. Manufacturer's field reports.

H. Other types indicated.

I. Submit for Architect's knowledge as contract administrator or for Owner. No action will be taken.

3.7 SUBMITTALS FOR PROJECT CLOSEOUT

A. When the following are specified in individual sections, submit them at project closeout:

B. Project record documents.

C. Operation and maintenance data.

D. Warranties.

1. Bonds.

2. Other types as indicated.

a. Submit for Owner's benefit during and after project completion.

3.8 NUMBER OF COPIES OF SUBMITTALS

A. Documents: Submit one electronic copy in PDF format; an electronically-marked up file will be returned. Create PDFs at native size and right-side up; illegible files will be rejected.

B. Samples: Submit the number specified in individual specification sections; one of which will be retained by Architect.

C. After review, produce duplicates.

D. Retained samples will not be returned to Contractor unless specifically so stated.

3.9 SUBMITTAL PROCEDURES

A. Transmit each submittal with a copy of approved submittal form.

B. Transmit each submittal with approved form.

01 30 00 - 4

C. Sequentially number the transmittal form. Revise submittals with original number and a sequential alphabetic suffix.

D. Identify Project, Contractor, Subcontractor or supplier; pertinent drawing and detail number, and specification section number, as appropriate on each copy.

E. Apply Contractor's stamp, signed or initialed certifying that review, approval, verification of Products required, field dimensions, adjacent construction Work, and coordination of information is in accordance with the requirements of the Work and Contract Documents.

F. Schedule submittals to expedite the Project, and coordinate submission of related items.

G. For each submittal for review, allow 10 business days excluding delivery time to and from the Contractor.

H. Identify variations from Contract Documents and Product or system limitations that may be detrimental to successful performance of the completed Work.

I. Provide space for Contractor and Architect review stamps.

J. When revised for resubmission, identify all changes made since previous submission.

K. Distribute reviewed submittals as appropriate. Instruct parties to promptly report any inability to comply with requirements.

L. Submittals not requested will not be recognized or processed.

01 40 00 - 1

QUALITY REQUIREMENTS EASTMONTE PARK RESTROOM

SECTION 01 40 00

QUALITY REQUIREMENTS

PART 1 GENERAL

1.1 SECTION INCLUDES

A. Control of installation.

B. Testing and inspection services.

1.2 RELATED REQUIREMENTS

A. Section 01 3000 -Administrative Requirements: Submittal procedures.

B. Section 01 6000 -Product Requirements: Requirements for material and product quality.

1.3 REFERENCE STANDARDS

A. ASTM C1021 - Standard Practice for Laboratories Engaged in Testing of Building

Sealants; 2008 (Reapproved 2014).

B. ASTM C1077 - Standard Practice for Agencies Testing Concrete and Concrete

Aggregates for Use in Construction and Criteria for Testing Agency Evaluation; 2017.

C. ASTM C1093 - Standard Practice for Accreditation of Testing Agencies for Masonry;

2019.

D. ASTM D3740 - Standard Practice for Minimum Requirements for Agencies Engaged in the Testing and/or Inspection of Soil and Rock as Used in Engineering Design and Construction; 2019.

E. ASTM E329 - Standard Specification for Agencies Engaged in Construction Inspection, Testing, or Special Inspection; 2018.

F. ASTM E543 - Standard Specification for Agencies Performing Nondestructive Testing;

2015.

G. ASTM E699 - Standard Specification for Agencies Involved in Testing, Quality Assurance, and Evaluating of Manufactured Building Components; 2016.

H. IAS AC89 - Accreditation Criteria for Testing Laboratories; 2018.

1.4 SUBMITTALS

A. Testing Agency Qualifications:

1. Prior to start of Work, submit agency name, address, and telephone number, and names of full time registered Engineer and responsible officer.

B. Test Reports: After each test/inspection, promptly submit two copies of report to

Architect and to Contractor.

1. Include:

a. Date issued.

b. Project title and number.

c. Name of inspector.

d. Date and time of sampling or inspection.

e. Identification of product and specifications section.

f. Location in the Project.

01 40 00 - 2

g. Type of test/inspection.

h. Date of test/inspection.

i. Results of test/inspection.

j. Conformance with Contract Documents.

k. When requested by Architect, provide interpretation of results.

1.5 TESTING AND INSPECTION AGENCIES

A. Contractor shall employ and pay for services of an independent testing agency to perform other specified testing.

B. Employment of agency in no way relieves Contractor of obligation to perform Work in accordance with requirements of Contract Documents.

C. Contractor Employed Agency:

1. Testing agency: Comply with requirements of ASTM E 329, ASTM E 543, ASTM C 1021, ASTM C 1077, and ASTM C 1093.

2. Inspection agency: Comply with requirements of ASTM D3740 and ASTM E329.

3. Laboratory: Authorized to operate in the State in which the Project is located.

4. Laboratory Staff: Maintain a full time registered Engineer on staff to review services.

5. Testing Equipment: Calibrated at reasonable intervals either by NIST or using an

NIST established Measurement Assurance Program, under a laboratory measurement quality assurance program.

PART 2 PRODUCTS -NOT USED

PART 3 EXECUTION

3.1 CONTROL OF INSTALLATION

A. Monitor quality control over suppliers, manufacturers, products, services, site conditions, and workmanship, to produce Work of specified quality.

B. Comply with manufacturers' instructions, including each step in sequence.

C. Should manufacturers' instructions conflict with Contract Documents, request clarification from Architect before proceeding.

D. Comply with specified standards as minimum quality for the Work except where more stringent tolerances, codes, or specified requirements indicate higher standards or more precise workmanship.

E. Have Work performed by persons qualified to produce required and specified quality.

F. Verify that field measurements are as indicated on shop drawings or as instructed by the manufacturer.

G. Secure products in place with positive anchorage devices designed and sized to withstand stresses, vibration, physical distortion, and disfigurement.

3.2 TESTING AND INSPECTION

A. Testing Agency Duties:

1. Provide qualified personnel at site. Cooperate with Architect and Contractor in performance of services.

01 40 00 - 3

2. Perform specified sampling and testing of products in accordance with specified standards.

3. Ascertain compliance of materials and mixes with requirements of Contract Documents.

4. Promptly notify Architect and Contractor of observed irregularities or non-conformance of Work or products.

5. Perform additional tests and inspections required by Architect.

6. Submit reports of all tests/inspections specified.

B. Limits on Testing/Inspection Agency Authority:

1. Agency may not release, revoke, alter, or enlarge on requirements of Contract

Documents.

2. Agency may not approve or accept any portion of the Work.

3. Agency may not assume any duties of Contractor.

4. Agency has no authority to stop the Work.

C. Contractor Responsibilities:

1. Deliver to agency at designated location, adequate samples of materials proposed to be used that require testing, along with proposed mix designs.

2. Cooperate with laboratory personnel, and provide access to the Work and to manufacturers' facilities.

3. Provide incidental labor and facilities:

a. To provide access to Work to be tested/inspected.

b. To obtain and handle samples at the site or at source of Products to be tested/inspected.

c. To facilitate tests/inspections.

d. To provide storage and curing of test samples.

1) Notify Architect and laboratory 24 hours prior to expected time for operations requiring testing/inspection services.

2) Employ services of an independent qualified testing laboratory and pay for additional sample tests, and inspections required by Contractor beyond specified requirements.

3) Arrange with Owner's agency and pay for additional samples, tests, and inspections required by Contractor beyond specified requirements.

D. Re-testing required because of non-conformance to specified requirements shall be performed by the same agency on instructions by Architect.

E. Re-testing required because of non-conformance to specified requirements shall be paid for by Contractor.

3.3 DEFECT ASSESSMENT

A. Replace Work or portions of the Work not conforming to specified requirements.

B. If, in the opinion of Architect, it is not practical to remove and replace the Work, Architect will direct an appropriate remedy or adjust payment.

01 50 00 - 1

TEMPORARY FACILITIES AND CONTROLS EASTMONTE PARK RESTROOM

SECTION 01 50 00

TEMPORARY FACILITIES AND CONTROLS

PART 1 GENERAL

1.1 SECTION INCLUDES

A. Dewatering B. Temporary utilities.

C. Temporary sanitary facilities.

D. Temporary Controls: Barriers, enclosures, and fencing.

E. Vehicular access and parking.

F. Waste removal facilities and services.

G. Project identification sign.

1.2 DEWATERING

A. Provide temporary means and methods for dewatering all temporary facilities and controls.

B. Maintain temporary facilities in operable condition.

1.3 TEMPORARY UTILITIES

A. Provide and pay for all electrical power, lighting, water, heating and cooling, and ventilation required for construction purposes.

B. Existing facilities may not be used.

C. Use trigger-operated nozzles for water hoses, to avoid waste of water.

1.4 TEMPORARY SANITARY FACILITIES

A. Provide and maintain required facilities and enclosures. Provide at time of project mobilization.

B. Maintain daily in clean and sanitary condition.

1.5 BARRIERS

A. Provide barriers to prevent unauthorized entry to construction areas, to prevent access to areas that could be hazardous to workers or the public, to allow for owner's use of site and to protect existing facilities and adjacent properties from damage from construction operations and demolition.

B. Provide barricades and covered walkways required by governing authorities for public rights-of-way.

C. Provide protection for plants designated to remain. Replace damaged plants.

D. Protect non-owned vehicular traffic, stored materials, site, and structures from damage.

1.6 FENCING

A. Provide 6 foot high fence around construction site; equip with vehicular and pedestrian gates with locks.

01 50 00 - 2

TEMPORARY FACILITIES AND CONTROLS EASTMONTE PARK RESTROOM

1. Fence screening: Provide black, dark blue, or dark green mesh fabric material approved by the city free from fading, mold, mildew, dirt, stains, or growths.

Anchor screening securely to the fence. Maintian screening material in good condtion. Repair and/or replace fabric materail that is ripped, torn, tattered, loose or unfastened.

1.7 VEHICULAR ACCESS AND PARKING

A. Coordinate access and haul routes with governing authorities and Owner.

B. Provide and maintain access to fire hydrants, free of obstructions.

C. Provide means of removing mud from vehicle wheels before entering streets.

D. Provide temporary parking areas to accommodate construction personnel. When site space is not adequate, provide additional off-site parking.

1.8 WASTE REMOVAL

A. Provide waste removal facilities and services as required to maintain the site in clean and orderly condition.

B. Provide containers with lids. Remove trash from site periodically.

C. If materials to be recycled or re-used on the project must be stored on-site, provide suitable non-combustible containers; locate containers holding flammable material outside the structure unless otherwise approved by the authorities having jurisdiction.

D. Open free-fall chutes are not permitted. Terminate closed chutes into appropriate containers with lids.

1.9 PROJECT IDENTIFICATION

A. Provide project identification sign of design, construction, and location approved by

Owner.

B. No other signs are allowed without Owner permission except those required by law.

1.10 REMOVAL OF UTILITIES, FACILITIES, AND CONTROLS

A. Remove temporary utilities, equipment, facilities, materials, prior to Date of Substantial

Completion inspection.

B. Remove underground installations to a minimum depth of 2 feet. Grade site as indicated.

C. Clean and repair damage caused by installation or use of temporary work.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION - NOT USED

01 60 00 - 1

PRODUCT REQUIREMENTS EASTMONTE PARK RESTROOM

SECTION 01 60 00

PRODUCT REQUIREMENTS

PART 1 GENERAL

1.1 SECTION INCLUDES

A. General product requirements.

B. Re-use of existing products.

C. Transportation, handling, storage and protection.

D. Product option requirements.

E. Substitution limitations and procedures.

F. Maintenance materials, including extra materials, spare parts, tools, and software.

1.2 SUBMITTALS

A. Product Data Submittals: Submit manufacturer's standard published data. Mark each copy to identify applicable products, models, options, and other data. Supplement manufacturers' standard data to provide information specific to this Project.

B. Shop Drawing Submittals: Prepared specifically for this Project; indicate utility and electrical characteristics, utility connection requirements, and location of utility outlets for service for functional equipment and appliances.

C. Sample Submittals: Illustrate functional and aesthetic characteristics of the product, with integral parts and attachment devices. Coordinate sample submittals for interfacing work.

1. For selection from standard finishes, submit samples of the full range of the manufacturer's standard colors, textures, and patterns.

PART 2 PRODUCTS

2.1 EXISTING PRODUCTS

A. Do not use materials and equipment removed from existing premises unless specifically required or permitted by the Contract Documents.

B. Unforeseen historic items encountered remain the property of the Owner; notify Owner promptly upon discovery; protect, remove, handle, and store as directed by Owner.

C. Existing materials and equipment indicated to be removed, but not to be re-used, relocated, reinstalled, delivered to the Owner, or otherwise indicated as to remain the property of the Owner, become the property of the Contractor; remove from site.

D. Reused Products: Reused products include materials and equipment previously used in this or other construction, salvaged and refurbished as specified.

2.2 NEW PRODUCTS

A. Provide new products unless specifically required or permitted by the Contract

Documents.

B. DO NOT USE products having any of the following characteristics:

C. Made using or containing CFC's or HCFC's.

01 60 00 - 2

D. Adhesives and Joint Sealants:

1. Provide only products having lower volatile organic compound (VOC) content than required by South Coast Air Quality Management District Rule No.1168.

2. Require each installer to certify compliance and submit product data showing product content.

3. Specific Product Categories: Comply with limitations specified elsewhere.

2.3 PRODUCT OPTIONS

A. Products Specified by Reference Standards or by Description Only: Use any product meeting those standards or description.

B. Products Specified by Naming One or More Manufacturers: Use a product of one of the manufacturers named and meeting specifications, no options or substitutions allowed.

C. Products Specified by Naming One or More Manufacturers with a Provision for

Substitutions: Submit a request for substitution for any manufacturer not named.

D. Products shall have Florida Product Approval NOA.

2.4 MAINTENANCE MATERIALS

A. Furnish extra materials, spare parts, tools, and software of types and in quantities specified in individual specification sections.

B. Deliver to Project site; obtain receipt prior to final payment.

PART 3 EXECUTION

3.1 SUBSTITUTION PROCEDURES

A. Instructions to Bidders specify time restrictions for submitting requests for substitutions during the bidding period. Comply with requirements specified in this section.

B. Document each request with complete data substantiating compliance of proposed substitution with Contract Documents.

C. A request for substitution constitutes a representation that the submitter:

1. Has investigated proposed product and determined that it meets or exceeds the quality level of the specified product.

2. Will provide the same warranty for the substitution as for the specified product.

3. Will coordinate installation and make changes to other Work that may be required for the Work to be complete with no additional cost to Owner.

4. Waives claims for additional costs or time extension that may subsequently become apparent.

D. Substitution Submittal Procedure:

1. Submit three copies of request for substitution for consideration. Limit each request to one proposed substitution.

2. Submit shop drawings, product data, and certified test results attesting to the proposed product equivalence. Burden of proof is on proposer.

3. The Architect will notify Contractor in writing of decision to accept or reject request.

01 60 00 - 3

3.2 TRANSPORTATION AND HANDLING

A. Coordinate schedule of product delivery to designated prepared areas in order to minimize site storage time and potential damage to stored materials.

B. Transport and handle products in accordance with manufacturer's instructions.

C. Transport materials in covered trucks to prevent contamination of product and littering of surrounding areas.

D. Promptly inspect shipments to ensure that products comply with requirements, quantities are correct, and products are undamaged.

E. Provide equipment and personnel to handle products by methods to prevent soiling, disfigurement, or damage.

F. Arrange for the return of packing materials, such as wood pallets, where economically feasible.

3.3 STORAGE AND PROTECTION

A. Designate receiving/storage areas for incoming products so that they are delivered according to installation schedule and placed convenient to work area in order to minimize waste due to excessive materials handling and misapplication.

B. Store and protect products in accordance with manufacturers' instructions.

C. Store with seals and labels intact and legible.

D. Store sensitive products in weather tight, climate controlled, enclosures in an environment favorable to product.

E. For exterior storage of fabricated products, place on sloped supports above ground.

F. Cover products subject to deterioration with impervious sheet covering. Provide ventilation to prevent condensation and degradation of products.

G. Prevent contact with material that may cause corrosion, discoloration, or staining.

H. Provide equipment and personnel to store products by methods to prevent soiling, disfigurement, or damage.

I. Arrange storage of products to permit access for inspection. Periodically inspect to verify products are undamaged and are maintained in acceptable condition.

01 70 00 - 1

EXECUTION REQUIREMENTS EASTMONTE PARK RESTROOM

SECTION 01 70 00

EXECUTION REQUIREMENTS

PART 1 GENERAL

1.1 SECTION INCLUDES

A. Examination, preparation, and general installation procedures.

B. Pre-installation meetings.

C. Surveying for laying out the work.

D. Cleaning and protection.

E. Starting of systems and equipment.

F. Demonstration and instruction of Owner personnel.

G. Closeout procedures, including Contractor's Correction Punch List, except payment procedures.

H. Definition of Substantial Completion

1.2 SUBMITTALS

A. See Section 01 30 00 - Administrative Requirements, for submittal procedures.

B. Survey work: Submit name, address, and telephone number of Surveyor before starting survey work.

1. On request, submit documentation verifying accuracy of survey work.

2. Submit a copy of site drawing signed by the Land Surveyor, that the elevations and locations of the work are in compliance with Contract Documents.

3. Submit surveys and survey logs for the project record.

1.3 QUALIFICATIONS

A. For surveying work, employ a land surveyor registered in the State in which the Project is located and acceptable to Architect. Submit evidence of surveyor's Errors and Omissions insurance coverage in the form of an Insurance Certificate. Employ only individual(s) trained and experienced in collecting and recording accurate data relevant to ongoing construction activities, B. For field engineering, employ a professional engineer of the discipline required for specific service on Project, licensed in the State in which the Project is located. Employ only individual(s) trained and experienced in establishing and maintaining horizontal and vertical control points necessary for laying out construction work on project of similar size, scope and/or complexity.

C. For design of temporary shoring and bracing, employ a Professional Engineer experienced in design of this type of work and licensed in the State in which the Project is located.

1.4 PROJECT CONDITIONS

A. Use of explosives is not permitted.

B. Grade site to drain. Maintain excavations free of water. Provide, operate, and maintain pumping equipment.

01 70 00 - 2

C. Protect site from puddling or running water. Provide water barriers as required to protect site from soil erosion.

D. Perform dewatering activities, as required, for the duration of the project.

E. Dust Control: Execute work by methods to minimize raising dust from construction operations. Provide positive means to prevent air-borne dust from dispersing into atmosphere and over adjacent property.

F. Erosion and Sediment Control: Plan and execute work by methods to control surface drainage from cuts and fills, from borrow and waste disposal areas. Prevent erosion and sedimentation.

1. Provide temporary measures such as berms, dikes, and drains, to prevent water flow.

2. Construct fill and waste areas by selective placement to avoid erosive surface silts or clays.

3. Periodically inspect earthwork to detect evidence of erosion and sedimentation;

promptly apply corrective measures.

G. Noise Control: Provide methods, means, and facilities to minimize noise produced by construction operations.

1. At All Times: Excessively noisy tools and operations will not be tolerated inside the building at any time of day; excessively noisy includes jackhammers.

2. Outdoors: Limit conduct of especially noisy exterior work to the hours of 8 am to

5 pm.

H. Pest and Rodent Control: Provide methods, means, and facilities to prevent pests and insects from damaging the work.

I. Pollution Control: Provide methods, means, and facilities to prevent contamination of soil, water, and atmosphere from discharge of noxious, toxic substances, and pollutants produced by construction operations. Comply with federal, state, and local regulations.

1.5 COORDINATION

A. Coordinate scheduling, submittals, and work of the various sections of the Project

Manual to ensure efficient and orderly sequence of installation of interdependent construction elements.

B. Notify affected utility companies and comply with their requirements.

C. Verify that utility requirements and characteristics of new operating equipment are compatible with site utilities. Coordinate work of various sections having interdependent responsibilities for installing, connecting to, and placing in service, such equipment.

D. Coordinate space requirements, supports, and installation of mechanical and electrical work that are indicated diagrammatically on drawings. Follow routing indicated for pipes, ducts, and conduit, as closely as practicable. Utilize spaces efficiently to maximize accessibility for other installations, for maintenance, and for repairs.

E. In finished areas, conceal pipes, ducts, and wiring within the construction. Coordinate locations of fixtures and outlets with finish elements.

01 70 00 - 3

F. Coordinate completion and clean-up of work of separate sections.

G. After Owner occupancy of premises, coordinate access to site for correction of defective work and work not in accordance with Contract Documents, to minimize disruption of Owner's activities.

1.6 DEFINITION OF SUBSTANTIAL COMPLETION

A. The stage of work determined by the Architect/Engineer through issuance of a

Certificate of Substantial Completion documenting the progress of the work or designated portion is sufficiently complete in accordance with the contract documents so that the owner can occupy or use the work for its intended purpose and when only minor, corrective, or warranty work remaining for the entire project. The Certificate of Substantial completion will not be issued prior to the issuance of a Certificate of Occupancy by the Authority Having Jurisdiction (AHJ).

PART 2 PRODUCTS

2.1 PATCHING MATERIALS

A. New Materials: As specified in product sections; match existing products and work for patching and extending work.

B. Type and Quality of Existing Products: Determine by inspecting and testing products where necessary, referring to existing work as a standard.

C. Product Substitution: For any proposed change in materials, submit request for substitution described in Section 01 60 00 - Product Requirements.

PART 3 EXECUTION

3.1 EXAMINATION

A. Verify that existing site conditions and substrate surfaces are acceptable for subsequent work. Start of work means acceptance of existing conditions.

B. Verify that existing substrate is capable of structural support or attachment of new work being applied or attached.

C. Examine and verify specific conditions described in individual specification sections.

D. Take field measurements before confirming product orders or beginning fabrication, to minimize waste due to over-ordering or misfabrication.

E. Verify that utility services are available, of the correct characteristics, and in the correct locations.

F. Prior to Cutting: Examine existing conditions prior to commencing work, including elements subject to damage or movement during cutting and patching. After uncovering existing work, assess conditions affecting performance of work. Beginning of cutting or patching means acceptance of existing conditions.

3.2 PREPARATION

A. Clean substrate surfaces prior to applying next material or substance.

B. Seal cracks or openings of substrate prior to applying next material or substance.

01 70 00 - 4

C. Apply manufacturer required or recommended substrate primer, sealer, or conditioner prior to applying any new material or substance in contact or bond.

3.3 PREINSTALLATION MEETINGS

A. When required in individual specification sections, convene a preinstallation meeting at the site prior to commencing work of the section.

B. Require attendance of parties directly affecting, or affected by, work of the specific section.

C. Notify Architect four days in advance of meeting date.

D. Prepare agenda and preside at meeting:

1. Review conditions of examination, preparation and installation procedures.

2. Review coordination with related work.

E. Record minutes and distribute copies within two days after meeting to participants, with two copies to Architect, Owner, participants, and those affected by decisions made.

3.4 LAYING OUT THE WORK

A. Verify locations of survey control points prior to starting work.

B. Promptly notify Architect of any discrepancies discovered.

C. Protect survey control points prior to starting site work; preserve permanent reference points during construction.

D. Promptly report to Architect the loss or destruction of any reference point or relocation required because of changes in grades or other reasons.

E. Replace dislocated survey control points based on original survey control. Make no changes without prior written notice to Architect.

F. Utilize recognized engineering survey practices.

G. Establish elevations, lines and levels. Locate and lay out by instrumentation and similar appropriate means:

1. Site improvements including pavements; stakes for grading, fill and topsoil placement; utility locations, slopes, and invert elevations.

2. Grid or axis for structures.

3. Building foundation, column locations, ground floor elevations.

4. Controlling lines and levels required for mechanical and electrical trades.

H. Periodically verify layouts by same means.

I. Maintain a complete and accurate log of control and survey work as it progresses.

J. On completion of foundation walls and major site improvements, prepare a certified survey illustrating dimensions, locations, angles, and elevations of construction and site work.

3.5 GENERAL INSTALLATION REQUIREMENTS

A. Install products as specified in individual sections, in accordance with manufacturer's instructions and recommendations, and so as to avoid waste due to necessity for replacement.

01 70 00 - 5

B. Make vertical elements plumb and horizontal elements level, unless otherwise indicated.

C. Install equipment and fittings plumb and level, neatly aligned with adjacent vertical and horizontal lines, unless otherwise indicated.

D. Make consistent texture on surfaces, with seamless transitions, unless otherwise indicated.

E. Make neat transitions between different surfaces, maintaining texture and appearance.

3.6 PROGRESS CLEANING

A. Maintain areas free of waste materials, debris, and rubbish. Maintain site in a clean and orderly condition.

B. Broom and vacuum clean interior areas prior to start of surface finishing, and continue cleaning to eliminate dust.

C. Collect and remove waste materials, debris, and trash/rubbish from site periodically and dispose off-site; do not burn or bury.

3.7 PROTECTION OF INSTALLED WORK

A. Protect installed work from damage by construction operations.

B. Provide special protection where specified in individual specification sections.

C. Provide temporary and removable protection for installed products. Control activity in immediate work area to prevent damage.

D. Provide protective coverings at walls, projections, jambs, sills, and soffits of openings.

E. Protect finished floors, stairs, and other surfaces from traffic, dirt, wear, damage, or movement of heavy objects, by protecting with durable sheet materials.

F. Remove protective coverings when no longer needed; reuse or recycle coverings if possible.

3.8 SYSTEM STARTUP

A. Coordinate schedule for start-up of various equipment and systems.

B. Verify that each piece of equipment or system has been checked for proper lubrication, drive rotation, belt tension, control sequence, and for conditions that may cause damage.

C. Verify tests, meter readings, and specified electrical characteristics agree with those required by the equipment or system manufacturer.

D. Verify that wiring and support components for equipment are complete and tested.

E. Execute start-up under supervision of applicable Contractor personnel and manufacturer's representative in accordance with manufacturers' instructions.

F. When specified in individual specification Sections, require manufacturer to provide authorized representative to be present at site to inspect, check, and approve equipment or system installation prior to start-up, and to supervise placing equipment or system in operation.

01 70 00 - 6

G. Submit a written report that equipment or system has been properly installed and is functioning correctly.

3.9 DEMONSTRATION AND INSTRUCTION

A. Demonstrate start-up, operation, control, adjustment, trouble-shooting, servicing, maintenance, and shutdown of each item of equipment at scheduled time, at equipment location.

B. Provide a qualified person who is knowledgeable about the Project to perform demonstration and instruction of Owner's personnel.

3.10 ADJUSTING

A. Adjust operating products and equipment to ensure smooth and unhindered operation.

3.11 FINAL CLEANING

A. Execute final cleaning prior to Substantial Completion.

1. Clean areas to be occupied by Owner prior to final completion before Owner occupancy.

B. Use cleaning materials that are nonhazardous.

C. Remove all labels that are not permanent. Do not paint or otherwise cover fire test labels or nameplates on mechanical and electrical equipment.

D. Clean equipment and fixtures to a sanitary condition with cleaning materials appropriate to the surface and material being cleaned.

E. Clean filters of operating equipment.

F. Clean debris from roofs, gutters, downspouts, scuppers, overflow drains, area drains, and drainage systems.

G. Clean site; sweep paved areas, rake clean landscaped surfaces.

H. Remove waste, surplus materials, trash/rubbish, and construction facilities from the site; dispose of in legal manner; do not burn or bury.

3.12 CLOSEOUT PROCEDURES

A. Make submittals that are required by governing or other authorities.

1. Provide copies to Architect and Owner.

B. Accompany Engineer on preliminary inspection to determine items to be listed for completion or correction in the Contractor's Correction Punch List for Contractor's Notice of Substantial Completion.

C. Notify Architect when work is considered ready for Architect's Substantial Completion inspection.

D. Submit written certification containing Contractor's Correction Punch List, that Contract Documents have been reviewed, work has been inspected, and that work is complete in accordance with Contract Documents and ready for Architect's Substantial Completion inspection.

1. Provide copy of Certificate of Occupancy issued by the Authority Having

Juristiction (AHJ) to Architect.

01 70 00 - 7

E. Conduct Substantial Completion inspection and create Final Correction Punch List containing Architect's and Contractor's comprehensive list of items identified to be completed or corrected and submit to Architect.

F. Correct items of work listed in Final Correction Punch List and comply with requirements for access to Owner-occupied areas.

G. Notify Architect when work is considered finally complete and ready for Architect's Substantial Completion final inspection.

H. Complete items of work determined by Architect listed in executed Certificate of Substantial Completion.

01 78 00 - 1

CLOSEOUT SUBMITTALS EASTMONTE PARK RESTROOM

SECTION 01 78 00

CLOSEOUT SUBMITTALS

PART 1 GENERAL

1.1 SECTION INCLUDES

A. Project Record Documents.

B. Operation and Maintenance Data.

C. Warranties and bonds.

1.2 RELATED REQUIREMENTS

A. Section 01 3000 - Administrative Requirements: Submittals procedures, shop drawings, product data, and samples.

B. Individual Product Sections: Specific requirements for operation and maintenance data.

C. Individual Product Sections: Warranties required for specific products or Work.

1.3 SUBMITTALS

A. Project Record Documents: Submit documents to Architect with claim for final

Application for Payment B. Operation and Maintenance Data:

1. Submit two copies of preliminary draft or proposed formats and outlines of contents before…