QUESTIONS_AND_RESPONSES.pdf

PDF 80 KB Posted

Attached to
USP Lee - Upgrade Automatic Power Transfer System
Solicitation number
IFBP01171700002
Issued by

View the file

Other files

File Type Posted
LEE_ABSTRACT_-_SIGNED.pdf PDF
Site_Visit_Photos.pdf PDF
Flap_B_Tab_3A_-_Meeting_Minutes_and_Sign_In_Sheet.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QUESTIONS AND ANSWERS

USP LEE – UPGRADE APTS

IFBP01171700002 - PROJECT 1B7Y

SUBMITTED BY Microgrid Generation Services:

1. Could you please provide data sheet and wiring diagrams of each GE Spectra Switchboards showing the connection for the essential and nonessential breakers and power meters?

CLARIFICATION: NOT AVAILABLE.

2. Please provide wiring diagram of the existing controller showing all I/O connections.

CLARIFICATION: THESE WILL BE MADE AVAILABLE UPON AWARD TO THE PRIME CONTRACTOR.

3. Would you be able to provide functional software codes of the existing 90-30

PLC?

CLARIFICATION: NOT AVAILABLE.

4. Please confirm if the existing I/O connections/ wires route through the electrical rooms from each switchboards. Please indicate which of the following locations have the existing wires that can be used for the new remote PLCs.

a. H1

b. H2.

c. H3

d. Area A, B,C & D,E,F ,G and H

e. Central Utility Bldg

f. Garage/ Landscape

g. Warehouse

h. Camp Shared Facilities

i. Camp housing

j. Administration building

CLARIFICATION: PLEASE SEE DRAWINGS. THE DRAWINGS CALL FOR NEW WIRING BETWEEN

SWITCHBOARD AND NEW I/O CONTROL PANELS FOR EACH BUILDING. THERE IS TYPICALLY A

“PMCS” (POWER MONITORING AND CONTROL SYSTEM) PULLBOX IN EACH ELECTRICAL ROOM

WHERE THE EXISTING WIRES ARE PULLED FROM THE SWITCHBOARD BEFORE BEING ROUTED

OUTSIDE TO THE CENTRAL PLANT BUILDING.

5. Please confirm the availability of existing fiber optic cables at each remote I/O PLC locations. How many strands are available and what is the size of each fiber cables?

CLARIFICATION: THIS INFORMATION IS SHOWN ON THE DRAWINGS. SEE E102, KEYNOTE 6

WHICH STATES THAT THE FIBER OPTIC CABLE IS EXISTING FROM EACH BUILDING TO THE

ADMINISTRATION BUILDING. THERE IS EXISTING FIBER IN ALL “ELECTRONICS ROOM” (NOT

“ELECTRICAL ROOM”) WHERE IDF CABINETS ARE LOCATED FOR SERVING EACH BUILDING. IN

MANY CASES THE I/O CONTROL PANEL FOR THE BUILDING WILL ALSO BE HOUSED IN THE

“ELECTRONICS ROOM” BUT NOT IN ALL CASES. CONTRACTOR IS RESPONSIBLE FOR PROVIDING

CONDUIT FROM IDF CABINET TO THE I/O CONTROL PANEL AND PULLING FIBER.

6. Is there an existing conduit from Main Control Panel to the Network Cabinets in the Administration building to route the fiber optic cables? What is the linier distance from the Main control panel to the network cabinets located in the administration building?

CLARIFICATION: THIS QUESTION DOES NOT MAKE SENSE. THE MAIN CONTROL PANEL IS IN

THE CENTRAL PLANT BUILDING. THE NETWORK CABINETS ARE LOCATED IN THE

ADMINISTRATION BUILDING. THE OUTDOOR CONDUIT SYSTEMS AND FIBER ARE ALL EXISTING,

THEY GO FROM THE ADMIN BUILDING MDF COMMUNICATION RACK TO ALL OTHER BUILDING IDF

COMMUNICATION RACKS. THE NEW CONDUIT IS REQUIRED BETWEEN EACH COMMUNICATION RACK

AND THE RESPECTIVE I/O CONTROL UNIT. SEE E102.

7. Sequence of operations:

a. How is the generator connected to the new controller? Is the new PLC starting/stopping the generator and synchronizing?

CLARIFICATION: THE GENERATOR STARTING/STOPPING AND SYNCHRONIZING IS ACCOMPLISHED

BY THE EXISTING GENERATOR SWITCHGEAR “GSG-4A”. THE NEW PLC SYSTEM IS ONLY

CONTROLLING THE OPERABLE BREAKERS AT EACH BUILDING IN ORDER TO CONTROL THE

“ESSENTIAL” AND “NON-ESSENTIAL” LOAD CIRCUIT BREAKERS. PLEASE SEE DRAWING E002

FOR FURTHER INFORMATION.

b. How is the generator synchronization function controlled and does the new PLC take any action to mitigate generator operation?

CLARIFICATION: THE GENERATION FAILURE TO SYNC SIGNAL IS SENT TO THE PLC SYSTEM SO THAT THE PLC SYSTEM DOES NOT OPERATE THE BREAKERS WHEN THE GENERATORS HAVE FAILED

TO SYNCHRONIZE. NO ACTION IS TO BE TAKEN BY THE PLC TO MITIGATE GENERATOR

OPERATION.

c. Is the event of utility loss, which control system manages the utility and 52G breakers?

CLARIFICATION: EXISTING GENERATOR SWITCHGEAR “GSG-4A”, NOT THE NEW PLC SYSTEM.

d. What are the real time inputs from the generator and how are they going to be connected?

CLARIFICATION: PLEASE REFER TO SHEET E002 WHERE THIS INFORMATION IS DISCUSSED.

SPECIFICALLY SEE NOTE 6 UNDER “PROGRAMMABLE LOGIC CONTROL (PLC) SYSTEM”.

e. How many total Input and outputs are required for each switchboards and generators?

CLARIFICATION: REFER TO SHEET E002 AND SPECIFICATIONS TO ENSURE THE CORRECT

QUANTITY INCLUDING SPARE CAPACITY IS CONSIDERED.

f. How many 4-20 mA signals are required and what are their functions? What are the control sequence for the 4-20 mA signals?

CLARIFICATION: THE 4-20 MA SIGNAL IS FOR THE GENERATOR CAPACITY TO BE READ BY THE

NEW PLC SYSTEM.

g. Does the remote PLCs require 4-20mA I/O?

CLARIFICATION: Not required, but the remote PLC does need to sense the reading from the power meter in each main switchboard of the building. The reading from each meter shall be transmitted to the main PLC / SCADA Desktop Computer.

h. How many digital power meters are required? Is there a preference for interfacing the digital meters? Can it be connected with each remote PLC by Cat 6 and then broadcasted by the remote PLC?

CLARIFICATION: A DIGITAL METER FOR BOTH ESSENTIAL AND NON-ESSENTIAL LOADS IS

REQUIRED AT THE MAIN SWITCHBOARD AT EVERY BUILDING. REVIEW THE DRAWINGS FOR EXACT

QUANTITY. YES THE DESIGN ASSUMES CONNECTION FROM METER TO REMOTE PLC USING CAT 6

CABLE.

8. Is there a preferred mounting location for the 7” HMI monitor? Does it need to be inside or outside of the new 2’x2’ enclosure?

CLARIFICATION: THE PREFERENCE WOULD BE FOR IT TO BE VISIBLE ON THE ENCLOSURE,

HOWEVER THIS IS NOT A REQUIREMENT.

9. How would material receiving be handled? Do we need to be present when shipment arrives?

CLARIFICATION: SEE PAGE 70 OF THE SPECIFICATIONS. THE FBOP WILL NOT BE

RESPONSIBLE TO RECEIVE YOUR PRODUCT. WHILE IT MAY BE DELIVERED, PRIME CONTRACTOR

STAFF WILL BE RESPONSIBLE TO RECEIVE ALL DELIVERIES.

10. What is the minimum advance notice required for the extended work hour requests? What is the process to manage extended work hour request for the same day due to unforeseen situations?

CLARIFICATION: SEE PAGE 7 OF THE SPECIFICATION.

11. Can we share drawings with subcontractors for bidding purposes?

CLARIFICATION: YES.

12. Is there a requirement for Arc Flash study for each switchboards?

CLARIFICATION: NO.

13. Questions and request made during and after the site visit has direct impact on the bid, would you consider extending bid submission date so we can process all the information?

CLARIFICATION: NO, THIS IS THE SECOND TIME THIS REQUIREMENT HAS BEEN PUBLISHED.

THE CLOSING DATE WILL REMAIN AS IS.

SUBMITTED BY VIRGINIA ENERGY:

1. Can we have enough guards to support 3 actives in 3 different locations.

Example working on Manholes, running conduit, pulling out old copper wire, this is just one example there are many others on this project.

CLARIFICATION: DEPENDING ON THE NATURE OF THE DAILY WORK SCHEDULE, WE ANTICIPATE

MAKING 3-4 ESCORTS AVAILABLE DAILY. HOWEVER, THREE LOCATIONS DAILY WILL NOT BE

PERMITTED DUE TO SECURITY CONCERNS.

2. Will manhole covers be able to be left off doing this project and covered with plywood and barricaded at night.

CLARIFICATION: IT IS A SECURITY MEASURE THAT ALL MANHOLE LIDS SHALL BE REAPPLIED

AND SECURED AT THE END OF EACH DAY TO THE ORIGINAL STATUS. HOWEVER, SHOULD A

CONTRACTOR CHOOSE TO OBTAIN AND UTILIZE A MINIMUM 1” STEEL PLATE TO COVER THE

ENTIRE EXCAVATION SITE TO INCLUDE MANHOLE, THIS WOULD BE ACCEPTABLE. THE STEEL

PLATE MUST BE A MINIMUM OF 32 SQUARE FEET, AND IN PLACE FOR NO MORE THAN 36

HOURS. STEEL PLATES MAY NOT BE IN PLACE OVER A WEEKEND.

3. Can a conex be left inside fence area for storage of material and tools.

CLARIFICATION: DUE TO SECURITY CONCERNS, NO.

4. Can equipment backhoe, exciter be left in fenced area.

CLARIFICATION: DUE TO SECURITY CONCERNS, NO.

5. What is the procedure for delivery of material by suppliers for this project?

CLARIFICATION: CONTRACTOR SHALL NOTIFY COR REGARDING SCHEDULED DELIVERIES.

CONTRACTOR MUST ACCEPT HIS OWN DELIVERIES. OUR WAREHOUSE IS OPEN BETWEEN THE

HOURS OF 7:30 AM – 3:00 PM, MONDAY THROUGH FRIDAY EXCLUDING HOLIDAYS. CONTRACTOR

IS RESPONSIBLE FOR ACCOUNTING FOR AND INSPECTING ALL MATERIALS DELIVERED AND ALL

MATERIALS SHALL BE DELIVERED TO THE WAREHOUSE.

6. Can we use existing conduit provided conduit fill is correct.

CLARIFICATION: DESIGN CALLS FOR NEW CONDUIT.

7. Can equipment be mounted in existing boxes or racks to mount equipment, because there is no room in order to mount boxes, racks for equipment in areas as shown on drawings.

CLARIFICATION: THERE IS ADEQUATE SPACE IN ALL AREAS.

8. There is existing wire and fiber already run that can be used. The cable would be tested and test results turned in as part of turn over package for project.

CLARIFICATION: THE FIBER BACKBONE IS EXISTING. ALL COPPER WIRE IS NEW AS SHOWN ON

DRAWINGS.

9. There are 18 existing electrically operated breakers the new system will be controlling that have not had any maintenance performed since installed. The need to be inspected, tested and have preventive maintenance performed to insure the system will function properly. Please confirm this is to be included in the bid pricing.

CLARIFICATION: THE ENTIRETY OF THE NEW SYSTEM SHOULD BE TESTED AND DEMONSTRATED

AS FUNCTIONAL. PERFORMING TESTING AND PREVENTATIVE MAINTENANCE IS NOT INCLUDED IN

THE SCOPE OF WORK.

10. The specifications and drawings show that the new master terminals display parallel system data and engine data from the existing generator parallel system however it does not state that this is to be upgraded as well. To insure full system control and functionality please confirm that the generator parallel control system is to be modernized as well.

CLARIFICATION: THE GENERATOR CONTROLS WILL REMAIN THE SAME. THE PLC IS ONLY

RETRIEVING DATA FROM THE MAIN SWITCHGEAR AND GENERATOR SYSTEM. PLEASE SEE FURTHER

INFORMATION ON SHEET E002.

11. Is the intent of the facilities management to upgrade the generator controls for this project to get better reliability in future- The Generator controller is a Woodward model 9907-028 SPM-A. This unit is obsolete and EPI has seen several failures with this unit in the last several years. Woodward has had several upgraded designs since this unit came out- SMP-A-LS4, EZ-Gen, EZ-Gen 3500 and the latest version EZ-Gen XT (With Ethernet). You can see the units on-site are no longer supported. The generator protection is General Electric-Multilin SR-489 Generator protection relays and are still in production. These would not have to be replaced. With newer controls you can have a softer transition or even closed transitions with utility.

CLARIFICATION: THE ENTIRETY OF THE NEW SYSTEM SHOULD BE TESTED AND DEMONSTRATED

AS FUNCTIONAL. PERFORMING TESTING AND PREVENTATIVE MAINTENANCE IS NOT INCLUDED IN

THE SCOPE OF WORK.

12. This project is to control the secondary main and feeder breakers during times for load sheading. Is the intent to verify that all affected main and feeder breakers are working properly with regards to operation of the electrical functions (Charge, Close and Trip) and circuit protection. If so are we to perform maintenance testing and inspections as per NETA-MTS-2015 section:7.6.1.1.

EPI would also suggest the following equipment also be tested and inspected: 1ea 15kv Utility Main breaker with relay protection, 15kv Generator Main breaker with relay protection, 480vac Generator paralleling breakers be tested along with the protection relays. NETA or IEEE suggest that circuit protection testing be performed on no longer than a seven and one-half year rotation. With this rotation, you can expect a low reliability result.

CLARIFICATION: THAT IS NOT INCLUDED IN THE SCOPE OF WORK.

SUBMITTED BY TDX QUALITY, LLC:

1. Temporary data and power during new installation. How will it affect security/alarms?

CLARIFICATION: NO TEMPORARY DATA OR POWER REQUIRED. EXISTING SYSTEM IS NOT IN

SERVICE.

2. Temporary communication cabling during removal of existing communication cabling outside buildings at + - 88 manholes and connecting cabling.

CLARIFICATION: NO TEMPORARY COMMUNICATION CABLING REQUIRED. EXISTING SYSTEM IS

NOT IN SERVICE.

3. Phasing requirements inside the 15-Building?

CLARIFICATION: PHASING IS NOT REQUIRED. SCHEDULING INFORMATION MUST INCLUDED IN

PROJECT SCHEDULE.

4. Phasing outside Building to the 15-buildings from the 88-manholes?

CLARIFICATION: PHASING IS NOT REQUIRED. SCHEDULING INFORMATION MUST INCLUDED IN

PROJECT SCHEDULE.

5. Spec. 011000, 1.8 F and 1011002, 3.4. Requires badging of employees. What duration should the contractor plan on for the investigation / badging task?

CLARIFICATION: 14 CALENDAR DAYS ARE INCLUDED IN THE PERFORMANCE PERIOD TO OBTAIN

CLEARANCE, ONCE A COMPLETE PACKAGE IS SUBMITTED BY THE PRIME CONTRACTOR. SEE PAGE

7 OF THE SOLICITATION.

6. Spec. 011000, 1.8 G. Requires contractor to comply with Owner's requirements for drug and background screening. Please provide a copy of the drug screening process / procedure.

CLARIFICATION: SEE PAGES 7 AND 17 OF THE SOLICITATION. THESE ARE THE

REQUIREMENTS. DRUG SCREENING IS NOT REQUIRED.

7. Spec. 011003, 3.7. Prohibits cell phones with camera capabilities. As almost all cell phones have camera capability, will the Contractor be allowed to have cell phones of supervisors screened and approved for use on the site?

CLARIFICATION: THIS IS A FEDERAL PRISON – NO, NOT UNDER ANY CIRCUMSTANCES.

8. Work hours and restrictions. Spec. section 1.8B provides work hours for interior operations. What are the work hours for outside site & electrical work?

CLARIFICATION: THE WORK HOURS ARE THE SAME. THEY DO NOT CHANGE.

9. Sanitation (porta johns) for workers outside (restrictions)

CLARIFICATION: THERE IS NO QUESTION HERE. SEE CLAUSE 52.236-14 ON PAGE 13 OF THE

SOLICITATION. ALSO SEE SPECIFICATION SECTION 015000 PARA 3.3.E.

10. Will we be able to use existing dumpster, bring in our own or not allow a dumpster?

CLARIFICATION: THE PRIME WILL BE RESPONSIBLE TO PROVIDE THEIROWN DUMPSTER. SEE

SPECIFICATION SECTION 017419 3.1.A.

11. Notification requirements for deliveries for security screening.

CLARIFICATION: THIS IS UNCLEAR - IF YOU ARE REFERING TO SECURITY SCREENING FOR

EMPLOYEES, SEE PAGE 7 OF THE SOLICITATION. IF YOU ARE REFERRING TO DELIVERY OF

PRODUCT TO BE SCREENED, ALL DELIVERIES ARE MADE TO THE WAREHOUSE AND THE PRIME

SHOULD MAKE NOTIFICATION TO THE COR WHEN PRODUCT ORDER AND DELIVERY DATE IS

CONFIRMED.

12. Will an existing space be made available for a temporary Contractor Office and if not will an mobile office trailer be allowed?

CLARIFICATION: SEE PAGE 63 OF THE SPECIFICATION.

13. I do not see where they tell us what software must be used for the Project Schedule. We are we planning on? If P6 we should ask questions so other also have to provide it.

CLARIFICATION: SEE CLAUSE 52.236-15 ON PAGE 13 OF THE SOLICITATION. ALSO, SEE

SPECIFICATION SECTION 013200 1.6.A.1.

14. For our proposed schedule we need to allow 15-days for Gov. review time.

(Spec 13300, 1-6C)

CLARIFICATION: THIS IS NOT A QUESTION.

15. The QC Manager may also be the Proj. Supt. (Spec. 14000, 1.7B)

CLARIFICATION: THIS IS NOT A QUESTION.

16. Is there any temporary dust protection required inside the 15-buildings?

CLARIFICATION: YES. REFER TO SECTION 015000 PARA 3.3.C.

SUBMITTED BY GROT, INCORPORATED:

1. In reviewing the SOW, Plans and Specs for both IFBP01171700002 and IFBP01171700001, we are unable to see any noticeable differences after comparison. Please identify the differences between the two IFB’s.

CLARIFICATION: NONE.

2. It was stated at the site visit that there are months where there is heavy fog in the morning. Q: Will the government extend the contract completion date due to fog delays?

CLARIFICATION: NO. THERE IS CONTINGENT TIME BUILT INTO THE PERIOD OF PERFORMANCE.

3. At what point will the government consider fog delays to be excessive where the contractor will be compensated via a modification?

CLARIFICATION: WHEN THE WEATHER IS FAR OUTSIDE THE NORMAL WEATHER PATTERN.

4. Can the manholes be dug and left open and made secure for 48 hours until the contractor can justify the minimum delivery amount for concrete?

CLARIFICATION: IT IS A SECURITY MEASURE THAT ALL MANHOLE LIDS SHALL BE REAPPLIED

AND SECURED AT THE END OF EACH DAY TO THE ORIGINAL STATUS. HOWEVER, SHOULD A

CONTRACTOR CHOOSE TO OBTAIN AND UTILIZE A MINIMUM 1” STEEL PLATE TO COVER THE

ENTIRE EXCAVATION SITE TO INCLUDE MANHOLE, THIS WOULD BE ACCEPTABLE. THE STEEL

PLATE MUST BE A MINIMUM OF 32 SQUARE FEET, AND IN PLACE FOR NO MORE THAN 36

HOURS. STEEL PLATES MAY NOT BE IN PLACE OVER A WEEKEND.

5. Will the contractor be able to schedule inside work and outside work being performed at the same time?

CLARIFICATION: DEPENDING ON THE NATURE OF THE DAILY WORK SCHEDULE, WE ANTICIPATE

MAKING 3-4 ESCORTS AVAILABLE DAILY. HOWEVER, MULTIPLE LOCATIONS DAILY WILL NOT BE

PERMITTED DUE TO SECURITY CONCERNS.

6. It was stated at the site visit that the facility will allow the contractor to use its equipment and hand tools on this project. Q: Will the contractor be able to use these hand tools and equipment?

CLARIFICATION: UNDER NO CIRCUMSTANCES WILL THE PRIME CONTRACTOR HAVE ACCESS TO OR

UTILIZE GOVERNMENT EQUIPMENT OR HAND TOOLS.

7. Will be the contractor be able to use the facility’s backhoe?

CLARIFICATION: NO

8. How many manholes will the contractor be allowed to dig per day and not re-pour concrete?

CLARIFICATION: IT IS A SECURITY MEASURE THAT ALL MANHOLE LIDS SHALL BE REAPPLIED

AND SECURED AT THE END OF EACH DAY TO THE ORIGINAL STATUS. HOWEVER, SHOULD A

CONTRACTOR CHOOSE TO OBTAIN AND UTILIZE A MINIMUM 1” STEEL PLATE TO COVER THE

ENTIRE EXCAVATION SITE TO INCLUDE MANHOLE, THIS WOULD BE ACCEPTABLE. THE STEEL

PLATE MUST BE A MINIMUM OF 32 SQUARE FEET, AND IN PLACE FOR NO MORE THAN 36

HOURS. STEEL PLATES MAY NOT BE IN PLACE OVER A WEEKEND.

9. It was stated during the site visit that the contractor is to expect one escort per day at the facility. How many escorts will the contractor have per day?

CLARIFICATION: DEPENDING ON THE NATURE OF THE DAILY WORK SCHEDULE, WE ANTICIPATE

MAKING 3-4 ESCORTS AVAILABLE DAILY. HOWEVER, MULTIPLE LOCATIONS DAILY WILL NOT BE

PERMITTED DUE TO SECURITY CONCERNS.

10. Will the contractor be allowed to leave the manholes, inside the perimeter and outside the perimeter open overnight if they are blocked off with safety materials?

CLARIFICATION: IT IS A SECURITY MEASURE THAT ALL MANHOLE LIDS SHALL BE REAPPLIED

AND SECURED AT THE END OF EACH DAY TO THE ORIGINAL STATUS. HOWEVER, SHOULD A

CONTRACTOR CHOOSE TO OBTAIN AND UTILIZE A MINIMUM 1” STEEL PLATE TO COVER THE

ENTIRE EXCAVATION SITE TO INCLUDE MANHOLE, THIS WOULD BE ACCEPTABLE. THE STEEL

PLATE MUST BE A MINIMUM OF 32 SQUARE FEET, AND IN PLACE FOR NO MORE THAN 36

HOURS. STEEL PLATES MAY NOT BE IN PLACE OVER A WEEKEND.

11. Will the contractor have to slump test on concrete delivered and/or hand mixed concrete?

CLARIFICATION: SLUMP TEST IS REQUIRED, HOWEVER, NO HAND MIXED CONCRETE WILL BE

ACCEPTED.

12. Will the contractor be able to work an interior (inside the prison) crew on electrical/fiber work and an outside (outside the prison) crew working on the manholes simultaneously?

CLARIFICATION: DEPENDING ON THE NATURE OF THE DAILY WORK SCHEDULE, WE ANTICIPATE

MAKING 3-4 ESCORTS AVAILABLE DAILY. HOWEVER, MULTIPLE LOCATIONS DAILY WILL NOT BE

PERMITTED DUE TO SECURITY CONCERNS.

13. Will the delivery driver for the concrete truck have to complete an NCIC daily for entry?

CLARIFICATION: SEE PAGE 17 OF THE SOLICITATION.

14. Will the concrete truck be able to drive to all manhole locations to pour concrete?

CLARIFICATION: YES.

15. If concrete truck is not allowed to drive to all manhole locations, What approved method will the owner allow to transport concrete from the rear gate?

CLARIFICATION: SEE RESPONSE ABOVE.

16. Drawing Sheet T0.1, Note 9 provide complete programming of PLCS control system to automatically transfer all buildings normal power to the emergency power source (existing generators) in the event of loss of power. Sequence of power transfer shall be as identified on drawings. Are the existing circuit breakers electrically operated in order to transfer from normal power to emergency power?

CLARIFICATION: YES. THE NEW PLCS IS JUST THE REPLACEMENT OF THE EXISTING PLCS

THAT IS OBSOLETE AND NO LONGER OPERATIONAL.

17. Drawing Sheet T0.1, Note 6 provide new conduit and copper wiring from existing circuit breakers to the new PLCS control panel in each building. Do the existing circuit breakers in each location have auxiliary contacts (NO & NC) already on the breakers?

CLARIFICATION: YES. THE AUXILIARY CONTACTS WILL BE USED AS BEFORE.

18. Sheet C301, Details 1, 2, 3 – “Pent Head Bolt with washers on 29-3/8” B.C.”

Is superimposed over 13 x 2 McGard Secure Bolts”. Are the McGard Secure Bolts no longer required?

CLARIFICATION: FBOP TECHNICAL DESIGN GUIDELINES STATE “A. FOR MANHOLES LOCATED

INSIDE THE SECURE PERIMETER, REPLACE THE NORMAL ANCHOR BOLTS THAT SECURE THE

MANHOLE COVER WITH PATENTED SECURITY BOLTS SUCH AS THE MAN-LOCK MANUFACTURED BY

MCGARD. THE WORK IS NOT LIMITED TO THE MANUFACTURER IDENTIFIED HEREIN. USE

STATE’S DEPARTMENT OF TRANSPORTATION STANDARD DETAILS WHERE AVAILABLE AND

APPLICABLE.

1. Other manufacturers who manufacture similar items shall be permitted to submit their products in accordance with substitution and submittal requirements specified in Division 1.

2. Standard manholes require preparation to receive security bolts.

a. Bolt to be made from alloy steel, heat treated to 1035 MPa (150 ksi) tensile strength.

b. Head of bolt to be selectively hardened to Rc 60 min. to prevent the use of files, hacksaws, and chisels.

c. Bolt to be made with either a flat or 120 degree cone seat as required.

d. Bolt to be torqued by means of a recessed curvalinear ("Daisy") groove in top face of bolt head. A special mating key is required to operate in the groove for installation or removal of bolt.

e. Outside head of bolt shall have a special, non-standard, thread for mounting of a protective plastic cap.

f. Bolts to be triple nickel chrome plated meeting ASTM B 368 C.A.S.S. test for 22 hours.

g. Bolt lengths to be within +/- 3 mm (0.12").

h. Bolt threads to be class UNC-2A.

19. Section 024119-2, 1.4 Selective Demolition Materials Ownership Who takes ownership of old existing manhole covers and frames?

CLARIFICATION: USP LEE WILL TAKE OWNERSHIP OF THE EXISTING MANHOLE COVERS AND

FRAMES. THE EXISTING MANHOLE COVERS AND FRAMES WILL BE PLACED IN AN AREA

DESIGNATED BY USP LEE. THESE ITEMS WILL BECOME PART OF THE INSTITUTION’S

RECYCLING PROGRAM.

20. Drawing Sheet E001, Definition: The word provide means that the contractor shall furnish, install adjust, test and integrate into a complete system the item indicated including all hardware, wiring and miscellaneous items as necessary for a complete and operational system. Will existing circuit breakers have to be replaced to be compatible with the new control system?

CLARIFICATION: NO. THE EXISTING CIRCUIT BREAKER WILL RECEIVE THE COMMAND FROM THE

NEW PLCS TO CLOSE OR OPEN.

21. Section 017900, 1.5 Quality Assurance, B., Preinstruction Conference:

Inspect and discuss locations and other facilities required for instruction.

Does this mean we have to visit, review, and prepare training documentation for other facilities?

CLARIFICATION: NO. THE SPECS REQUIRE TRAINING OF THE FACILITIES STAFF AT USP LEE.

22. Section 017900, 1.9, Instruction B. Engage qualified instructors to instruct owners personnel to adjust, operate and maintain systems, sub-systems, and equipment not part of a system. Does this mean any and all equipment that is not part of this system?

CLARIFICATION: NO. ONLY THE SYSTEM AFFECTED BY THIS WORK.

23. Drawing sheet TO.1, Note 11 Salvage copper control wiring to the maximum extent possible and deliver to on-site location to be determined by owner.

a. If the contractor is unable to remove cable, please provide procedure for cables that cannot be removed.

CLARIFICATION: WE EXPECT THAT ALL CABLE CAN BE REMOVED. SHOULD THE PRIME DISCOVER

AN UNFORESEEN CIRCUMSTANCE, THE PRIME WILL MAKE NOTIFICATION TO THE COR AND

CONTRACTING OFFICER.

b. Can the control wiring cables be abandoned in place if they cannot be removed?

CLARIFICATION: YES. THE CONTRACTOR SHALL LABEL THEM “ABANDONED”.

c. Are the existing copper control cables to be removed, in the same raceways with conductors to remain? If they are, how much force is the contractor to use that could damage the cables that are to remain?

CLARIFICATION: NO, CONDUCTORS TO BE REMOVED ARE IN THEIR OWN RACEWAYS.

d. If contractor uses reasonable effort to remove the control cables and the cables that are to remain are damaged, will the contractor receive a modification to repair and replace?

CLARIFICATION: SEE RESPONSE TO C.

24. Drawings Sheet E003, One Line Diagrams, Note 1 One-line diagram provided for reference. Contractor responsible for providing (N) energy meters for essential and non- essential loads in each (E) distribution board as well as reconnecting

(E) circuit breaker contacts. The (E) distribution system equipment are to remain as shown.

a. Are the existing circuit breakers electrically operated?

CLARIFICATION: YES, THE PLC CONTROL CABLING SYSTEM ALLOWS FOR OPERATION FROM THE

POWERHOUSE TO REMOTELY OPEN AND CLOSE ALL SUB-AREAS NON-ESSENTIAL AND ESSENTIAL

BREAKERS. REFER TO THE PERFORMANCE REQUIREMENT SECTION ON E0002.

b. If the breakers are electrically operated, where are the battery power supplies to operate the breakers?

CLARIFICATION: THE BREAKERS DO NOT HAVE BATTERY POWER SUPPLIES. REFER TO THE

PERFORMANCE REQUIREMENT SECTION ON E0002.

25. Drawings Sheet E004, One Line Diagrams, Note 1 One-line diagram provided for reference. Contractor responsible for providing (N) energy meters for essential and non- essential loads in each (E) distribution board as well as reconnecting

(E) circuit breaker contacts. The (E) distribution system equipment are to remain as shown.

a. Are the existing circuit breakers electrically operated?

CLARIFICATION: YES. THE “M” ENCLOSED BY THE CIRCLE MEANS MOTORIZED CIRCUIT

BREAKER. THIS IS TAKEN FROM THE AS-BUILT DRAWING.

b. If the breakers are electrically operated, where are the battery power supplies to operate the breakers?

CLARIFICATION: THE CIRCUIT BREAKERS ARE OPERATING AT 120VAC THEREFORE; WE BELIEVE

THAT EACH SWITCHBOARDS HAS CONTROL POTENTIAL TRANSFORMER (CPT) AHEAD OF THE

CIRCUIT BREAKERS TO ENERGIZE THE NON-ESSENTIAL AND ESSENTIAL CIRCUIT BREAKERS.

26. Solicitation SF1442, line 13, Additional Solicitation Requirements, A.

states that the sealed bids will be received January 4, 2017, no later than 11:00 EST. Can the bid date be changed to January 10, 2017 to allow for timely and accurate proposals due to the interruption of working days and factory shutdowns during the holidays?

CLARIFICATION: THIS IS A REPEAT QUESTION FROM THE INTITIAL SOLICITATION EARLIER

THIS YEAR AND HAS NO BEARING ON THE CURRENT SOLICITATION.

27. At 100 % design approvals, are there any additional design narratives from the Engineers, Architects or FBOP?

CLARIFICATION: NO.