FINALSPECPDF.pdf

PDF 7 MB Posted

Attached to
RECOVERY-Canutillo Phase I Levee Improvements Federal contract opportunity
Solicitation number
IBM10B0003
Issued by
International Boundary and Water Commission U.S.-Mexico

About this file

Specifications for Canutillo Levee Segment

View the file

Other files for this federal contract opportunity

Other files attached to RECOVERY-Canutillo Phase I Levee Improvements, newest first.
File Type Posted
Canutillo Abstract Spreadsheet 12-22-09 pg 1.xls XLS spreadsheet
attachment-IBM10B0003 1-130 questions Canutillo.pdf PDF
Amend A002-IBM10B0003_Canutillo.pdf PDF
attachment-IBM10B0003 questions Canutillo.pdf PDF
attachment-IBM10003 Summary of Specs sections Plan sheets_1.pdf PDF
attachment-IBM10B0003 1 addl questions_Canutillo.pdf PDF
contract questions.doc DOC document
Canutillo Bidder Questions_1_15.pdf PDF
IBM10B0003 Plan Holder List.pdf PDF
IBM10B0003 A001.pdf PDF
sf24_f.pdf PDF
IBWC 110.pdf PDF
tx wage det.pdf PDF
IBWC 117.pdf PDF
nm wage det.pdf PDF
sf28.pdf PDF
IBM10B0003.pdf PDF
IBWC 116.pdf PDF
Show all 18

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FINAL

TECHNICAL SPECIFICATIONS

FOR

Upper Rio Grande Flood Control Project Canutillo Levee Segment

From Vado Bridge to Borderland Bridge Doña Ana County, New Mexico and El Paso County, Texas

Prepared for:

United States Section, International Boundary & Water Commission

Submitted / Prepared by:

Texas Firm No. 1582

Project Manager: Daniel O. Rios, P.E.

Task Manager: James M. Sassin, P.E.

Senior Project Manager: Michael C. Riojas, P.E.

Contract No. IBM05D0001 Task Order No. IBM09T0030

November 16, 2009

11/13/2009 11/13/2009

This Page Intentionally Blank

Rehabilitation Improvements for the Canutillo Levee System

Doña Ana County, New Mexico

DIVISION 00-

USIBWC Contract No.: IBM05D0001��� PROCUREMENT AND CONTRACTING REQUIREMENTS

US INTERNATIONAL BOUNDARY & WATER COMMISSION

GOVERNING TECHNICAL SPECIFICATIONS AND PROVISIONS

DIVISION 00 – PROCUREMENT AND CONTRACTING

REQUIREMENTS

(INTRODUCTORY / AVAILABLE INFORMATION)

DIVISION 00-

USIBWC Contract No.: IBM05D0001��� PROCUREMENT AND CONTRACTING REQUIREMENTS

El Paso County, Texas

PROJECT TITLE

USIBWC Contract No.: IBM05D0001 Page 00.01.01 - 1

INTRODUCTORY INFORMATION 00.01.01

The title of this project is as follows:

International Boundary & Water Commission – United States Section

Rehabilitation Improvements for the Canutillo Levee System From Vado Bridge to Borderland Bridge

El Paso County, Texas

USIBWC Contract No.: IBM05D0001 Page 00.01.01 - 2

El Paso County, Texas

TABLE OF CONTENTS

USIBWC Contract No.: IBM05D0001 Page 00.01.10 - 1

Proposed Specification List

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

SPECIFICATION 00 01 01 PROJECT TITLE

SPECIFICATION 00 01 10 TABLE OF CONTENTS

SPECIFICATION 00 01 15 LIST OF CONTRACT DRAWINGS

SPECIFICATION 00 01 20 LIST OF SCHEDULES

SPECIFICATION 00 31 19 EXISTING CONDITION INFORMATION

SPECIFICATION 00 31 21 SURVEY INFORMATION (RIGHT OF WAY)

SPECIFICATION 00 31 24 ENVIRONMENTAL ASSESSMENT INFORMATION

SPECIFICATION 00 31 26 EXISTING HAZARDOUS MATERIAL INFORMATION

SPECIFICATION 00 31 32 GEOTECHNICAL DATA

SPECIFICATION 00 31 43 PERMIT APPLICATION

SPECIFICATION 00 31 50 OTHER PROJECT INFORMATION

DIVISION 01 - GENERAL REQUIREMENTS

SPECIFICATION 01 01 00 IDENTIFICATION OF TECHNICAL SPECIFICATIONS

SPECIFICATION 01 19 00 SCOPE OF WORK

SPECIFICATION 01 27 00 MEASUREMENT AND PAYMENT

SPECIFICATION 01 31 00 PROJECT MANAGEMENT AND COORDINATION

SPECIFICATION 01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION

SPECIFICATION 01 33 00 SUBMITTALS

SPECIFICATION 01 39 00 SAFETY

SPECIFICATION 01 42 00 REFERENCES

SPECIFICATION 01 46 00 QUALITY CONTROL / QUALITY ASSURANCE

SPECIFICATION 01 51 00 TEMPORARY UTILITIES

SPECIFICATION 01 56 00 BARRICADES AND SIGNS

SPECIFICATION 01 57 00 TEMPORARY EROSION, SEDIMENTATION AND

ENVIRONMENTAL CONTROLS

SPECIFICATION 01 59 00 TEMPORARY CONTROLS FOR WORK AREAS /

PROJECT-SPECIFIC LOCATIONS

SPECIFICATION 01 69 00 CONTROL OF MATERIALS

SPECIFICATION 01 70 00 MOBILIZATION

SPECIFICATION 01 71 00 FIELD ENGINEERING

SPECIFICATION 01 77 00 CONTRACT CLOSE-OUT

DIVISION 02 - EXISTING CONDITIONS

SPECIFICATION 02 02 00 EXISITING CONDITIONS

SPECIFICATION 02 91 00 REMOVE / RELOCATE FENCE

DIVISIONS 31 / 34 - SITE GRADING

SPECIFICATION 31 04 00 REMOVE CONCRETE

SPECIFICATION 31 05 00 REMOVE STABILIZED BASE AND ASPHALT

SPECIFICATION 31 11 00 PREPARING RIGHT OF WAY

El Paso County, Texas

USIBWC Contract No.: IBM05D0001 Page 00.01.10 - 2

SPECIFICATION 31 12 00 OBLITERATE ROADWAY

SPECIFICATION 31 14 00 REMOVE / STOCKPILE EXISTING MATERIALS

SPECIFICATION 31 81 00 PROOF ROLLING

SPECIFICATION 31 92 00 VEGETATION FOR EROSION CONTROL

SPECIFICATION 34 01 00 CLEAN EXISTING CHANNELS

DIVISION 35 - WATERWAY / MARINE

SPECIFICATION 35 41 00 CONSTRUCTION OF LEVEE

SPECIFICATION 35 42 00 RIPRAP

SPECIFICATION 35 43 00 TOE DRAIN

DIVISION 50 - ROADWAY CONSTRUCTION

SPECIFICATION 50 11 00 ROADWAY EMBANKMENT

SPECIFICATION 50 12 00 ROADWAY EXCAVATION

SPECIFICATION 50 20 00 ROADWAY BASE

SPECIFICATION 50 21 00 PRIME COAT

SPECIFICATION 50 23 00 EQUIPMENT FOR ASPHALT CONCRETE PAVEMENT

SPECIFICATION 50 24 00 ASPAHLT, OILS, AND EMULSIONS

SPECIFICATION 50 25 00 HOT MIX ASPHALT CONCRETE PAVEMENT

SPECIFICATION 50 29 00 CONCRETE CURB AND GUTTER

SPECIFICATION 50 30 00 CONCRETE PAVEMENT

SPECIFICATION 50 90 00 REFLECTIVE PAVEMENT MARKINGS

SPECIFICATION 50 91 00 REMOVE AND REINSTALL/REFURB TRAFFIC SIGNS

SPECIFICATION 50 93 00 TEMPORARY TRAFFIC CONTROL DEVICES

SPECIFICATION 50 94 00 DELINEATOR AND OBJECT MARKER ASSEMBLIES

DIVISION 60 - STRUCTURES

SPECIFICATION 60 01 00 FLOWABLE BACKFILL

SPECIFICATION 60 02 00 TRENCH EXCAVATION PROTECTION

SPECIFICATION 60 10 00 EXCAVATION AND BACKFILL FOR STRUCTURES

SPECIFICATION 60 20 00 CONCRETE STRUCTURES

SPECIFICATION 60 21 00 HYDRAULIC CEMENT

SPECIFICATION 60 23 00 FLOODWALL

SPECIFICATION 60 38 00 CLEAN AND SEAL JOINTS

SPECIFICATION 60 40 00 REINFORCING STEEL

SPECIFICATION 60 41 00 STEEL STRUCTURES

SPECIFICATION 60 42 00 METAL FOR STRUCTURES

SPECIFICATION 60 45 00 GALVANIZING

SPECIFICATION 60 46 00 CLEANING AND PAINTING STEEL

SPECIFICATION 60 47 00 STRUCTURAL BOLTING

SPECIFICATION 60 48 00 WELDING

SPECIFICATION 60 50 00 RAILING

SPECIFICATION 60 62 00 CORRUGATED METAL PIPE

SPECIFICATION 60 63 00 CONCRETE BOX CULVERTS AND STORM DRAINS

El Paso County, Texas

USIBWC Contract No.: IBM05D0001 Page 00.01.10 - 3

SPECIFICATION 60 64 00 REINFORCED CONCRETE PIPE

SPECIFICATION 60 65 00 MANHOLES AND INLETS

SPECIFICATION 60 66 00 HEADWALLS AND WINGWALLS

SPECIFICATION 60 67 00 SLOPE END-SAFETY AND TREATMENT

SPECIFICATION 60 68 00 SLUICE GATE

SPECIFICATION 60 69 00 SLUICE GATE MAINTENANCE

SPECIFICATION 60 79 00 ABANDON AND PLUG STRUCTURE

SPECIFICATION 60 80 00 FLOOD GATE

SPECIFICATION 60 96 00 REMOVING EXISTING STRUCTURES

SPECIFICATION 60 98 00 CLEAN EXISTING STRUCTURES

DIVISION 90 - MISCELLANEOUS

SPECIFICATION 90 79 00 VEHICULAR GATE

SPECIFICATION 90 80 00 REMOVE, REFURBISH AND REPLACE VEHICULAR

GATE

SPECIFICATION 90 81 00 BOULDERS

-END OF SPECIFICATION-

El Paso County, Texas

USIBWC Contract No.: IBM05D0001 Page 00.01.10 - 4

El Paso County, Texas

LIST OF CONTRACT DRAWINGS

USIBWC Contract No.: IBM05D0001 Page 00.01.15 - 1

INTRODUCTORY INFORMATION 00.01.15

The Contract Drawings applicable to this Contract are entitled: “United States Section International Boundary and Water Commission, Upper Rio Grande Flood Control Project, Rehabilitation for the Canutillo Levee System, El Paso County, Texas, Doña Ana County, New Mexico.” An index of drawings is identified on the title sheet, and includes the following:

INDEX OF SHEETS-CANUTILLO LEVEE SYSTEM

SHEET NO. DESCRIPTION

01.01 TITLE SHEET

02.01-02.05 PROJECT LAYOUT

02.06-02.07 SURVEY CONTROL SHEETS

03.01 GENERAL NOTES

04.01 ESTIMATE OF QUANTITIES

05.01-05.05 SUMMARY OF QUANTITIES

06.01-06.05 EXISTING & PROPOSED TYPICAL SECTIONS

07.01-07.10 ALIGNMENT DATA SHEETS

07.11-07.15 BENCHMARK DATA SHEETS

08.001-08.051 PLAN & PROFILE – CE1 LEVEE

08.052-08.127 PLAN & PROFILE – CW1 LEVEE�

08.128-08.129 PLAN & PROFILE – CE1 LEVEE ACCESS ROADS

08.130-08.131 PLAN & PROFILE – CW1 LEVEE ACCESS ROADS

08.132-08.155 PLAN & PROFILE – CE1 LEVEE ACCESS RAMPS

08.156-08.177 PLAN & PROFILE – CW1 LEVEE ACCESS RAMPS

09.01-09.26 BORE LOGS

10.001-10.122 CE1 CROSS-SECTIONS

10.123-10.304 CW1 CROSS-SECTIONS

11.01-11.02 SIGN DETAILS & TYPICAL ACCESS RAMP

El Paso County, Texas

USIBWC Contract No.: IBM05D0001 Page 00.01.15 - 2

12.01-12.05 STRUCTURE LAYOUTS

12.07-12.27 CULVERT LAYOUTS

12.28-12.47 STRUCTURE & FLOOD GATE DETAILS

12.48-12.49 TRAFFIC CONTROL FOR FLOODGATE INSTALLATION

13.01 EROSION CONTROL (SW3P)

14.01 EPIC

15.01 HEAVY DUTY VEHICULAR GATE

15.02

TRAFFIC CONTROL DETAILS TYPE III BARRICADES AND LANE

CLOSURES

15.03-15.05

TEMPORARY EROSION, SEDIMENT AND WATER POLLUTION

CONTROL METHODS

15.06-15.17 BARRICADES AND CONSTRUCTION DETAILS

15.18 WORK ZONE SHORT TERM PAVEMENT MARKING

El Paso County, Texas

LIST OF SCHEDULES

USIBWC Contract No.: IBM05D0001 Page 00.01.20 - 1

INTRODUCTORY INFORMATION 00.01.20

1. Schedule of Submittals. For this Project, the requirements for submittals are identified on the Contract Drawings and Technical Specifications (Divisions 01, 02, 31, 33, 34, 35, 50, 60, and 90). For this project, a schedule of submittals includes, but may not be limited to the following: (The Contractor shall refer to each Technical Specification for a full description of applicable submittals and submittal requirements.)

SPECIFICATION Submittal

01 32 00 Construction Progress Documentation Progress Schedule 01 39 00 Safety Accident Prevention Plan 01 46 00 Quality Control / Quality Assurance Contractor Quality Control Plan, Certifications for

Testing Personnel 01 51 00 Temporary Utilities 01 56 00 Barricades and Signs Traffic Control, Barricade and Signing Plans

Written Certification of Temporary Barriers 01 57 00 Temporary Erosion, Sedimentation, And

Environmental Controls FEM Qualifications

SW3P

Construction Plan

01 59 00 Temporary Controls For Work Areas / Project-Specific Locations

Staging Area Plan Layout

SW3P

Hazardous Materials Tests Hazardous Waste Manifests

01 69 00 Control of Materials Materials Source Identification and Certifications 01 71 00 Field Engineering Survey Plan and Submittals 01 70 00 Mobilization 01 77 00 Contract Close-Out As-Built Plans, Reports, Drawings

Final Inspection / Testing Records 02 02 00 Existing Conditions & Facilities Flood Protection Plan

Video Tape 02 91 00 Remove / Relocate Fence 31 04 00 Remove Concrete 31 05 00 Removing Stabilized Base and Asphalt

Pavement

31 11 00 Preparing Right of Way 31 12 00 Obliterate Roadway 31 14 00 Remove / Stockpile Existing Materials 31 81 00 Proof Rolling

31 92 00 Vegetation for Erosion Control Seeding Plan 33 46 00 Pipe Underdrain 34 01 00 Clean Existing Channel

El Paso County, Texas

USIBWC Contract No.: IBM05D0001 Page 00.01.20 - 2

35 41 00 Construction Of Levee Plan of Operations, Testing Facilities, Testing Results for Classification of Fill Material, Nuclear-Density Operator Certification, Test Results for Construction, Designs and Details for Contractor Repairs, Dewatering Controls, Excavation or Fill Support Details Moisture Content Adjustment Plan

35 41 10 Slurry Trench Slurry Trench Implementation Plan Off-site Borrow Samples

35 41 20 Geosynthetic Membrane Cutoff Wall QC Certificates Test Results

Panel Layout Drawing 35 42 00 Rip Rap Geotextile Membrane Shop Drawing, Data, Product

Warranty & Certification Submittal 35 43 00 Toe Drain Manufacturer’s Literature, Samples, & Written

Material Specs Sequence of Toe Drain Installation

35 44 00

Gabion Mattress and Block Alternative Wire Fasteners Supplier’s Certification

50 11 00 Roadway Embankment

50 12 00 Roadway Excavation

50 20 00 Roadway Base

50 21 00 Prime Coat 50 22 00 Anti-Stripping ACP - Mix Design Submittals and

Other Material and Equipment Certifications

50 23 00 HMAC Equipment 50 24 00 Asphalt, Oils, and Emulsions 50 25 00 Hot Mix Asphalt Concrete Pavement New Mixture Design 50 29 00 Concrete Curb and Gutter 50 30 00 Concrete Pavement Paving & Quality Control Plan—Any Applicable

Revisions Proposed Measures for Inclement Weather

Other Methods of Curing 50 90 00 Reflective Pavement Markings 50 91 00 Provide and Install New Traffic Signs 50 92 00 Remove, Refurbish, and Reinstall Access

Gates

50 93 00 Temporary Traffic Control Devices

50 94 00 Delineator and Object Marker Assemblies 60 02 00 Trench Excavation Protection 60 04 00 Driving Piling Structural Analysis and Corrective Action

El Paso County, Texas

USIBWC Contract No.: IBM05D0001 Page 00.01.20 - 3

Methods of Jetting Manufacturer Spec Data

Descriptions and Dimensions of materials 60 07 00 Steel Piling 60 10 00 Excavation and Backfill for Structures Details and Design Calculations 60 20 00 Concrete Structures Falsework and/or Forming Plans Submittals

Construction Methods Submittal Epoxy, Steel dowels, Construction joint Material, and

Steel Bolts Product information and testing Certifications

60 21 00 Hydraulic Cement Concrete Plant Admixture Certifications

Concrete Mix Design Grout Mix Design

60 23 00 Floodwall Casting Drawings, Construction Drawings, and Design Calculations

60 38 00 Clean and Seal Joints Information from the sealant manufacturer showing recommended equipment and installation procedures.

60 40 00 Reinforcing Steel Chemical Analysis Report

Material Certifications 60 41 00 Steel Structures Erection Drawings

Welding Shop Drawings Welding, Bolting and Fabrication Procedures

Non-Conformance Reports Bolt Correction Methods

60 42 00 Metal For Structures Mill Test Reports, Supplemental Test Documentation, and Certifications

60 45 00 Galvanizing 60 46 00 Cleaning and Painting Steel Cleaning and Painting Certifications

Painting Methods Containment Plan

Loads Analysis MSDS Sheet

60 47 00 Structural Bolting 60 48 00 Structural Field Welding Certified Testing Reports

Welder Certification or Qualification

WPS

Laboratory Certification Straightening Procedure

60 50 00 Railing Erection Drawings 60 62 00 Corrugated Metal Pipe 60 63 00 Concrete Box Culverts and Storm Drains 60 64 00 Reinforced Concrete Pipe 60 65 00 Manholes and Inlets 60 66 00 Headwalls and Wingwalls

El Paso County, Texas

USIBWC Contract No.: IBM05D0001 Page 00.01.20 - 4

60 67 00 Slope End-Safety and Treatment 60 68 00 Sluice Gate Gate and Lift Mechanism Shop Drawings and

Manufacturer’s Qualifications Design Calculations

60 69 00 Sluice Gate Maintenance Shop Drawing Replaced/Remanufactured Parts

60 71 00 Grates and Ladders Mill Test Reports and Certifications 60 79 00 Abandon and Plug Structure 60 80 00 Flood Gate Manufacturer’s Product Data Sheets

Shop Drawings 60 81 00 Polyvinyl Chloride Pipe Material Certification 60 96 00 Removing Existing Structures 60 98 00 Clean Existing Structures 90 79 00 Vehicular Gate

90 80 00 Remove, Refurbish, and Reinstall Heavy Duty Vehicular Gate

90 81 00 Boulders Rough Dimensions of Boulders 90 82 00 Geotextile Fabric Catalog Cut and Samples of Materials

Manufacturer’s Certification and Installation Procedures

2. Schedule of Assemblies, Materials, and Estimated Quantities. For this Project, the schedules of assemblies, material specifications and associated estimated quantities are identified on the Contract Drawings and Technical Specifications (Divisions 01, 02, 31, 33, 34, 35, 50, 60, and 90). Estimated quantities for each Bid Item are shown on Plan Sheet No. 4; and estimated quantities are also summarized by plan sheet on Plan Sheet Nos. 5 and 5A.

El Paso County, Texas

EXISTING CONDITION INFORMATION

USIBWC Contract No.: IBM05D0001 Page 00.31.19 - 1

AVAILABLE INFORMATION 00.31.19

The existing condition of the levee has been evaluated by the Government, and is included in a report entitled “Condition Assessment of U.S. International Boundary & Water Commission, Texas and New Mexico Levees” by the US Army Corps of Engineers (USACE) dated June 2004, and the “Flood Simulation Study of Rio Grande Levees Near Las Cruces, New Mexico, Using Seismic and Electrical Geophysical Methods” dated May 2007.The applicable sections of this report are available to the Contractor for the purposes of understanding the existing condition of the levee within the project limits of this Contract. Additionally, geotechnical investigations were performed during the final design of the project, and the associated geotechnical data and reports are identified in 00.31.32 Geotechnical Data herein.

El Paso County, Texas

USIBWC Contract No.: IBM05D0001 Page 00.31.19 - 2

El Paso County, Texas

SURVEY INFORMATION

USIBWC Contract No.: IBM05D0001 Page 00.31.21 - 1

AVAILABLE INFORMATION 00.31.21

For these Contract Drawings, surveying and data collection was performed as follows:

(1) Light Detection and Ranging (LIDAR) was obtained from the Government and used for preliminary information only.

(2) Control was performed in April / May 2009 by Frank X. Spencer & Associates., who developed and provided the following (at .01-foot accuracy):

(a) Control. The surveyor established points at cross-roads to establish horizontal and vertical control; control sheets were developed for each control point set, signed and sealed by a New Mexico/Texas Registered Professional Land Surveyor (RPLS). The control sheet includes a drawing of the control point with a 3-point tie to existing physical features, description of the control point, X,Y & Z coordinates and the coordinate system. Plan Sheet No. 2.08-2.09, within the Contract Drawings includes the control information data for all the control points set for the project, signed and sealed by the RPLS.

(b) Benchmarks. The surveyor established bench marks along project limits; vertical benchmarks were set at 1000-foot intervals at the right of way (ROW) line of the levee reach. A tabulation of the benchmarks is shown on the Plan Sheets within the Contract Drawings.

(3) Ultimately, an aerial survey (at 0.1-foot accuracy) was performed in April / May 2009 by

Martinez Corporation who developed and provided the following, which was used as the basis of design:

(a) Field Control for Photogrammetry. The surveyor set panels for aerial photogrammetry along the levee reach for a low-level flight (1500 feet). Panels were set along the flight path at 800-foot intervals and wing panels were set at cross-roads or 2400-foot intervals. The surveyor performed a global positioning (GPS) survey to establish x-y-z coordinates of the panel points.

(b) Aerial Photogrammetry. The aerial photogrammetry was developed as follows:

1. Black and white photography at a 1-inch = 250-foot photo scale (1500 feet above ground level (AGL))

2. Data Processing. The aerial photography was scanned at 12 microns to produce 0.25-foot pixel resolution; aerial triangulation process was performed to orient individual stereo pairs.

3. Planimetric and Topographic Data Compilation. Planimetric and topographic data was compiled (suitable for 1-inch = 50-foot map scale showing 1-foot contours.

El Paso County, Texas

USIBWC Contract No.: IBM05D0001 Page 00.31.21 - 2

4. Digital Orthophotos. A digital terrain model (DTM) was created for the project area to support the orthophoto rectification; rectified mosaic digital images to hold 0.25-foot ground pixel resolutions suitable for a 1-inch = 50-foot map scale.

(4) Supplemental ground surveys were performed by SLI Engineering Inc., Dos Land Surveying, LLC, and Valley Data Collection Specialists as follows:

(a) Voids. A topographic survey was performed by the surveyors to fill-in the voids of the aerial planimetrics; additionally, the surveyor performed topographic survey on existing structures, including bridges, inlets, culverts and irrigation structures.

(b) ROW Verification. The surveyors recovered and staked ROW points from available ROW maps supplied by the Government. This ROW information is shown on the plan / profile sheets of the Contract Drawings.

(c) Geotechnical Borings Survey. The surveyors obtained x-y-x coordinates for the geotechnical borings along the levee reach spaced at approximately 500-foot spacing’s.

(d) Utility Survey. The surveyors coordinated with utility notification companies to get utilities marked in the field; the surveyor performed field location of underground utilities as marked by utility companies along the levee reach and intersecting streets. These locations are shown on the plan / profile sheets of the Contract Drawings. NOTE: IT IS THE CONTRACTOR’S

RESPONSIBILITY TO VERIFY LOCATIONS OF ALL EXISTING UTILITIES (SHOWN

AND NOT SHOWN ON THE CONTRACT DRAWINGS) PRIOR TO CONSTRUCTION.

El Paso County, Texas

ENVIRONMENTAL ASSESSMENT INFORMATION

USIBWC Contract No.: IBM05D0001 Page 00.31.24 - 1

AVAILABLE INFORMATION 00.31.24

The Project’s can be obtained from the International Boundary and Water Commission (IBWC) website listed below. The project’s environmental documentation for the Rio Grande Canalization Project includes:

1) Final Environmental Assessment Flood Control Improvements to the Rio Grande Canalization Project, December 2007;

2) Final Environmental Impact Statement River Management Alternatives for the USIBWC Rio Grande Canalization Project, June 2004;

3) Record of Decision on River Management Alternatives EIS for the Rio Grande Canalization Project, June 2009. These documents are available on the USIBWC website at:

www.ibwc.state.gov/Organization/Environmental/reports_studies.html.

El Paso County, Texas

USIBWC Contract No.: IBM05D0001 Page 00.31.24 - 2

El Paso County, Texas

EXISTING HAZARDOUS MATERIAL INFORMATION

USIBWC Contract No.: IBM05D0001 Page 00.31.26 - 1

AVAILABLE INFORMATION 00.31.26

There is no available information regarding hazardous materials within / adjacent to the Project limits and/or right of way.

El Paso County, Texas

USIBWC Contract No.: IBM05D0001 Page 00.31.26 - 2

El Paso County, Texas

GEOTECHNICAL DATA

USIBWC Contract No.: IBM05D0001 Page 00.31.32 - 1

AVAILABLE INFORMATION 00.31.32

Geotechnical investigations were performed by Raba-Kistner Consultants, Inc.

The Contractor may request a copy of the report from the Government.

The data and report are not intended as a representation or warranty of continuity of conditions between soil borings nor of groundwater levels at dates and times other than date and time when measured. The Government will not be responsible for interpretations or conclusions drawn there from by the Contractor.

Data are solely made available for the convenience of Contractor. Additional test borings and other exploratory operations may be made by Contractor subsequent to award of the Contract at no additional cost to the Government.

El Paso County, Texas

USIBWC Contract No.: IBM05D0001 Page 00.31.32 - 2

El Paso County, Texas

PERMIT APPLICATION

USIBWC Contract No.: IBM05D0001 Page 00.31.43 - 1

AVAILABLE INFORMATION 00.31.43

No information is available regarding required permit applications. The Contractor will be required to research the need for any required permits. For the Work under this Contract, the Contractor shall be responsible for coordinating and obtaining all permits required by Federal, state, and local entities.

El Paso County, Texas

USIBWC Contract No.: IBM05D0001 Page 00.31.43 - 2

OTHER PROJECT INFORMATION

USIBWC Contract No.: IBM05D0001 Page 00.31.50 - 1

AVAILABLE INFORMATION 00.31.50

Table 1: Structure Summary - Canutillo Levee Phase I - CE1,CW1

COORDINATES

REACH BASELINE

STATION

CENTERLINE

STATION X (EASTING) Y (NORTHING)

STRUCTURE SIZE STRUCTURE

USAGE

OWNER / USIBWC

LICENSE PROPOSED RECOMMENDATIONS

CE1 654+42.00 655+06.69 R1 1,513,964.05 401,414.58 108-inch CMP Drainage IBWC / 28.8.5 None; Located in Levee Exception Area

CE1 671+38.00 670+90.36 R2 1,514,785.52 398,731.03 24-inch RCP Irrigation George Amis /

LSF/G-20

None; Located in Levee Exception Area

CE1 693+66.00 693+34.35 R2 1,513,980.18 396,663.48 QTY 2 - 4-foot X 4-foot RCB Irrigation IBWC / L 2.48 Clean channel on both sides

CE1 827+43.00 827+20.90 R2 1,513,048.30 384,023.57 18-inch RCP Irrigation Salopek Berino

Farms / LSF/G-925 Replace pipe, headwall, wingwalls, and flap gate on river side; Clean channel on river side; Replace headwall and wingwall and add a sluice gate on land side

CE1 868+10.00 867+82.57 R2 1,513,786.68 380,047.14 30-inch RCP IBWC / L 2.53 Plug structure CE1 908+72.00 907+84.10 R3 1,515,707.23 376,515.99 5-foot X 4-foot RCB Drainage IBWC / L 2.57 Clean channel on both sides CE1 928+40.00 927+39.23 R3 1,516,408.20 374,601.37 24-inch RCP IBWC / L 2.58 Plug structure CE1 931+40.55 930+39.82 R3 1,516,487.70 374,311.58 24-inch RCP Plug structure CE1 952+00.64 950+93.77 R3 1,517,050.65 372,441.33 10-inch Steel Pipe Drainage None CE1 1020+06.00 1019+06.04 R3 1,519,709.98 366,285.82 5-foot X 4-foot RCB Irrigation IBWC / L 2.13 Clean channel on both sides CE1 1136+00.00 1135+07.30 R3 1,526,250.78 356,854.89 30-inch RCP Drainage IBWC / L 2.16 Plug structure CE1 1194+62.00 1192+80.28 R4 1,530,147.83 352,626.40 QTY 2 - 5-foot X 4-foot RCB Drainage IBWC / L 2.19 Extend structure and replace headwall and wingwalls on land side

CW1 656+80.00 656+80.06 R1 1,513,822.21 400,601.25 24-inch RCP IBWC / L 2.47 Plug structure CW1 684+40.37 684+44.75 R2 1,513,237.76 396,996.37 24-inch RCP Drainage None CW1 719+60.00 719+36.38 R2 1,511,724.89 393,974.62 30-inch RCP Drainage IBWC / L 2.49 Plug structure CW1 785+84.00 785+82.32 R3 1,512,194.42 387,679.20 36-inch RCP Irrigation USBR / L 2.50 Extend structure and replace headwall and wingwalls on river side CW1 794+60.00 794+58.65 R3 1,512,145.85 386,805.04 30-inch RCP IBWC / L 2.52 Plug structure CW1 890+50.00 890+66.91 R4 1,514,113.87 377,516.65 QTY 2 - 4-foot X 4-foot RCB Drainage IBWC / L 2.55 None CW1 897+57.00 897+52.66 R4 1,514,392.65 376,890.16 QTY 3 - 5-foot X 5-foot RCB Irrigation IBWC / L 2.56 Repair wingwall on land side; Clean channel on both sides CW1 943+50.00 943+49.45 R4 1,516,082.66 372,720.03 24-inch RCP IBWC / L 2.59 Plug structure

CW1 1045+15.00 1045+04.45 R5 1,519,126.94 365,784.92 30-inch RCP Irrigation USBR / L 2.14 Extend pipe and replace headwall and wingwalls on river side; Install sluice gate on river side; Clean channel on both sides

CW1 1086+55.00 1085+96.88 R5 1,520,885.61 362,151.37 QTY 2 - 5-foot X 5-foot RCB Irrigation IBWC / L 2.15 Repair headwall on land side; Clean channel on both sides CW1 1146+75.00 1146+62.08 R6 1,524,739.51 357,474.06 24-inch RCP None; For information only.

CW1 1155+91.99 1155+78.74 R6 1,525,325.11 356,785.72 36-inch RCP Drainage USBR / L 2.139 Replace flap gate on river side; Clean channel on both sides CW1 1250+65.70 1250+55.38 R6 1,529,904.43 349,061.23 36-inch RCP Irrigation USBR / L 2.121 Clean channel on both sides

CW1 1350+09.00 1349+97.15 R7 1,530,257.69 339,104.62 30-inch RCP Drainage Public Service

Board / LSF/G-702 L 2.123

Extend pipe and replace headwall and wingwalls on river side; Install flap gate on river side; Clean channel on both sides

CW1 1385+24.00 1385+09.55 R7 1,530,629.04 335,611.90 5-foot X 5-foot RCB Drainage USBR / L 2.20 & L 10.82

Replace sluice gate on river side; Clean channel on both sides

CW1 1463+60.00 1463+44.94 R8 1,531,138.62 327,836.48 15-inch Corr. Iron Pipe Drainage J.J. Ulmer / LSF/G-

None

USIBWC Contract No.: IBM05D0001 Page 00.31.50 - 2

El Paso County, Texas Doña Ana County, New Mexico

DIVISION 01-

USIBWC Contract No.: IBM05D0001 GENERAL REQUIREMENTS

US INTERNATIONAL BOUNDARY & WATER COMMISSION

GOVERNING TECHNICAL SPECIFICATIONS AND PROVISIONS

DIVISION 01 – GENERAL REQUIREMENTS

El Paso County, Texas Doña Ana County, New Mexico

DIVISION 01-

USIBWC Contract No.: IBM05D0001 GENERAL REQUIREMENTS

El Paso County, Texas

IDENTIFICATION OF TECHNICAL SPECIFICATIONS

USIBWC Contract No.: IBM05D0001 Page 01.01.00 - 1

SPECIFICATION 01 01 00

This specification provides for the identification and introduction to the technical specifications and related information, and includes the following:

1.1 Governing Technical Specifications

1.2 Related Documents & Provisions

1.3 Provisions for Measurement and Payment

1.4 Specification / Bid Item Format and Conventions

PART 1 - GENERAL

1.1 GOVERNING TECHNICAL SPECIFICATIONS

A. All technical specifications applicable to this Contract are identified as follows:

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

SPECIFICATION 00 01 01 PROJECT TITLE

SPECIFICATION 00 01 10 TABLE OF CONTENTS

SPECIFICATION 00 01 15 LIST OF CONTRACT DRAWINGS

SPECIFICATION 00 01 20 LIST OF SCHEDULES

SPECIFICATION 00 31 19 EXISTING CONDITION INFORMATION

SPECIFICATION 00 31 21 SURVEY INFORMATION (RIGHT OF WAY)

SPECIFICATION 00 31 24 ENVIRONMENTAL ASSESSMENT INFORMATION

SPECIFICATION 00 31 26 EXISTING HAZARDOUS MATERIAL INFORMATION

SPECIFICATION 00 31 32 GEOTECHNICAL DATA

SPECIFICATION 00 31 43 PERMIT APPLICATION

SPECIFICATION 00 31 50 OTHER PROJECT INFORMATION

DIVISION 01 - GENERAL REQUIREMENTS

SPECIFICATION 01 01 00 IDENTIFICATION OF TECHNICAL SPECIFICATIONS

SPECIFICATION 01 19 00 SCOPE OF WORK

SPECIFICATION 01 27 00 MEASUREMENT AND PAYMENT

SPECIFICATION 01 31 00 PROJECT MANAGEMENT AND COORDINATION

SPECIFICATION 01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION

SPECIFICATION 01 33 00 SUBMITTALS

SPECIFICATION 01 39 00 SAFETY

SPECIFICATION 01 42 00 REFERENCES

SPECIFICATION 01 46 00 QUALITY CONTROL / QUALITY ASSURANCE

SPECIFICATION 01 51 00 TEMPORARY UTILITIES

SPECIFICATION 01 56 00 BARRICADES AND SIGNS

SPECIFICATION 01 57 00 TEMPORARY EROSION, SEDIMENTATION AND

ENVIRONMENTAL CONTROLS

El Paso County, Texas

USIBWC Contract No.: IBM05D0001 Page 01.01.00 - 2

SPECIFICATION 01 59 00 TEMPORARY CONTROLS FOR WORK AREAS /

PROJECT-SPECIFIC LOCATIONS

SPECIFICATION 01 69 00 CONTROL OF MATERIALS

SPECIFICATION 01 70 00 MOBILIZATION

SPECIFICATION 01 71 00 FIELD ENGINEERING

SPECIFICATION 01 77 00 CONTRACT CLOSE-OUT

DIVISION 02 - EXISTING CONDITIONS

SPECIFICATION 02 02 00 EXISITING CONDITIONS

SPECIFICATION 02 91 00 REMOVE / RELOCATE FENCE

DIVISIONS 31 / 34- SITE GRADING

SPECIFICATION 31 04 00 REMOVE CONCRETE

SPECIFICATION 31 05 00 REMOVE STABILIZED BASE AND ASPHALT

SPECIFICATION 31 11 00 PREPARING RIGHT OF WAY

SPECIFICATION 31 12 00 OBLITERATE ROADWAY

SPECIFICATION 31 14 00 REMOVE / STOCKPILE EXISTING MATERIALS

SPECIFICATION 31 81 00 PROOF ROLLING

SPECIFICATION 31 92 00 VEGETATION FOR EROSION CONTROL

SPECIFICATION 34 01 00 CLEAN EXISTING CHANNELS

DIVISION 35 - WATERWAY / MARINE

SPECIFICATION 35 41 00 CONSTRUCTION OF LEVEE

SPECIFICATION 35 42 00 RIPRAP

SPECIFICATION 35 43 00 TOE DRAIN

DIVISION 50 - ROADWAY CONSTRUCTION

SPECIFICATION 50 11 00 ROADWAY EMBANKMENT

SPECIFICATION 50 12 00 ROADWAY EXCAVATION

SPECIFICATION 50 20 00 ROADWAY BASE

SPECIFICATION 50 21 00 PRIME COAT

SPECIFICATION 50 23 00 EQUIPMENT FOR ASPHALT CONCRETE PAVEMENT

SPECIFICATION 50 24 00 ASPAHLT, OILS, AND EMULSIONS

SPECIFICATION 50 25 00 HOT MIX ASPHALT CONCRETE PAVEMENT

SPECIFICATION 50 29 00 CONCRETE CURB AND GUTTER

SPECIFICATION 50 30 00 CONCRETE PAVEMENT

SPECIFICATION 50 90 00 REFLECTIVE PAVEMENT MARKINGS

SPECIFICATION 50 91 00 REMOVE AND REINSTALL/REFURB TRAFFIC SIGNS

SPECIFICATION 50 93 00 TEMPORARY TRAFFIC CONTROL DEVICES

SPECIFICATION 50 94 00 DELINEATOR AND OBJECT MARKER ASSEMBLIES

DIVISION 60 - STRUCTURES

SPECIFICATION 60 01 00 FLOWABLE BACKFILL

El Paso County, Texas

USIBWC Contract No.: IBM05D0001 Page 01.01.00 - 3

SPECIFICATION 60 02 00 TRENCH EXCAVATION PROTECTION

SPECIFICATION 60 10 00 EXCAVATION AND BACKFILL FOR STRUCTURES

SPECIFICATION 60 20 00 CONCRETE STRUCTURES

SPECIFICATION 60 21 00 HYDRAULIC CEMENT

SPECIFICATION 60 38 00 CLEAN AND SEAL JOINTS

SPECIFICATION 60 40 00 REINFORCING STEEL

SPECIFICATION 60 41 00 STEEL STRUCTURES

SPECIFICATION 60 42 00 METAL FOR STRUCTURES

SPECIFICATION 60 45 00 GALVANIZING

SPECIFICATION 60 46 00 CLEANING AND PAINTING STEEL

SPECIFICATION 60 47 00 STRUCTURAL BOLTING

SPECIFICATION 60 48 00 WELDING

SPECIFICATION 60 50 00 RAILING

SPECIFICATION 60 62 00 CORRUGATED METAL PIPE

SPECIFICATION 60 63 00 CONCRETE BOX CULVERTS AND STORM DRAINS

SPECIFICATION 60 64 00 REINFORCED CONCRETE PIPE

SPECIFICATION 60 65 00 MANHOLES AND INLETS

SPECIFICATION 60 66 00 HEADWALLS AND WINGWALLS

SPECIFICATION 60 67 00 SLOPE END-SAFETY AND TREATMENT

SPECIFICATION 60 68 00 SLUICE GATE

SPECIFICATION 60 69 00 SLUICE GATE MAINTENANCE

SPECIFICATION 60 71 00 GRATES AND LADDERS

SPECIFICATION 60 79 00 ABANDON AND PLUG STRUCTURE

SPECIFICATION 60 80 00 FLOOD GATE

SPECIFICATION 60 96 00 REMOVING EXISTING STRUCTURES

SPECIFICATION 60 98 00 CLEAN EXISTING STRUCTURES

DIVISION 90 - MISCELLANEOUS

SPECIFICATION 90 79 00 VEHICULAR GATE

SPECIFICATION 90 80 00 REMOVE, REFURBISH AND REPLACE VEHICULAR

GATE

SPECIFICATION 90 81 00 BOULDERS

B. In any case where these technical specifications conflict with the Federal Acquisition Regulations

(FAR), FAR requirements will take precedence. In any case where FAR requirements are more strict or impose a higher standard than these technical specifications, FAR requirements will take precedence.

1.2 RELATED DOCUMENTS & PROVISIONS

Other related documents describing the requirements for the Work to be performed include the construction drawings entitled “UPPER RIO GRANDE PROJECT – INTERIOR LEVEES, REHABILITATION FOR CANUTILLO FLOODWAY, EL PASO COUNTY, TEXAS” or

“UPPER RIO GRANDE FLOOD CONTROL PROJECT – INTERIOR LEVEES,

REHABILITATION FOR CANUTILLO FLOODWAY, DONA ANA COUNTY, NEW MEXICO”,

the technical specifications, and the associated provisions included in the Contract.

El Paso County, Texas

USIBWC Contract No.: IBM05D0001 Page 01.01.00 - 4

1.3 PROVISIONS FOR MEASUREMENT AND PAYMENT

For Work performed by the Contractor under this Contract, the identified technical specifications (as shown in paragraph 1.1 herein) are those under which payment is to be made to the Contractor.

Measurement and payment of work shall be in accordance with SPECIFICATION 01 27 00 of this Contract.

1.4 SPECIFICATION / BID ITEM FORMAT AND CONVENTIONS

A. Specification Format. The technical specifications are organized into Divisions, and identified in Level 2 title format, using the Construction Specifications Institute’s (CSI) "MasterFormat – 2004 Edition" numbering system. For this Contract, the Divisions are grouped in two categories: (1) Standard Divisions, which are Divisions identified and defined by CSI, and (2) Special Divisions, which are Divisions that have been developed using industry standards, for some unique items of Work under this Contract.

B. Bid Item Format. Bid Items under this Contract have been derived from the governing specifications identified in paragraph 1.1 herein. Bid Items are numbered in Level 3 title format, using CSI’s “MasterFormat – 2004 Edition" numbering system. All Bid Items are identified in Section B of the Contract Provisions.

PART 2 – MATERIALS & EQUIPMENT (Not Applicable To This Specification)

PART 3 – CONSTRUCTION (Not Applicable To This Specification)

PART 4 – MEASUREMENT AND PAYMENT (Not Applicable To This Specification)

- END OF SPECIFICATION -

El Paso County, Texas

SCOPE OF WORK

USIBWC Contract No.: IBM05D0001 Page 01.19.00 - 1

SPECIFICATION 01 19 00

This specification includes descriptions and requirements for the following:

1.1 Related Documents

1.2 Work Covered by the Contract Documents

1.3 Sequence of Work / Time for Completion of Work

1.4 Work Under Other Contracts

1.5 Materials and Equipment

1.6 Use of Right-of-Way

1.7 Occupancy of Right-of-Way

1.8 Work Restrictions

2.0 Materials and Equipment (Not Applicable to this Specification)

3.0 Construction Methods (Not Applicable to this Specification)

4.0 Measurement and Payment (Not Applicable to this Specification)

1.1 RELATED DOCUMENTS

The following may not include all related documents, contract clauses, & technical specifications, and does not relieve the Contractor of the responsibility of performing work associated with this specification in accordance with all terms of the Contract herein.

A. Related documents: As described in paragraph 1.2 of SPECIFICATION 01 01 00.

B. Contract: Section I “Specifications and Drawings for Construction”

C. Technical Specifications: All

1.2 WORK COVERED BY THE CONTRACT DOCUMENTS

A. Project Identification. The Project to be constructed under this Contract is identified as follows:

(1) Name of Project - “UPPER RIO GRANDE FLOOD CONTROL PROJECT, REHABILITATION FOR CANUTILLO LEVEE SYSTEM” from the Vado Bridge to Borderland Bridge

(2) Location of Project – El Paso, Texas; Doña Ana, New Mexico.

(3) When work is located in New Mexico, the contractor is to use the New Mexico Department of

Transportation’s (NMDOT) Best Practices, Methods of Construction, Safety Guidelines and state policies during construction. The Contractor is to obtain all required permits and coordinate with NMDOT for all detours or road closures on state highways and roads.

El Paso County, Texas

USIBWC Contract No.: IBM05D0001 Page 01.19.00 - 2

All work accomplished under this contract shall be in accordance with the current version of the AASHTO "A Policy on the Geometric Design of Highway and Streets," FHWA Policy, the current edition of the MUTCD, New Mexico Criminal and Traffic Law Manual, Roadside Design Guide and the Highway Capacity Manual, other Department Manuals, Standards, and Guidelines, Standard Specifications and Standard Procedures.

When work is located in Texas, the contractor is to use the Texas Department of Transportation’s (TxDOT) Best Practices, Methods of Construction, Safety Guidelines and state policies during construction. The Contractor is to obtain all required permits and coordinate with TxDOT for all detours or road closures on state highways and roads

B. General Description of Work. The Work consists of the rehabilitation for the Canutillo Levee

System, for a total reach of 28.67 miles. The majority of the proposed improvements include increasing the elevation of the existing earthen levee. Major construction efforts include:

(1) Proposed Raising Existing Levee,

(2) Proposed New Levee,

(3) Proposed Installing a Clay Cap to the Existing Levee,

(4) Proposed Floodgates, and floodwalls where shown on the plans,

(5) Various appurtenances to the levee (sluice gates, pipe crossings, connecting roadways, etc.)

are to be rehabilitated also, to accommodate the new height of the levee.

(6) New or Refurbished Vehicular Gates, Road Signs, and fences.

1.3 SEQUENCE OF WORK / TIME FOR COMPLETION OF WORK

A. The Work is to be performed in sequence as shown on the plans.

B. The Work under this Contract shall be completed within 365 calendar days.

1.4 WORK UNDER OTHER CONTRACTS

No work is anticipated to be performed at the Project site, under separate contract with other contractors, during the Contractor’s performance under this Contract.

1.5 MATERIALS AND EQUIPMENT

A. Materials Ordered in Advance. The Government has not negotiated any purchase orders in advance for suppliers of materials and equipment to be incorporated into the Work.

B. Other Government-Furnished Materials. The Government will not provide any materials for the

Work.

El Paso County, Texas

USIBWC Contract No.: IBM05D0001 Page 01.19.00 - 3

C. Materials and Equipment to be Furnished by the Contractor.

(1) The Contractor shall provide all materials and equipment required to execute the Project.

(2) All materials provided by the Contractor for the Project shall be new or recycled, high grade, free from defects, meeting the specifications herein. Quality of the Work shall be in accordance with the specifications herein. The COR and the testing company will ensure that materials, equipment, and Work quality strictly adhere to the requirements of the Contract documents.

(3) Materials, equipment, and work quality not conforming to the requirements of these specifications shall be considered defective and will be subject to rejection. Defective Work material, whether in place or not, or equipment shall be removed immediately from the site by the Contractor, at its expense, when so directed by the CO.

(4) If the Contractor fails to replace any defective or damaged work, materials or equipment after receiving notice, the CO may cause such work or materials to be replaced by other forces.

The replacement expense shall be deducted from the amount to be paid to the Contractor.

Defective equipment will not be allowed in the performance of any work.

1.6 USE OF RIGHT-OF-WAY

The Contractor shall limit use of the right-of-way to that which is indicated in the construction drawings, so as to allow for the USIBWC’s use and occupancy. Contractor operations shall be confined to the Project site and other areas permitted and identified by the construction drawings. Portions of the site beyond areas on which the work is to be performed are not to be disturbed. Roads serving the facility, and identified as such, shall be clear and available to the USIBWC as indicated in the construction drawings.

1.7 OCCUPANCY OF RIGHT-OF-WAY

A. Partial Government Occupancy. The Government may need to occupy the right-of-way during the entire construction period, with the exception of areas under construction. The Contractor shall cooperate with the Government during construction operations to minimize conflicts and facilitate Government access. The Contractor needs to maintain existing access to the facility, unless otherwise indicated in the construction drawings. The Contractor shall provide not less than seventy-two (72) hours notice to the Government of construction activities that will affect any Government activities.

B. Government Occupancy of Completed Areas of Construction. The Government reserves the right to occupy and to place and install equipment in completed areas of the facility, before Substantial Completion, provided such occupancy does not interfere with completion of the Work. Such placement of equipment and partial occupancy shall not constitute acceptance of the total Work.

El Paso County, Texas

USIBWC Contract No.: IBM05D0001 Page 01.19.00 - 4

1.8 WORK RESTRICTIONS

A. On-Site Work Hours. The Contractor’s attention is directed to the Contract Provisions.

B. Irrigation Pipe. Irrigation structures are owned by others. The work to be performed on irrigation structures shall be performed in accordance with the irrigation owner’s restrictions.

C. Cutting the Levee for Structure Improvements. In some instances, the work may require cutting the levee. This Work may not be performed during hurricane season or periods of known heavy rains or flooding.

PART 3 – CONSTRUCTION METHODS (Not Applicable To This Specification)

El Paso County, Texas

MEASUREMENT AND PAYMENT

USIBWC Contract No.: IBM05D0001 Page 01.27.00 - 1

SPECIFICATION 01 27 00

This specification identifies administrative and procedural requirements for measurement of the work and payment to the Contractor for Work performed, and includes the following:

1.1 Related Documents

1.2 Measurement of Quantities

1.3 Scope of Payment

1.4 Measurement and Payment for Changes in Work

1.5 List of Bid Items

2.0 Materials and Equipment (Not Applicable to this Specification)

4.0 Measurement and Payment (Not Applicable to this Specification)

The following may not include all related documents, contract clauses, & technical specifications, and does not relieve the Contractor of the responsibility of performing work associated with this specification

B. Contract: Section I, “Specifications and Drawings for Construction”

C. Technical Specifications: All

1.2 MEASUREMENT OF QUANTITIES

The Government or COR will measure all completed work using US standard measures. The method of measurement for each Bid Item is identified under the applicable technical specifications and the unit of measure is identified in the Summary of Quantities in the plans sheets in the contract documents.

1.3 SCOPE OF PAYMENT

Payment to the Contractor shall be at the Unit Price for each Bid Item, and shall, in general, be considered full compensation for all materials, equipment, labor, tools, supplies, and incidentals necessary to complete the Bid Items and the Work under the Contract. The method of payment for each Bid Item is further identified under the applicable technical specifications and the Unit Price set forth in the Bid Schedule of the Contract Documents. Payment of the Unit Price for each Bid Item will be payment in full for this Contract. All costs and expenses for which no specific Unit Price is set forth in the Bid Schedule shall be considered subsidiary, and included in the Unit Prices that are applicable and specifically set forth in the Bid Schedule, and no additional payment will be made therefore.

1.4 MEASUREMENT AND PAYMENT FOR CHANGES IN WORK

El Paso County, Texas

USIBWC Contract No.: IBM05D0001 Page 01.27.00 - 2

Measurement and payment to the Contractor for extra work directed and incorporated by Construction Change Directive, performed by the Contractor, and compliance-confirmed by the Government or COR, will be made in accordance with the provisions of the Contract.

1.5 LIST OF BID ITEMS

The items to be bid by the Contractor for the performance of Work under this Contract are located under SECTION B of the Contract.

El Paso County, Texas

PROJECT MANAGEMENT AND COORDINATION

USIBWC Contract No.: IBM05D0001 Page 01.31.00 - 1

SPECIFICATION 01 31 00

This specification identifies administrative provisions for coordinating construction operations while the Work is being performed by the Contractor, and includes the following:

1.1 Related Documents

1.2 Coordination

1.3 Project Meetings

1.4 Requests for Information

2.0 Materials and Equipment (Not Applicable to this Specification)

4.0 Measurement and Payment

PART 1 – GENERAL

The following may not include all related documents, contract clauses, & technical specifications, and does not relieve the Contractor of the responsibility of performing work associated with this specification

B. Contract: Section I, “Specifications and Drawings for Construction”

C. Technical Specifications: 01 19 00 Scope of Work 01 27 00 Measurement and Payment 01 32 00 Construction Progress Documentation 01 33 00 Submittals 01 57 00 Temporary Erosion, Sedimentation, and Environmental

Controls Written Health and Safety Plan Divisions 31, 33, 34, 35, 50, 60 and 90

1.2 COORDINATION

In general, construction operations shall be coordinated to ensure efficient and orderly installation of each part of the work. In addition to a Project Superintendent, the Contractor shall provide other administrative and supervisory personnel as required for proper coordination and administration of the work. The Contractor’s Project Superintendent shall be available to the Government during business hours, as well as emergency contact. Other coordination responsibilities and activities required to be provided by the Contractor includes the following:

A. The Contractor shall be responsible for ascertaining the nature and extent of any simultaneous, collateral, and essential work by others. The Government, its workers and contractors, and others, shall have the right to operate within or adjacent to the Construction site to perform such work.

El Paso County, Texas

USIBWC Contract No.: IBM05D0001 Page 01.31.00 - 2

B. In accordance with the provisions and time frames stated in SPECIFICATION 01 32 00, the

Contractor shall submit to the COR a proposed Schedule of Work. This Schedule of Work shall be in the form as described in SPECIFICATION 01 32 00, and shall reflect all coordination efforts of the Work under this Contract.

1.3 PROJECT MEETINGS

All meetings, unless otherwise directed shall be scheduled and conducted at the American Dam Field Office at 2616 W. Paisano Drive, El Paso, Texas 79922 site. The COR shall inform participants and others involved, and individuals whose presence is required, of date and time of each meeting. The COR shall prepare the meeting agenda, and distribute to all invited attendees. The COR shall record significant discussions and agreements achieved, and distribute the meeting minutes to everyone concerned, within seven (7) calendar days of the meeting. The following meetings are anticipated, and the Contractor shall identify them in the Schedule of Work:

A. Preconstruction Conference. A preconstruction conference shall be scheduled by the COR prior to the start of construction, but no later than fifteen (15) calendar days after Government receipt of acceptable payment and performance bonds and proof of insurance. The preconstruction conference will be held at the location specified on the letting/bidding documentation. The purpose of the meeting is to introduce project personnel and review responsibilities and procedures. The Contractor shall provide a copy of his Draft Schedule of Work as specified under SPECIFICATION 01 32 00, Construction Progress and Documentation.

(1) Attendees - Authorized representatives of the Government (including the COR), the Engineer, the Contractor’s Superintendent, major subcontractors, suppliers; and other concerned parties shall attend the conference. All participants at the conference shall be familiar with the Project and authorized to conclude matters relating to the Work.

(2) Agenda – Discussion of items of significance that could affect the Work and project, including the following: introduction / designation of key personnel and their duties; review of the Draft Schedule of Work, phasing, critical work sequencing and long-lead items; review of procedures for handling and processing field decisions, Change Orders, RFIs, testing and inspection, applications for payment, and submittals; preparation of record documents; use of right-of-way; work restrictions; USIBWC and others occupancy requirements; responsibilities for temporary facilities and controls; construction waste management and recycling; field office, parking, Work, and storage areas; equipment and materials deliveries and priorities;

safety and first aid; security; maintenance of project site; and working hours.

(3) Meeting Minutes – The Government’s Construction Management Contractor will record the discussions of the meeting, and distribute the minutes.

B. Progress Meetings. The COR will arrange and conduct weekly progress meetings. The meetings shall include the Government, and the Contractor’s Project Manager, Field Superintendents, and Quality Control Manager. The purpose of these meetings shall be to analyze the progress of the work of the Contractor, resolve conflicts, and in general, coordinate the operation of all organizations active at the project site. Minutes of the meetings will be kept and distributed by the

El Paso County, Texas

USIBWC Contract No.: IBM05D0001 Page 01.31.00 - 3

Government. The Government may call other meetings on an "as needed" basis. All meetings will be held at the time and locations chosen by the COR.

1.4 REQUESTS FOR INFORMATION (RFI)

Immediately on discovery of the need for interpretation of the Contract Documents, and if not possible to request interpretation at Project meeting, the Contractor shall prepare and submit an RFI in the form specified.

A. Content of the RFI. The RFI shall include a detailed, legible description of item needing interpretation and the following:

(1) Project name.

(2) Date.

(3) Name of Contractor.

(4) RFI number, numbered sequentially.

(5) Specification number, title and related paragraphs, as appropriate.

(6) Drawing number and detail references, as appropriate.

(7) Field dimensions and conditions, as appropriate.

(8) Contractor's suggested solution(s). If Contractor's solution(s) impact the Contract Time or the Contract Sum, Contractor shall state impact in the RFI.

(9) Contractor's signature.

(10) Attachments: Include drawings, descriptions, measurements, photos, Product Data, Shop Drawings, and other information necessary to fully describe items needing interpretation.

Supplementary drawings prepared by Contractor shall include dimensions, thicknesses, structural grid references, and details of…