IFB 26-001 Tree Trim WBMLP 6July2026.pdf

PDF 436 KB Posted

Attached to
Tree trimming/line clearance
Solicitation number
BD-26-2075-WBMLP-WBMLP-131110
Issued by
Worcester County, Massachusetts

About this file

IFB 26-001 Tree Trim WBMLP Summary

This is an Invitation for Bid (IFB) issued by the Massachusetts municipality for tree trimming and line clearance services. The project encompasses vegetation management and tree trimming operations to maintain utility line clearance and public safety. The bid solicitation establishes specific performance requirements and deliverables for contractors to remove vegetation, trim tree branches, and clear lines within designated service areas. The IFB includes provisions for a bidders conference and site visit opportunities to allow prospective bidders to inspect project conditions and clarify scope requirements. Responses are due by the specified deadline outlined in the solicitation documents, with contract award anticipated following a formal bid evaluation process. The contract term and any renewal or extension options are defined within the IFB terms and conditions.

Pricing for the project will be submitted on a competitive bid basis, with contractors required to provide itemized cost proposals according to the pricing schedule specified in the IFB. The solicitation may include set-aside provisions for minority-owned, women-owned, or locally-based businesses as applicable under Massachusetts procurement regulations. Funding for the contract is derived from municipal or state sources allocated for utility infrastructure maintenance and vegetation management. Contractors should review all technical specifications, drawings, and supporting exhibits provided with the IFB to ensure accurate bid preparation and understanding of all work requirements and performance standards.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

WEST BOYLSTON MUNICIPAL LIGHTING PLANT

4 Crescent Street, West Boylston, Massachusetts 01583 Telephone

(508) 835-3681 Fax (508) 835-2952

July 6, 2026

Subject: Invitation For Bid (IFB) 26-001

To All Interested Bidders, The West Boylston Municipal Light Plant (WBMLP), 4 Crescent Street, West Boylston, Massachusetts, hereby solicits bids through IFB 26-001 for FY2026 Tree Trimming (line clearance and maintenance). Bid Specifications are included within this Bid Package. All completed bids shall be submitted to the General Manger and shall be placed in a sealed envelope and plainly marked with the Bid Number 26-001.

Sealed bids will be received by 1:00 P.M. Eastern Standard Time on August 6, 2026, at the

WBMLP office, 4 Crescent Street, West Boylston, Massachusetts 01583. E-mailed bids will be accepted to jfitch@wbmlp.org.

All incomplete bids will be rejected. The WBMLP reserves the right to reject any or all bids.

Sincerely, Jonathan V. Fitch

General Manager

West Boylston Municipal Light Plant mailto:jfitch@wbmlp.org

INSTRUCTIONS TO BIDDERS

• Bids shall be sealed and plainly marked with the IFB Number on the outer envelope furnished with the Bid Package. All bids shall be submitted by the deadline to WBMLP, 4 Crescent Street, West Boylston, MA 01583.

• All bids shall be typewritten or written in ink. The person signing the bid must initial any changes or strikeouts.

• WBMLP reserves the right to reject any or all proposals, to cancel this bid document at any time, and to waive immaterial defects and minor irregularities in this request.

• WBMLP reserves the right of evaluation and the right to determine the methodology for evaluation of the proposals to determine which the best proposal is and to accept the proposal deemed to be in the best interest of the WBMLP. WBMLP reserves the right to award the bid to any vendor or combination of vendors, and WBMLP reserves the right to negotiate with any Bidder as necessary.

• The issuance of this bid document does not constitute a commitment by WBMLP to enter into a contract for the completion of this project or to pay any costs incurred by any

Bidder in the preparation of their response to this bid document.

• All proposals will become the property of WBMLP and are considered proprietary information.

• The successful Bidder must comply with all Local, State, and Federal laws, regulations and policies applicable to this request. This includes all required environmental and regulatory permits.

• Bidders should carefully examine the specifications and fully inform themselves as to all conditions and matters, which can in any way affect the work or the costs thereof. Should a Bidder find discrepancies in, or omissions from the bid document, Specifications or other documents, or should be in doubt as to their meanings, he should notify WBMLP project contacts at once and obtain clarification prior to submitting any proposal.

• Bidder shall provide (1) copy of the Sealed Bid.

• Bidder must pay prevailing wages per M.G.L. Chapter 149 Section 26D. See attached prevailing wage schedule for the appropriate “laborer, tree remover” and “apprentice laborer” classification and prevailing wages.

• Bids signed by an agent must be accompanied by written authorization to sign or other evidence of delegated authority to sign.

• Bidders must provide the name, title, address, telephone number, facsimile number, and e-mail of a "Contact Person" possessing sufficient technical and/or operating knowledge of the item(s) being Bid to whom technical questions or requests for clarification may be addressed.

• Bids shall be valid for ninety (90) days prior to acceptance. Under unusual circumstances, bids may be extended as necessary as deemed by the General Manager.

• Based on direct experience with the equipment and/or work scope contained in this IFB, the Bidder shall provide a qualification and an experience summary statement in the Bid

Proposal and furnish the name, title, address and phone number of three (3) business references (preferable utility references).

• All required certifications should be made as part of the Bid Package.

• WBMLP is exempt from sales tax.

• The Awarding authority is the General Manager.

• The General Manager of WBMLP reserves the right to reject any and all bids, to waive informalities and minor irregularities in bids received, and also to accept any bid in total or in part but not necessarily the lowest bid, if it is deemed to be in the best interest of the

WBMLP to do so.

• WBMLP reserves the right to postpone the award of the Bid Package. This will be conveyed to all Bidders in a timely fashion.

• These Specifications are intended to be complete, but the Bidder shall consider himself bound by good engineering practices if omissions in the Specifications are encountered.

• AII Bidders shall specify their main business location and any satellite offices as well as the office/shop hours for each location. All communications and correspondence shall be addressed to: West Boylston Municipal Lighting Plant, Attn: Jonathan V. Fitch, 4

Crescent Street, West Boylston, MA 01583, (508) 835-3681, jfitch@wbmlp.org mailto:jfitch@wbmlp.org

TERMS AND CONDITIONS

1. AGREEMENT. An Agreement is a written, binding Purchase Order or Contract between the

Owner and the Seller. No Agreement shall be binding unless it is in writing and signed by an authorized representative of the Owner.

1.1. The successful bidder (herein Seller) must execute a contract with WBMLP upon being awarded the contract.

1.2. After contract signing, WBMLP will issue a Notice to Proceed.

1.3. This bid document and the Seller's response shall become part of the contract covering this project.

2. ENTIRE AGREEMENT. This Agreement shall constitute the entire understanding between the Owner and the Seller, and no modifications, release, waiver or termination of this

Agreement or any of its terms and conditions, shall be binding on the Owner unless agreed to in writing by the Owner. By acknowledging receipt of this Agreement or by shipping the merchandise, the Seller agrees to all the terms and conditions of this Agreement. Any additional or different terms proposed by the Seller are hereby objected to and rejected by the

Owner.

3. PERFORMANCE/DELIVERY DATE. A written work schedule including a final delivery date for the trimming shall be provided and if the Seller misses the delivery date without just cause a 10% reduction in price shall be applied to the final bill. The WBMLP reserves the right to inspect the performance on site and to review operations at any time. Seller will not commence work until September 15, 2026, and all work must be completed by December 31, 2026, unless approved by WBMLP General Manager.

4. COMPLIANCE WITH LAW. Any provision required by law to be included herein shall be deemed included as a part of this Agreement whether or not specifically referenced. The

Seller shall comply with all applicable Federal, State and Local laws, rules and regulations.

The Seller also agrees to indemnify and hold the Owner harmless from all damages and liabilities assessed against the Owner as a result of the Seller's noncompliance therewith.

5. APPLICABLE LAW. The laws of the Commonwealth of Massachusetts shall govern the rights and obligations arising from this Agreement.

6. TAXES. The Owner is an organization exempt from the payment of State and Local taxes of tangible property and services and will not reimburse the Seller for such taxes incurred by the

Seller associated with this Agreement.

7. ASSIGNMENT. This Agreement is placed on condition that the Seller shall not assign it or any payment due or to become due hereunder, without the Owner's prior written consent.

Any such assignment(s) without the Owner's prior written consent shall be void. Should the

Owner agree to an assignment, the Seller shall remain fully responsible for the acts and omissions of the Seller's assignee and the Seller shall indemnify and hold the Owner harmless from any and all loss and expense arising out of the assignment.

8. CONFIDENTIALITY. Any of the Owner's drawings, discussions, meetings, specifications or technical information, etc. used by the Seller hereunder, shall remain the property of the

Owner and shall be held in confidence by the Seller and shall not be reproduced or disclosed to others without the written permission of the Owner.

9. WAIVER. In the event the Owner fails to insist on strict performance of any of the terms and conditions or fails to exercise any of its rights and privileges hereunder, such failure shall not constitute a waiver of such terms, conditions, rights or privileges.

10. COMPLETION. This Agreement will not be considered complete until all technical specifications; final review, and I or acceptance of the Owner have been satisfied and accepted.

11. MODIFICATIONS. Owner may modify all terms and conditions in writing. Such modifications shall be mutually agreed upon and shall not nullify the original intent or any of the existing terms of this Agreement.

TECHNICAL SPECIFICATIONS

PURPOSE: The purpose of this Invitation for Bid (IFB) is for 2026 TREE-TRIMMING (LINE

CLEARANCE), which meets or exceeds the technical specifications described herein, and offers the best value to the West Boylston Municipal Light Plant.

2026 TREE-TRIMMING (LINE CLEARANCE) BID SPECIFICATIONS:

• Minimum Number of Tree-Trimming Workers: 2 (typically one laborer and one apprentice laborer)

• Minimum Number of Wood-Chippers: 1

• Minimum Number of Tree-Trimming Trucks: 1

• Minimum Tree-Trimming Truck Working Height: 65'

• Must Submit Certificate of Insurance.

• Must Submit Signed Copy of "Certification of Good Faith" Form (per M.G.L. Chapter

30B, Section 10)

• Must submit all safety and training certifications for electric line-clearance trimming.

• Please provide hourly rates for tree removals that are over 8 inches in diameter.

• Must pay the prevailing wage per M.G.L. Chapter 149 Section 26D. See attached prevailing wage schedule.

• Bidder is responsible for coordination and payment of all required police details.

WBMLP recommends contacting the West Boylston Police Department for detail requirements based on the road listing.

• Branches and brush debris will be chipped, cleaned up, and hauled away. The work areas shall be left as clean as they were before the work was performed.

• Large limbs and wood that is not chipped shall be hauled away.

• Please provide line clearance trimming as a cost per road for the list of roads on page 9.

• Technical Point of Contact for WBMLP is David Renzetti, General Foreman, West

Boylston Municipal Light Plant, 4 Crescent Street, West Boylston, MA 0183, Cell Phone:

508-425-0178, drenzetti@wbmlp.org.

• Pre-bid discussions are available by phone with WBMLP’s Technical Point of Contact to discuss any questions for up to three (3) days prior to Bid Opening. All questions and answers will be shared with interested bidders.

mailto:drenzetti@wbmlp.org

TECHNICAL SPECIFICATIONS

Tree Trimming Clearance Area

A 20-foot area (Zone A) that is measured 10 feet out from each side of the pole line.

Zone A Vegetation Management

• Any tree 8 inches and under in diameter (Measured 5’ up the trunk), that is growing within 10 feet on either side of the pole line (zone A), shall be removed during the vegetation management cycle.

• Trees not subject to removal shall be trimmed in such a manner to achieve a five-year

"no contact" period with the WBMLP electric system.

• Trees shall be trimmed to establish a vertical clearance of 20 feet over the WBMLP electric system to account for ice, snow and wind load.

• Do not trim or remove decorative trees within Zone A. Please contact WBMLP’s

Technical Point of Contact to meet on -site and discuss decorative tree trimming and removals first

• High risk trees over 8 inches in diameter that are endangering WBMLP’s electric distribution system shall be reported to WBMLP for approval and separate pricing to remove.

Zone B Vegetation Management

• Trees growing in Zone B but encroaching into Zone A, shall be trimmed back to the trunk or a major limb.

• Any trees 8 inches and under in diameter, as identified by WBMLP to be high risk, shall be removed.

• High risk trees over 8 inches in diameter that are endangering WBMLP’s electric distribution system shall be reported to WBMLP for approval and separate pricing to remove.

LIST OF ROADS FOR LINE CLEARANCE

R O

A D

N A

M E

STA

R

T P O

LE #

EN

D P

O

LE #

N U

M B

ER

O

F

SP

A

N S

P R

IM

A

R Y

V O

LTA

G

E

P O

LE C

O

N

STR

U C

TIO

N

C re sce n t Stre e t P

1 C re sce n t Stre e t P

33 C re sce n t Stre e t

13800/7970 Sp ace r/R id ge p in

C re sce n t Stre e t P

16 M ald e n

Stre e t P

43 C re se n ct Stre e t

7970/240 R id ge p in

/Se co n d ary rack

M ald e n

Stre e t P

25 G o o d ale Stre e t

P 44 M ald e n Stre e t

7970/240

R id ge p in /Se co n d ary rack

Lyn w o o d D rive P

30 C re sce n t Stre e t P

5 Lyn w o o d D rive

7970/240 R id ge p in

/Se co n d ary rack

P in e A rd e n D rive P

32 C re sce n t Stre e t P

16 P in e A rd e n D rive

R id ge p in

To w n se n d

D rive

P 5 P in e

A rd e n

D rive

P 16 P in e

A rd e n

D rive

7970/240

R id ge p in /Se co n d ary R ack

To w n se n d

C ircle

P 3 To w n se n d D rive P

3 To w n se n d

C ircle

7970/240

R id ge P in /Se co n d ary R ack

N o rth M ain Stre e t

P 1 N o rth

M ain

Stre e t P

39 N o rth M ain Stre e t

13800/7970

Sp ace r/R id ge p in

R e e d

Stre e t P

1 R e e d

Stre e t P

3 R e e d

Stre e t

Se co n d ary R acks

M ay Stre e t

P 1 N o rth

M ain

Stre e t P

6 M ay Stre e t

7970/240

R id ge p in /Se co n d ary R ack

P e arso n

Stre e t P

3 G re e n

Stre e t P

4 M ay Stre e t

Se co n d ary R ack

G re e n

Stre e t P

2 N o rth M ain Stre e t

P 4 M ay Stre e t

Se co n d ary R ack

K e ye s Stre e t

P 19 H o sm e r

P 1 K e ye s Stre e t

R id ge p in

H o sm e r Stre e t P

28 Lau re l Stre e t P

37 H o sm e r Stre e t

R id ge p in

H igh

Stre e t P

1 H igh

Stre e t P

11 H igh

Stre e t

7970/240 R id ge p in

/Se co n d ary rack

Fo ste r Stre e t P

8 H igh

Stre e t P

3 Fo ste r Stre e t

R id ge p in

Lau re l Stre e t P

7 N o rth M ain Stre e t

P 61 Lau re l Stre e t

13800/7970

A rm le ss/R id ge p in

R aym o n d H u n tin gto n H w y.

P 58 Lau re l Stre e t

P 26 R aym o n d

H u n tin gto n

H w y.

R id ge

P in

W

EST B

O Y

LSTO

N

TR

EE TR

IM

M

IN

G

/V

EG

ETA

TIO

N M

A N

A G

EM

EN

T C Y

C

LE 2

BID: Please submit bids in this format on your company letterhead.

Date:

Jonathan V. Fitch

General Manager

West Boylston Municipal Light Plant

4 Crescent Street

West Boylston, MA 01583

RE: IFB 26-0001, BID PROPOSAL FOR 2026 TREE-TRIMMING (LINE CLEARANCE).

Dear Mr. Fitch, We the undersigned, doing business as (please insert your company name here) and hereinafter known as the Bidder hereby propose to perform in accordance with IFB 26-0001 to furnish Tree

Trimming (Line Clearance) as specified below to WBMLP. We also understand WBMLP reserves the right to reject any bid.

Total Bid Price:_______________________

Company Name and company contact.

ROAD NAME Estimated Days to trim Cost per road

Crescent Street

Crescent Street

Malden Street

Lynwood Drive

Pine Arden Drive

Townsend Drive

Townsend Circle

North Main Street

Reed Street

May Street

Pearson Street

Green Street

Keyes Street

Hosmer Street

High Street

Foster Street

Laurel Street

Raymond Huntington Hwy.

Certificate of Good Faith (Per M.G.L. Chapter 30 B, Section 10)

The undersigned certifies under penalties of perjury that this bid, or proposal has been made and submitted in good faith and without collusion or fraud with any other person. As used in this certification, the word "person" shall mean any natural person, business, partnership, corporation, union, committee, club, or other organization, entity, or group of individuals.

(Signature of individual submitting bid or proposal)

(Name of business)

THE COMMONWEALTH OF MASSACHUSETTS

EXECUTIVE OFFICE OF LABOR AND WORKFORCE DEVELOPMENT

DEPARTMENT OF LABOR STANDARDS

Prevailing Wage Rates

MAURA HEALEY

Governor

KIM DRISCOLL

Lt. Governor

As determined by the Director under the provisions of the Massachusetts General Laws, Chapter 149, Sections 26 to 27H

LAUREN JONES

Secretary

MICHAEL FLANAGAN

Director

Awarding Authority: West Boylston - Municipal Light Plant City/Town: WEST BOYLSTON

Contract Number: 26-011

Description of Work: Perform tree trimming around overhead electrical distribution lines along (17) roads in West Boylston.

Job Location: 4 Crescent Street, West Boylston MA 01583

Information about Prevailing Wage Schedules for Awarding Authorities and Contractors

The wage rates will remain in effect for the duration of the project, except in the case of multi-year public construction projects. For construction projects lasting longer than one year, awarding authorities must request an updated wage schedule no later than two weeks before the anniversary of the date the contract was executed by the awarding authority and the general contractor. For multi-year CM AT RISK projects, the awarding authority must request an annual update no later than two weeks before the anniversary date, determined as the earlier of: (a) the execution date of the GMP Amendment, or (b) the execution date of the first amendment to permit procurement of construction services. The updated wage schedule must be provided to all contractors, including general and sub-contractors, working on the construction project.

This annual update requirement is generally not applicable to 27F “rental of equipment” contracts. For such contracts, the prevailing wage rates issued by DLS shall remain in effect for the duration of the contract term. However, if the prevailing wage rate sheet issued does not contain wage rates for each year covered by the contract term, the Awarding Authority must request updated rate sheets from DLS and provide them to the contractor to ensure the correct rates are being paid throughout the duration of the contract. Additionally, if an Awarding Authority exercises an option to renew or extend the contract term, they must request updated rate sheets form DLS and provide them to the contractor.

This wage schedule applies only to the specific project referenced at the top of this page and uniquely identified by the “Wage Request Number” on all pages of this schedule.

An Awarding Authority must request an updated wage schedule if it has not opened bids or selected a contractor within 90 days of the date of issuance of the wage schedule. For CM AT RISK projects (bid pursuant to G.L. c.149A), the earlier of: (a) the execution date of the GMP Amendment, or (b) the bid for the first construction scope of work must be within 90-days of the wage schedule issuance date.

The wage schedule shall be incorporated in any advertisement or call for bids for the project as required by M.G.L. c. 149, § 27. The wage schedule shall be made a part of the contract awarded for the project. The wage schedule must be posted in a conspicuous place at the work site for the life of the project in accordance with M.G.L. c. 149 § 27. The wages listed on the wage schedule must be paid to employees performing construction work on the project whether they are employed by the prime contractor, a filed sub-bidder, or a sub-contractor.

Apprentices working on the project are required to be registered with the Massachusetts Division of Apprentice Standards (DAS). Apprentices must keep their apprentice identification card on their persons during all work hours on the project. An apprentice registered with DAS may be paid the lower apprentice wage rate at the applicable step as provided on the prevailing wage schedule. Any apprentice not registered with DAS regardless of whether they are registered with another federal, state, local, or private agency must be paid the journeyworker's rate.

Every contractor or subcontractor working on the construction project must submit weekly payroll reports and a Statement of Compliance directly to the awarding authority by mail or email and keep them on file for three years. Each weekly payroll report must contain: the employee’s name, address, occupational classification, hours worked, and wages paid. Do not submit weekly payroll reports to DLS. For a sample payroll reporting form go to http://www.mass.gov/dols/pw.

Contractors with questions about the wage rates or classifications included on the wage schedule have an affirmative obligation to inquire with DLS at (617)

626-6953.

Contractors must obtain the wage schedules from awarding authorities. Failure of a contractor or subcontractor to pay the prevailing wage rates listed on the wage schedule to all employees who perform construction work on the project is a violation of the law and subjects the contractor or subcontractor to civil and criminal penalties.

Employees not receiving the prevailing wage rate set forth on the wage schedule may file a complaint with the Fair Labor Division of the office of the Attorney

General at (617) 727-3465.

Page 1 of 37Wage Request Number: 20260701110359Issue Date: 07/01/2026

Construction

Classification Effective Date Base Wage Health Pension Annuity Supplemental

Unemployment Total Rate

6/1/2026 $41.95 $16.17 $21.78 $0.00 $0.00 $79.90

6/1/2026 $41.95 $16.17 $21.78 $0.00 $0.00 $79.90

12/1/2026 $41.95 $16.17 $23.52 $0.00 $0.00 $81.64

12/1/2026 $41.95 $16.17 $23.52 $0.00 $0.00 $81.64

1/1/2027 $41.95 $16.77 $23.52 $0.00 $0.00 $82.24

(2 AXLE) DRIVER - EQUIPMENT

TEAMSTERS JOINT COUNCIL NO. 10

TEAMSTERS JOINT COUNCIL NO. 10 ZONE B

1/1/2027 $41.95 $16.77 $23.52 $0.00 $0.00 $82.24

6/1/2026 $42.02 $16.17 $21.78 $0.00 $0.00 $79.97

6/1/2026 $42.02 $16.17 $21.78 $0.00 $0.00 $79.97

12/1/2026 $42.02 $16.17 $23.52 $0.00 $0.00 $81.71

12/1/2026 $42.02 $16.17 $23.52 $0.00 $0.00 $81.71

1/1/2027 $42.02 $16.77 $23.52 $0.00 $0.00 $82.31

(3 AXLE) DRIVER - EQUIPMENT

TEAMSTERS JOINT COUNCIL NO. 10

TEAMSTERS JOINT COUNCIL NO. 10 ZONE B

1/1/2027 $42.02 $16.77 $23.52 $0.00 $0.00 $82.31

6/1/2026 $42.14 $16.17 $21.78 $0.00 $0.00 $80.09

6/1/2026 $42.14 $16.17 $21.78 $0.00 $0.00 $80.09

12/1/2026 $42.14 $16.17 $23.52 $0.00 $0.00 $81.83

12/1/2026 $42.14 $16.17 $23.52 $0.00 $0.00 $81.83

1/1/2027 $42.14 $16.77 $23.52 $0.00 $0.00 $82.43

(4 & 5 AXLE) DRIVER - EQUIPMENT

TEAMSTERS JOINT COUNCIL NO. 10

TEAMSTERS JOINT COUNCIL NO. 10 ZONE B

1/1/2027 $42.14 $16.77 $23.52 $0.00 $0.00 $82.43

8/1/2024 $117.16 $10.08 $11.62 $12.67 $0.00 $151.53ADS/SUBMERSIBLE PILOT

PILE DRIVER LOCAL 56

PILE DRIVER LOCAL 56 (ZONE 2)

8/1/2024 $117.16 $10.08 $11.62 $12.67 $0.00 $151.53

For apprentice rates see "Apprentice- PILE DRIVER"

6/1/2026 $42.41 $10.90 $9.75 $9.11 $0.00 $72.17

12/1/2026 $43.85 $10.90 $9.75 $9.11 $0.00 $73.61

6/1/2027 $45.30 $10.90 $9.75 $9.11 $0.00 $75.06

12/1/2027 $46.75 $10.90 $9.75 $9.11 $0.00 $76.51

6/1/2028 $48.25 $10.90 $9.75 $9.11 $0.00 $78.01

AIR TRACK OPERATOR

LABORERS

LABORERS - ZONE 2

12/1/2028 $49.75 $10.90 $9.75 $9.11 $0.00 $79.51

For apprentice rates see "Apprentice- LABORER"

6/1/2026 $42.41 $10.90 $9.75 $9.21 $0.00 $72.27AIR TRACK OPERATOR (HEAVY & HIGHWAY)

LABORERS

LABORERS - ZONE 2 (HEAVY & HIGHWAY)

12/1/2026 $43.85 $10.90 $9.75 $9.21 $0.00 $73.71

For apprentice rates see "Apprentice- LABORER (Heavy and Highway)

ASBESTOS WORKER (PIPES & TANKS)

HEAT & FROST INSULATORS LOCAL 6

HEAT & FROST INSULATORS LOCAL 6 (WORCESTER)

12/1/2025 $44.80 $14.50 $4.30 $6.75 $0.00 $70.35

6/1/2026 $41.91 $10.90 $9.75 $9.11 $0.00 $71.67

12/1/2026 $43.35 $10.90 $9.75 $9.11 $0.00 $73.11

6/1/2027 $44.80 $10.90 $9.75 $9.11 $0.00 $74.56

12/1/2027 $46.25 $10.90 $9.75 $9.11 $0.00 $76.01

6/1/2028 $47.75 $10.90 $9.75 $9.11 $0.00 $77.51

ASPHALT RAKER

LABORERS

LABORERS - ZONE 2

12/1/2028 $49.25 $10.90 $9.75 $9.11 $0.00 $79.01

For apprentice rates see "Apprentice- LABORER"

Page 2 of 37Wage Request Number: 20260701110359Issue Date: 07/01/2026

Supplemental

Unemployment Total Rate

6/1/2026 $41.91 $10.90 $9.75 $9.21 $0.00 $71.77ASPHALT RAKER (HEAVY & HIGHWAY)

LABORERS

LABORERS - ZONE 2 (HEAVY & HIGHWAY)

12/1/2026 $43.35 $10.90 $9.75 $9.21 $0.00 $73.21

For apprentice rates see "Apprentice- LABORER (Heavy and Highway)

6/1/2026 $59.38 $17.05 $13.35 $3.25 $0.00 $93.03

6/1/2026 $59.38 $17.05 $13.35 $3.25 $0.00 $93.03

12/1/2026 $60.83 $17.05 $13.35 $3.25 $0.00 $94.48

ASPHALT/CONCRETE/CRUSHER PLANT-ON SITE

OPERATING ENGINEERS LOCAL 4

OPERATING ENGINEERS LOCAL 4

12/1/2026 $60.83 $17.05 $13.35 $3.25 $0.00 $94.48

For apprentice rates see "Apprentice- OPERATING ENGINEERS"

6/1/2026 $59.38 $17.05 $13.35 $3.25 $0.00 $93.03

6/1/2026 $59.38 $17.05 $13.35 $3.25 $0.00 $93.03

12/1/2026 $60.83 $17.05 $13.35 $3.25 $0.00 $94.48

BACKHOE/FRONT-END LOADER

OPERATING ENGINEERS LOCAL 4

OPERATING ENGINEERS LOCAL 4

12/1/2026 $60.83 $17.05 $13.35 $3.25 $0.00 $94.48

For apprentice rates see "Apprentice- OPERATING ENGINEERS"

6/1/2026 $41.91 $10.90 $9.75 $9.11 $0.00 $71.67

12/1/2026 $43.35 $10.90 $9.75 $9.11 $0.00 $73.11

6/1/2027 $44.80 $10.90 $9.75 $9.11 $0.00 $74.56

12/1/2027 $46.25 $10.90 $9.75 $9.11 $0.00 $76.01

6/1/2028 $47.75 $10.90 $9.75 $9.11 $0.00 $77.51

BARCO-TYPE JUMPING TAMPER

LABORERS

LABORERS - ZONE 2

12/1/2028 $49.25 $10.90 $9.75 $9.11 $0.00 $79.01

For apprentice rates see "Apprentice- LABORER"

6/1/2026 $42.41 $10.90 $9.75 $9.11 $0.00 $72.17

12/1/2026 $43.85 $10.90 $9.75 $9.11 $0.00 $73.61

6/1/2027 $45.30 $10.90 $9.75 $9.11 $0.00 $75.06

12/1/2027 $46.75 $10.90 $9.75 $9.11 $0.00 $76.51

6/1/2028 $48.25 $10.90 $9.75 $9.11 $0.00 $78.01

BLOCK PAVER, RAMMER / CURB SETTER

LABORERS

LABORERS - ZONE 2

12/1/2028 $49.75 $10.90 $9.75 $9.11 $0.00 $79.51

For apprentice rates see "Apprentice- LABORER"

6/1/2026 $42.41 $10.90 $9.75 $9.21 $0.00 $72.27BLOCK PAVER, RAMMER / CURB SETTER (HEAVY &

HIGHWAY)

LABORERS

LABORERS - ZONE 2 (HEAVY & HIGHWAY)

12/1/2026 $43.85 $10.90 $9.75 $9.21 $0.00 $73.71

For apprentice rates see "Apprentice- LABORER (Heavy and Highway)

BOILER MAKER

BOILERMAKERS LOCAL 29

BOILERMAKERS LOCAL 29

1/1/2024 $48.12 $7.07 $14.60 $6.00 $0.00 $75.79

Apprentice: BOILER MAKER

Effective Date: 1/1/2024

Step Percent Apprentice Base Wage Health Pension Annuity

Supplemental Unemployment

Total Rate

1 65.00 $31.28 $7.07 $9.32 $3.90 $0.00 $51.57

2 65.00 $31.28 $7.07 $9.32 $3.90 $0.00 $51.57

3 70.00 $33.68 $7.07 $10.03 $4.20 $0.00 $54.98

Page 3 of 37Wage Request Number: 20260701110359Issue Date: 07/01/2026

Supplemental

Unemployment Total Rate

2/1/2026 $65.81 $12.84 $15.57 $7.33 $0.00 $101.55

8/1/2026 $68.01 $12.84 $15.57 $7.33 $0.00 $103.75

BRICK/STONE/ARTIFICIAL MASONRY (INCL. MASONRY

WATERPROOFING)

BRICKLAYERS LOCAL 3

BRICKLAYERS LOCAL 3 (WORCESTER) 2/1/2027 $69.41 $12.84 $15.57 $7.33 $0.00 $105.15

6/1/2026 $58.70 $17.05 $13.35 $3.25 $0.00 $92.35

6/1/2026 $58.70 $17.05 $13.35 $3.25 $0.00 $92.35

12/1/2026 $60.14 $17.05 $13.35 $3.25 $0.00 $93.79

BULLDOZER/GRADER/SCRAPER

OPERATING ENGINEERS LOCAL 4

OPERATING ENGINEERS LOCAL 4

12/1/2026 $60.14 $17.05 $13.35 $3.25 $0.00 $93.79

For apprentice rates see "Apprentice- OPERATING ENGINEERS"

6/1/2026 $50.40 $10.90 $9.75 $9.80 $0.00 $80.85CAISSON & UNDERPINNING BOTTOM MAN

LABORERS

LABORERS - FOUNDATION AND MARINE

12/1/2026 $51.90 $10.90 $9.75 $9.80 $0.00 $82.35

Apprentice: BOILER MAKER

Effective Date: 1/1/2024

Step Percent Apprentice Base Wage Health Pension Annuity

Supplemental Unemployment

Total Rate

4 75.00 $36.09 $7.07 $10.74 $4.50 $0.00 $58.40

5 80.00 $38.50 $7.07 $11.45 $4.80 $0.00 $61.82

6 85.00 $40.90 $7.07 $12.18 $5.10 $0.00 $65.25

7 90.00 $43.31 $7.07 $12.88 $5.40 $0.00 $68.66

8 95.00 $45.71 $7.07 $13.62 $5.70 $0.00 $72.10

Apprentice to Journeyworker Ratio: 1:4

Apprentice: BRICK/STONE/ARTIFICIAL MASONRY (INCL. MASONRY WATERPROOFING)

Effective Date: 2/1/2026

Step Percent Apprentice Base Wage Health Pension Annuity

Supplemental Unemployment

Total Rate

1 50.00 $32.91 $12.84 $15.57 $7.33 $0.00 $68.65

2 60.00 $39.49 $12.84 $15.57 $7.33 $0.00 $75.23

3 70.00 $46.07 $12.84 $15.57 $7.33 $0.00 $81.81

4 80.00 $52.65 $12.84 $15.57 $7.33 $0.00 $88.39

5 90.00 $59.23 $12.84 $15.57 $7.33 $0.00 $94.97

Apprentice: BRICK/STONE/ARTIFICIAL MASONRY (INCL. MASONRY WATERPROOFING)

Effective Date: 8/1/2026

Step Percent Apprentice Base Wage Health Pension Annuity

Supplemental Unemployment

Total Rate

1 50.00 $34.01 $12.84 $15.57 $7.33 $0.00 $69.75

2 60.00 $40.81 $12.84 $15.57 $7.33 $0.00 $76.55

3 70.00 $47.61 $12.84 $15.57 $7.33 $0.00 $83.35

4 80.00 $54.41 $12.84 $15.57 $7.33 $0.00 $90.15

5 90.00 $61.21 $12.84 $15.57 $7.33 $0.00 $96.95

Apprentice to Journeyworker Ratio: 1:5

Page 4 of 37Wage Request Number: 20260701110359Issue Date: 07/01/2026

Supplemental

Unemployment Total Rate

For apprentice rates see "Apprentice- LABORER"

6/1/2026 $49.25 $10.90 $9.75 $9.80 $0.00 $79.70CAISSON & UNDERPINNING LABORER

LABORERS

LABORERS - FOUNDATION AND MARINE

12/1/2026 $50.75 $10.90 $9.75 $9.80 $0.00 $81.20

For apprentice rates see "Apprentice- LABORER"

6/1/2026 $49.58 $10.90 $9.75 $9.80 $0.00 $80.03CAISSON & UNDERPINNING TOP MAN

LABORERS

LABORERS - FOUNDATION AND MARINE

12/1/2026 $51.08 $10.90 $9.75 $9.80 $0.00 $81.53

For apprentice rates see "Apprentice- LABORER"

6/1/2026 $41.91 $10.90 $9.75 $9.11 $0.00 $71.67

12/1/2026 $43.35 $10.90 $9.75 $9.11 $0.00 $73.11

6/1/2027 $44.80 $10.90 $9.75 $9.11 $0.00 $74.56

12/1/2027 $46.25 $10.90 $9.75 $9.11 $0.00 $76.01

6/1/2028 $47.75 $10.90 $9.75 $9.11 $0.00 $77.51

CARBIDE CORE DRILL OPERATOR

LABORERS

LABORERS - ZONE 2

12/1/2028 $49.25 $10.90 $9.75 $9.11 $0.00 $79.01

For apprentice rates see "Apprentice- LABORER"

3/1/2026 $50.85 $11.08 $11.47 $8.50 $0.00 $81.90

9/1/2026 $52.10 $11.08 $11.47 $8.50 $0.00 $83.15

CARPENTER

CARPENTERS

CARPENTERS -ZONE 2 (Eastern Massachusetts) 3/1/2027 $53.35 $11.08 $11.47 $8.50 $0.00 $84.40

Apprentice: CARPENTER

Effective Date: 3/1/2026

Step Percent Apprentice Base Wage Health Pension Annuity

Supplemental Unemployment

Total Rate

1 45.00 $22.88 $11.08 $0.00 $1.73 $0.00 $35.69

2 45.00 $22.88 $11.08 $0.00 $1.73 $0.00 $35.69

3 55.00 $27.97 $11.08 $0.00 $3.40 $0.00 $42.45

4 55.00 $27.97 $11.08 $0.00 $3.40 $0.00 $42.45

5 70.00 $35.60 $11.08 $11.41 $5.10 $0.00 $63.19

6 70.00 $35.60 $11.08 $11.41 $5.10 $0.00 $63.19

7 80.00 $40.68 $11.08 $11.44 $6.80 $0.00 $70.00

8 80.00 $40.68 $11.08 $11.44 $6.80 $0.00 $70.00

Apprentice: CARPENTER

Effective Date: 9/1/2026

Step Percent Apprentice Base Wage Health Pension Annuity

Supplemental Unemployment

Total Rate

1 45.00 $23.45 $11.08 $0.00 $1.73 $0.00 $36.26

2 45.00 $23.45 $11.08 $0.00 $1.73 $0.00 $36.26

3 55.00 $28.66 $11.08 $0.00 $3.40 $0.00 $43.14

4 55.00 $28.66 $11.08 $0.00 $3.40 $0.00 $43.14

5 70.00 $36.47 $11.08 $11.41 $5.10 $0.00 $64.06

6 70.00 $36.47 $11.08 $11.41 $5.10 $0.00 $64.06

7 80.00 $41.68 $11.08 $11.44 $6.80 $0.00 $71.00

Page 5 of 37Wage Request Number: 20260701110359Issue Date: 07/01/2026

Supplemental

Unemployment Total Rate

10/1/2025 $27.37 $7.38 $4.47 $1.00 $0.00 $40.22CARPENTER WOOD FRAME

CARPENTERS

CARPENTERS-ZONE 3 (Wood Frame) 10/1/2026 $28.47 $7.38 $4.47 $1.00 $0.00 $41.32

All Aspects of New Wood Frame Work

7/1/2026 $54.49 $13.35 $16.43 $7.78 $1.80 $93.85

1/1/2027 $55.94 $13.35 $16.43 $7.78 $1.80 $95.30

7/1/2027 $57.29 $13.35 $16.43 $7.78 $1.80 $96.65

CEMENT MASONRY/PLASTERING

PLASTERERS AND CEMENT MASONS LOCAL 534

Plasterers and Cement Masons - Zone 1

1/1/2028 $58.64 $13.35 $16.43 $7.78 $1.80 $98.00

Apprentice: CARPENTER

Effective Date: 9/1/2026

Step Percent Apprentice Base Wage Health Pension Annuity

Supplemental Unemployment

Total Rate

8 80.00 $41.68 $11.08 $11.44 $6.80 $0.00 $71.00

Apprentice to Journeyworker Ratio: 1:5

Apprentice: CARPENTER WOOD FRAME

Effective Date: 10/1/2025

Step Percent Apprentice Base Wage Health Pension Annuity

Supplemental Unemployment

Total Rate

1 60.00 $16.42 $7.38 $0.00 $0.00 $0.00 $23.80

2 60.00 $16.42 $7.38 $0.00 $0.00 $0.00 $23.80

3 65.00 $17.79 $7.38 $0.00 $1.00 $0.00 $26.17

4 70.00 $19.16 $7.38 $0.00 $1.00 $0.00 $27.54

5 75.00 $20.53 $7.38 $3.80 $1.00 $0.00 $32.71

6 80.00 $21.90 $7.38 $3.80 $1.00 $0.00 $34.08

7 85.00 $23.26 $7.38 $3.80 $1.00 $0.00 $35.44

8 90.00 $24.63 $7.38 $3.80 $1.00 $0.00 $36.81

Apprentice: CARPENTER WOOD FRAME

Effective Date: 10/1/2026

Step Percent Apprentice Base Wage Health Pension Annuity

Supplemental Unemployment

Total Rate

1 60.00 $17.08 $7.38 $0.00 $0.00 $0.00 $24.46

2 60.00 $17.08 $7.38 $0.00 $0.00 $0.00 $24.46

3 65.00 $18.51 $7.38 $0.00 $1.00 $0.00 $26.89

4 70.00 $19.93 $7.38 $0.00 $1.00 $0.00 $28.31

5 75.00 $21.35 $7.38 $3.80 $1.00 $0.00 $33.53

6 80.00 $22.78 $7.38 $3.80 $1.00 $0.00 $34.96

7 85.00 $24.20 $7.38 $3.80 $1.00 $0.00 $36.38

8 90.00 $25.62 $7.38 $3.80 $1.00 $0.00 $37.80

Page 6 of 37Wage Request Number: 20260701110359Issue Date: 07/01/2026

Supplemental

Unemployment Total Rate

6/1/2026 $41.91 $10.90 $9.75 $9.11 $0.00 $71.67

12/1/2026 $43.35 $10.90 $9.75 $9.11 $0.00 $73.11

6/1/2027 $44.80 $10.90 $9.75 $9.11 $0.00 $74.56

12/1/2027 $46.25 $10.90 $9.75 $9.11 $0.00 $76.01

6/1/2028 $47.75 $10.90 $9.75 $9.11 $0.00 $77.51

CHAIN SAW OPERATOR

LABORERS

LABORERS - ZONE 2

12/1/2028 $49.25 $10.90 $9.75 $9.11 $0.00 $79.01

For apprentice rates see "Apprentice- LABORER"

6/1/2026 $60.61 $17.05 $13.35 $3.25 $0.00 $94.26

6/1/2026 $60.61 $17.05 $13.35 $3.25 $0.00 $94.26

12/1/2026 $62.09 $17.05 $13.35 $3.25 $0.00 $95.74

CLAM SHELLS/SLURRY BUCKETS/HEADING MACHINES

OPERATING ENGINEERS LOCAL 4

OPERATING ENGINEERS LOCAL 4

12/1/2026 $62.09 $17.05 $13.35 $3.25 $0.00 $95.74

For apprentice rates see "Apprentice- OPERATING ENGINEERS"

6/1/2026 $37.63 $17.05 $13.35 $3.25 $0.00 $71.28

6/1/2026 $37.63 $17.05 $13.35 $3.25 $0.00 $71.28

12/1/2026 $38.58 $17.05 $13.35 $3.25 $0.00 $72.23

COMPRESSOR OPERATOR

OPERATING ENGINEERS LOCAL 4

OPERATING ENGINEERS LOCAL 4

12/1/2026 $38.58 $17.05 $13.35 $3.25 $0.00 $72.23

For apprentice rates see "Apprentice- OPERATING ENGINEERS"

DELEADER (BRIDGE) 1/1/2026 $59.56 $10.35 $12.00 $12.60 $0.00 $94.51

Apprentice: CEMENT MASONRY/PLASTERING

Effective Date: 7/1/2026

Step Percent Apprentice Base Wage Health Pension Annuity

Supplemental Unemployment

Total Rate

1 50.00 $27.25 $13.35 $16.43 $0.00 $0.00 $57.03

2 60.00 $32.69 $13.35 $16.43 $7.78 $1.80 $72.05

3 65.00 $35.42 $13.35 $16.43 $7.78 $1.80 $74.78

4 70.00 $38.14 $13.35 $16.43 $7.78 $1.80 $77.50

5 75.00 $40.87 $13.35 $16.43 $7.78 $1.80 $80.23

6 80.00 $43.59 $13.35 $16.43 $7.78 $1.80 $82.95

7 90.00 $49.04 $13.35 $0.00 $7.78 $0.00 $70.17

Apprentice: CEMENT MASONRY/PLASTERING

Effective Date: 1/1/2027

Step Percent Apprentice Base Wage Health Pension Annuity

Supplemental Unemployment

Total Rate

1 50.00 $27.97 $13.35 $16.43 $0.00 $0.00 $57.75

2 60.00 $33.56 $13.35 $16.43 $7.78 $1.80 $72.92

3 65.00 $36.36 $13.35 $16.43 $7.78 $1.80 $75.72

4 70.00 $39.16 $13.35 $16.43 $7.78 $1.80 $78.52

5 75.00 $41.96 $13.35 $16.43 $7.78 $1.80 $81.32

6 80.00 $44.75 $13.35 $16.43 $7.78 $1.80 $84.11

7 90.00 $50.35 $0.00 $16.43 $0.00 $0.00 $66.78

Page 7 of 37Wage Request Number: 20260701110359Issue Date: 07/01/2026

Supplemental

Unemployment Total Rate

PAINTERS LOCAL 35

PAINTERS LOCAL 35 - ZONE 2

6/1/2026 $49.30 $10.90 $9.75 $9.65 $0.00 $79.60

12/7/2026 $50.80 $10.90 $9.75 $9.65 $0.00 $81.10

6/7/2027 $52.40 $10.90 $9.75 $9.65 $0.00 $82.70

12/6/2027 $54.00 $10.90 $9.75 $9.65 $0.00 $84.30

6/5/2028 $55.68 $10.90 $9.75 $9.65 $0.00 $85.98

DEMO: ADZEMAN

LABORERS

LABORERS - ZONE 2

12/4/2028 $57.35 $10.90 $9.75 $9.65 $0.00 $87.65

For apprentice rates see "Apprentice- LABORER"

6/1/2026 $50.30 $10.90 $9.75 $9.65 $0.00 $80.60

12/7/2026 $51.80 $10.90 $9.75 $9.65 $0.00 $82.10

6/7/2027 $53.40 $10.90 $9.75 $9.65 $0.00 $83.70

12/6/2027 $55.00 $10.90 $9.75 $9.65 $0.00 $85.30

6/5/2028 $56.68 $10.90 $9.75 $9.65 $0.00 $86.98

DEMO: BACKHOE/LOADER/HAMMER OPERATOR

LABORERS

LABORERS - ZONE 2

12/4/2028 $58.35 $10.90 $9.75 $9.65 $0.00 $88.65

For apprentice rates see "Apprentice- LABORER"

6/1/2026 $50.05 $10.90 $9.75 $9.65 $0.00 $80.35

12/7/2026 $51.55 $10.90 $9.75 $9.65 $0.00 $81.85

6/7/2027 $53.15 $10.90 $9.75 $9.65 $0.00 $83.45

12/6/2027 $54.75 $10.90 $9.75 $9.65 $0.00 $85.05

6/5/2028 $56.43 $10.90 $9.75 $9.65 $0.00 $86.73

DEMO: BURNERS

LABORERS

LABORERS - ZONE 2

12/4/2028 $58.10 $10.90 $9.75 $9.65 $0.00 $88.40

For apprentice rates see "Apprentice- LABORER"

6/1/2026 $50.30 $10.90 $9.75 $9.65 $0.00 $80.60

12/7/2026 $51.80 $10.90 $9.75 $9.65 $0.00 $82.10

6/7/2027 $53.40 $10.90 $9.75 $9.65 $0.00 $83.70

12/6/2027 $55.00 $10.90 $9.75 $9.65 $0.00 $85.30

6/5/2028 $56.68 $10.90 $9.75 $9.65 $0.00 $86.98

DEMO: CONCRETE CUTTER/SAWYER

LABORERS

LABORERS - ZONE 2

12/4/2028 $58.35 $10.90 $9.75 $9.65 $0.00 $88.65

For apprentice rates see "Apprentice- LABORER"

Apprentice: DELEADER (BRIDGE)

Effective Date: 1/1/2026

Step Percent Apprentice Base Wage Health Pension Annuity

Supplemental Unemployment

Total Rate

1 50.00 $29.78 $10.35 $0.00 $0.00 $0.00 $40.13

2 55.00 $32.76 $10.35 $0.00 $6.93 $0.00 $50.04

3 60.00 $35.74 $10.35 $0.00 $7.56 $0.00 $53.65

4 65.00 $38.71 $10.35 $0.00 $8.19 $0.00 $57.25

5 70.00 $41.69 $10.35 $12.00 $8.82 $0.00 $72.86

6 75.00 $44.67 $10.35 $12.00 $9.45 $0.00 $76.47

7 80.00 $47.65 $10.35 $12.00 $10.08 $0.00 $80.08

8 90.00 $53.60 $10.35 $12.00 $11.34 $0.00 $87.29

Apprentice to Journeyworker Ratio: 1:1

Page 8 of 37Wage Request Number: 20260701110359Issue Date: 07/01/2026

Supplemental

Unemployment Total Rate

6/1/2026 $50.05 $10.90 $9.75 $9.65 $0.00 $80.35

12/7/2026 $51.55 $10.90 $9.75 $9.65 $0.00 $81.85

6/7/2027 $53.15 $10.90 $9.75 $9.65 $0.00 $83.45

12/6/2027 $54.75 $10.90 $9.75 $9.65 $0.00 $85.05

6/5/2028 $56.43 $10.90 $9.75 $9.65 $0.00 $86.73

DEMO: JACKHAMMER OPERATOR

LABORERS

LABORERS - ZONE 2

12/4/2028 $58.10 $10.90 $9.75 $9.65 $0.00 $88.40

For apprentice rates see "Apprentice- LABORER"

6/1/2026 $49.30 $10.90 $9.75 $9.65 $0.00 $79.60

12/7/2026 $50.80 $10.90 $9.75 $9.65 $0.00 $81.10

6/7/2027 $52.40 $10.90 $9.75 $9.65 $0.00 $82.70

12/6/2027 $54.00 $10.90 $9.75 $9.65 $0.00 $84.30

6/5/2028 $55.68 $10.90 $9.75 $9.65 $0.00 $85.98

DEMO: WRECKING LABORER

LABORERS

LABORERS - ZONE 2

12/4/2028 $57.35 $10.90 $9.75 $9.65 $0.00 $87.65

For apprentice rates see "Apprentice- LABORER"

6/1/2026 $58.70 $17.05 $13.35 $3.25 $0.00 $92.35DIRECTIONAL DRILL MACHINE OPERATOR

OPERATING ENGINEERS LOCAL 4

OPERATING ENGINEERS LOCAL 4

12/1/2026 $60.14 $17.05 $13.35 $3.25 $0.00 $93.79

For apprentice rates see "Apprentice- OPERATING ENGINEERS"

8/1/2024 $78.11 $10.08 $11.62 $12.67 $0.00 $112.48DIVER

PILE DRIVER LOCAL 56

PILE DRIVER LOCAL 56 (ZONE 2)

8/1/2024 $78.11 $10.08 $11.62 $12.67 $0.00 $112.48 as of 8-1-24, Apprentices with diving licenses begin at second year. % of Diver wage 70/80/90 2A $69.83, 3A $91.79,4A $102.14 Total Rate

8/1/2024 $51.97 $10.08 $11.62 $12.67 $0.00 $86.34DIVER TENDER

PILE DRIVER LOCAL 56

PILE DRIVER LOCAL 56 (ZONE 2)

8/1/2024 $51.97 $10.08 $11.62 $12.67 $0.00 $86.34 as of 8-1-24, Apprentices with diving licenses begin at second year. % of Piledriver wage 70/80/90 2A $54.20, 3A $73.93,4A $82.05 Total Rate

8/1/2024 $83.69 $10.08 $11.62 $12.67 $0.00 $118.06DIVER TENDER (EFFLUENT)

PILE DRIVER LOCAL 56

PILE DRIVER LOCAL 56 (ZONE 2)

8/1/2024 $83.69 $10.08 $11.62 $12.67 $0.00 $118.06

For apprentice rates see "Apprentice- PILE DRIVER"

8/1/2024 $117.16 $10.08 $11.62 $12.67 $0.00 $151.53DIVER/SLURRY (EFFLUENT)

PILE DRIVER LOCAL 56

PILE DRIVER LOCAL 56 (ZONE 2)

8/1/2024 $117.16 $10.08 $11.62 $12.67 $0.00 $151.53

For apprentice rates see "Apprentice- PILE DRIVER"

DRAWBRIDGE OPERATOR (Construction)

DRAWBRIDGE - SEIU LOCAL 888

DRAWBRIDGE - SEIU LOCAL 888

7/1/2020 $26.77 $6.67 $3.93 $0.00 $0.16 $37.53

9/7/2025 $48.16 $14.98 $14.30 $5.30 $0.00 $82.74ELECTRICIAN

ELECTRICIANS LOCAL 96

ELECTRICIANS LOCAL 96

9/6/2026 $49.38 $15.96 $14.57 $5.43 $0.00 $85.34

Page 9 of 37Wage Request Number: 20260701110359Issue Date: 07/01/2026

Supplemental

Unemployment Total Rate

1/1/2026 $69.23 $16.38 $11.06 $10.70 $0.00 $107.37ELEVATOR CONSTRUCTOR

ELEVATOR CONSTRUCTORS LOCAL 41

ELEVATOR CONSTRUCTORS LOCAL 41

1/1/2027 $72.23 $16.48 $11.16 $11.00 $0.00 $110.87

Apprentice: ELECTRICIAN

Effective Date: 9/7/2025

Step Percent Apprentice Base Wage Health Pension Annuity

Supplemental Unemployment

Total Rate

1 40.00 $19.26 $14.98 $0.58 $0.00 $0.00 $34.82

2 45.00 $21.67 $14.98 $0.65 $0.00 $0.00 $37.30

3 48.00 $23.12 $14.98 $13.55 $2.54 $0.00 $54.19

4 55.00 $26.49 $14.98 $13.65 $2.92 $0.00 $58.04

5 65.00 $31.30 $14.98 $13.80 $3.45 $0.00 $63.53

6 80.00 $38.53 $14.98 $14.02 $4.24 $0.00 $71.77

Apprentice: ELECTRICIAN

Effective Date: 9/6/2026

Step Percent Apprentice Base Wage Health Pension Annuity

Supplemental Unemployment

Total Rate

1 40.00 $19.75 $15.96 $0.59 $0.00 $0.00 $36.30

2 45.00 $22.22 $15.96 $0.67 $0.00 $0.00 $38.85

3 48.00 $23.70 $15.96 $13.80 $2.61 $0.00 $56.07

4 55.00 $27.16 $15.96 $13.90 $2.99 $0.00 $60.01

5 65.00 $32.10 $15.96 $14.05 $3.53 $0.00 $65.64

6 80.00 $39.50 $15.96 $14.28 $4.35 $0.00 $74.09

Apprentice to Journeyworker Ratio: 2:3

Apprentice: ELEVATOR CONSTRUCTOR

Effective Date: 1/1/2026

Step Percent Apprentice Base Wage Health Pension Annuity

Supplemental Unemployment

Total Rate

1 50.00 $34.62 $16.38 $0.00 $0.00 $0.00 $51.00

2 55.00 $38.08 $16.38 $11.06 $10.70 $0.00 $76.22

3 65.00 $45.00 $16.38 $11.06 $10.70 $0.00 $83.14

4 70.00 $48.46 $16.38 $11.06 $10.70 $0.00 $86.60

5 80.00 $55.38 $16.38 $11.06 $10.70 $0.00 $93.52

Apprentice: ELEVATOR CONSTRUCTOR

Effective Date: 1/1/2027

Step Percent Apprentice Base Wage Health Pension Annuity

Supplemental Unemployment

Total Rate

1 50.00 $36.12 $16.48 $0.00 $0.00 $0.00 $52.60

2 55.00 $39.73 $16.48 $11.16 $11.00 $0.00 $78.37

3 65.00 $46.95 $16.48 $11.16 $11.00 $0.00 $85.59

Page 10 of 37Wage Request Number: 20260701110359Issue Date: 07/01/2026

Supplemental

Unemployment Total Rate

1/1/2026 $48.46 $16.38 $11.06 $10.70 $0.00 $86.60ELEVATOR CONSTRUCTOR HELPER

ELEVATOR CONSTRUCTORS LOCAL 41

ELEVATOR CONSTRUCTORS LOCAL 41

1/1/2027 $50.56 $16.48 $11.16 $11.00 $0.00 $89.20

For apprentice rates see "Apprentice - ELEVATOR CONSTRUCTOR"

6/1/2026 $41.91 $10.90 $9.75 $9.21 $0.00 $71.77FENCE & GUARD RAIL ERECTOR (HEAVY & HIGHWAY)

LABORERS

LABORERS - ZONE 2 (HEAVY & HIGHWAY)

12/1/2026 $43.35 $10.90 $9.75 $9.21 $0.00 $73.21

For apprentice rates see "Apprentice- LABORER (Heavy and Highway)

5/1/2026 $54.40 $16.55 $13.35 $3.25 $0.00 $87.55

11/1/2026 $55.69 $16.55 $13.35 $3.25 $0.00 $88.84

FIELD ENG.INST.PERSON-BLDG,SITE,HVY/HWY

OPERATING ENGINEERS LOCAL 4

OPERATING ENGINEERS LOCAL 4

5/1/2027 $57.12 $16.55 $13.35 $3.25 $0.00 $90.27

For apprentice rates see "Apprentice- OPERATING ENGINEERS"

5/1/2026 $56.02 $16.55 $13.35 $3.25 $0.00 $89.17

11/1/2026 $57.32 $16.55 $13.35 $3.25 $0.00 $90.47

FIELD ENG.PARTY CHIEF-BLDG,SITE,HVY/HWY

OPERATING ENGINEERS LOCAL 4

OPERATING ENGINEERS LOCAL 4

5/1/2027 $58.77 $16.55 $13.35 $3.25 $0.00 $91.92

For apprentice rates see "Apprentice- OPERATING ENGINEERS"

5/1/2026 $26.28 $16.55 $13.35 $3.25 $0.00 $59.43

11/1/2026 $27.04 $16.55 $13.35 $3.25 $0.00 $60.19

FIELD ENG.ROD PERSON-BLDG,SITE,HVY/HWY

OPERATING ENGINEERS LOCAL 4

OPERATING ENGINEERS LOCAL 4

5/1/2027 $27.89 $16.55 $13.35 $3.25 $0.00 $61.04

For apprentice rates see "Apprentice- OPERATING ENGINEERS"

9/7/2025 $48.16 $14.98 $14.30 $5.30 $0.00 $82.74FIRE ALARM INSTALLER

ELECTRICIANS LOCAL 96

ELECTRICIANS LOCAL 96

9/6/2026 $49.38 $15.96 $14.57 $5.43 $0.00 $85.34

For apprentice rates see "Apprentice- ELECTRICIAN"

9/7/2025 $48.16 $14.98 $14.30 $5.30 $0.00 $82.74FIRE ALARM REPAIR / MAINT/COMMISSIONING

ELECTRICIANS LOCAL 96

ELECTRICIANS LOCAL 96

9/6/2026 $49.38 $15.96 $14.57 $5.43 $0.00 $85.34

For apprentice rates see "Apprentice- ELECTRICIAN"

6/1/2026 $47.55 $17.05 $13.35 $3.25 $0.00 $81.20FIREMAN (ASST. ENGINEER)

OPERATING ENGINEERS LOCAL 4

OPERATING ENGINEERS LOCAL 4

12/1/2026 $48.73 $17.05 $13.35 $3.25 $0.00 $82.38

For apprentice rates see "Apprentice- OPERATING ENGINEERS"

6/1/2026 $29.21 $10.90 $9.75 $9.21 $0.00 $59.07FLAGGER & SIGNALER (HEAVY & HIGHWAY)

LABORERS

LABORERS - ZONE 2 (HEAVY & HIGHWAY)

12/1/2026 $29.21 $10.90 $9.75 $9.21 $0.00 $59.07

Apprentice: ELEVATOR CONSTRUCTOR

Effective Date: 1/1/2027

Step Percent Apprentice Base Wage Health Pension Annuity

Supplemental Unemployment

Total Rate

4 70.00 $50.56 $16.48 $11.16 $11.00 $0.00 $89.20

5 80.00 $57.78 $16.48 $11.16 $11.00 $0.00 $96.42

Page 11 of 37Wage Request Number: 20260701110359Issue Date: 07/01/2026

Supplemental

Unemployment Total Rate

For apprentice rates see "Apprentice- LABORER (Heavy and Highway)

FLOORCOVERER

FLOORCOVERERS LOCAL 2168

FLOORCOVERERS LOCAL 2168 ZONE II

3/1/2024 $48.93 $10.33 $11.47 $8.80 $0.00 $79.53

6/1/2026 $59.38 $17.05 $13.35 $3.25 $0.00 $93.03

6/1/2026 $59.38 $17.05 $13.35 $3.25 $0.00 $93.03

12/1/2026 $60.83 $17.05 $13.35 $3.25 $0.00 $94.48

FORK LIFT/CHERRY PICKER

OPERATING ENGINEERS LOCAL 4

OPERATING ENGINEERS LOCAL 4

12/1/2026 $60.83 $17.05 $13.35 $3.25 $0.00 $94.48

For apprentice rates see "Apprentice- OPERATING ENGINEERS"

6/1/2026 $37.63 $17.05 $13.35 $3.25 $0.00 $71.28

6/1/2026 $37.63 $17.05 $13.35 $3.25 $0.00 $71.28

12/1/2026 $38.58 $17.05 $13.35 $3.25 $0.00 $72.23

GENERATOR/LIGHTING PLANT/HEATERS

OPERATING ENGINEERS LOCAL 4

OPERATING ENGINEERS LOCAL 4

12/1/2026 $38.58 $17.05 $13.35 $3.25 $0.00 $72.23

For apprentice rates see "Apprentice- OPERATING ENGINEERS"

GLAZIER (GLASS PLANK/AIR BARRIER/INTERIOR SYSTEMS)

GLAZIERS LOCAL 35

GLAZIERS LOCAL 35 (ZONE 2)

1/1/2026 $49.06 $10.35 $12.00 $12.60 $0.00 $84.01

Apprentice: FLOORCOVERER

Effective Date: 3/1/2024

Step Percent Apprentice Base Wage Health Pension Annuity

Supplemental Unemployment

Total Rate

1 50.00 $24.47 $10.33 $0.00 $1.76 $0.00 $36.56

2 55.00 $26.91 $10.33 $0.00 $1.76 $0.00 $39.00

3 60.00 $29.36 $10.33 $0.00 $3.52 $0.00 $43.21

4 65.00 $31.80 $10.33 $0.00 $3.52 $0.00 $45.65

5 70.00 $34.25 $10.33 $11.47 $5.28 $0.00 $61.33

6 75.00 $36.70 $10.33 $11.47 $5.28 $0.00 $63.78

7 80.00 $39.14 $10.33 $11.47 $7.04 $0.00 $67.98

8 85.00 $41.59 $10.33 $11.47 $7.04 $0.00 $70.43

Apprentice Notes

Steps are 750 hrs.

Apprentice to Journeyworker Ratio: 1:1

Apprentice: GLAZIER (GLASS PLANK/AIR BARRIER/INTERIOR SYSTEMS)

Effective Date: 1/1/2026

Step Percent Apprentice Base Wage Health Pension Annuity

Supplemental Unemployment

Total Rate

1 50.00 $24.53 $10.35 $0.00 $0.00 $0.00 $34.88

2 55.00 $26.98 $10.35 $0.00 $6.88 $0.00 $44.21

3 60.00 $29.44 $10.35 $0.00 $7.50 $0.00 $47.29

4 65.00 $31.89 $10.35 $0.00 $8.13 $0.00 $50.37

Page 12 of 37Wage Request Number: 20260701110359Issue Date: 07/01/2026

Supplemental

Unemployment Total Rate

6/1/2026 $59.38 $17.05 $13.35 $3.25 $0.00 $93.03

6/1/2026 $59.38 $17.05 $13.35 $3.25 $0.00 $93.03

12/1/2026 $60.83 $17.05 $13.35 $3.25 $0.00 $94.48

HOISTING ENGINEER/CRANES/GRADALLS

OPERATING ENGINEERS LOCAL 4

OPERATING ENGINEERS LOCAL 4

12/1/2026 $60.83 $17.05 $13.35 $3.25 $0.00 $94.48

7/1/2026 $43.48 $13.24 $11.01 $9.92 $2.13 $79.78

1/1/2027 $43.48 $13.54 $11.01 $11.12 $2.13 $81.28

7/1/2027 $44.98 $13.54 $11.01 $11.12 $2.13 $82.78

HVAC (DUCTWORK)

SHEETMETAL WORKERS LOCAL 63

SHEETMETAL WORKERS LOCAL 63

Apprentice: GLAZIER (GLASS PLANK/AIR BARRIER/INTERIOR SYSTEMS)

Effective Date: 1/1/2026

Step Percent Apprentice Base Wage Health Pension Annuity

Supplemental Unemployment

Total Rate

5 70.00 $34.34 $10.35 $12.00 $8.75 $0.00 $65.44

6 75.00 $36.80 $10.35 $12.00 $9.38 $0.00 $68.53

7 80.00 $39.25 $10.35 $12.00 $10.00 $0.00 $71.60

8 90.00 $44.15 $10.35 $12.00 $11.25 $0.00 $77.75

Apprentice to Journeyworker Ratio: 1:1

Apprentice: HOISTING ENGINEER/CRANES/GRADALLS

Effective Date: 6/1/2026

Step Percent Apprentice Base Wage Health Pension Annuity

Supplemental Unemployment

Total Rate

1 55.00 $32.66 $0.00 $0.00 $0.00 $0.00 $32.66

2 60.00 $35.63 $17.05 $13.35 $3.25 $0.00 $69.28

3 65.00 $38.60 $17.05 $13.35 $3.25 $0.00 $72.25

4 70.00 $41.57 $17.05 $13.35 $3.25 $0.00 $75.22

5 75.00 $44.54 $17.05 $13.35 $3.25 $0.00 $78.19

6 80.00 $47.50 $17.05 $13.35 $3.25 $0.00 $81.15

7 85.00 $50.47 $17.05 $13.35 $3.25 $0.00 $84.12

8 90.00 $53.44 $17.05 $13.35 $3.25 $0.00 $87.09

Apprentice: HOISTING ENGINEER/CRANES/GRADALLS

Effective Date: 6/1/2026

Step Percent Apprentice Base Wage Health Pension Annuity

Supplemental Unemployment

Total Rate

1 55.00 $32.66 $0.00 $0.00 $0.00 $0.00 $32.66

2 60.00 $35.63 $17.05 $13.35 $3.25 $0.00 $69.28

3 65.00 $38.60 $17.05 $13.35 $3.25 $0.00 $72.25

4 70.00 $41.57 $17.05 $13.35 $3.25 $0.00 $75.22

5 75.00 $44.54 $17.05 $13.35 $3.25 $0.00 $78.19

6 80.00 $47.50 $17.05 $13.35 $3.25 $0.00 $81.15

7 85.00 $50.47 $17.05 $13.35 $3.25 $0.00 $84.12

8 90.00 $53.44 $17.05 $13.35 $3.25 $0.00 $87.09

Apprentice to Journeyworker Ratio: 1:6

Page 13 of 37Wage Request Number: 20260701110359Issue Date: 07/01/2026

Supplemental

Unemployment Total Rate

1/1/2028 $46.48 $13.54 $11.01 $11.12 $2.13 $84.28

For apprentice rates see "Apprentice- SHEET METAL WORKER"

9/7/2025 $48.16 $14.98 $14.30 $5.30 $0.00 $82.74HVAC (ELECTRICAL CONTROLS)

ELECTRICIANS LOCAL 96

ELECTRICIANS LOCAL 96

9/6/2026 $49.38 $15.96 $14.57 $5.43 $0.00 $85.34

For apprentice rates see "Apprentice- ELECTRICIAN"

7/1/2026 $43.48 $13.24 $11.01 $9.92 $2.13 $79.78

1/1/2027 $43.48 $13.54 $11.01 $11.12 $2.13 $81.28

7/1/2027 $44.98 $13.54 $11.01 $11.12 $2.13 $82.78

HVAC (TESTING AND BALANCING - AIR)

SHEETMETAL WORKERS LOCAL 63

SHEETMETAL WORKERS LOCAL 63

1/1/2028 $46.48 $13.54 $11.01 $11.12 $2.13 $84.28

For apprentice rates see "Apprentice- SHEET METAL WORKER"

HVAC (TESTING AND BALANCING -WATER)

PLUMBERS LOCAL 4

PLUMBERS LOCAL 4

3/1/2026 $55.90 $13.10 $9.71 $8.06 $0.00 $86.77

For apprentice rates see "Apprentice- PIPEFITTER" or "PLUMBER/PIPEFITTER"

HVAC MECHANIC

PLUMBERS LOCAL 4

PLUMBERS LOCAL 4

3/1/2026 $55.90 $13.10 $9.71 $8.06 $0.00 $86.77

For apprentice rates see "Apprentice- PIPEFITTER" or "PLUMBER/PIPEFITTER"

6/1/2026 $42.41 $10.90 $9.75 $9.11 $0.00 $72.17

12/1/2026 $43.85 $10.90 $9.75 $9.11 $0.00 $73.61

6/1/2027 $45.30 $10.90 $9.75 $9.11 $0.00 $75.06

12/1/2027 $46.75 $10.90 $9.75 $9.11 $0.00 $76.51

6/1/2028 $48.25 $10.90 $9.75 $9.11 $0.00 $78.01

HYDRAULIC DRILLS

LABORERS

LABORERS - ZONE 2

12/1/2028 $49.75 $10.90 $9.75 $9.11 $0.00 $79.51

For apprentice rates see "Apprentice- LABORER"

6/1/2026 $42.41 $10.90 $9.75 $9.21 $0.00 $72.27HYDRAULIC DRILLS (HEAVY & HIGHWAY)

LABORERS

LABORERS - ZONE 2 (HEAVY & HIGHWAY)

12/1/2026 $43.85 $10.90 $9.75 $9.21 $0.00 $73.71

For apprentice rates see "Apprentice- LABORER (Heavy and Highway)

9/1/2025 $54.31 $14.75 $9.52 $10.09 $0.00 $88.67INSULATOR (PIPES & TANKS)

HEAT & FROST INSULATORS LOCAL 6

HEAT & FROST INSULATORS LOCAL 6 (WORCESTER)

9/1/2026 $57.38 $14.75 $9.52 $10.09 $0.00 $91.74

Apprentice: INSULATOR (PIPES & TANKS)

Effective Date: 9/1/2025

Step Percent Apprentice Base Wage Health Pension Annuity

Supplemental Unemployment

Total Rate

1 50.00 $27.16 $14.75 $9.27 $5.05 $0.00 $56.23

2 60.00 $32.59 $14.75 $9.32 $6.05 $0.00 $62.71

3 70.00 $38.02 $14.75 $9.37 $7.06 $0.00 $69.20

4 80.00 $43.45 $14.75 $9.42 $8.07 $0.00 $75.69

Page 14 of 37Wage Request Number: 20260701110359Issue Date: 07/01/2026

Supplemental

Unemployment Total Rate

IRONWORKER/WELDER

IRONWORKERS LOCAL 7

IRONWORKERS LOCAL 7 (WORCESTER AREA)

3/16/2026 $58.35 $9.25 $12.75 $15.00 $0.00 $95.35

6/1/2026 $41.91 $10.90 $9.75 $9.11 $0.00 $71.67

12/1/2026 $43.35 $10.90 $9.75 $9.11 $0.00 $73.11

6/1/2027 $44.80 $10.90 $9.75 $9.11 $0.00 $74.56

12/1/2027 $46.25 $10.90 $9.75 $9.11 $0.00 $76.01

6/1/2028 $47.75 $10.90 $9.75 $9.11 $0.00 $77.51

JACKHAMMER & PAVING BREAKER OPERATOR

LABORERS

LABORERS…